Technical Inputs to Dredging Estimates. Robert Ramsdell Manager of Production Engineering Great Lakes Dredge & Dock

Similar documents
APPENDIX J DREDGE AND CAPPING EQUIPMENT SELECTION AND PRODUCTION RATES

8. The backhoe or Dipper dredger

APPENDIX J DREDGE AND CAPPING EQUIPMENT SELECTION AND PRODUCTION RATES

2a. Excavating and Lifting

FUEL PROVISIONS FOR DREDGING PROJECTS

EXECUTIVE SUMMARY Dredging Equipment DAMEN DOP PUMP

Hydraulic power is the key to the utility of many excavators.

Dredging 101 Dredging and Disposal Workshop

BELL BOOSTER STATIONS 16 Main Specifications INDEX

Ask for genuine Bobcat buckets.

Parameters Affecting Selection of Dredge Equipment

THE DESIGN OF ANCHOR ELEVATION PLATFORMS FOR CUTTER SUCTION DREDGE D ARTAGNAN

Table C-1. POLB Middle Harbor Redevelopment Construction/Demolition Activities and Noise Data

Excavation Equipment: Shovel

Steel Products. 8M Series

INDEX. BELL PUMPS 4 Overview Characteristics Production Applications & Areas Of Operation. STRONG POINTS 7 Basic Design Spares & Services

INDEX. BELL PUMPS 4 Overview Characteristics Production Applications & Areas Of Operation. STRONG POINTS 7 Basic Design Spares & Services

Economics of Driven Pile Foundations

7.3 Maintenance of Dredging Fleet

WEDA EASTERN CHAPTER MEETING GLDD S ATB ELLIS ISLAND & TUG D.B. MACKIE. Eastern Shipbuilding Group Panama City Florida.

FEMA's Schedule of Equipment Rates

306E. Mini Hydraulic Excavator. Engine Model Cat C2.6 (DI Turbo) Operating Weight 5795 kg

ESG Press Release November 27, 2017

FEMA's Schedule of Equipment Rates

Attachments for Excavators

Swinging Ladder Dredges

Cutter Suction Dredges

MACON CHARTER. RED OCTOBER, an S-type Donge Dipperdredger with Backacter 1100 :

**Equipment production**

MACON CHARTER "NO WOMAN NO CRY" No Woman No Cry, an S-type Donge Dipperdredger:

BUILT FOR BETTER PERFORMANCE

FMB13437 Self Propelled Cutter Suction Dredger

C-SERIES BACKHOES SPECIFICATIONS OPTIONS & EXTRA EQUIPMENT

AxeBlade. Ridged diamond element bit

Dredging Equipment EXECUTIVE SUMMARY DAMEN CUTTER SUCTION DREDGERS

SmartBall Gas Leak Inspection

CHAPTER 10 FLOATING WHARVES

E08 - E10. Compact Excavators

Tahoe-Reno Industrial Center Total Bonding Amounts Engineer's Opinion of Probable Construction Costs (30% Submittal) Project No. 783.

M06For MT52 and. Maximum digging depth of more than 6 ft. Narrow width for working in tight areas.

: Anandro Amellonado. Alternatives of Dredging Method Based on Interpretation of Soil Investigation in The North Kalibaru Project

NEXT GENERATION EXCAVATORS 320GC I 320 I 323

3 in. Steel Single and Double Wall Municipal Shields XLSM3. XLSM3 Sidewalls 3 in. Steel Single Wall Municipal Trench Shield

Bobcat Backhoe Attachments

Safety Sense Ballast Under Cutter

Side Cutter Kit (Left and Right - fits all 68", 72", 80" Buckets) 48" Pallet Fork

CLAMSHELL BARGE OR SHIP UNLOADER

A Technique for Selecting Appropriate Allowable Pile Loads for Driven-Pile Projects: Load Matching

302.5C Mini Hydraulic Excavator

LOW CARBON FOOTPRINT HYBRID BATTERY CHARGER PROJECT PROPOSAL

DAMEN DREDGING EQUIPMENT

M06For MT52 and. Maximum digging depth of more than 6 ft. Narrow width for working in tight areas. quick and easy attachment changes.

