SAFE WORK METHOD STATEMENT OVERHEAD AND UNDERGROUND ELECTRICAL CABLES

Similar documents
WORKING IN THE VICINITY OF OVERHEAD AND UNDERGROUND ELECTRIC LINES

Presenter s Notes SLIDE 1. Before darkening the room, offer a welcome and overview. Begin by introducing the program and its topic:

Presenter s Notes SLIDE 1

Work safely around power lines.

Electrical Safety Slide Show Presenter s Notes

Guidelines when working near TasNetworks electrical assets

SAFETY FACT SHEETS. Electrical Hazards Safety Non Negotiable. G-HS-ST Electrical Hazards. G-HS-FS Version:1

Electricity Entity Requirements: Working Near Overhead and Underground Electric Lines

WORKING SAFELY NEXT TO WEST MIDLANDS METRO

STAY SAFE NEAR ELECTRICITY

Avoidance of Danger from Electricity Overhead Lines and Underground Cables

Close Approach to Power Lines. Close Approach to Power Lines v

Before darkening the room, offer a welcome and overview. Begin by introducing the program and its topic:

AVOIDING ELECTROCUTION HAZARDS

Procedure PR D Electrical Permits. Engineering Procedure Electrical Distribution Unit. Version 1.0. Date in Force: 4 November 2015

RSC-G-004-B Guidelines For The Design Of Section 3 3 ELECTRIC TRACTION SYSTEMS 2

ELECTRICAL SAFET Y FOR CONTRACTORS

7. Residential Single-Family and Duplex Buildings (Dwellings)

Table of provisions. Safety and technical requirements. Safeguarding persons working with conductors and electrical equipment

Private Overhead Electric Lines. Safety and Responsibility

Surface Regulations and Policies

ELECTRICAL SAFETY-RELATED WORK PRACTICES

5. Underground Requirements

Energized Electrical Work

SSC-JE STAFF SELECTION COMMISSION ELECTRICAL ENGINEERING STUDY MATERIAL. Estimation and Costing & Utilization of Electrical Energy

Comparison of Indian Electricity Rules, 1956 Vs CEA (Measures relating to Safety and Electric Supply) Regulations, 2010

OSH5063EP(PRS3607) Workplace and Work Equipment Hazard. Session 10. Lifting Operation

D9-3. No. WIRING DIAGRAM CONNECTIONS FOR UNDERGROUND SELF CONTAINED METERS JRH JED krich95 LINE LINE ABCN SOURCE SOURCE GROUND GROUND STUD STUD SOURCE

36CSR27 TITLE 36 LEGISLATIVE RULE BOARD OF COAL MINE HEALTH AND SAFETY SERIES 27 RULES AND REGULATIONS GOVERNING SURFACE AREAS

Unified requirements for systems with voltages above 1 kv up to 15 kv

7 Hazard assessment 8 Worker participation 9 Hazard elimination and control

ELECTRICAL INSPECTOR EXAMINATION 14 November 2015 QUESTION AND ANSWER BOOKLET Time Allowed: Three hours

Item L.1 Voltages 1. The consumer voltage must be between +10% and -10% of the nominal national voltage (nnv.)

Appalachian Power Company Policy No. 2 Cover Up Procedures. Policy Summary:

FATAL AND SEVERE RISK PROGRAM

Procedure PR D Definitions and Conventions for Electrical Safety. Engineering Procedure Electrical Distribution Unit. Version 1.

1 Clearheart Construction Co., Inc. Mobile Crane - Onshore MOBILE CRANES Cranes and derricks

Uncontrolled When Printed Document to be superseded on 01/12/2012 Superseded by GERT8000-HB15 Iss 2 published on 01/09/2012

Vehicle Operation Procedure HSE

For Conduit Inspections

While handling materials, employees must abide by the following requirements:

PRIVATELYOWNED POWER POLES AND POWERLINES

Control, Safe Use and Operation of Excavators, Loaders and Earth Moving Equipment

Title: Lifting Operations Involving Crane or Gantry Offshore

Electricity Safety (Installations) Regulations 2009

AURELIA LTD A59 EXCAVATOR 360 ABOVE 10 TONNES INC LIFTING TECHNICAL TEST THEORY CPCS Issue 09-Jul-2012

See NT POWERCOS , Classification Based On Service Size.

Concrete Delivery Requirements

PAGE 1 OF 5 HEALTH, SAFETY & ENVIRONMENTAL MANUAL PROCEDURE: S360 Overhead Cranes & Lifts Procedure REV 4.0 8/14/2012

Network Safeworking Rules and Procedures

OSHA Update. Electric Power Generation, Transmission and Distribution Standard (Part 1910 & 1926)

PROCEDURE. Revision: 1. Author: D Steel CONTENTS

SECTION 14: AERIAL LIFT PROGRAM

UNDERGROUND SERVICE. Items to consider. There will be charges from ComEd if you convert from overhead to underground service.

