Identification of Acceptable Restoration Strategies

Similar documents
Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Control System for a Diesel Generator and UPS

A STUDY ON ENERGY MANAGEMENT SYSTEM FOR STABLE OPERATION OF ISOLATED MICROGRID

Implementation of Steady-State Power System Visualizations Using PowerWorld Simulator. Dr. Jung-Uk Lim, Department of Electrical Engineering

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008

Interconnection System Impact Study Report Request # GI

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

STABILIZATION OF ISLANDING PEA MICRO GRID BY PEVS CHARGING CONTROL

DEVELOPMENT OF VIBRATION CONDITION MONITORING SYSTEM APPLYING OPTICAL SENSORS FOR GENERATOR WINDING INTEGRITY OF POWER UTILITIES

Dynamic Study of Bonaire Island Power System: Model Validation and Project Experience

Review paper on Fault analysis and its Limiting Techniques.

High-voltage Direct Inverter Applied to Induced Draft Fan Motor at Takehara Thermal Power Station No. 3 of Electric Power Development Co., Ltd.

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Operational Objectives

Design Modeling and Simulation of Supervisor Control for Hybrid Power System

RECONFIGURATION OF RADIAL DISTRIBUTION SYSTEM ALONG WITH DG ALLOCATION

The Role of Electricity Storage on the Grid each location requires different requirements

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

Use of Microgrids and DERs for black start and islanding operation

Copyright 2003 Advanced Power Technologies, Inc.

Guide to Restoration. Marketplace Training

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

Computer Aided Transient Stability Analysis

Guideline for Parallel Grid Exit Point Connection 28/10/2010

New York Science Journal 2017;10(3)

Journal of American Science 2015;11(11) Integration of wind Power Plant on Electrical grid based on PSS/E

Project #148. Generation Interconnection System Impact Study Report

Essential Reliability Services Engineering the Changing Grid

Interconnection Feasibility Study Report GIP-226-FEAS-R3

TRANSMISSION PLANNING CRITERIA

Stability, Protection and Control of Systems with High Penetration of Converter Interfaced Generation

Composite Load Model Sensitivity Study

A simulator for the control network of smart grid architectures

Grid Stability Analysis for High Penetration Solar Photovoltaics

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Regenerative Utility Simulator for Grid-Tied Inverters

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

Guidelines for connection of generators:

Electric Power Transmission: Research Needs to Sustain a Critical National Infrastructure

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Planning for a Power Engineering Institute

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Reactive power support of smart distribution grids using optimal management of charging parking of PHEV

ECEN 667 Power System Stability Lecture 19: Load Models

2013 Grid of the Future Symposium. Utilizing Single Phase Operation Scheme on Untransposed 765kV lines for a Stability-Limited Plant

Renewables from a TSO Perspective. M.BENA, SmartGrids Director, RTE, French TSO Vienna, 18 May 2015

Design and Control of Lab-Scale Variable Speed Wind Turbine Simulator using DFIG. Seung-Ho Song, Ji-Hoon Im, Hyeong-Jin Choi, Tae-Hyeong Kim

Safe, fast HV circuit breaker testing with DualGround technology

Power Conditioning of Microgrids and Co-Generation Systems

DG system integration in distribution networks. The transition from passive to active grids

Laboratory Scale Microgrid Test-Bed Hardware Implementation

An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

Electrical grid stability with high wind energy penetration

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Solar Photovoltaic Inverter Current Distribution during Fault on Distribution and Transmission System

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA

Transforming Transforming Advanced transformer control and monitoring with TEC

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Adaptive Power Flow Method for Distribution Systems With Dispersed Generation

Grid Operations & Planning R&D Area Overview

CONTINGENCY ANALYSIS AND RANKING ON 400 KV KARNATAKA NETWORK BY USING MIPOWER

Power Flow Simulation of a 6-Bus Wind Connected System and Voltage Stability Analysis by Using STATCOM

Western Alberta Transmission Line (WATL) HVDC Project

Performance Evaluation of Electric Vehicles in Macau

Small Electrical Systems (Microgrids)

400/230 Volt 60Hz UPS Power

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Analysis of Grid Connected Solar Farm in ETAP Software

Wind Power Plants with VSC Based STATCOM in PSCAD/EMTDC Environment

PES Cook Islands KEMA Grid Study Final Report

Performance Analysis of Green Car using Virtual Integrated Development Environment

String Monitoring and Control System for Solar Photo Voltaic Power Plants

Reliability determination of ignition system of rocket platform using reliability block diagram and FMEA analysis

