PROJECTS $500K AND OVER FOR 2012

Similar documents
EMERGING REQUIREMENTS

PROJECTS $500K AND OVER FOR 2014

TORONTO TRANSIT COMMISSION REPORT NO.

Mr. Vince Mauceri General Manager Transportation Operations and Technology

Scarborough Transit Planning

TORONTO TRANSIT COMMISSION REPORT NO.

TRANSFORMING THE WAY OUR REGION MOVES

CONNECTING THE REGION

CREATING CONNECTIONS IN WATERLOO REGION

CREATING CONNECTIONS IN THE CITY OF KITCHENER

CREATING CONNECTIONS IN THE CITY OF WATERLOO

TORONTO TRANSIT COMMISSION REPORT NO.

The Regional Transportation Plan PLAN BUILD OPERATE

CREATING CONNECTIONS IN THE TOWN OF NEWMARKET

5 RAPID TRANSIT NETWORK PLAN PRINCIPLES, METROLINX BUSINESS CASE, AND ALTERNATIVE FINANCE AND PROCUREMENT ANALYSIS UPDATE

Developing Toronto's Transit Network Plan: Phase 1

Developing Toronto s Transit Network Plan to 2031

Spadina Subway Extension Downsview Station to Steeles Avenue Environmental Assessment

EMERGING REQUIREMENTS

EGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT)

Metrolinx Electrification Project

CONNECTING THE REGION

Location Concept Plan Amendment Recommendation Approved 2011 Concept Plan

APPENDIX 6: Transportation Modelling Considerations City of Toronto, February 2014

Developing Toronto s Transit Network Plan to Public Information Meeting June 21, 2016

Attachment 1 - City of Toronto Priority Projects for Phase 1: Federal Public Transit Infrastructure Fund (PTIF)

Rail alignment and benefits (rab) study

5 VAUGHAN METROPOLITAN CENTRE AND SURROUNDING AREAS TRANSPORTATION STUDY PROGRESS

Metrolinx: Transforming the Way We Move - A Network Wide Approach. Greg Percy, Chief Operating Officer November 1, 2016

CREATING CONNECTIONS IN EAST GWILLIMBURY

Issues Facing the Panel

Update on Community or Heritage Rail Project (Project Manager Services) The Engineering Department recommends that Council:

Regional Express Rail: Kipling Station Project Update. Ryah Kazman, Community Relations Specialist Metrolinx

O-Train Confederation Line Stage 1

TORONTO TRANSIT COMMISSION REPORT NO.

Opportunities for Improved Bus Service on Finch Avenue 27 April 2011

welcome to the BC Hydro community open house

Waterfront Transit Reset Phase 2 Study. Public Information & Consultation Meetings September 18 & 26, 2017

2.1 TRANSIT VISION 2040 FROM VISION TO ACTION. Expand regional rapid transit networks STRATEGIC DIRECTION

YRRTC Business Plan

STH 60 Northern Reliever Route Feasibility Study Report

STREET LIGHTING AND ELECTRICAL SYSTEM UNDERGROUNDING. Underground Vault

Functional Design Presentation At-Grade Section: Don Mills to Ionview Please review the presentation and complete the survey. February 26, 2013 to

CREATING CONNECTIONS IN RICHMOND HILL

PROJECT BACKGROUND 3

Western ND Meeting. February 19, 2014 Grant Levi, NDDOT Director

EGLINTON CROSSTOWN LIGHT RAIL TRANSIT (LRT) PLEASE SIGN IN

STREET LIGHTING AND ELECTRICAL SYSTEM UNDERGROUNDING

GTA West Corridor Planning and EA Study Stage 1

Wentzville Parkway South Phase 2 & 2A

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

Energy Technical Memorandum

Welcome. Green Line in Your Community

Presentation A Blue Slides 1-5.

Proposed Program of Interrelated Projects

TORONTO TRANSIT COMMISSION REPORT NO.

