American Transmission Company LLC Northern Umbrella Plan (NUP) Projects

Similar documents
Northern Umbrella Plan Update. December 15, 2006

Northern Umbrella Plan Update. December 7, 2007

Northern Umbrella Plan and U.P. Capital Projects Update Transmission Business Briefing October 29, 2008

Northern Umbrella Plan Phase 1 Projects Impacts On U.P. Export Capability

Northern Umbrella Plan & Projects- Update

Capital Project Update Northern Umbrella Plan Update

Section IV CHANGES TO THE YEAR ASSESSMENT

Section III STATUS OF PROJECTS. Table III-1 Projects Completed Since September Year Assessment

Highly Constrained Elements Within ATC Footprint

Appendix B. Summary of Changes to the Year Assessment

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009

ATC Year Asessment Network Project List. Zone 2 switching initiative ASAP*** Operating flexibility Proposed -- --

ATC Year Assessment Network Project List. MTEP Cost Reason for Change since Previous System Addition

AMERICAN TRANSMISSION COMPANY

Northeast Wisconsin/Upper Peninsula Separation 11/14/01. Incident Investigation Report

Wisconsin Housing Statistics

Wisconsin Local Employment & Unemployment Estimates Released

WHEDA. Wisconsin Standard Multifamily Tax Subsidy Project Estimated Maximum Income and Rent Limits. Effective April 1, 2018

Year Over Year Unemployment Rates Decline Or Hold Steady In All 12 Wisconsin Metro Areas For 58 th Consecutive Month

Region NC. Page 1 of 6. Total Salt. Total Salt. Severity Index. Total Salt. Salt. Total Sand. Total Clear- Total Thaw- Lane.

Region NC. Page 1 of 6. Total Salt. Total Salt. Salt. Total Salt. Total LM per Anti- Icing. Lane. Total Clear- Total Thaw- Total Sand.

ATTACHMENT Y STUDY REPORT

Flowgate 10515, an OTDF flowgate, consists of the following elements:

U.P. Energy Summit February 16, 2017

Summary Report. September The Future Grid. 10-Year Transmission System Assessment.

Appendix D Black Hills Project Summary

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Wisconsin Multifamily Tax Subsidy Project Housing and Economic Recovery Act (HERA Special) Income and Rent Limits

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Michigan Commercial Motor Vehicles

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

Western Area Power Administration

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

BEMIDJI GRAND RAPIDS 230-KV TRANSMISSION LINE

U.S. Army Corps of Engineers, Detroit District 2018 PHOTO CONTEST CALENDAR

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Market Efficiency Update

March 7, Subject: Southern California Edison 2011 Annual Progress Report

Upper Midwest Marketing Area -- F.O. 30 State and County Data* (pool pounds) August 2000

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

BC Hydro System 2011 Annual Progress Report

Transitways. Chapter 4

Black Hills Project Summary

South Dakota 890 Study

West Station-West Cañon 115 kv Transmission Project

Sub-Regional RTEP Committee PJM South

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

2013 / 2014 Revenue Comparison: OCTOBER

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

TransWest Express Transmission AC and DC Project Interregional Transmission Project Submittal

CUSTOMER/ TWIN ARROWS PROJECT

Ex.-Applicants-Stevenson-22

MTEP14 West SPM #2. ATC, DPC, XEL Project Review. April 2, 2014

TABLE OF CONTENTS SPEED LIMITS ORDINANCE WOOD COUNTY ORDINANCE # Chapter PURPOSE

Key to Status Fields in the Project List

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5

Illinois State Report

FISCHER, FRANKLIN & FORD Attorneys and Counsellors GUARDIAN BUILDING, SUITE GRISWOLD STREET DETROIT, MICHIGAN

EXCEPTIONS TO RELIABILITY RULES Revision 11 February 9, 2018

SUMMARY REPORT. 10 Year Transmission System Assessment

Transmission Planning Attachment K Public Input Meeting

Market Efficiency Planning Study

INFRASTRUCTURE AND TRANSPORTATION ADVERTISING SCHEDULE 2015/2016 CONSTRUCTION AND MATERIAL SUPPLY TENDERS

Welcome. Highway 23 Gap New London to Paynesville. Open House. - Please Sign In -

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

VEHICLE TYPE CRASH INVOLVEMENT

Business Advisory Committee. July 7, 2015

Merger of the generator interconnection processes of Valley Electric and the ISO;

VERMONT ELECTRIC POWER COMPANY (VELCO)

EXCEPTIONS TO RELIABILITY RULES Revision 10 August 11, 2017

Business Advisory Committee. November 3, 2015

100 MW Wind Generation Project

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Updates and Modifications to Report

EXCEPTIONS TO RELIABILITY RULES REVISION 4 MAY 8, 2015

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

What Does it All Mean?