Seabrook Substation Reliability Improvement Project

INCREASING electrical network interconnection is

ETAP Implementation of Mersen s Medium Voltage Controllable Fuse to Mitigate Arc Flash Incident Energy

Performance Analysis of Transient Stability on a Power System Network

Design and Hardware Implementation of a Supervisory Controller for a Wind Power Turbine

IEEE SESSION COMPUTER AIDED SMART POWER GRID

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

Grid Impacts of Variable Generation at High Penetration Levels

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

The 1,400-MW Kii-Channel HVDC System

Role of Energy Storage Technologies in Providing Ancillary Services, Improving Power Quality and Reliability of the Indian Grid

SEVILLA, APRIL Microgeneration and Microgrids (modeling, islanding operation, black start, multi-microgrids) J. Peças Lopes Power Systems Unit

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

Fuzzy based STATCOM Controller for Grid connected wind Farms with Fixed Speed Induction Generators

Switching Impulse Flashover Tests and Analysis for 765kV Jumper V-strings with Damaged Insulators

ECONOMIC EXTENSION OF TRANSMISSION LINE IN DEREGULATED POWER SYSTEM FOR CONGESTION MANAGEMENT Pravin Kumar Address:

OPTIMUM ALLOCATION OF DISTRIBUTED GENERATION BY LOAD FLOW ANALYSIS METHOD: A CASE STUDY

The ABB Medium Scale Power Transmission Test Case

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

Advanced Protective Relay Training

Transcription:

Identification of Acceptable Restoration Strategies Seung-Tae Cha Nam-Ho Lee Eung-Bo Shim Korea Electric Power Research Institute Korea Electric Power Research Institute Korea Electric Power Research Institute stcha@kepri.re.kr nam100@kepri.re.kr ebshim@kepri.re.kr Jeong-Hoon Shin Korea Electric Power Research Institute jhshin@kepri.re.kr Hyun-Il Son Korea Electric Power Research Institute hison@hanyang.ac.kr Soo-Chul Nam Korea Electric Power Research Institute scnam@kepri.re.kr Abstract In recent years, we have seen several catastrophic & cascading failures of power systems throughout the world. Power system breakup and blackouts are rare events. However, when they occur, the effects on utilities & general population can be quite severe. To prevent or reduce cascading sequences of events caused by the various reasons, KEPRI is researching ways to revolutionize innovative strategies that will significantly reduce the vulnerability of the power system and will ensure successful restoration of service to customers. This paper describes a restoration guidelines / recommendations for the KEPS simulator, which allows power system operator and planner to simulate and plan restoration events in an interactive mode. The KEPS simulator provides a list of restoration events according to the priority based on some restoration rules and list of priority loads. Further, the paper will draw on research using information from a Jeju case study. Keywords Restoration, Blackouts, Cascading Failures, Real-Time Digital Simulator, Decision Support Tool 1. INTRODUCTION It is clear that the power systems of today are not what they were before open access and deregulation were introduced in many countries. Over the past few years, we have seen several catastrophic failures of power systems. Moreover, we are witnessing unusual generation and power flow patterns, unplanned congestion, and the introduction of renewable (wind, photovoltaic, fuel cell, etc) generation with its associated uncertainties. A major blackout in power system is usually caused by a consequence of cascading contingencies. The usual scenario of such events is that the power system is in a stressed state, followed by faults on critical facilities, followed by unanticipated tripping of other facilities, finally leading to system blackouts. System restoration following a blackout is one of the most important tasks of the operators. However, few computer tools have been developed and implemented for the real-time operational environment. Indeed, most power systems rely on non real-time restoration plans that are developed for selected scenarios of contingencies, and equipment outages. All power system operators strive to operate their systems with a high degree of reliability. In view of this, operators need to be aware of the situation & adapt to the changing system conditions during system restoration. Most operating companies maintain restoration plans based on their restoration objectives, operating philosophies and practices with the characteristics of their power plant restart capabilities and power system reintegration peculiarities. While these plans have successfully restored power systems in the past, they can be improved significantly by simulating transient and dynamic behavior of the power system under various restoration operating conditions and by real-time digital simulator reflecting many factors not readily modeled. It is therefore necessary to identify a general procedure or guidelines, and the available black start capabilities / the optimal sequence of switching and must be tested by real-time simulation to enhance rapid restoration. 2. REAL TIME DIGITAL SIMULATOR(KEPS) & DATA CONVERSION S/W 2.1 KEPCO s Enhanced Power system Simulator The KEPS is a parallel processing based power system simulator capable of continuous real-time simulation of both power systems and control systems. The power system network is modeled using the well known Dommel algorithm first incorporated into the EMTP. The availability of a substantial number of both analogue and digital input/output ports on the KEPS, coupled with operation in real-time permits interconnection of physical control and protection equipment to the simulation. It is thus possible for the user to study the performance of the external control and protection equipment under test in a closed loop manner. If the user does not have access to the physical control and protection equipment, that equipment can be modeled using the KEPS. This KEPS unit represents the world s largest and most advanced realtime digital simulator. It consists of 26 racks of modified RTDS hardware, each containing 1 GPC, 13 Triple Process Cards, 1 Workstation Interface Card, 1 ISSN: 1690-4524 SYSTEMICS, CYBERNETICS AND INFORMATICS VOLUME 6 - NUMBER 2 71

