Power Quality and Protective Device Coordination: Problems & Solutions Part 1 Undersizing of Utility Main Service Transformers

Similar documents
Are the New 2005 NEC Selective Coordination Requirements Causing an Increase in Arc Flash Energies and Reducing Distribution System Reliability?

Recommended Procedures

Service Entrance Methods

Engineering Dependable Protection

www. ElectricalPartManuals. com Engineering Dependable Protection

Michigan State University Construction Standards SECONDARY UNIT SUBSTATIONS PAGE

Selective Coordination Enforcement:

Selection Guide S&C ELECTRIC COMPANY. For Transformer-Primary Fuses in Medium- and High-Voltage

Data Bulletin. Ground-Censor Ground-Fault Protection System Type GC Class 931

Protective Device Coordination ETAP Star

Source-Side Fuse/Load-Side Recloser Coordination

Motor Protection. Presented By. Scott Peele PE

Selective Coordination Compliance Methods for Evaluation and Mitigation

Design Considerations to Enhance Safety and Reliability for Service Entrance Switchboards

Alternator protection, part 1: Understanding code requirements

3.2. Current Limiting Fuses. Contents

Enhancing Short Circuit Selective Coordination with Low Voltage Circuit Breakers

MOLDED CASE CIRCUIT BREAKER BASICS. David Castor, P.E.

Selective Coordination

Overcurrent Protection According to the 2011 NEC

Overcurrent Protection (2014 NEC) (Homestudy)

University of California, San Diego Cal (IT) 2 Technical Assignment #2. Brian Smith

Outdoor Distribution (15 kv through 25 kv) S&C Fault Tamer Fuse Limiter

Published for electrical engineers by EPOWERENGINEERING and available at The ABC s of Overcurrent Coordination

4-Day Power System Analysis, Coordination, System Studies

Secondaries. arc flash note Introduction. By Mike Lang, engineer and. Services Supervisor

SECTION LOW VOLTAGE DISTRIBUTION EQUIPMENT

Selective Coordination Requirements

Equipment Protection. Transformers 600V or Less

6/4/2017. Advances in technology to address safety. Thomas A. Domitrovich, P.E., LEED AP VP, Technical Sales Eaton

Shippensburg University

How to Use Coordinaide to Protect Transformers Against Secondary-Side Arcing Faults.

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

S&C Fault Tamer Fuse Limiter. Outdoor Distribution (15 kv through 25 kv)

Motor Protection. Voltage Unbalance & Single-Phasing

A. Submit manufacturer's literature and technical data before starting work.

Model ESV Uninterruptible Power System 1.5 KVA/KW KVA/KW Single Phase

ECET 211 Electric Machines & Controls Lecture 8 Motor Control Circuits (1 of 2) Lecture 8 Motor Control Circuits

Section SWITCHBOARDS. Introduction. Part 1 - General. Related Work

A. Provide a complete system of overcurrent protective devises as indicated on the drawings, and as specified herein.

SECTION MOTOR CONTROL

A system fault contribution of 750 mva shall be used when determining the required interrupting rating for unit substation equipment.

Power System Solutions (PSS)

2000 Cooper Bussmann, Inc. Page 1 of 9 10/04/00

Sectionalizing. Rick Seeling. Pete Malamen. Introduction Philosophy. Three Phase Reclosers High-Side Protection Specific Applications

Electromagnetic Industries LLP

SECTION PANELBOARDS

A. This section includes unit capacitors for power factor correction.

SURE-TRIP OEM RELACEMENT TRIP UNIT

A. This section includes enclosed dry type transformers for lighting and power loads, with primaries and secondaries rated 600 volts and less.

WARREN COUNTY, N.Y. M/E REFERENCE

Devices for Branch Circuits and Feeders

Grounding Of Standby & Emergency Power Systems

Application of Sepam Relays for Arc Flash Hazard Reduction at Low Voltage Switchgear

Understanding Arc Flash Hazards. White Paper

Equipment Protection. Transformers 600V or Less

That s how compact transformer protection is today. The customer newsletter of Kries-Energietechnik

Design Standards NEMA

9/16/2010. Chapter , The McGraw-Hill Companies, Inc. TRANSMISSION SYSTEMS. 2010, The McGraw-Hill Companies, Inc.