Green Line LRT: Beltline Recommendation Frequently Asked Questions

Ottawa LRT Stage 2. McKellar Park Information Session

PUBLIC INFRASTRUCTURE PROJECTS

TRAFFIC IMPACT STUDY DERRY GREEN CORPORATE BUSINESS PARK MILTON SECONDARY PLAN MODIFICATION

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

San Rafael Transit Center. Update. Golden Gate Bridge, Highway & Transportation District Transportation Committee of the Board of Directors

RELIEF LINE PRELIMINARY BENEFITS CASE ANALYSIS. November 2012

Mississauga Transit 2009 Budget

The Capital Grid Project:

The City of Toronto s Transportation Strategy July 2007

CREATING CONNECTIONS IN AURORA

CITY OF LONDON STRATEGIC MULTI-YEAR BUDGET ADDITIONAL INVESTMENTS BUSINESS CASE # 6

Construction Staging Area 4 Avenue Road

CRITICAL ISSUES DOWNTOWN CONTINGENCY PORTFOLIO

GO RAIL NETWORK ELECTRIFICATION TRANSIT PROJECT

Eglinton East LRT Project Update and Next Steps

Submission to Greater Cambridge City Deal

TORONTO TRANSIT COMMISSION REPORT NO.

CPG is pleased to report the following accomplishments this quarter:

Appendix F-1 Description of the Long-Term Alternatives

Transit City Etobicoke - Finch West LRT

EX29.1 REPORT FOR ACTION. SmartTrack Project Update and Next Steps SUMMARY

FREQUENTLY ASKED QUESTIONS

Mississauga Bus Rapid Transit Preliminary Design Project

2 MAJOR MACKENZIE DRIVE WEST JOG ELIMINATION AT HUNTINGTON ROAD CITY OF VAUGHAN

GO RAIL NETWORK ELECTRIFICATION TPAP FAQ LIST Updated May 2016

Attachment 5 Eglinton West LRT Planning and Technical Update

Develop ground transportation improvements to make the Airport a multi-modal regional

TRAVEL DEMAND FORECASTS

Rail alignment and benefits (rab) study

Chapter 11 Route Window NE10 Gidea Park station. Transport for London

City of Palo Alto (ID # 6416) City Council Staff Report

Planning of the HSR Network

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Yonge Relief Network Study (YRNS)

Benchmarking, Planning, and Promoting Transit- Oriented Intensification in Rapid Transit Station Areas: Project Key Indicators March 2016

Welcome to Open House #5 Scarborough Rapid Transit

A case study Showing a Specific Electric and Logistical Efforts to Restore Power following Super Storm Sandy

Link LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion


CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE

East San Fernando Valley Transit Corridor. Information Session, October 10, 2017

STRATEGIC PRIORITIES AND POLICY COMMITTEE MAY 5, 2016

F.P.O. Yonge subway extension: concept plan and profile. Langstaff/Longbridge. Royal Orchard Station. Clark Station. Steeles Station.

Transcription:

EB-0-0 Page of PROJECTS $00K AND OVER FOR 0 EXTERNALLY INITIATED PLANT RELOCATIONS PORTFOLIO Table : Externally Initiated Plant Relocations Projects Estimate Estimated Cost Project Title Number ($ Millions) 0 Relocate BT/BT/BT/BT/BT. TTC Spadina Subway. 0 Relocate Feeders Serving Dafoe MS. Civil Work on East Liberty West of Bathurst. 0 Relocate AT/AT/AT.0 0 Relocate AT/AT/AT/AT.0 MTO Keele Bridge Rehab 0. Total Cost 0.

EB-0-0 Page of Portfolio: Externally Initiated Plant Relocations Project Title: Relocate BT/BT/BT/BT/BT Project Number: 0 Project Year: 0 Estimate Cost: $,, PROJECT DESCRIPTION Objective: The purpose of this project is to relocate five kv feeders from the Strachan Avenue rail crossing, in order to maintain the electrical capacity for the surrounding area. This will enable GO Transit and/or Metrolinx to perform their required grade separation at Strachan Avenue. This project is one of four electrical relocation projects required for the grade separation at Strachan Avenue. 0 Scope: The scope of work for this project is to relocate the five kv feeders of BT, BT, BT, BT and BT. These feeders cross the existing Strachan Avenue rail crossing to the new rail crossing to be constructed approximately 00m west at the northwest corner of Western Battery Road. It will also involve installing approximately.km of new cable that would be re-connected to existing kv feeders through new laterals and transition splices. DISTRICT DISTRICT NEIGHBOURHOOD STATION(S) FEEDER(S) TORONTO STRACHAN STRACHAN TS BT, BT, BT, BT, BT