Denver Metro Association of Realtors

Economics of Law Practice in Michigan

TEN YEAR HISTORY OF FALL ENROLLMENTS

The Applicants have taken the following actions to comply with the EO standards:

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Arizona Transmission Challenges

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

SPP Notification to Construct

Monthly Market Detail - June 2018 Single Family Homes Miami-Dade County

Monthly Market Detail - June 2018 Townhouses and Condos Miami-Dade County

Summary Statistics. Closed Sales. Paid in Cash. Median Sale Price. Average Sale Price. Dollar Volume. Median Percent of Original List Price Received

CITY OF PASADENA APPLICATION FOR PARTICIPATING TRANSMISSION OWNER STATUS

What Does it All Mean?

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

For only the third time in history, 8,000

CREATING CONNECTIONS IN WATERLOO REGION

Transit Project Delivery Status Report. Significant Issues

SCHEDULE A. SPEED LIMITS (A part of Section )

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

State Bar of Michigan

Transcription:

American Transmission Company LLC Northern Umbrella Plan (NUP) Projects February 21, 2006

Agenda Northern Umbrella Plan Individual Project Discussion Summary

System Prior to NUP Projects

NUP Projects Wien Arnett Rd. McMillan Hume Arpin Sigel WOOD Jackpine Clear Lake ONEIDA Eastom Tomahawk Grandfather Falls LINCOLN Alexander Boulder Jct. Hilltop Sherman St. Morrison Ave. Weston White Pine Stone UPSCO GOGEBIC VILAS Ontonagon ONTONAGON Mass Victoria Dam Bruce Crossing Land O Lakes Conover Cranberry St. Germain Pine Highway 8 MARATHON Bunker Hill Wausau Kelly Du Bay PORTAGE Northpoint Hoover Rocky Whiting Ave. Run Plover Coyne Three Lakes RPC Black Brook Hodag Venus Arnott Watersmeet Twin Lakes LANGLADE WAUPACA Winona FOREST HOUGHTON M-38 Prickett MENOMINEE BARAGA Warden IRON Way Dam Lakehead Hemlock Falls DICKINSON Strawberry Hill Iron River Crystal Falls Sagola Peavy Falls Lincoln Nordic Felch Twin Lakes Randville Michigamme Antigo I Harrison Waupaca G Crandon Summit Lk. Aurora St. SHAWANO W. Shawano Badger Caroline Clintonville Werner West Laona Silver Cliff Bass Lk Armory Pine Grede FLORENCE Big Q Niagara Paper Cauldron Falls High Falls Thunder MARINETTE Fox Hill Johnson Falls Sandstone Pound OCONTO Morgan Greenstone Humboldt Lena Brule Goodman Amberg Daves Falls Mountain Florence OUTAGAMIE North Hintz Appleton Ellington F White Lake D CWIS White Clay E. Shawano H Twin Fls Falls Pioneer Roselawn Skygen Plains Champion BROWN Hoist Perch Lake Crivitz McClure See Insert A Cataract MARQUETTE MENOMINEE Alger-Delta Nathan Chalk Hills White Rapids Stiles Howard Velp Mason St. James St. Liberty Eastman Glory Rd. Red Maple C Lost Dauphin Ropes Foundry Pulliam A1 A3 Tower Dr. Preble E Highway V Myst. Hills Powers Grand Rapids KEWAUNEE Arnold Bay De Noc Menominee 30th Ave. 2nd St. Roosevelt Rd. West Marinette GREEN BAY Rosiere CEDAR LINE CLARKSBURG LINE East Krok A2 DOOR Presque Isle Marquette Dead River AuTrain Chatham KI Sawyer Gwinn Cornell Forsyth Chandler Delta West Side Harris Canal National Tilden Insert A Perkins Gladstone Mead Escanaba ALGER DELTA Empire Munising Indian Lake Lakehead LAKE SUPERIOR SCHOOLCRAFT B LAKE MICHIGAN Glen Jenks Manistique Seney Newberry Corr. Facility Engadine Hiawatha Curtis Lakehead Valley Blaney Park Gould City LUCE Lou-Pac Newberry Newberry Village Roberts Rexton Lakehead KEY 345 kv Substation Generation CHIPPEWA Eckerman Hulbert Trout Lake 115 or 138 kv Substation <=69 kv Substation 345 kv Transmission 115 or 138 kv Transmission 69 kv Transmission Proposed Projects MACKINAC Brevort Straits McGulpin Emmet Brimley Pine River Oden To Livingston 4

