Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Similar documents
2013 ANNUAL PROGRESS REPORT

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

Local Transmission Plan

March 7, Subject: Southern California Edison 2011 Annual Progress Report

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Pacific Gas and Electric Company s 2013 Annual Progress Report

BC Hydro System 2011 Annual Progress Report

BC Hydro System 2016 Annual Progress Report

Appendix D Black Hills Project Summary

Gateway South Transmission Project

Black Hills Project Summary

TOT1A: Metering Point Relocation Comprehensive Progress Report (WECC Path 30)

Status of PNM s Completed Transmission Construction Projects 11/30/2017

BC Hydro System 2017 Annual Progress Report

Rocky Mountain Power Five Year Study Findings & Kick Off Meeting

best to you all Gail Carbiener Page 1 of 5

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

2013 ANNUAL PROGRESS REPORT

West Station-West Cañon 115 kv Transmission Project

Date: March 15, Mr. Enoch Davies WECC Technical Staff 155 North 400 West, Suite 200 Salt Lake City, Utah

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

Transmission Planning. WECC 2014 Progress Report. March 14, 2014

Consulting Agreement Study. Completed for Transmission Customer

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

Wyoming electricity use is growing

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

Wyoming Energy Projects

SunZia Southwest Transmission Project

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

Illinois State Report

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Transmission Planning Attachment K Public Input Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA PACIFICORP. Direct Testimony of Richard A. Vail

Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016

Transmission Planning Report

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Interconnection Feasibility Study Report GIP-157-FEAS-R2

SunZia Southwest Transmission Project

Preliminary Plan of Development

Interconnection System Impact Study Report Request # GI

New 115 kv Disconnect Switches at Bloomsburg MTS

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Sub-Regional RTEP Committee PJM South

Decision on Merced Irrigation District Transition Agreement

New Jersey State Report

Arizona Transmission Challenges

Ten-year Plan. Figure 1 and Table 1. Each of the facilities shown in the plan is described in greater depth in the last appendix of this report.

Updates and Modifications to Report

Updates and Modifications to Report

Merger of the generator interconnection processes of Valley Electric and the ISO;

Falcon-Midway 115 kv Line Uprate Project Report

Verde Transmission, LLC. Verde Project. System Impact Study Report

North Oregon Coast Area Study. Adam Lint

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

Q0044 interconnection at

PSE Attachment K Puget Sound Area Transmission Meeting

Local Transmission Plan. Rev. 1: April 2018

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

100 MW Wind Generation Project

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Process Timeline. Area Bubbles. Legend. Problem Area that have been resolved. Recurring Areas from previous System Assessment.

Impact of Distributed Energy Resources on Transmission System Reliability

Overview of ISO New England and the New England Wholesale Power Markets

TransWest Express Project

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Sub Regional RTEP Committee Mid-Atlantic

Alternatives for meeting the need for transmission improvement described

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Craig Quist Craig Quist

Georgia Transmission Corporation Georgia Systems Operations Corporation

Supplemental Report on the NCTPC Collaborative Transmission Plan

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

APPENDIX F: Project Need and Description

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

MAP OR PHOTO. Public Meeting & Open House July 23, Project Roadway Limits From: FM 1957 To: FM 471. Counties Bexar & Medina

Designated Entity Pre-Qualification Materials. Exelon Corporation

SPP Notification to Construct

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment

PREPARED DIRECT TESTIMONY

Generation Interconnection Impact Study Results for Eurus Energy America Corporation s Eurus Combine Hills I, LLC Power Project.

