Mohammad Alauddin Deputy Secretary Power Division Ministry of Power, Energy & Mineral Resources Govt. of the People s Republic of Bangladesh mohammad_alauddin4124@yahoo.com December 19, 2013
Total area of about 147,570 sq. km Between 20 34 & 26 38 North Latitude 88 01 & 92 41 East Longitude Population of 153.6 million with a growth rate of 1.37% [2011] GDP per capita US$ 838 (FY 2012-13 ) GDP Growth Rate 6.03 Source : Bangladesh Economic Review 2013. December 19, 2013
Power Sector: At a Glance Installed Capacity (MW) 10213 Electricity Growth 9% (FY-2013);12 % (FY-2012) Max. Generation (MW) 6,675 [12 July 13] Total Consumers (Million) 14.2 Transmission Lines (ckt km) 9, 300 Distribution Lines (km) 2,90,000 Per Capita Generation (kwh) 321 Access to Electricity 62%[including 7% RE] Source : Bangladesh Power Development Board[BPDB] 3
Present Generation Capacity (November 13) S L Source Installed Generation Capacity (MW) Sector 1. BPDB 4186 Public 2. APSCL 777 3. EGCB 622 4. NWPGCL 300 5. RPCL 77 Subtotal 5,962 58% 1. IPPs 1655 Private 2. 15 YR. Rental 167 3. 3/5 YR. Rental 1929 4. Power Import 500 Subtotal 4,251 Total 10,213 42% Source : BPDB 4
Net Generation in Bangladesh Net Energy Generation in GWh 45,000 40,000 35,000 30,000 25,000 20,000 15,000 10,000 5,000 883 681 1,031 1,202 1,256 1,387 1,538 1,817 2,016 2,236 2,529 2,885 3,261 3,768 4,302 4,560 5,308 6,214 6,759 7,345 7,857 8,450 8,746 9,295 10,266 10,901 11,243 12,194 13,638 14,739 16,255 17,445 18,458 20,302 21,408 22,978 23,268 24,946 26,533 29,247 31,355 35,118 38,229 0 1970-71 1972-73 1974-75 1976-77 1978-79 1980-81 1982-83 1984-85 1986-87 1988-89 1990-91 1992-93 1994-95 1996-97 1998-99 2000-01 2002-03 2004-05 2006-07 2008-09 2010-11 2012-13 Source : BPDB December 19, 2013
Installed Capacity 38,700 MW 30,000MW c 20,000MW 10,000MW Installed Capacity 7300 MW Oil 9% Coal 5% Gas 82% Installed Capacity 24000 MW Others 15% Oil 10% Coal 20% Gas 55% Others 15% Oil 10% Coal 50% Gas 25% Others including Renewable Energy 2010 2021 2030 Source: Power Sector Master Plan[PSMP] 2010
Primary Fuel Sources by 2030 Sl. No. Sources Capacity (MW) Probable Location (s) 1 Domestic Coal Imported Coal 11,250 8,400 North West Region at Mine Mouth Chittagong and Khulna 2 Domestic Gas/LNG 8,850 Gas -Near Load Centers LNG- Near Coastal Area 3 Nuclear 4,000 Rooppur 4 Regional Grid 3,500 Bahrampur - Bheramara, Silchar - Fenchuganj, Purnia-Bogra- Bongaigaon, Myanmar - Chittagong 5 Others (Oil, Hydro & Renewable) 2,700 Near Load Centers Total 38,700 Source: PSMP 2010
Fuel Diversity & Sustainable Supply of Fuel Private Sector Participation Harnessing Renewable Energy Resources Demand Side Management (DSM) & Energy Efficiency Improvement Program Regional Co-operation on Cross Border Power Trade December 19, 2013
Possible Regional Grid Interconnection PURNEA BARAPUKURIA BONGAIGAON BARAPUKURIA FENCHUGAN J SILCHAR FENCHUGANJ 500MW [2013-] 500MW [2018-] BAHARAMPUR BHERAMAR A BAHARAMPUR BHERAMARA MYANMAR CHITTAGONG
Bangladesh-India Grid Interconnection MoU on 11.01.2010 for co-operation in power sector. Grid Connectivity Exchange of Power Joint Technical Team proposed an interconnection between Bheramara & Baharampur. Establishment of 400 KV, 100 km double circuit line & back-to-back HVDC station at Bheramara. 10
December 19, 2013
Main Components (BD part) i) 27.35 km 400 kv double circuit transmission line ii) 400 kv Back-to-Back HVDC station at Bheramara iii) 4.5 km LILO of double circuit Ishurdi-Khulna 230kV line at Bheramara. Main Components (Indian part) i) 73.5 km 400 kv double circuit transmission line ii) 400 kv switching station at Baharampur. December 19, 2013
Project Cost (BD part) i) F. E = Tk 910.71 Crore[111.06 Million USD] (ADB) ii) L. C = Tk 669.12 Crore (GoB+PGCB) Total =Tk 1,579.83 Crore Project Cost (Indian part) Total = Rs 160.32 Crore December 19, 2013
400 kv Transmission Line (BD Part) Contract Signed : 30-Dec-2010 Contractor : Cobra, Spain Consultant : PGCIL, India Target of Completion : May, 2013 Actual Completion : 30 th June, 2013 Line Energization : 30 th August, 2013 December 19, 2013
Back-to-Back HVDC Station Contract Signed : March 29, 2011 Target of Completion : July, 2013 Test Power Flow : September 27, 2013 Inauguration : October 5, 2013 COD for 175 MW : October 5, 2013 COD for 500 MW: December 4, 2013 December 19, 2013
PPA PPA 1 : 250 MW (25 yrs. with delivery starting 2013) NVVN (NTPC trading arm) signed a PPA with BPDB in February 28, 2012. Round the clock power supply. Power allocation by GoI from discretionary share of NTPC projects. Tariff at regulated rate + trading margin + wheeling costs 16
PPA PPA 2 : 250 MW (3 yrs. with delivery starting in 2013) PTC India Ltd. signed a PPA with BPDB in November 14, 2013. Round the clock power supply. Tariff= Non-escalable capacity charge + Nonescalable energy charge 17
Expand energy development beyond boundaries. Link potential sources to markets. Facilitate investment to serve a regional market Lower operational costs & improve the supply mix. Address demand supply imbalance & improve reliability of supply Eventually contributes towards development of an Asian energy highway.