EPR TM reactors in the world Rome, January 19, 2010 Marco Graziano AREVA Vice President Business Development
Outline EPR TM reactors under-construction Experience feedback from current EPR TM projects Upcoming EPR TM projects and corresponding opportunities for suppliers Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.2
EPR TM reactors underconstruction
4 EPR Reactors under construction worldwide Flamanville 3 Olkiluoto 3 Taishan 1&2 Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.4
Olkiluoto 3 The EPR Reactor construction projects Flamanville 3 Taishan 1&2 Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.5
The OL3 project description Olkiluoto 3 Where Olkiluoto, Finland Contract signed Dec 18, 2003 Customer Teollisuuden Voima Oy (TVO) Supplier Consortium formed by AREVA and Siemens AG (73% / 27%) and led by AREVA Supply scope 1 EPR unit in turnkey construction First Concrete July 2005 Net electric output 1,600 MWe Reactor thermal output 4,300 MWth Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.6
Reactor Building & Safeguard buildings view Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.7
Main Control Room lifted & in place Main Control Room lifting 20.5.09 Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.8
Reactor Pressure Vessel (RPV) and Steam Generators (SG) on site January 09 RPV delivery at OL3 November 09 SG delivery at OL3 Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.9
The EPR Reactor construction projects Olkiluoto 3 Flamanville 3 Copyright EDF Taishan 1&2 Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.10
Flamanville 3 The FA3 project description Where Flamanville, France Contract signed Apr 11, 2007 Customer Main Suppliers AREVA Supply scope Electricité de France (EDF) AREVA & Alstom First Concrete Dec 2007 Net electric output Reactor thermal output 1 EPR unit - Nuclear Island Nuclear Steam Supply System (NSSS) - Nuclear Island Engineering & Procurement (NI EP) 1,630 MWe 4,300 MWth Copyright EDF Copyright EDF Copyright EDF Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.11
The FA3 Site On the AREVA perimeter: 70%+ of orders placed Engineering 65%+ completed Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.12
Steam Generator Manufacturing ongoing Copyright EDF Machining of the Steam Generators AREVA Saint-Marcel Copyright EDF Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.13
The EPR Reactor construction projects Olkiluoto 3 Flamanville 3 Taishan 1&2 Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.14
Taishan 1&2 Project description Taishan Where Taishan, China Contract signed November 26, 2007 Customer China Guangdong Nuclear Power Holding Corp. Ltd. (CGNPC), Main Suppliers represented by the Taishan Nuclear Power Company (TSNPC) AREVA in consortium with two subsidiaries of CGNP, Alstom AREVA Supply scope First Concrete November 2009 NI Design and Procurement for 2 EPR units Net electric output Reactor thermal output 1,660 MWe 4,590 MWth Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.15
Main developments Creation of a New Joint Design Team in Shenzhen (October 09) Creation of WECAN, a joint AREVA-CGNPC engineering JV Primary equipment progress Forging: launched for heavy components Manufacturing of the steam generator has started in AREVA St Marcel for Taishan Unit 1 in November and is ongoing Manufacturing of the Reactor Pressure Vessel in MHI has started in November and is in progress Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.16
Experience feedback from current EPR TM projects
Lessons Learned Process A well defined and continuous Lessons Learned process: over 500 lessons learned so far (captured, analyzed, distributed) including 300 from OL3 Construction Site A valuable input toward future projects, Standard EPR, Project Management, Procurement, Construction and Engineering Methods A common and simple tool accessible to all project teams Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.18 AREVA NP
Lessons Learned Experience Feedback OLKILUOTO 3 FLAMANVILLE 3 TAISHAN 1&2 FUTURE EPR TM The AREVA experience from four EPR TM under construction is: systematically taken into account from the beginning made available for future EPR TM projects increasing the performance of the AREVA group Future EPR TM will benefit from these experiences Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.19
Building licensing certainty: A significant asset for future projects Years 00 01 02 03 04 05 06 07 08 09 10 11 12 13 14 Generic Design Acceptance Nuclear Site Licensing Pre-Design Certification Combined License Decision in Principle Construction License Operating License Construction Authorization Operating License Construction Authorization Operating License Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.20
Upcoming EPR TM projects and corresponding opportunities for suppliers
The nuclear revival is here New builds 359 Forecasts published by international organizations 824: WEO 1-2008- 450 ppm Policy Scenario 748: IAEA - 2008 High Estimate 731: WNA 2-2007- High Estimate 684: WEO- 2008-550 ppm Policy Scenario AREVA target (AREVA target 2007: 636) 529: WNA - 2007 - Reference 498: DOE 3 EIA 4-2008 Reference Case 473: IAEA - 2008 Low Estimate 433: WEO - 2008 Reference Scenario 262 End of theoretical lifetime 549 1. World Energy Outlook 2. World Nuclear Association 3. US Department of Energy 4. Energy Information Administration 190 Lifetime extensions 373 GWe nets installed 660 2008 2030 AREVA targets 1/3 of accessible new build market and the leadership in life extension and power uprates (market worth tens of billions of euros) Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.22
More than 20 EPR reactor projects under development worldwide Under construction Under development Prospects 4 + 4 UK 4 units announced by EDF 4 units targeted with EON/RWE Further units with GDF- SUEZ, Iberdrola & SSE Industrial partnerships with Balfour Beatty-Vinci and Rolls Royce covering engineering, manufacturing and construction 1 OLKILUOTO 3 under construction 1 FINLAND FRANCE FLAMANVILLE 3 under construction 2 CHINA 2 units (TAISHAN 1&2) under construction 4 USA EPR technology selected by six utilities Design Certification Application rulemaking planned for 2012 1 + 1 FRANCE Second EPR project for EDF, GDF SUEZ, Total in Penly Possible 3 rd EPR TM project under discussion 10 4 PROSPECTS minimum The Netherlands, Czech Republic, Switzerland, Poland, Finland, Brazil, Canada and China ITALY ENEL and EDF decided to develop a project for the construction of 4 EPR reactors in Italy 2 + 4 INDIA Memorandum of Understanding with NPCIL for 2 EPR reactors at the Jaitapur site, up to 6 units possible Strategic alliance with Bharat Forge Framework agreement with TCE Consulting Engineers (Tata) for engineering services Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.23
be part of the AREVA supply chain and potentially participate in ~10 projects before the first Italy EPR comes online By 2020, ~10 EPRs are planned to be already online with current opportunities in: The UK The US France A unique business opportunity to ramp up your skills and increase your business before taking part in the Italian EPR construction Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.24
Summary 1 2 Become part of the EPR supply chain on numerous ongoing projects worldwide and build up your capabilities Leverage your capabilities and Certified Supplier status to build the EPR Italian fleet Success is in your hands Company management commitment Disseminate safety and quality cultures Relation based on trust and transparency Tavolo ENEL-CONFINDUSTRIA per la qualificazione delle imprese Roma 19 Gennaio 2010 p.25