Dual Inter Rack Communication Card and various auxiliary components. In addition, many significant enhancements and improvements were made to KEPS hardware and software. A number of application software developments were undertaken and many are also part of on-going projects. Data Conversion S/W converts existing PSS/E files to KEPS/Draft file including initial system conditions. System Reduction S/W, evaluate existing and create custom techniques used to reduce large systems, but maintain system dynamics. 3-Dimensional Visualization S/W helps display results from large simulations. It is also expected that KEPS facility will serve as a training and education tool for KEPCO/KEPRI engineers and operators. Fig.2 Data file conversion s/w Fig.1 An overview of KEPS Simulator The Data Conversion Software has been developed by KEPRI, LS & RTI engineers to facilitate the set-up and data specification for KEPS simulation cases. Another words, the data conversion software automatically converts existing PSS/E data files of a particular format to the KEPS Graphical Draft file. This automatic data conversion process results in fewer human errors. The software is reliable and allows the parameters that are required as input to the KEPS power system component models and the efficient operation of the KEPS. 2.2 Data Conversion S/W In general, PSS/E type programs require less detailed data than EMTP programs. Therefore, these would have to be added manually or automatically. The structure of RSCAD Draft is such that the graphical image assembled by the user is converted to a data file before being passed to the RTDS compiler. Hence, there is a possible way to interface at the data level instead of at the Draft level. Currently, KEPRI/KEPCO use PSS/E programs widely and therefore have much of the system data in a format acceptable by PSS/E. With relatively large power systems being a primary focus and an automatic conversion process was desirable, we are now making good use of the PSS/E to RTDS format conversion facility. This feature allows the users to convert systems already available in PSS/E and run them on the RTDS. Fig.3 Partial Draft of Jeju system 3. SIMULATION STUDY 3.1 Review of Jeju Power System While in some severe situations, it is difficult to determine the disturbance source correctly because of the difficulty in collecting reliable information about the disturbance. Experience based methods usually adopted will suffer a great difficulty and sometimes lead to a delay for the restoration process. Therefore, special concerns have been given to the development of system restoration scheme done by electric utilities in advance. IEEE working group also gave a special report about power system restoration. Due to different properties and different requirements for each power system, it is necessary for us to study this problem at individual system and to develop a suitable restoration scheme for each particular system to direct the operations of the system operators accordingly. Jeju power network is isolated from the main land and 72 SYSTEMICS, CYBERNETICS AND INFORMATICS VOLUME 6 - NUMBER 2 ISSN: 1690-4524

