Draft Guideline for the connection of smallscale inverter based distributed generation. EEA Asset Management Forum 22 June 2016 Dr Richard Strahan

Similar documents
Reliability-related matters from the GREEN Grid project

Integrating hosting capacity into Part 6 of the Code on low voltage networks

Developing tools to increase RES penetration in smart grids

Increasing PV Hosting Capacity in Distribution Networks: Challenges and Opportunities. Dr Andreas T. Procopiou

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Connecting your business diesel generation

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

SA Power Networks Commissioning Witnessing Checklist

Micro Embedded Generating Units (0-30 kva)

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

GRID CONNECTION ISSUES FOR DISTRIBUTED GENERATION REVIEW & STANDARDS

Relative Power Factor Correction costs

DG Standard Updates. IEEE 1547, UL 1741 SA, and Rule 21 CHASE SUN GII/PG&E 3/28/18

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011

The Role of Electricity Storage on the Grid each location requires different requirements

AS/NZS AS/NZS

Connecting your home or small business generation

Guidelines for connection of generators:

Session 8: Distributed Energy Resources Utility Concerns, Grid Impacts and Mitigation Strategies October 21, 2015 Santiago, Chile

Enquiry Form for Micro and Small Generators 5MW and Less

EC Forum on Model Approaches to Distribution Pricing. June 2009

Grid Management Voltage Control Distribution Grid Voltage Regulation with DER. Michael Sheehan, P.E. IREC Pacific Northwest Solar Partnership

PV Grid Integration Research in the U.S.

Using Hosting Capacity Methodology to Develop Simplified Screens for New Solar PV Interconnections

MARLBOROUGH LINES DISTRIBUTED GENERATION INFORMATION PACK

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Regenerative Utility Simulator for Grid-Tied Inverters

Grid Interconnection and Grid Integration Features of PV Inverters

Solar Microgrid Technical Presentation

Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 25 kw to 10 MVA or less)

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

Export limits for Embedded Generators up to 200 kva connected at Low Voltage

Technical Standard - TS 129. Small Inverter Energy Systems (IES) - Capacity not exceeding 30kW. SA Power Networks. Published: November 2017

Integration of DER: Grid Support Functions and Connectivity

Minnesota Dept. of Commerce, Division of Energy Resources. Distributed Generation Workshop Interconnection Standards

AS/NZS :2016. Grid connection of energy systems via inverters AS/NZS :2016. Part 1: Installation requirements

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

PHILIPPINE DISTRIBUTION CODE 2017 EDITION

Design and Implementation of Reactive Power with Multi Mode Control for Solar Photovoltaic Inverter in Low Voltage Distribution System

Appendix UA Ideal Power UL 1741 SA Advanced Inverter Features

SUBMISSION SUBMISSION ON THE. Energy Innovation (Electric Vehicles and Other Matters) Amendment Bill

Document Requirements for Engineering Review- PV Systems v1.1 12/6/2018

Renewable Energy & Storage Best Practice at TPL and Issues Faced. Murray Sheerin Power Generation Manager, Tonga Power Limited.

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

Standards, Procedures and Policies for Grid Connection

Tomorrow s Energy Grid

GREEN Grid Conference 2017

Renewable Grid Integration Research in the U.S.

Managing the renewables challenge in secondary distribution networks. Tim Spearing, Product Marketing Manager Lucy Electric, United Kingdom

NEDO s Smart Grid Demonstration Projects in the U. S. JUMPSmartmaui Project in Hawaii

Utility Distribution Planning 101

Maryland Level 2, Level 3 & Level 4 Interconnection Request Application Form (Greater than 10 kw to 10 MW or less)

IFC Workshop on Distributed Generation, 13 February 2013, Moscow, Russia

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

Aggregation of plug-in electric vehicles in electric power systems for primary frequency control

DYNAMIC LOAD FLOW STUDIES OF DISTRIBUTION FEEDS IN THE SAN JOAQUIN VALLEY REGION

Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules

Modeling of Momentary Cessation and Voltage Ride-Through Level 2 NERC Alert Loss of Solar Resources during Transmission Disturbances due to Inverter

Inverter Advancements in UL1741 and UL 62109

Overview of State Distributed Generation Interconnection Rules

Electrical Power Electric power electrical electric power Electric power electric electric

Georgia Transmission Corporation Georgia Systems Operations Corporation

Technical Requirements for Renewable Energy Power System

Large Embedded Generation User Guide A

Bulletin Interconnection of electric power production sources Rules 2-010, , , , , , and

PSNH INTERCONNECTION REQUEST

Copyright 2003 Advanced Power Technologies, Inc.