EB-0-0 Page of JUSTIFICATION 0 Project Background GO Transit is creating a rail link to Pearson Airport, part of the Georgetown South Service Expansion. Within this project there are over separate locations where THESL infrastructure crosses the tracks. Of these locations, the Strachan Avenue underground crossing is the largest. THESL has a total of 0 ducts crossing under the railway at Strachan Avenue. These ducts are separated into three separate duct runs, one is a x duct bank and the other two are x duct banks. Within these ducts, there are five kv feeders and sixteen.kv feeders for a total of feeders crossing under the railway. 0 GO Transit has plans to lower the tracks at Strachan Avenue five meters, while raising the road two meters, allowing trains to run at faster speeds on the route. This would require all utilities crossing the tracks, including the five kv feeders identified in this project, to relocate elsewhere. GO plans to have this project completed in time for the Pan Am games in the summer of 0, and has asked all utilities to be out of the crossing area by mid 0. THESL has requested it feeders on the completed bridge over the new rail crossing on Strachan Avenue in 0. Since all THESL infrastructure installed through the existing rail crossing is on GO and/or Metrolinx land, the existing rail crossing agreement applies and therefore all THESL infrastructure is to be removed at the utilities own cost. Alternatives A number of alternatives to relocate the five kv feeders, in addition to all other THESL feeders were reviewed, including relocating to overhead and using other routes to cross

EB-0-0 Page of the tracks. Relocating the feeders overhead was not practical because there are feeders crossing at Strachan Avenue, which would result in a number of poles lines in the middle of a construction zone. Also, some of the underground feeders crossing at Strachan Avenue are -wire feeders and cannot be moved from underground to overhead. The other option reviewed was alternate crossing locations at Bathurst Street and Atlantic Avenue. Both of these routes involved extensive civil work and longer cable detours, which would have resulted in higher costs to THESL. 0 Benefits Maintains the current customers and existing capacity supply Establishes a new crossing under the GO tracks IMPACT OF DEFERRAL If this work were to be deferred, it would negatively impact the staging of the GO Transit construction at Strachan Avenue, which would subsequently delay the completion of the Air Rail Link for the 0 Pan Am Games. THESL would lose the window of opportunity to better coordinate with appropriate utilities and agencies on infrastructure work.

EB-0-0 Page of Portfolio: Externally Initiated Plant Relocations Project Title: TTC Spadina Subway Project Number: Project Year: 0 Estimate Cost: $,0, PROJECT DESCRIPTION Objective: The purpose of this project is to assist the TTC in the construction of the Toronto-York Spadina Subway Extension ( TYSSE ) through the relocation of THESL infrastructure, in conflict with the proposed construction for the TYSSE. 0 Scope: The scope of work for this project is to cover a number of projects associated with the TYSSE, as well as any other projects anticipated to arise over this time. As such, work to be addressed through this project include relocations for Finch West Station, Sheppard West Station, York University Subway Station, Steeles West Station and any other locations where the Tunnel Boring Machines will come above ground, as well as relocation or temporary wire removals where required. DISTRICT DISTRICT NEIGHBOURHOOD STATION(S) FEEDER(S) NORTH YORK KEELE N/A N/A

EB-0-0 Page of JUSTIFICATION Project Background The TYSSE is intended to provide a critical extension for the existing TTC subway system across the municipal boundary between the City of Toronto and The Regional Municipality of York. This project is funded through various levels of federal, provincial and municipal government agencies. Environmental assessments for this project in 00 and construction started in 00. Lastly, all costs incurred during this project are paid 00% by the TTC. 0 Alternatives At each project location, the needs and requirements from the TTC and THESL are reviewed to determine what options are available. These alternatives include various relocation routes as well as the possibility of supporting and protecting THESL infrastructure. Benefits Maintains the current load configuration 0 IMPACT OF DEFERRAL If this work were to be deferred, it would negatively impact the staging of the TYSSE and possibly delay the proposed operational date in 0. Moreover, delays in funding would also result in a loss of resources and effort, as there is work currently ongoing or has been completed. Lastly, THESL would also lose the window of opportunity to better coordinate with appropriate utilities and agencies on infrastructure work.