interconnected by HVDC lines from Haenam S/S to Jeju S/S. This 12-pulse bipolar system normally conveys 150MW, which corresponds to 60% of the total load demand in Jeju island. There are 3 large thermal power plants, 5 diesel power plants and 4 gas turbines in various sizes. Total generating capacity of this network is about 530MW by the end of 2007. Peak load during the summer 2005 was 490MW. Approximately one half of the production is directly connected to 154kV network and controlled by provincial control center, and the other half comprises gas turbines, diesel generators, small thermal plants by area control centers and partly by district control centers. A RTDS model of the Jeju power system corresponding to the actual summer peak of June 2005 (490MW/214MVar) has been developed. Fig.3. consists of 20 buses, 35 branches, 24 transformers and 16 generators. The total power is mainly provided by 3 thermal plants and other diesel & steam/gas turbine plants. A strong 154kV transmission network of 300km superposed to provide the necessary power flows. System loads are modeled as mixed type constant power/constant admittance. Summary Original System # of generators 14 # of buses 29 # of branches 36 # of loads 9 # of transformers 19 Total generation 495 Total load 490 Table 1 Description of original system 3.2 Jeju Area Power System Restoration Plan The purpose of the Jeju area power system restoration procedure is to provide guidance to the system operator to manage system restoration events that affect the Jeju area and adjoining control areas. KEPCO and KPX utilize an all-open switching strategy following a major system failure. The adapted build-up strategy entails the main guidelines described in restoration plans, namely, ; Assessment of power system status; faulted area isolation if it is known or search for its identification Starting as soon as possible of GT generating stations Voltage is supplied to the main switching stations Units of power stations are synchronized Consumers are reconnected to the network When Jeju system disturbance results in a complete loss or a partial blackout, the plan is split into four steps. The first is relevant to the detection of the blackout status at the different control levels and to the switching sequences to be performed for network preparation by the ACCs. It is of prime importance the role played by, in starting the plan, by disconnecting loads and most of the lines, or stopping it if necessary. At the end of this step, early restoration plants must be started up. The objective of the second phase is to quickly constitute a transmission path between black start units and thermal plants in order to recover them into service as soon as possible. The third phase is entirely by the RCCs. The plant operators resynchronize the thermal units to the path and start the load pick-up. The fourth phase is managed by the RCC. As the thermal units have reached their lower capability limit, connection between independent paths is performed. At the end of this phase, the network will have sufficient power and stability to withstand the transients related to further load reconnection and recovery of other generating units. Table 2 below summarizes, at a very high level, the restoration plans of Jeju area. Type of restoration plan In the event of a complete system shutdown the plan defines a specific switching sequence along with general guidelines to restore the system Primary priority To start an early restoration plants and to establish a cranking path to provide start up power to all other plants & connect them together. Secondary priority Restore ac supply to critical loads AC & DC station service for switchyards, substations, generating station, control centers & interdependent infrastructure Table 2 A quick reference of area restoration plan Black start unit : Unit 3 at the gas turbine power plant of Jeju Supply no load branch : Jeju TP Bus Circuit Breaker On Establish a cranking path Provide start up power to early restoration generator, Hanlim GT Restore the basic minimum power to generating stations & transmission stations Coordinate & direct all transmission connections Provide start up power to major generating plants Similarly, in the event of a partial system shutdown only the applicable guidelines and steps are followed. These plans address the possibility of a complete system blackout by calling for the building of a basic minimum power system from designated key facilities. The ultimate goal of this rebuilding process is to reconnect electrical areas to reestablish a fully interconnected system. 3.3 Typical simulation results A simulation model of the Jeju power system corresponding to the actual summer of June 2005 has been developed. This restoration test just discussed has been analysed by RTDS. From the whole operative sequence the black start, start-up of early ISSN: 1690-4524 SYSTEMICS, CYBERNETICS AND INFORMATICS VOLUME 6 - NUMBER 2 73

restoration generator, a defined path approach and gradual system reconnection from a complete blackout are here examined in detail, as they collect significant aspects of the restoration process. Fig. 7 Sinjeju S/S M.TR #1,#2 reenergized (5MW, 1.56Mvar) Fig. 4 The Jeju Power System Fig. 8 Dongjeju S/S circuit breaker 6133 ON Fig. 5 Terminal voltage for Jeju GT#3 Fig. 9 Dongjeju S/S M.TR #1,#2, #3 (5MW, 1.56Mvar) Fig. 6 Sinjeju S/S circuit breaker 6233 ON Fig. 10 Terminal voltage for Jeju GT#3 74 SYSTEMICS, CYBERNETICS AND INFORMATICS VOLUME 6 - NUMBER 2 ISSN: 1690-4524

Fig. 15 Synchronize Hanlim units Fig. 11 A phase voltage & current for Jeju TP & Hanlim CC Fig. 16 A phase voltage & current for Hanlim CC Fig. 12 Raise terminal voltage for Jeju GT#3(0.9 1.0pu) Fig. 17 Sinjeju S/S M.TR #1,#3 (10MW, 3.122Mvar) & M.TR #4 (5MW, 1.56Mvar) Fig. 13 Hanlim C/C circuit breaker 6133 ON Fig. 14 Hanlim C/C circuit breaker 637 ON Fig. 18 Hanlim CC output after restoration ISSN: 1690-4524 SYSTEMICS, CYBERNETICS AND INFORMATICS VOLUME 6 - NUMBER 2 75