Small Electrical Systems (Microgrids)

Y9. GEH2.3: FREEDM Cost Benefit Analysis based on Detailed Utility Circuit Models

An Integrated Grid Path for Solar. Thomas Key, EPRI Senior Technical Executive. ISES Webinar. April 22, 2016

Solar Impact Case Study. Trishia Swayne, P.E. Leidos

Standardized and modular scalable from 30 kw up to several MW. Plug-and-play integration of renewable energy in off-grid and ongrid applications

Magellan Stand Alone Power System (3P) Magellan Renewables Range

Electrical grid stability with high wind energy penetration

Document Requirements for Engineering Review PV Systems v1.0 6/9/2017

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Rate Impact of Net Metering. Jason Keyes & Joseph Wiedman Interstate Renewable Energy Council April 6, 2010

REALIZING INCREASED GRID CAPACITY FOR HIGH PENETRATION OF RENEWABLE GENERATION. TechAdvantage 2015 Orange Country Convention Center Orlando, FL

Grid Stability Analysis for High Penetration Solar Photovoltaics

Using Active Customer Participation in Managing Distribution Systems

Implementing a Microgrid Using Standard Utility Control Equipment

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1

Impacts and integration of PV in LV networks

Legal Name of the Customer (or, if an individual, individual's name): Name: Contact Person: Mailing Address: Physical Address: City: State: Zip Code:

Integrated Plant Control and Q on Demand 24/7 SUNNY TRIPOWER

Technical Requirements for Export Limiting Schemes

Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA

RESILIENT SOLAR CASE STUDY: SUNY New Paltz NYPA Integrated Grid Pilot

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Optimal and Modular Configuration of Wind Integrated Hybrid Power Plants for Off-Grid Systems

PV System Impact Guide

PES Cook Islands KEMA Grid Study Final Report

TEST REPORT DIN V VDE V

National Distributed Energy Resources Grid Connection Guidelines. Technical Guidelines for Basic Micro EG Connections

Smart Grids and the Change of the Electric System Paradigm

Electricity Network pricing schedule. Module 15 Effective April 1, 2011 for Electricity line charges. Version

Certificate of Conformity self-generation unit

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Grid Impacts of Variable Generation at High Penetration Levels

Transcription:

Draft Guideline for the connection of smallscale inverter based distributed generation EEA Asset Management Forum 22 June 2016 Dr Richard Strahan

Outline 1. Introduction and Issues to Address 2. Methodology to develop the DG Guideline 3. DG Connection Application Assessment Process 4. DG Installation and Inverter Key Technical Requirements 5. Pro forma DG Application Form 2

1. Introduction and Issues to Address 2. Methodology to develop the DG Guideline 3. DG Connection Application Assessment Process 4. DG Installation and Inverter Key Technical Requirements 5. Pro forma DG Application Form 3

2009-1 2009-7 2010-1 2010-7 2011-1 2011-7 2012-1 2012-7 2013-1 2013-7 2014-1 2014-7 2015-1 2015-7 2016-1 MW Peak Introduction and Issues to Address: Growth of PV based Generation in NZ PV based DG increased by a factor of 1.6 over the last year 90% of installed PV capacity is made up of small-scale residential grid-tied systems rated below 10 kw 40 30 20 10 NZ cumulative PV uptake, all capacities This corresponds to about 300-400 new PV systems being installed each month within LV networks 0 4

Phase to neutral voltage Introduction and Issues to Address: Reverse power flow Simulation of LV Network over-voltage DG can introduce reverse power flow into the LV network, which causes issues of: Over-voltage (>1.06 p.u.) Phase imbalance Over-loading of conductors Over-loading of transformer Safety and Protection High DG export Low DG export Maximum permitted voltage rise from the transformer to the point of supply is only 0.02 p.u., i.e. 4.6 V 5

Introduction and Issues to Address: DG Connection Application Assessment The Situation SSDG applications are typically processed without technical assessment? No consistent approach to assessing applications and connection requirements across EDB s Technical complexity of assessment compounded by introduction of advanced inverter technology as captured in the new AS/NZS 4777.2 (2015) Grid connection of energy systems via inverters Part 2: Inverter Requirements Some Questions What criteria does an EDB use to assess a connection application under EIPC 2010 Schedule 6.1, Part 1A up to 10 kw export power? What information does the EDB need from the applicant on the DG application form? Can an application be auto-assessed, and if so, when should an application be manually assessed? Are there circumstances when an applicant can use low cost inverter technology (e.g. which does not have power quality response modes)? Providing consistent connection requirements and standardization across EDBs would be of major benefit to installers, inverter manufacturers, and consumers 6