EB-0-0 Page of Portfolio: Externally Initiated Plant Relocations Project Title: Relocate Feeders Serving Dafoe MS Project Number: 0 Project Year: 0 Estimate Cost: $,,0 PROJECT DESCRIPTION Objective: The purpose of this project is to relocate the four.kv feeders that supply Dafoe MS from the Strachan Avenue rail crossing, in order to maintain the electrical capacity for the surrounding area. This will enable GO Transit and/or Metrolinx to perform their required grade separation at Strachan Avenue. 0 Scope: The scope of work for this project is to relocate the four.kv feeders of AT, AT, AT and AT. These feeders cross the existing Strachan Avenue rail crossing to the new rail crossing to be constructed approximately 00m west at the northwest corner of Western Battery Road. It will also involve installing approximately.km of new cable that would be re-connected to existing.kv feeders through transition splices to continue service Dafoe MS. DISTRICT DISTRICT NEIGHBOURHOOD STATION(S) FEEDER(S) TORONTO STRACHAN STRACHAN TS AT, AT, AT, AT

EB-0-0 Page of JUSTIFICATION 0 Project Background GO Transit is creating a rail link to Pearson Airport, part of the Georgetown South Service Expansion. Within this project there are over separate locations where THESL infrastructure crosses the tracks. Of these locations, the Strachan Avenue underground crossing is the largest. THESL has a total of 0 ducts crossing under the railway at Strachan Avenue. These ducts are separated into three separate duct runs, one is a x duct bank and the other two are x duct banks. Within these ducts, there are five kv feeders and sixteen.kv feeders for a total of feeders crossing under the railway. 0 GO Transit has plans to lower the tracks at Strachan Avenue five meters, while raising the road two meters, allowing trains to run at faster speeds on the route. This would require all utilities crossing the tracks, including the four.kv feeders identified in this project, to relocate elsewhere. GO plans to have this project completed in time for the Pan Am games in the summer of 0, and has asked all utilities to be out of the crossing area by mid 0. THESL has requested it feeders on the completed bridge over the new rail crossing on Strachan Avenue in 0. Since all THESL infrastructure installed through the existing rail crossing is on GO and/or Metrolinx land, the existing rail crossing agreement applies and therefore all THESL infrastructure is to be removed at the utilities own cost. Alternatives A number of alternatives to relocate the four.kv feeders, in addition to all other THESL feeders were reviewed, including relocating to overhead and using other routes to

EB-0-0 Page of cross the tracks. Relocating the feeders overhead was not practical because there are feeders crossing at Strachan Avenue, which would result in a number of poles lines in the middle of a construction zone. Also, some of the underground feeders crossing at Strachan Avenue are -wire feeders and cannot be moved from underground to overhead. The other option reviewed was alternate crossing locations at Bathurst Street and Atlantic Avenue. Both of these routes involved extensive civil work and longer cable detours, which would have resulted in higher costs to THESL. 0 Benefits Maintains the current customers and existing capacity supply Establishes a new crossing under the GO tracks IMPACT OF DEFERRAL If this work were to be deferred, it would negatively impact the staging of the GO Transit construction at Strachan Avenue, which would subsequently delay the completion of the Air Rail Link for the 0 Pan Am Games. THESL would lose the window of opportunity to better coordinate with appropriate utilities and agencies on infrastructure work.