Advanced Guide To Understanding Assembly Short-Circuit Current Rating WITH ENGINEERING SOLUTIONS AND OVERCURRENT PROTECTION DEVICES TO ENHANCE SCCR

A. This Section includes Low Voltage Switchgear Work, as indicated on the drawings, and as specified herein.

SURE TRIP RETRO KITS

K-SEC 030. Fusing Equipment. Kearney Fuse Links GENERAL INTERNAL CONSTRUCTION SINGLE TIN ELEMENT

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

ECET Distribution System Protection. Overcurrent Protection

THE CURVE FOR DOUBLE PROTECTION TRANSFORMER & SYSTEM PROTECTION WITH CHANCE SLOFAST FUSE LINKS

POW ER EN G IN EER S, L LC

SECTION ENCLOSED SWITCHES AND CIRCUIT BREAKERS

A comparison of metal-enclosed load interrupter (ME) switchgear and metal-clad (MC) switchgear

UBC Technical Guidelines Section Edition Commissioning of Electrical Systems Page 1 of 5

www. ElectricalPartManuals. com Instructions for Field Testing of Ground Fault Systems Utilizing Cutler-Hammer Magnum DS Circuit Breakers

Protectors. Manual motor. Types MS116, MS132, MS45x, MS49x. MS Series. Manual motor protectors. Type MS116. Type MS132. Type MS45x.

DIVISION 26 ELECTRICAL SECTION CIRCUIT BREAKERS

MECKLENBURG COUNTY. Land Use and Environmental Service Agency Code Enforcement 2/8/12 ELECTRICAL CONSISTENCY MEETING. Code Consistency Questions

Generator Fire Safety: Generator assemblies should be located outside the building.

7. SERVICES OVER 600 VOLTS

FUSERBLOC CD. The universal Fuse Combination Switch FROM 20 TO 1250 A. Industrial Switching & Protection Systems

APPENDIX E. Electrical System Single Line Diagram Overcurrent Protection Study Overcurrent Protection Device Specifications

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

Fusing Equipment. Kearney Fuse Links. general. Internal Construction. tin element

Machine, Panel, and Plant Level Solutions

Current Ratings. Standards & codes note 1. Introduction. interest. By Steve Hansen Sr. Field Engineer

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Switchboards. Basis of Design. Design Evaluation

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

Figure 1. Two and Three-phase MagneX.

TRANSMISSION SYSTEMS

Applying Interrupting Rating: Circuit Breakers

Applying Interrupting Rating: Circuit Breakers

ACHIEVING MAXIMUM BENEFITS WITH A FUSE PROTECTED MOTOR CONTROL CENTER

DESIGN GUIDELINES LOW VOLTAGE SWITCHGEAR PAGE 1 of 5

Chapter 6 Generator-Voltage System

Critical Power Switchboards. Selection and Application Guide

Selection and application guide

Net Metering Interconnection Requirements

PREFACE ********************************************************** IT IS NOT INTENDED THAT THESE STANDARDS BE COPIED AND USED AS A SPECIFICATION!

SafeGear TM Motor Control Center Arc resistant metal-clad construction Motor Control Center Descriptive bulletin

Motor Protection Fundamentals. Motor Protection - Agenda

Standby Power Systems

EON Model EL3 Three Phase Centralized Emergency Lighting Inverter. General Specification 40KW 55KW Systems

What's New with UL508A Codes & Standards Presented by Jeff Woolfolk Manufacturing in America March 14-15, 2018

Transcription:

Power Quality and Protective Device Coordination: Problems & Solutions Part 1 Undersizing of Main Service s INTRODUCTION by Robert E. Fuhr, P.E. The use of electronic equipment has dramatically increased during the last 20 years. Some of these electronic devices include variable speed drives, programmable controllers, computers, and even solid state protective relays. Electronic equipment is much more sensitive to power quality. A lot of attention has been given to power quality in the last several years. Most of this focus has been on harmonics, power sags, and surges. One important aspect of power quality that is extremely important is Protective Device Coordination. Protective Device Coordination Studies determine settings for circuit breakers and relays. These studies also verify the correct fuse size and determine the protection required for conductors, transformers, and other equipment. The goal of this study is to determine settings which would reduce damage to equipment and to isolate only the circuit that has a short circuit or fault. This causes the least amount of disturbance to the remainder of the distribution system. POWER QUALITY AND PROTECTIVE DEVICE COORDINATION: PROBLEMS & SOLUTIONS Part 1 & Part 2 will focus on two unique problems that are affecting power system protection, owners, and design engineers. These two problems are: Part 1 - Under-sizing of utility main service transformers for buildings, plants, and facilities. Part 2 - High inrush currents on low temperature or K-Rated transformers. This article will address Part 1 - Under-sizing of utility main service transformers for buildings, plants, and facilities. BACKGROUND When a building is designed by electrical engineers, the engineers are required to use the National Electric Code (NEC). This code is a safety code which is designed to protect life and property. The code has minimum requirements for the number of outlets in a room, number of receptacles on a circuit, and the size of equipment. The designer must use these minimum requirements when they design the electrical distribution system for a building or facility. The use of the NEC results in a distribution system that is initially oversized. The design engineer calculates the anticipated loads for the building using the National Electric Code (NEC). The designer uses: 1. Estimated motor horsepower determined by the mechanical design engineers. 2. Estimated lighting loads based upon the type of fixtures used, square footage of the building, and the governmental energy requirements. 3. Estimated receptacle loads based on NEC and type of building loads. 4. Known client purchased equipment loads. 5. Fudge factors for those unknown loads. 6. Load growth factors for future loads. Together with the NEC code calculations, estimations, requirements, and the future growth factors, the Page 1