Introduction and Issues to Address: AS/NZS 4777.2 (2015) Grid connection of energy systems via inverters Part 2: Inverter Requirements Questions What inverter protection settings are appropriate for NZ? How should inverter power quality response modes be applied here? Does AS/NZS 4777.2 provide all the appropriate information and suitable requirements for the NZ context? Can inverters actually perform as required? What are the technical requirements for the installation? 7

Introduction and Issues to Address: Export Congestion The Situation The Code requires each EDB to publically disclose a list of all locations on its distribution network that it knows to be subject to export congestion; or expects to be subject to export congestion within the next 12 months Manual assessment of NZ s many thousands of LV networks may be impractical Some Questions Is there a simple method that automates congestion evaluation for each LV network, such that only a much smaller subset of networks would be flagged for needing closer assessment? Could this method provide a simple parameter describing the degree of congestion for any LV network for planning purposes? 8

1. Introduction and Issues to Address 2. Methodology to develop the DG Guideline 3. DG Connection Application Assessment Process 4. DG Installation and Inverter Key Technical Requirements 5. Pro forma DG Application Form 9

Methodology to develop the DG Guideline Literature review Modelling DG in LV networks DG Hosting capacity for connection requirements DG Guideline Consulting Industry (NAG) Reviewing Draft AS/NZS 4777.2 and making submissions Programme of inverter testing Considering key technical and safety requirements 10

Methodology to develop the DG Guideline: Review of AS 4777 update to AS/NZS 4777 Grid connection of energy systems via inverters Existing Parts AS 4777.1:2005 Installation requirements Listed in the Electrical (Safety) Regulations 2010, under Schedule 2 AS 4777.2:2005 Inverter requirements Replacement Parts Draft AS/NZS 4777.1:2016 Installation requirements made submission to Standards Australia on behalf of NAG, in May 2016 AS/NZS 4777.2:2015 Inverter requirements AS 4777.3:2005 Grid protection requirements Standard now in use, but it states a transitional period until 9 th October 2016 during which AS 4777.2 and AS 4777.3, which it supercedes, may also be used. made submission to Standards Australia on behalf of the NAG, in May 2014, and May 2015. 11

Methodology to develop the DG Guideline: Applying Hosting Capacity to determine connection requirements DG hosting capacity is defined as the maximum real export power (in Watts), per ICP with DG installed, on a LV network which can be tolerated without causing voltage or current limits to be exceeded in the network. 12

Methodology to develop the DG Guideline: Applying Hosting Capacity to determine connection requirements DG hosting capacity is defined as the maximum real export power (in Watts), per ICP with DG installed, on a LV network which can be tolerated without causing voltage or current limits to be exceeded in the network. 13

Methodology to develop the DG Guideline: Applying Hosting Capacity to determine connection requirements DG hosting capacity is defined as the maximum real export power (in Watts), per ICP with DG installed, on a LV network which can be tolerated without causing voltage or current limits to be exceeded in the network. It is calculated for two thresholds, which are: 1. a lower connection threshold H 1 above which mitigation measures are necessary, 2. an upper connection threshold H 2 above which mitigation via inverter reactive power control alone (specifically the Volt-VAr response mode) enabled for all connected DG, is insufficient. Hosting capacity is calculated via either full simulation (recommended) or by an approximation method such as the EPECentre s DGHost 14

1. Introduction and Issues to Address 2. Methodology to develop the DG Guideline 3. DG Connection Application Assessment Process 4. DG Installation and Inverter Key Technical Requirements 5. Pro forma DG Application Form 15

DG Connection Application Assessment Process: Traffic light system H 1 Green: application auto-assessed and approved Customer applies to connect DG (they specify max real export power) EDB assesses application based on network hosting capacity for customer s location > H 1 H 2 Amber: application auto-assessed and approved subject to requirement for inverter Volt-VAr response available and enabled > H 2 Red: application manually assessed Assessment Example Customer DG Application LV Network Hosting Capacity Outputs Max real export power [kw] Connection threshold H 1 [kw] (upper limit for no mitigation) Connection threshold H 2 [kw] (upper limit with mitigation Volt-VAr response) 4.5 2.7 7.2 16