EB-0-0 Page 0 of Portfolio: Externally Initiated Plant Relocations Project Title: Civil Work on East Liberty West of Bathurst Street Project Number: Project Year: 0 Estimate Cost: $,, PROJECT DESCRIPTION Objective: The purpose of this project is to construct the required civil infrastructure so that all existing THESL infrastructure currently crossing the Strachan Avenue rail crossing can be relocated, in order to maintain the electrical capacity for the surrounding area. This will enable GO and/or Metrolinx to perform their required grade separation at Strachan Avenue. 0 0 Scope: The project has two parts, one north of the new railing crossing being constructed 00m west of Strachan Avenue and one south of the new rail crossing. The scope of work for this project, south of the new rail crossing, is to build new civil infrastructure to accommodate the necessary relocation of Liberty Village. It would involved the installation of approximately 00m of new civil infrastructure including concrete encased ducts and approximately cable chambers to be installed in this area. To the north of the new rail crossing, the scope of work for this project is to install approximately cable chambers are to be rebuild and 00m of the existing duct bank on Douro Street will be expanded from a x duct size to the standard x duct.

EB-0-0 Page of DISTRICT DISTRICT NEIGHBOURHOOD STATION(S) FEEDER(S) TORONTO STRACHAN N/A N/A JUSTIFICATION Project Background GO Transit is creating a rail link to Pearson Airport, part of the Georgetown South Service Expansion. Within this project, there are over separate locations where THESL infrastructure crosses the tracks. Of these locations, the Strachan Avenue underground crossing is the largest. 0 0 THESL has a total of 0 ducts crossing under the railway at Strachan Avenue. These ducts are separated into three separate duct runs, one is a WH duct backs and the other two are WH duct banks. Within these ducts, there are five kv feeders and sixteen.kv feeders, for a total of feeders crossing under the railway. GO Transit has plans to lower the tracks to run at faster speeds on the route. This would require all utilities crossing the tracks to relocate elsewhere on a temporary or permanent basis. GO plans to have this project completed in time for the Pan Am games in the summer of 0, and has asked all utilities to be out of the crossing area by mid 0. THESL has requested it feeders on the completed bridge over the new rail crossing on Strachan Avenue in 0. Since all THESL infrastructure installed through the existing rail crossing is on GO and/or Metrolinx land, the existing rail crossing agreement applies and therefore all THESL infrastructure is to be removed at the utilities own cost.

EB-0-0 Page of 0 Alternatives A number of alternatives were reviewed including relocating to overhead and using other routes to cross the tracks. Relocating the feeders overhead was not practical because there are feeders crossing at Strachan Avenue, which would result in a number of pole lines in the middle of a construction zone. Also, some of the underground feeders crossing at Strachan Avenue are -wire feeders and are not able to be moved from underground to overhead. The other main alternative reviewed was alternate crossing location at Bathurst Street and Atlantic Avenue. Both of these routes involved extensive civil work and longer cable detours, which would have resulted in higher costs to THESL. Benefits Maintains the current customer and supply capacity Establishes a new crossing under the GO tracks 0 IMPACT OF DEFERRAL If this work were to be deferred, it would negatively impact the staging of the GO Transit construction at Strachan Avenue, which would subsequently delay the completion of the Air Rail Link for the 0 Pan Am Games. THESL would lose the window of opportunity to better coordinate with appropriate utilities and agencies on infrastructure work.

EB-0-0 Page of Portfolio: Externally Initiated Plant Relocations Project Title: Relocate AT/AT/AT Project Number: 0 Project Year: 0 Estimate Cost: $,00, PROJECT DESCRIPTION Objective: The purpose of this project is to relocate the three.kv feeders from the Strachan Avenue rail crossing, in order to maintain the electrical capacity for the surrounding area. This project is one of four electrical relocation projects required for the grade separation at Strachan Avenue. 0 Scope: The scope of work for this project is to relocate the three.kv feeders of AT, AT and AT that cross the existing Strachan Avenue rail crossing to the new rail crossing to be constructed approximately 00m west at the northwest corner of Western Battery Road. It will also involve installing approximately.km of new cable that would be reconnected to existing.kv feeders through transition splices. DISTRICT DISTRICT NEIGHBOURHOOD STATION(S) FEEDER(S) TORONTO STRACHAN STRACHAN TS AT, AT, AT