distribution system becomes oversized. During the design process, the electrical designer contacts the utility company to determine the location and transformer size for the building. The design engineer needs to know the size of the transformer to perform a short circuit study. The short circuit calculations are needed to specify the electrical equipment. Panelboards, switchboards, motor control centers and most other electrical distribution equipment all have a short circuit rating. This is similar to a full load current and voltage rating. The short circuit rating is a rating given to a piece of equipment by the manufacturer or electrical testing laboratory. This rating indicates the amount of short circuit or fault current that a device can withstand or interrupt. Section 110-10 of the NEC requires that all equipment that is installed must have a short circuit rating larger than the calculated short circuit at the equipment location. The utility engineer will usually supply the design engineer the transformer size and impedance based upon the load that the design engineer calculated. Initially, the utility companies are not required by the Authority Having Jurisdiction (AHJ) to use the NEC. The utilities can use whatever methods or means that work for them, regardless of safety or equipment protection issues. Due to experience, the utilities have seen that buildings designed using the NEC result in an overdesigned distribution system. The actual demand load will be much less than the load that the electrical engineer calculated. They know that the actual demand load will be 40-60% of the load calculated by the design engineer. The utilities are also facing major industry changes due to de-regulation. This is forcing them to look for ways to be more efficient and reduce costs. Therefore, most utilities are now ordering and installing smaller transformers. This has a negative impact on protective device coordination. After the contractor or owner has ordered the facility s electrical equipment and before the contractor installs it, a protection engineer must perform a protective device coordination study. Section 240-12 of the NEC also requires that this study be performed. The engineer is usually hired by the contractor or equipment manufacturer to perform this study. As stated earlier, the protective device coordination study is needed to determine the settings for the main service, for both main and feeder breakers. Determining breaker settings becomes increasingly complex, as many of today s circuit breakers are equipped with solid state trip units. These devices have numerous pick up and time delay adjustments. PROTECTIVE DEVICE COORDINATION PROBLEMS The protective device coordination problem occurs due to the smaller utility transformer. This size reduction makes it impossible to coordinate the main breaker with the utility transformer and the primary fuse. A fault downstream from the main service switchboard can take out the switchboard feeder breaker or transformer primary fuse. The result is an uncoordinated system that is susceptible to prolonged outages. This affects the facility s overall power quality. An example distribution system one line is shown on Sheet P1-1. This is a simple distribution system with a 2000 ampere Main Distribution Switchboard. It is being fed by a normally sized 1500 kva AA/FA transformer. The full load current of this transformer is 1,807 amperes without fans and 2,349 with fans. The design engineer has specified a 2000 ampere main breaker equipped with solid state trip units. An 800 ampere feeder breaker with solid state trip units feeds. The main breaker in is an 800 ampere breaker with thermal magnetic trip units. The protection engineer performs a protective Page 2