Western NY Public Policy Transmission Planning Report

SPP Notification to Construct

Arizona Energy Consortium Conference

Salt Lake County Electrical Plan Task Force October Douglas N. Bennion, P.E. Vice President Rocky Mountain Power

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

New Mexico Transmission Expansion Concepts For Wind Resources

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

SPS Planning Criteria and Study Methodology

Transcription:

March 8, 2013 David Franklin Chair, Technical Studies Subcommittee Southern California Edison 1 Innovation Way Pomona, CA 91768 MHanson@idahopower.com (208) 388-2253 Enoch Davies Western Electricity Coordinating Council 155 North 400 West Salt Lake City, UT 84103-1114 Subject: Idaho Power s 2013 WECC Annual Progress Report Dear David and Enoch: Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions. Sincerely, Enclosure cc: D. M. Angell PCC Representative O. A. Ciniglio TSS Representative D. W. Streebel SRWG Representative

Waiver of Significant Transmission Project Status Idaho Power is requesting waiver of the Significant Transmission Project status for the following project: Midpoint T232 230/138 kv Transformer Addition Project Midpoint T342 345/230 kv Transformer Replacement Project The Midpoint T342 345/230 kv 500 MVA transformer is to be replaced with a larger 700 MVA transformer matching the existing Midpoint T341 345/230 kv 700 MVA transformer. The existing 500 MVA transformer will become a system spare and remain at Midpoint to be eventually installed as Midpoint T343 (third 345/230 kv transformer) at a later date. The scheduled/projected in-service date is mid June 2012. This project has no significant impact on the WECC transmission system. The Midpoint T342 345/230 kv Transformer Replacement Project was completed in July 2012. Langley Gulch Generation Project The Langley Gulch combined cycle generation project is being constructed near New Plymouth, ID in Payette County, Idaho on the outskirts of the Treasure Valley (Boise and surrounding area). The Langley Gulch combined cycle generating plant will consist of one natural gas combustion turbine/generator and one steam turbine/generator. The maximum summer output of the plant is 300 MW (at 32 o C) and the maximum winter output is 325 MW (at -7 o C) to 345 MW (at -18 o C). The proposed commercial operation date is July 1, 2012. The integration of the Langley Gulch combined cycle generation project requires the construction of a new short double-circuit 230 kv line and a new 138 kv line. A new 2.5 mile double-circuit with single conductor 1272 MCM ACSR 230 kv line will be constructed to loop in-and-out the Ontario-Caldwell 230 kv line into the proposed Langley Gulch generation site; thus creating an Ontario-Langley Gulch 230 kv line and a Caldwell-Langley Gulch 230 kv line. And, a new 16 mile single conductor 1590/1272 MCM ACSR 138 kv line (constructed 230 kv and operate at 138 kv) will be constructed from the proposed Langley Gulch generation site tapping the existing Caldwell-Willis 138 kv line at the proposed future Wagner Tap location which is approximately three miles out from the Caldwell substation; and, thus creating a Langley Gulch-Caldwell 138 kv line. The Langley Gulch-Caldwell 138 kv circuit will share double-circuit towers with the Langley Gulch-Caldwell 230 kv line for approximately 2.0 + miles entering into the Caldwell substation. In addition to the transmission line improvements, a new 230/138 kv 335 MVA transformer will be installed at the Langley Gulch generation site. The Langley Gulch Generation Project will conform to the NERC TPL-001-0 thru TP-004-0 Standards and WECC TPL-(001 thru 004)-WECC-1-CR System Performance Criteria, This project has no significant impact on the WECC transmission system. The Langley Gulch Generation Project was completed in July 2012. Justice 230/138 kv Substation Project A new Justice 230/138 kv substation will be constructed near the existing King 138 kv substation with a 300 MVA 230/138 kv transformer to accommodate approximately 135 150 MW of additional wind generation in the Hagerman area. The Justice substation will be interconnected to the 230 kv transmission system by looping in-and-out the existing Midpoint- 1