OVERHEAD & GANTRY CRANE / RIGGING

Solar PV General Introduction Guide for Electricians

UNDERGROUND SERVICES - SECONDARY

Network Safeworking Rules and Procedures

Construction and Connection of Street Light Assets

MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION

PROCEDURE. Operative Date: 22/12/2016 Department: HSEC. Revision: Author: D Steel CONTENTS

Module AC. AC electrified lines

MAINTENANCE WORK INSTRUCTION. Mech OFF Replace Head Pulley CVXXX

1. General Requirements

Powering Sydney s Future

SAFE USE AND HANDLING OF HOSES AND FLEXIBLE CONNECTIONS IN THE SOLVENTS INDUSTRY

Presenter s Notes SLIDE 1

Electrical Awareness for Construction Activities. Overhead Power Lines & Underground Cables

Safe Working on or near low voltage electrical installations & equipment

NEC 2011 Code Changes

Pentahead bolts See note 2. Conduit run as specified. Company facility. Refer to drawing SS8.6-2 or SS8.6-3 STANDARD SERVICE INSTALLATION

Working in Proximity to Overhead Power Lines

Plan Check Policies and Guidelines

First Responder Beware

Nanometrics Solar Power System

ADO-Aerial Apparatus Manipulative Skill Objectives PREVENTIVE MAINTENANCE

Technical Test Theory Excavator 360 above 10 tonnes A59

Excavator 360 above 10 Tonnes A59

Step 1. PLANNING FOR THE INSTALLATION TOOLS REQUIRED

190M. Medical ScopeMeter. Safety Information

Safe Work Instructions Tools and Equipment

Uncontrolled When Printed Supersedes GERT8000-DC Iss 2 on 01/03/2014. Module DC. GE/RT8000/DC Rule Book. DC electrified lines. Issue 3.

NETWORK FACILITIES WHS RISK PROFILE

Electrical. Earthing & Bonding. Installation Techniques. Learning Notes MODULE 2.2 UNIT PHASE:2

WPS SERVICE MANUAL. Section 7 Clearances. 7-1 Basic Electric Clearances - Services Miscellaneous Clearances Antenna Clearances...

Asset Maintenance Policy

JCP&L Verbatim Response to Middletown Township s Questions

ELECTRICIANS REGULATIONS EXAMINATION 23 November 2013 QUESTION AND ANSWER BOOKLET

DISCONNECT SWITCH REQUIREMENTS FOR DISTRIBUTED GENERATION CUSTOMERS

Code of Practice. For works on, near or adjacent to the Luas Tramway

Customer Requirements Pole Attachment Requirements for Telecommunications (non-rf)

SAFETY GUIDANCE MATERIAL

TEMPORARY ELECTRICAL SERVICE

Advice and safety instructions. for Trafikverket track areas

Chapter 5. Imagine That Engineering Inc. Assured Equipment Grounding Conductor Program (AEGCP) Ground Fault Circuit Interrupter (GFCI)

Control, Safe Use and Operation of Road-Rail Plant

2 x 25 kv ac / 1 x 25 kv ac Grounding and Bonding

Electrical Hazards in Construction

KD1E Range Potential Indicators

WORKERS COMPENSATION (OCCUPATIONAL HEALTH AND SAFETY) AMENDMENT ACT, 1998

Transcription:

SAFE WORK METHOD STATEMENT OVERHEAD AND UNDERGROUND ELECTRICAL CABLES NOTE: = Risk Rating befe controls implemented - = Risk Rating after controls are implemented Task - Contact will not be made with underground utilities (contact dial befe you dig) and use suitable utility locating devices OVERHEAD ELECTRIC LINES 1. Ensure wk is not conducted in close proximity to electrical power lines. Check f: - Overhead power lines (including high and low voltage distribution conducts - Single wire earth return (SWER) - Service cables to premises - Communications cables - Electrical transfmers (mounted - lower than cables) 2. Identify: - Befe wk commences in the vicinity of an energised electrical part, no go zones should be established. - Maximum range of equipment and how close equipment load can come to asset (known as design envelope) - Clearance distances f type of asset (***) - Type of asset/cabling (if in doubt contact electrical supplier) - Voltage level - Height of conduct at lowest point - Minimum distance between wires and ground - Degree of sag and sway *** Minimum Clearance zones: - High voltage electrical conducts = 2,000mm - Un-insulated low voltage conducts = 1,000mm - Insulated low voltage (between50v and 1,000 V) = 500mm - Communications cabling = 300mm WARNING: DO NOT ATTEMPT TO DIRECTLY MEASURE THE HEIGHT OF OVERHEAD ELECTRIC LINES. DO NOT USE CONDUCTIVE METALLIC OBJECTS OR MEASURING DEVICES SUCH AS METAL TAPE MEASURES FOR ESTIMATING THE HEIGHT OF OVERHEAD ELECTRIC LINES