22 ICP network with 5 exporting DG Penetration level = 5/22 = 23% DG Connection Application Assessment Process: Penetration level Penetration level (PL) is defined as the proportion of ICPs in a given network that have export-capable DG installed. Hosting capacity decreases as penetration level increases A long term best estimate of the penetration level should be used. The guideline recommends a penetration level between 25% to 100%. Setting a lower PL ---> increases hosting capacity thresholds ---> reduces manual assessments, allows more lower spec (cheaper) inverters Setting a higher PL ---> decreases hosting capacity thresholds ---> increases manual assessments, allows less lower spec (cheaper) inverters. LV network aggregate export capacity increased by having more Volt-VAr capable inverters. 17

1. Introduction and Issues to Address 2. Methodology to develop the DG Guideline 3. DG Connection Application Assessment Process 4. DG Installation and Inverter Key Technical Requirements 5. Pro forma DG Application Form 18

DG Installation and Inverter Key Technical Requirements: The Installation Draft AS/NZS 4777.1 (2016) states that: The rating limit for single phase Inverter Energy Systems (IES) is 5 kva. Therefore the maximum current rating for single-phase connected IES is 21.7 A at 230 V. For multi-phase IES the unbalance between phases shall be no greater that 5 kva. Therefore, for two phase IES, the rating limit is 10 kva. 19

DG Installation and Inverter Key Technical Requirements: Recommended inverter settings for New Zealand Parameter Limit Minimum trip delay time Maximum disconnection (trip) time Passive anti-islanding set-point values V nom-max (10minute average) Overvoltage 1 Overvoltage 2 Undervoltage Under-frequency Over-frequency Minimum reconnection time Volt response modes: Volt-VAr, Q(V) and Volt-Watt, P(V) 248 V 260 V 1 second 2 seconds 265 V - 0.2 seconds 180 V 1 second 2 seconds 45 Hz 1 second 2 seconds 52 Hz - 0.2 seconds 60 Seconds Applicability determined according to traffic light system designed Volt-response curves 20

DG Installation and Inverter Key Technical Requirements: Volt response mode curves for New Zealand Volt-VAr response mode Volt-Watt response mode LAGGING VAR/RATED VA (%) LEADING 80% 60% 40% 20% 0% 20% 40% 60% 80% 200 V1 V2 V3 V4 207 220 235 244 PF = 0.8 lead 210 220 230 240 250 260 PF = 0.8 lag INVERTER VOLTAGE, V 270 POWER, P/P rated % V1 V2 V3 V4 207 220 244 246 100% 80% 60% 40% 20% 0 200 210 220 230 240 250 260 270 INVERTER VOLTAGE, V 21

1. Introduction and Issues to Address 2. Methodology to develop the DG Guideline 3. DG Connection Application Assessment Process 4. DG Installation and Inverter Key Technical Requirements 5. Pro forma DG Application Form 22

Pro forma DG Application Form: Application to Connect Inverter Based Distributed Generation (DG) of 10kW or less in total Located in Appendix A of the Guideline 8 pages in length Includes questions regarding: a) Information the Applicant must provide according to the Code b) Information required for the traffic light system c) Inverter protection settings d) Inverter power quality response modes 23

Panel Comments and Participants Questions 24

Pro forma DG Application Form: Application to Connect Inverter Based Distributed Generation (DG) of 10kW or less in total Table headings: 1. Contact details 2. Site details 3. Distributed generation details 4. Intended connection configuration 5. Inverter approval 6. Power export calculation 7. Inverter protection settings 8. Inverter power quality response modes 9. Inverter volt reference values 10. Inverter demand response modes (DRMs) 11. Battery energy storage system (BESS) 12. Power limiting device 13. Installer requirements 14. ICP holder signature 25

Pre-conference submission 1. The DG hosting capacity would see the introduction of equal rationing of local DG capacity. No, the traffic light system only specifies connection requirements. Connected DG installations will vary in size. 2. For a complete and accurate application, connection must be approved within 10 business days after the distributor receives the application. Problem: there is no extra time allowance for manual assessments if these are required. Is the answer for the Code to allow more time under Part 1A if the EDB indicates a manual assessment is necessary? 3. A DG may have been procured and installed before application approval, and then the applicant finds out that the EDB requires inverter volt response modes the DG does not have, or operating restrictions or other requirements. How is this dealt with? Note Draft AS/NZS 4777.1 (2016) Clause 3.4.7 states that Additional requirements from the electricity distributor may include the activation or connection of (b) volt response modes 4. The Guideline suggests distributors remove inverters from their approved lists that do not have power quality response modes (Section 2.3.4.2.). 5. undertaking detailed and complex modelling as well as lengthening application form requirements may drive additional costs into businesses. 26

28