device coordination study by plotting the protective device time current curve characteristics on a graph called a Time Current Curve (TCC). The graph is a log-log graph of time versus current. Each breaker, fuse, and relay has a time current characteristic curve published by the manufacturer that is plotted on industry standard log-log graph paper. An example of a time current curve is shown on Sheet P1-2. The curve shows the available fault current, which is a phase to phase short circuit. The curve shows the time current characteristic of the 800 ampere thermal magnetic molded case circuit breaker. The curve also shows a transformer protection curve. This curve represents the transformer withstand level. They are defined by the ANSI/NEMA Standards below: ANSI/NEMA ST20 (1972), R (1982) for Specialty s ANSI C57.12.00 (1980), for Liquid Immersed Distribution & Power s ANSI C57.12.01 (1979), for Dry Distribution & Power s These standards are design requirements for transformer windings. The transformer is required to withstand without injury or damage, thermal and mechanical stresses caused by short circuits on its terminals for a defined period of time. The curves are based upon the transformer: 1. Type (liquid, dry, or low voltage) 2. Size (kva) 3. Impedance (Z%) 4. Primary and Winding connections (Delta, Wye, Wye Grounded) The curve is shifted by an ANSI Factor which is based upon the primary and secondary winding connections. Table P-1 shows these factors for the various types of transformer winding configurations. Sheet P1-3 shows a 1500 kva transformer connected Delta-Wye and the same transformer connected Wye-Wye. Note that the Delta-Wye solidly grounded transformer curve is shifted to the left by a factor of 0.58. Winding Connections Type of Fault Primary Winding Connection Secondary Winding Connection Tertiary Winding Connection Three Phase Phase to Phase Line to Ground ANSI Factor Delta Delta 1.0 0.87 N.A. 0.87 Delta Wye-Grounded 1.0 1.16 0.58 0.58 Delta Wye 1.0 1.15 N.A. 1.0 Wye-Grounded Wye 1.0 1.0 N.A. 1.0 Wye-Grounded Wye-Grounded 1.0 1.0 1.0 1.0 Wye Wye-Grounded Core Type 1.0 1.0 0.87 0.87 Wye Wye-Grounded Shell Type 1.0 1.0 N.A. 1.0 Wye Wye 1.0 1.0 N.A. 1.0 Wye-Grounded Delta 1.0 1.0 N.A. 1.0 Wye Delta 1.0 1.0 N.A. 1.0 Delta Delta Wye-Grounded 1.0 1.15 1.0 1.0 Wye-Grounded Delta Wye-Grounded 1.0 1.0 0.87 0.87 Wye Delta Wye-Grounded 1.0 1.0 0.87 0.87 Wye Delta Wye 1.0 1.0 N.A. 1.0 Table P1-1 ANSI Factor List For the transformer to be protected properly, all the downstream secondary devices and the primary fuse must lie to the left of the curve. The primary fuse can lie on top of the curve but it should never be completely to the right of the transformer protection curve. Page 3

.01.1 1 Time in Seconds 10 100 1000 P UTILITY XFMR-PRI Y-Y XFMR-SEC Main Fdr to Pnl P1 P1 Main PANEL-P1.5 1 10 100 1000 10000 Current in Amperes X 100 M Y-Y 750 KVA 2000 Amp Bus 800 Amp Bus P1 Main SIEMENS MD6 HMD6 800 Amp 480 Volt Phase Time-Current Characteristic Curves Sheet P1-2 1500 kva Xfmr D-Y,, & Main 9/23/99 9:24:16am

.01.1 1 Time in Seconds 10 100 1000 P UTILITY XFMR-PRI D-Y XFMR-SEC D-Y 1500 KVA.5 1 10 100 1000 10000 Current in Amperes X 100 M Y-Y 1500 KVA 480 Volt Phase Time-Current Characteristic Curves Sheet P1-3 1500 kva Xfmr D-Y & Y-Y Xfmrs 9/23/99 9:36:50am