No Go Zone Approval of the electricity supply authity A no go zone extends in all directions, not just sideways; it is all around the electrical part. A person should not enter a no go zone. The areas of a no go zone may vary, but it will always exist. A no go zone is the area around overhead electric lines electric parts that fms a safety envelope. A safety envelope is the space encapsulating an item of plant, including attachments such as rotating/flashing lights radio aerials, categised as: a design envelope - the space encapsulating all possible movements of the plant and any load attached under maximum reach, a transit envelope - the area encompassing the nmal height and width of a vehicle plant when travelling to from a wksite. No part of a person, hand tools, equipment any other materials held by a person, cranes, vehicles items of mobile operating plant including the load, controlling ropes and any other accessies may cross into the no go zone while the electrical part is energised without the written approval of the electricity supply authity. This approval should be made available at the wksite.

Possible Safety Personal Injury: - Electric shock No go zones apply whenever carrying out wk operating plant (f example tip truck, crane, elevating wk platfm, concrete pumping truck), around an energised electrical part and the risk cannot be eliminated. Figure 1: Distance that should be assessed f each wksite In general: - 3m above, either side and below power lines is No Go Zone. - Between 3-6.4m of power lines a Spotter is required. - Further than 6.4m of power lines is open area - No wk to be conducted within 10m radius of SWER transfmer No wk to be conducted within Minimum Clearance Zones without written permission from power supplier and Spotter Wk outside Minimum Clearance Zone, but still in No Go Zones, site-specific SWMS to be developed and Spotter required. Note: Spotter is not required where wk is 6.4m from power line, but design envelope reaches into No Go Zone if: - Wk is designed so no part of machinery load enters within 6.4m - Documented site-specific SWMS is developed and responsible persons assigned to oversee the SWMS

3. Implement suitable controls. Examples: - Relocation of cables - Disconnection of power supply (evidence must be obtained from power supplier) WARNING: EVEN IF IT IS BELIEVED THAT THE SUPPLY HAS BEEN ISOLATED, IT MUST BE ASSUMED THAT ALL CONDUCTORS AND COMPONENTS ARE ENERGISED UNTIL AN ACCESS AUTHORITY OR OTHER FORM OF WRITTEN DOCUMENTATION HAS BEEN RECEIVED FROM THE ELECTRICITY SUPPLY COMPANY - Use equipment with smaller design envelope Tempary physical height barriers to limit loads - Longitudinal fencing height markers to indicate extent of allowed movement - Signage - Use of Spotter - establish effective communication system with operat. Note: A Spotter should: be used whenever the wk activity is likely to be perfmed in the authised person zone be positioned at a suitable location to effectively observe both the overhead electric lines and plant be able to immediately and effectively communicate with the operat of the crane mobile plant, other persons if required ensure that all persons stay outside the specified approach distance (unless perfming a rescue in accdance with approved procedures carrying out a specific task that is described in the safe wk method statement, f example a crane dogman holding a non-conductive tag line attached to a load suspended from a mobile crane) not carry out any other wk while acting as a safety observer, which includes the passing of tools, equipment materials directly to the personnel perfming the wk not observe me than one wk activity at a time monit the wk activity being carried out and have the authity to suspend the wk at any time.

LOW VOLTAGE OVERHEAD ELECTRIC LINES NEAR BUILDINGS AND STRUCTURES Electric lines are any low voltage overhead service lines, including: electricity supply authity s low voltage overhead lines including service lines low voltage overhead lines fming part of consumers installations insulated low voltage aerial conducts and associated electrical equipment that are connected from the point of supply (either the overhead electric pole located on the street the consumer s boundary) and terminated on the consumer s building, pole structure at the point of attachment insulated low voltage aerial consumers mains and associated electrical equipment fming part of the consumer s electrical installation. 1. Ensure wk is not conducted in close proximity to electrical power lines. Check f: - Overhead power lines (including high and low voltage distribution conducts - Single wire earth return (SWER) - Service cables to premises - Communications cables - Electrical transfmers (mounted - lower than cables) Figure 14: Low Voltage Overhead Service Lines