Heavy Lift Hovercraft. Date: Jan 2017

INDEX. BELL PUMP 4 Overview Characteristics Production Applications/Areas Of Operation

SOUND FLEET FACTS: SUSTAINED COMMITMENT, INCREASING CAPABILITIES

County of Yolo UNDERGROUND STORAGE TANK PROGRAM INSTALLATION/MODIFICATION/REPAIR APPLICATION

Haul & Load Practical Cost Reduction Volvo Construction Equipment

Calc. No. Job No. Sheet

GOPALAN COLLEGE OF ENGINEERING AND MANAGEMENT Department of Civil Engineering COURSE PLAN

CAT MINI EXCAVATOR ATTACHMENT OPTIONS

06GB backhoe 4/10/06 1:51 PM Page 1. Great Bend Backhoes. For 15 to 100 PTO HP Tractors

Cat MINI HYDRAULIC EXCAVATORS

ECO 250 CUTTER SUCTION DREDGER

CONSTRUCTION and OFF ROAD EQUIPMENT

MIDI EXCAVATORS PRODUCT RANGE

Build-A-Box. Modular Trench Shielding System. Tabulated Data Effective January 4, Revised: April 21, with CHANGE THREE

Schedule of Equipment Rates

ATTACHMENTS FOR LOADER CRANES

CEM 417 WEEK 6. CONSTRUCTION TECHNOLOGY & maintenance. Construction Plants 22/02/2011 WEEK 6 CONSTRUCTION PLANTS

RBH65 BACKHOE LOADER

7. Grab or Clamshell dredger

BACKHOE. attachments

liu OIL TRANSFERING BETWEEN

State of Minnesota PRICING PAGE - METHOD # 2 (Typed Responses Required)

Mayor and Assembly Briefings

DAMEN DREDGING EQUIPMENT

TE 210. te210 TUNNEL EXCAVATOR. Technical Main Data. For heading in soft to medium hard ground Tunnel excavation boom with swivel dipper stick

Red Line Customer Capacity Update. Fiscal & Management Control Board September 19, 2016

Cover Sheet Drainage District 7 DSR Butler County, Missouri

Elongated Tube. Series. offs. Unique Router Design. on Outer Skin and. Page 4

smart&solution&for&hard&work

Aqua Green Utility Inc.

Trailer Buyers Guide Riverside Road, Abbotsford, BC V2S 7P1. Ph: Fx:

Build-A-Box Modular Trench Shielding System

CAT MINI EXCAVATOR ATTACHMENT OPTIONS

AMPHIBIOUS 5070 AMPHIBIOUS 5070

Attachment Lineup. You have a lot of choices in attachments; they re all in here. Make more money with your compact equipment.

Backhoe Range. For Tractors from 15HP

Grabs and Rotators. Attachments for truck mounted crane.

BACKACTER 1100 World s strongest dredge

Loaders Loaders And Mounts To Fit Your Tractor. Backhoes Ability To Do Your Own Dirt Work. Attachments A Variety Of Options For Your Loader

IHC Beaver 300 SE Cutter suction dredger

44. Bit record form Rig site daily drilling report form Office drilling report Computerized drilling information network

PERFECT IN TUNNELING

Why? Faster To reduce the duration of the process

Cummins / 6CTA8.3-C or Rhino Tier 2 (Tier 3, Tier 4) 6 8.3(506) 188(252) Direct Injection Turbocharged, air-to-air charge air cooler COOLING Fan Drive

EXCAVATOR BUCKETS AND GROUND ENGAGING TOOLS FOR KOMATSU EXCAVATORS

Mini-excavator ViO20. Operating weight: 2335/2230 kg Arm digging force: 1200 kgf Bucket digging force: 1900 kgf

Loading and Hauling. Håkan Gustafsson David Nus Martin Mattsson

TERRAGRADER 3000 TERRAGRADER 2000

Transcription:

Technical Inputs to Dredging Estimates Robert Ramsdell Manager of Production Engineering Great Lakes Dredge & Dock

Production Engineering Estimate the productivity of dredging equipment Work to improve productivity on ongoing projects Evaluate the design of new and upgraded equipment

Cost Estimator How much money? Project Estimate Production Estimator How much time? Takeoff How much work?

Cost Estimator Answers the Question: How much will the project cost?

Cost Estimator Mobilization, subcontract & supply costs Daily cost for dredging plant Lays out estimate

Dredging Area Plan

Rock Contours

Takeoff Answers the Question: How much work is there to do?

Takeoff Dredge/Borrow Area Dredge & fill quantities (CY) Material quantities/breakout (CY) Area to be dredged or filled (SF) Pipeline/Sail/Haul Distances (LF/NM)

Takeoff: Project Layout Maps Cross-Sections & Profiles

Production Estimator Answers the Question: How long will the project take?

Production Estimator Evaluate Geotechnical Information: Adequacy of the information Material Types Strength Size

Evaluating Materials Are there enough borings? Are there enough useful tests?

Production Estimator Productivity of equipment CSD vs Hopper vs Mechanical Digging versus pumping for each section of the project References to similar past projects Time = Qty/Production

Crucial Variables for Production Material Type Face/Thickness Strength Grain Size Extents/Distribution Pipeline Length

Material Classification

Material Strength Standard Penetration Test Compressive, tensile or shear strength Indicative or non-standard tests are no substitute for proper tests!

Grain Size Distribution Important in determining how well the material can be pumped.