The protective devices and transformer curves are plotted on the time current curve. The devices are selectively coordinated for all levels of fault current (a short circuit going phase-to-phase, line-to-line, or line-to-ground) and time if they do not touch or lie on top of each other. An example of some selectively coordinated devices is shown on Sheet P1-4. If a 20,000 ampere fault occurs in the Panelboard P1, the main breaker will trip instantaneously. If it fails to operate, then the upstream 800 ampere feeder in the main switchboard will trip between 0.08 and 0.12 seconds. If this fails to trip, then the main will trip between 0.16 and 0.2 seconds. The primary fuse, main and feeder breakers are selectively coordinated for phase-to-phase faults. The 800 ampere thermal magnetic breaker, however, is not coordinated. The breaker overlaps with the feeder and main solid state trip breakers. On Sheet P1-4, the devices are selectively coordinated using the 1500 kva Delta-Wye transformer and a 100T fuse. On this sheet, the devices do not overlap each other. Sheet P1-5 shows what can happen if the utility installs a 750 kva Delta-Wye transformer and a 50T fuse. The transformer protection curve is shifted to the left and now overlaps the downstream protective devices. The primary fuse is shifted over because its size is reduced to protect the smaller transformer. The result is an uncoordinated system with the transformer and fuse curves overlapping the downstream devices. This results in mis-coordination. For some faults, the primary fuse will operate before or at the same time as the downstream devices. This results in a total facility outage. This reduces the power system reliability and thus the facility power quality. SOLUTIONS Sheet P1-6 shows the same 750 kva transformer but it is now a wye-wye unit. The primary fuse is now an 80T. The transformer curve is shifted to the right. This improves the coordination between the secondary devices. The 80T fuse does overlap the main breaker curve. This represents a compromise, but is still an improvement. What can the protection engineer, designer, and the utility do to avoid this problem? The first step is to improve the communication between the engineers and the utility. They all must work together and solve the problem. There is a compromise that will satisfy both the designer and utility engineer. The utility will be able to install a smaller transformer and the protection engineer will be able to achieve coordination. This win win situation will occur if the utility installs a wye-wye transformer and increases the primary fuse size. The wye-wye connection shifts the ANSI/NEMA transformer protection curve to the right and away from the downstream device curves. The primary fuse can be increased because the transformer curve has been shifted. SUMMARY Power Quality is a very important issue that is affecting every building and facility. Good facility power quality starts with a reliable power distribution system. A reliable power system must be properly coordinated with the facility and the utility protective devices. If the protection, design, and the utility engineers work closely together and communicate with each other, then the utility engineer can order the correct transformer size and winding connection, thereby eliminating any protective device coordination problems. Page 4

.01.1 1 Time in Seconds 10 100 1000 D-Y 1500 KVA.5 1 10 100 1000 10000 Current in Amperes X 100 M S&C Universal (T) 100T 2000 Amp Bus Main RL-2000 2000 Amp 800 Amp Bus Fdr to Pnl P1 RL-800 800 Amp 480 Volt Phase Time-Current Characteristic Curves Sheet P1-4 1500 Xfmr D-Y, Main, Fdr to Pnl P1, & P1 Main 9/23/99 9:35:22am

.01.1 1 Time in Seconds 10 100 1000 D-Y 750 KVA.5 1 10 100 1000 10000 Current in Amperes X 100 M S&C Universal (T) 50T 2000 Amp Bus Main RL-2000 2000 Amp 800 Amp Bus Fdr to Pnl P1 RL-800 800 Amp 480 Volt Phase Time-Current Characteristic Curves Sheet P1-5 750 kva Xfmr D-Y, Main, Fdr to Pnl P1 9/23/99 9:38:51am

.01.1 1 Time in Seconds 10 100 1000.5 1 10 100 1000 10000 Current in Amperes X 100 M Y-Y 750 KVA S&C Universal (T) 80T 2000 Amp Bus Main RL-2000 2000 Amp 800 Amp Bus Fdr to Pnl P1 RL-800 800 Amp 480 Volt Phase Time-Current Characteristic Curves Sheet P1-6 750 Xfmr Y-Y, Main, Fdr to Pnl P1, & P1 Main 9/23/99 9:40:24am

Robert E. Fuhr graduated with a B.S.E.E. from the University of Wisconsin in 1980. Before graduating, Mr. Fuhr worked for Madison Gas and Electric in Madison, WI and Tennessee Valley Authority in Knoxville, TN. After graduation, he worked for General Electric Company from 1980 to 1986 as a Field Engineer. From 1986 to 1989 he worked as a Senior Facilities Engineer at the University of Washington. In 1986, he established Power Systems Engineering, a consulting firm that specializes in power systems studies. As Power Systems Engineering s Senior Electrical Engineer, he has performed power studies for many commercial buildings and large industrial facilities. He is the sales agent for EDSA Power System Analysis Software. He also teaches classes in electrical safety, power factor correction, harmonics and filter design. Mr. Fuhr is a Professional Engineer registered in Washington, Oregon, California, and Alaska. Bob has been actively involved in IEEE and the Industrial Applications Society since 1986. He has served as an officer for IAS from 1988 to 1992. He was the 1991 to 92 Chairperson of IAS. He was a Memberat-large for the Seattle Section of IEEE for 1992-93. He is a board member of Power Quality Interest Group and is a member of the Electric League of the Pacific Northwest. Page 5