4. CONCLUSION In this paper, the application of real time digital simulator for power system restoration studies is presented. The KEPS is specially adapted to simulate the behavior of a Jeju electric power system experiencing a restoration plan / procedures following a blackout condition. It is shown that KEPS can provide an effective means by which the operator can be trained to deal with real restoration situations in a secure, controllable and real time simulation environment and they can be used for effective restoration planning. All the work done at this stage is preliminary to the new formulation of guidelines for an operator decision and training support system, for KEPS. The overall results obtained appear quite satisfactory. Based on these results, the system could modify the suggested sequence of actions to help arrive at an improved restoration. More advanced indices and guidelines would be certainly needed in order to exploit the simulator as an on-line restoration aid to system operators and dispatchers. With some major system modifications (200MW Namjeju thermal units, wind generators, etc) and minor procedural changes, any problems which might occur can be avoided. 5. BIOGRAPHIES Seung-Tae Cha has a B.S degree in Electrical Engineering from Illinois Institute of Technology, Chicago in 1992, and a M.S degree in Electrical Engineering from Yonsei University, Korea in 1997. Upon graduation, he joined the Korea Electric Power Research Institute where he was actively engaged in the development of KEPS, a fully digital real-time simulator, other various research projects and instruction of utility personnel in technical & software training courses. He is a senior researcher and his present interest includes real-time simulation of power systems, model development, studies involving load flow, system planning & operation. Nam-Ho Lee received his B.S and M.S degrees in Electrical Engineering from Myongji University, Korea in 1998 and 2001 respectively. He has been a researcher of LS Industrial Systems Co. Ltd since 2004 where he performed several projects related to Real Time Digital Simulation of power systems. His major research topics include real-time power system simulation, power system modeling and restoration. Eung-Bo Shim was born in Cheonan, Korea in Feb, 1955. He received his B.S, M.S and Ph.D. degrees in Electrical Engineering from Yonsei University, Korea, in 1978, 1980 and 1990 respectively. From 1991 to 1992, he was a visiting researcher at MIT, USA. He is currently a leader of power quality and reliability areas at Power System Laboratory, KEPRI. Jeong-Hoon Shin received his B.S, M.S and Ph.D. degrees in Electrical Engineering from KyungPook National University, Korea, in 1993, 1995 and 2006 respectively. He is a senior member of the Technical Staff in the Power System Analysis Center at KEPRI which is a research center of Korea Electric Power Corporation (KEPCO), Korea. His research interest includes real-time digital simulation, transient & dynamic stability, power system planning and operation. Hyun-Il Son received his B.S and M.S degree in Electrical Engineering from Hanyang University, Korea in 2001 and 2005 respectively. He has extensive experience with power transmission system, economic dispatch and power system reliability. He has performed the probabilistic power flow and ATC. Mr. Son joined KEPRI's Power System Analysis Group as a researcher in Jan 2006 where he has developed an integrated optimization scheme for reactive power management system for KEPCO and also participating in several transmission power system studies. Soo-Chul Nam received his B.S and M.S degree in Electrical Engineering from Korea University, Korea in 2001 and 2006 respectively. He has extensive experience with transient and dynamic stability. He has performed and directed load flow, short circuit, railroad electrical system, and protective relaying studies. Mr. Nam joined KEPRI s Power System Analysis Center as a researcher in Feb 2006 where he is developing an integrated optimization scheme for reactive power management system for KEPCO and also participating in several transmission power system studies. Acknowledgements The work described in this paper was sponsored by the Ministry of Commerce, Industry & Energy (MOCIE). We express our appreciation for the support provided by MOCIE under grant NF-200 received. I would like to thank all corresponding authors for their kind assistance in the preparation of the paper. References CHA, S.T., 2007, Real Time Simulation of KEPCO s Largest Equivalent System, International Conference on Electrical Engineering, ICEE Conference Proceedings, ICEE 2007 LEE, N.H., 2006, Development of the Restoration and Training System for Jeju Network using RTDS, ICEE Conference, ICEE, 2006 DELFINO, B., 1996, Black-start and Restoration of a Part of the Italian HV network; Modelling and Simulation of a Field Test, IEEE Transactions on Power Systems, IEEE Transactions, 1997: Vol. 11 No. 3, p1371-1379 Task Force on Coordination of Operation, NPCC Inter- Area Power System Restoration Procedure, 2007 CHA, S.T., 2007, Development of detail power equipment modeling and education & training system, Final Technical Report, NF -200, KEPRI 76 SYSTEMICS, CYBERNETICS AND INFORMATICS VOLUME 6 - NUMBER 2 ISSN: 1690-4524