Material Type The Perils of Poor Information Estimate: 1438 m 3 /WH Estimate: 5 Teeth/Day

Material Type The Perils of Poor Information Estimate: 1440 m 3 /WH Actual: 605 m 3 /WH Estimate: 5 Teeth/Day Actual: 104 Teeth/Day

SPT vs. CORING Via boring & SPT Via coring

Bank Height Face The thickness of material to be dredged.

Layout of Face Similar cross-sectional area, but layout requires two different digging methods.

Production vs Face 1000 900 Production CY/WH) 800 700 600 500 400 300 200 Estimate assumes: 24 CY Payload, 45 sec 8000 Cycle 100 0 6000 0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 Prioduction (CY/WH) Face (Ft) Production (CM/WH) Backhoe Dredge Production Face (Ft) 4000 CSD Theoretical Production Curve 2000 2,000 0 1,800 1,600 0 1 2 3 4 1,400 Face (m) 1,200 1,000 800 600 400 200 0 0.00 2.00 4.00 6.00 8.00 10.00 12.00

Bucket Dredge Production Curve Production CY/WH) 1000 900 800 700 600 500 400 300 200 100 Estimate assumes: 24 CY Payload, 45 sec Cycle 0 0.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 Face (Ft)

Backhoe Dredge Production Curve Backhoe Dredge Production 8000 Production (CM/WH) 6000 4000 2000 0 0 1 2 3 4 Face (m)

Cutter Suction Dredge Digging Curve CSD Theoretical Production Curve Prioduction (CY/WH) 2,000 1,800 1,600 1,400 1,200 1,000 800 600 400 200 0 Swing Limit Dig or Pump Limit 0.00 2.00 4.00 6.00 8.00 10.00 12.00 Face (Ft)

Hopper Dredge in Low Face Hang Time

Pumping Capacity 2800 2600 2400 Prodcution (CY/WH) 2200 2000 1800 1600 1400 1200 1000 10000 15000 20000 25000 30000 35000 Line Length (Ft)

Pumping Production PROD pump = f (L/D pipeline, P pumps, Material )

Hopper Dredge Pump Capacity Pumpout Rate (CY/min) 30.0 25.0 20.0 15.0 10.0 5.0 0.0 Dredge Alone 0 5,000 10,000 15,000 20,000 25,000 Pipeline Length (m) Booster Added

Other Important Variables Layout Narrow or Odd Shaped Cuts Slope Cuts Tow or Sail Distance Water Depth

Layout of Face Similar cross-sectional area, but layout requires two different digging methods.

Dredging Area Plan

Tow and Sail Distance For Clamshell, a matter of adding barges and tugs For hopper, another element of the overall cycle In both cases, consider the route when determining distance

Water Depth Can the dredge physically reach the material in deep water? Can the dredge float and dig in shallow water? For clam, cycle is directly dependent on depth. For backhoe, bucket size is dependent on depth.

Estimating Dredge Productivity By analysis of the capabilities of the dredge as compared to the conditions of the project. By reference to similar projects in the past By combining the two Using analysis to extend references

Clamshell Fill & Cycle Analysis

CSD Production Limits Pumping capacity Dig limit ability to excavate the material Swing limit How fast can the dredge swing?

Production Engineering Tools Pump / system analysis

CSD Simulators

Hopper Load & Cycle Analysis

References Florida Beach 1995 Sub Job Booster Face Line Length Qty/Day 1 No 11.6 11000 37600 2 Yes 11 18900 33300 3 No 11.6 9500 28700 4 Yes 17.3 24900 29000 Total 12.4 17900 33300

Reference Comparison Florida Beach 2005 Sub Job Booster Face Line Length Qty/Day 1 9.6 14200 2 8.6 18800 T 3 10.8 23300 B 4 7.0 27800 A 5 6.8 30900 Total 8.4 22800

References Comparing Projects 1995 12.4 Face 17900 Pipe Dredge Alaska 2005 8.4 Face 22800 Pipe Dredge Texas

1995 Project by Face 70000 Production (CYDay) 60000 50000 40000 30000 20000 10000 0 0.0 5.0 10.0 15.0 20.0 25.0 Face (Ft)

1995 Project by Line Length 70000 Production (CY/Day) 60000 50000 40000 30000 20000 10000 0 0 5000 10000 15000 20000 25000 30000 Line Length (Ft) Work with Booster

1995 Project by Line Length 70000 Production (CY/Day) 60000 50000 40000 30000 20000 10000 0 0 5000 10000 15000 20000 25000 30000 Line Length (Ft) Work with Booster

2005 Project - Results Production (CY/Day) 60000 50000 40000 30000 20000 10000 2005 Project 1995 Project 0 0 5000 10000 15000 20000 25000 30000 Line Length (Ft)

Robert Ramsdell Manager of Production Engineering Great Lakes Dredge & Dock RCRamsdell@gldd.com