EB-0-0 Page of JUSTIFICATION 0 Project Background GO Transit is creating a rail link to Pearson Airport, part of the Georgetown South Service Expansion. Within this project, there are over separate locations where THESL infrastructure crosses the tracks. Of these locations, the Strachan Avenue underground crossing is the largest. THESL has a total of 0 ducts crossing under the railway at Strachan Avenue. These ducts are separated into three separate duct runs, one is a x duct backs and the other two are x duct banks. Within these ducts, there are five kv feeders and sixteen.kv feeders, for a total of feeders crossing under the railway. 0 GO Transit has plans to lower the tracks at Strachan Avenue five meters, while raising the road two meters, allowing trains to run at faster speeds on the route. This would require all utilities crossing the tracks, including the three.kv feeders identified in this project, to relocate elsewhere. GO plans to have this project completed in time for the Pan Am games in the summer of 0, and has asked all utilities to be out of the crossing area by mid 0. THESL has requested it feeders on the completed bridge over the new rail crossing on Strachan Avenue in 0. Since all THESL infrastructure installed through the existing rail crossing is on GO and/or Metrolinx land, the existing rail crossing agreement applies and therefore all THESL infrastructure is to be removed at the utilities own cost. Alternatives A number of alternatives to relocate the three.kv feeders in addition to all other THESL feeders were reviewed including relocating to overhead and using other routes to

EB-0-0 Page of cross the tracks. Relocating the feeders overhead was not practical because there are feeders crossing at Strachan Avenue, which would result in a number of pole lines in the middle of a construction zone. Also, some of the underground feeders crossing at Strachan Avenue are -wire feeders and are not able to be moved from underground to overhead. The other main alternative reviewed was alternate crossing location at Bathurst Street and Atlantic Avenue. Both of these routes involved extensive civil work and longer cable detours, which would have resulted in higher costs to THESL. 0 Benefits Maintain the current customer and supply capacity Establishes a new crossing under the GO tracks IMPACT OF DEFERRAL If this work were to be deferred, it would negatively impact the staging of the GO Transit construction at Strachan Avenue, which would subsequently delay the completion of the Air Rail Link for the 0 Pan Am Games. THESL would lose the window of opportunity to better coordinate with appropriate utilities and agencies on infrastructure work.

EB-0-0 Page of Portfolio: Externally Initiated Plant Relocations Project Title: Relocate AT/AT/AT/AT Project Number: 0 Project Year: 0 Estimate Cost: $, PROJECT DESCRIPTION Objective: The purpose of this project is to reconfigure and relocate the four.kv feeders from the Strachan Avenue rail crossing, in order to maintain the electrical capacity for the surrounding area. This project is one of four electrical projects required for the grade separation at Strachan. 0 Scope: The scope of work for this project is to reconfigure and transfer customers on the.kv feeders of AT and AT. It would also involve relocating feeders AT and AT from the existing Strachan Avenue rail crossing to the new rail crossing to be constructed approximately 00m west at the northwest corner of Western Battery Road. As such, approximately.km of new cable is to be installed and reconnected to the existing.kv feeders through transition splices. DISTRICT DISTRICT NEIGHBOURHOOD STATION(S) FEEDER(S) TORONTO STRACHAN STRACHAN TS AT, AT, AT, AT