Dram 230 kv line. Because the wind generation projects, which the Justice 230/138 kv project is to accommodate, have been slow in their development; the in-service date has been deferred to December 2012. This project has no significant impact on the WECC transmission system. The Justice 230/138 kv Substation Project was completed in January 2013. Hemingway - Boardman Transmission Project Idaho Power s 2011 Integrated Resource Plan, a biennially-produced 20-year resource plan for meeting our electric service obligation, identified Pacific Northwest generation resources as one component of the preferred resource portfolio. Requirements of Idaho Power s wholesale transmission customers are also increasing. The existing transmission system to the Pacific Northwest has been fully subscribed during high-demand periods. To meet the need for more transmission capacity, Idaho Power plans to build a 500 kv transmission line from southern Idaho to northeast Oregon. The plan of service is to construct a 300 mile 500 kv transmission line from Hemingway station in southwestern Idaho to a new Grassland station near the existing Boardman Power Plant in northeastern Oregon. The Hemingway-Boardman Transmission Line Project s proposed and alternative routes are shown in Figure 1. The Hemingway-Boardman Transmission Line Project scheduled in-service date will be no earlier than 2018. The Hemingway-Boardman Transmission Project facilities to accommodate a 2250 MW west to east (1050 MW increase) and a 3400 MW east to west (1000 MW increase) transfer capacity ratings on the Idaho-Northwest (Path 14) transfer path are listed below: Hemingway-Boardman 500 kv line, 300 miles with approximately 50% series compensation (split equally at each end) the termination will be at the Grassland switching station near the Boardman Power Plant Hemingway, 500 kv Line Terminal with Shunt Reactors and Series Capacitor Grassland, 500 kv Line Terminal with Shunt Reactors and Series Capacitor, and 150 Mvar 500 kv Shunt Capacitor Hemingway-Bowmont #2 230 kv line, 13 miles with single 1590 MCM ACSR Lapwing conductor Bowmont-Hubbard 230 kv line, 16 miles with single 1590 MCM ACSR Lapwing conductor Bowmont, 2 nd 230/138 kv 300 MVA Auto-Transformer The Hemingway-Boardman Transmission Project will conform to the NERC TPL-001-0 thru TPL-004-0 Standards and TPL-001-WECC-RBP-2 System Performance, and the WECC Overview of Policies and Procedures for Project Coordination, Project Rating Review, and Progress Reports. A Hemingway-Boardman Transmission Project Comprehensive Progress Report (Phase I) was released for comment in November 2008 and was granted Phase II status in March 2009. Idaho Power began the Phase II study process in 2011; the initial kick-off project review work group meeting was held on June 22, 2011, and the second project review group meeting was held on November 15, 2011. 2

Figure 1 Hemingway to Boardman 500 kv Transmission Line Project Proposed & Alternative Routes 3

The third project review group meeting was held on March 22, 2012. On August 10, 2012, a conference call/webinar was held to solicit comments on the initial Phase II draft report. In August 2012, Idaho Power submitted the Idaho-Northwest Up-rate, Hemingway-Boardman 500 kv Transmission Project Phase II Report to WECC and was granted Phase 3 status on November 29, 2012 with an Accepted Rating of 2250 MW west-to-east and 3400 MW east-towest. Gateway West Transmission Project Please see the Gateway West Transmission Project section in PacifiCorp s 2013 WECC Annual Progress Report. Based on the agreement between PacifiCorp and Idaho Power, executed in early 2012, PacifiCorp (Rocky Mountain Power) will assume responsibility for shepherding all Gateway West transmission facilities through the National Environmental Policy Act (NEPA) process and through the project construction phase. The Gateway West Transmission Project facilities in the Idaho area are listed below: Kinport-Midpoint 345 kv line (existing), will be split/converted to: Kinport-Borah 345 kv line Borah-Midpoint 500 kv line (constructed 500 kv/operating at 345 kv) Borah, 500/345 kv 1500 MVA Auto-Transformer Populus-Borah 500 kv line, 55 miles Cedar Hill-Hemingway 500 kv line, 161 miles with approximately 50% series compensation Cedar Hill-Midpoint 500 kv line, 34 miles (Phase 2) Midpoint-Hemingway #2 500 kv line, 126 miles with approximately 50% series compensation (Phase 2) Midpoint T232 230/138 kv Transformer Addition Project A second 230/138 kv 200 MVA transformer will be installed at the Midpoint substation due to load growth in the Magic Valley area. The scheduled/projected in-service date is June 2020. This project has no significant impact on the WECC transmission system. Please direct all questions or concerns regarding these projects to: Idaho Power Company 1221 W Idaho P.O. Box 70 Boise, Idaho 83707-0070 Tel. (208) 388-2253 Fax. (208) 388-6647 E-mail MHanson@idahopower.com 4