2. Identify Approach Distances Table 4 provides approach distances f unauthised persons: perfming min building wk in the vicinity of low voltage overhead service lines, (including hand tools held by a person) operating cranes (and their loads) and items of mobile plant in the vicinity of low voltage overhead service lines handling metal materials in the vicinity of overhead service lines (f example scaffolding, roofing materials and guttering) handling non-conductive materials in the vicinity of overhead service lines (f example timber, plywood, PVC pipes and guttering) driving operating a vehicle under overhead service lines. The approach distance specified in Table 4 below is based on the fact that the design transit envelope of the vehicle does not allow any part of the vehicle to come closer than the 0.6 metre approach distance specified. Table 4: Approach distances f wk in the vicinity of low voltage overhead service lines. Hand held tools Unauthised Persons (metres) Operation of crane mobile plant Handling of metal materials (e.g. scaffolding, roofing, guttering, pipes, etc) Handling of nonconductive materials (e.g. timber, plywood, PVC pipes and guttering, etc) Driving operating vehicle 3.0 3.0 4.0 1.5 0.6

If the voltage of the line cannot be determined, the line should be deemed as a high voltage line Examine an insulated low voltage overhead line f visible defects to ensure that the insulation is intact with no tears, cracks other physical defects There are no exposed energised parts anywhere on the line If you cannot determine whether the line is effectively insulated, the line should be treated as being bare. 3. Implement suitable controls. Examples: - Relocation of cables - Disconnection of power supply (evidence must be obtained from power supplier) WARNING: EVEN IF IT IS BELIEVED THAT THE SUPPLY HAS BEEN ISOLATED, IT MUST BE ASSUMED THAT ALL CONDUCTORS AND COMPONENTS ARE ENERGISED UNTIL AN ACCESS AUTHORITY OR OTHER FORM OF WRITTEN DOCUMENTATION HAS BEEN RECEIVED FROM THE ELECTRICITY SUPPLY COMPANY - Use equipment with smaller design envelope Tempary physical height barriers to limit loads - Longitudinal fencing height markers to indicate extent of allowed movement - Signage - if wk has to be carried out in close proximity to the point of attachment and the electricity cannot be isolated, arrange f the electricity supply authity to fit insulated matting and tiger tails at the point of attachment and over the overhead service lines befe the wk commences - Use of Spotter - establish effective communication system with operat

UNDERGROUND ELECTRIC CABLES - Contact Dial Befe You Dig - If it is not known whether cables, conduits, equipment situations fm an electrical safety risk, you should either assume that the risk exists, have a qualified person investigate and rept. - Use locat - never assume that the plans you receive contain exact location of underground assets - Befe digging water jetting near a high voltage electrical cable, check with SA Power Netwks on 1300 650 014 ElectraNet on 1800 243 853 if there are any special conditions that apply - Paint location marks on ground - Pot hole dig carefully by hand to expose underground assets befe using any excavation heavy digging. Sometimes several potholes will need to be dug manually to determine the exact location because of deviations in the cable alignment. - Always use insulated hand tools (eg spades and shovels, preferably with curved edges). Do not throw spike into the ground. Ease in with gentle foot pressure and dig with the blade of the shovel parallel to the cable route - Arrange f water jetting high velocity air jets incpating vacuum removal if necessary

- Where possible the electricity supply to the underground cable should be isolated befe digging - If you need to isolate a SA Power Netwks cable you will need to apply f a permit. The permit will ensure the powerlines will be turned off until the permit is returned. To apply, contact the SA Power Netwks line on 1300 650 014. Private Property - If excavating on private property, contact the owner occupier of the premises about buried cables befe starting wk. - Look around the property look f such things as direction of overhead cables coming into the property, sewer and IP connections and gas meter plans - Use locat Operation Once an asset location has been determined excavation may proceed - Do not commence mechanical excavation without a dedicated spotter - Visual and verbal contact must be maintained between Operat and Spotter at all times during operation. - Use extreme care dig slowly - Excavate alongside the asset rather than directly above it, where possible - If marker tape is found, stop mechanical excavation. - Final exposure of the asset by hizontal hand digging Always use insulated hand tools (eg spades and shovels, preferably with curved edges). Do not throw spike into the ground. Ease in with gentle foot pressure and dig with the blade of the shovel parallel to the cable route

Emergency Procedures - Numerous - Develop and implement an emergency response plan f the site if possible. Include: - Assembly points - Communication /Responsible persons - Emergency contacts - First Aid and Rescue procedures Ensure documented/rehearsed procedures implemented f response after contacting live electricity other utilities. Ensure all relevant persons trained in procedures.