EB-0-0 Page of JUSTIFICATION 0 Project Background GO Transit is creating a rail link to Pearson Airport, part of the Georgetown South Service Expansion. Within this project, there are over separate locations where THESL infrastructure crosses the tracks. Of these locations, the Strachan Avenue underground crossing is the largest. THESL has a total of 0 ducts crossing under the railway at Strachan Avenue. These ducts are separated into three separate duct runs, one is a x duct backs and the other two are x duct banks. Within these ducts, there are five kv feeders and sixteen.kv feeders, for a total of feeders crossing under the railway. 0 GO Transit has plans to lower the tracks at Strachan Avenue five meters, while raising the road two meters, allowing trains to run at faster speeds on the route. This would require all utilities crossing the tracks, including the four.kv feeders indentified in this project, to relocate elsewhere. GO plans to have this project completed in time for the Pan Am games in the summer of 0, and has asked all utilities to be out of the crossing area by mid 0. THESL has requested it feeders on the completed bridge over the new rail crossing on Strachan Avenue in 0. Since all THESL infrastructure installed through the existing rail crossing is on GO and/or Metrolink land, the existing rail crossing agreement applies and therefore all THESL infrastructure is to be removed at the utilities own cost. Alternatives A number of alternatives to relocate the four.kv feeders in addition to all other THESL feeders were reviewed including relocating to overhead and using other routes to

EB-0-0 Page of cross the tracks. Relocating the feeders overhead was not practical because there are feeders crossing at Strachan Avenue, which would result in a number of pole lines in the middle of a construction zone. Also, some of the underground feeders crossing at Strachan Avenue are -wire feeders and are not able to be moved from underground to overhead. The other main alternative reviewed was alternate crossing location at Bathurst Street and Atlantic Avenue. Both of these routes involved extensive civil work and longer cable detours, which would have resulted in higher costs to THESL. 0 Benefits Maintain the current customer and supply capacity Establishes a new crossing under the GO tracks IMPACT OF DEFERRAL If this work were to be deferred, it would negatively impact the staging of the GO Transit construction at Strachan Avenue, which would subsequently delay the completion of the Air Rail Link for the 0 Pan Am Games. THESL would lose the window of opportunity to better coordinate with appropriate utilities and agencies on infrastructure work.

EB-0-0 Page of Portfolio: Externally Initiated Plant Relocations Project Title: MTO Keele Bridge Rehabilitation Project Number: Project Year: 0 Estimate Cost: $, PROJECT DESCRIPTION Objective: The purpose of this project is to maintain the existing crossing on Keele Street across the 0 Highway. 0 Scope: The scope of work for this project is to relocate 0m of an existing duct structure along with cable chambers around and on the Keele Street Bridge to a new alignment under Highway 0. The new ducts will be diverted under the 0 using directional drilling. It would also involve the installation of an additional cable chambers, and during the relocation, THESL plans to increase the number of ducts crossing the 0 from to ducts. The additional ducts will provide greater operational flexibility and allow for future expansion across the 0, with only a minimal increase in the material costs of the project, as the labour requirements to install either or ducts would remain the same. DISTRICT DISTRICT NEIGHBOURHOOD STATION(S) FEEDER(S) ETOBICOKE KEELE FAIRBANKS II TS NYM

EB-0-0 Page 0 of JUSTIFICATION 0 Project Background The Ontario Ministry of Transportation ( MTO ) is rehabilitating the Keele Street Bridge over Highway 0. An order was issued to all utilities to remove all their infrastructures off the bridge. MTO is allowing all the utilities to relocate their plants under Highway 0. At the same time, MTO is also widening and reconfiguring the traffic lights along Keele Street south of Highway 0, which accounts for approximately 0 meters of the duct relocation. This project falls under the Public Service Works on Highways Act, which states that the MTO will cover 0% of the cost for labour and equipment while Toronto Hydro covers the other 0% of the costs for labour and equipment as well as 00% of the material costs. Alternatives The alternative of eliminating the 0 crossing at Keele Street and crossing at an alternative location were both considered. These were not acceptable alternatives as the feeder tie at Keele Street could not be lost, and other crossing locations would be too far away to effectively tie in. Also, the possibility of relocating overhead across the 0 Highway was not an acceptable proposal to the MTO. 0 Benefits Maintains the current feeder ties Increases duct capacity crossing Highway 0 and Keele Street to allow for operational flexibility and future expansion IMPACT OF DEFERRAL If this project were to be deferred, an integral feeder tie would be lost. Also, this would also delay rehabilitation of the Keele Street Bridge over Highway 0. Lastly, if this

EB-0-0 Page of work were to be deferred, THESL would lose the opportunity to build and enhance system infrastructure to support future operational needs.