NUP Projects A: Plains Stiles 138 kv Rebuild B: Indian Lake Hiawatha 69 kv to 138 kv Rebuild C: Morgan Stiles 138 kv Rebuild D: Morgan White Clay 138 kv Up-rate E: Add 2 nd Plains Transformer F: New Werner West 345/138 kv Substation G: Cranberry Conover Plains Project H: Morgan Werner West 345 kv Line (including Clintonville Werner West 138 kv) I: New Weston Central Wisconsin 345 kv Line (for generator interconnection)

Project Schedule/Status: Plains-Stiles 138kV Rebuild Reconductor Amberg to White Rapids complete Rebuild White Rapids to West Marinette complete Rebuild Plains to Stiles Plains-Amberg rebuild complete Transfer of second circuit from temporary structures scheduled for completion by February 2006 is now complete. Amberg Stiles rebuild started in December 2005 as scheduled and is on schedule for completion by November 2006 6

Project Schedule/Status: Indian Lake to Hiawatha 69 kv to 138 kv Rebuild (Phase 2) Line rebuild was started in November 2004 Work is approximately 95% complete Forecasted to be complete and energized March 2006 7

Project Cost/Schedule/Status: Morgan to Stiles Rebuild The rebuild of the existing 11 mile H-frame supported, single circuit with double circuit mono-pole steel structures is complete Modifications (e.g. breakers, switches, jumpers, etc.) required at Morgan, Falls, and Pioneer to upgrade the substation equipment to match the new line rating are also complete Modifications at Stiles substation to upgrade equipment to match the new line rating will be completed in Spring 2006 8

Project: Add 2 nd Plains SS Transformer Scope Add a 2 nd 345/138 kv, 250MVA transformer Schedule/Status Will obtain authorization in early 2007 Start design late 2007 Install in 2008 9

Project Cost/Schedule/Status: New Werner West Substation Received Certificate of Authority from PSC in June 2005 Slated for construction start in spring 2006 and project completion December 2006 Ordered all long lead equipment Engineering in final phase 10

Project Schedule/Status: Cranberry-Conover-Plains Pre-certification activities ATC Executive approval ATC Board approval File CPCN application CPCN Order issued Construction activities Project completion and in-service June 2004 Sept 2006 July 2005 July 2005 November 2005 November 2006 April 2007-Dec 2009 Dec 2009 11

Project Schedule/Status: New Morgan-Werner West 345kV Line (including Clintonville-Werner 138kV) ATC Executive approval 2/2005 ATC Board approval 2/2005 File CPCN application 3/2005 CPCN anticipated issue 6/2006 Pre-construction activities 1/2006-6/2007 (Surveying, engineering, real estate, material procurement) Construction period 10/2006-12/2009 Project in-service 12/2009 12

Project Schedule/Status: New Gardner Park-Central WI 345kV line (includes Central WI Switching Station) ATC Executive approval 2/2005 ATC Board approval 2/2005 File CPCN application 3/2005 CPCN anticipated issue 6/2006 Pre-construction activities 1/2006-6/2007 (Surveying, engineering, real estate, material, procurement) Construction period 10/2006-12/2009 Project in-service 12/2009 13

Project Status Summary Project Key Need Drivers Projected In-Service Date Projected Cost Status A: Plains Stiles 138 kv Rebuild A1: Plains Amberg A2: Amberg West Marinette A3: Amberg Stiles Physical condition; transfer capability; solution also results in a more robust parallel path for 2/3 of P-S corridor October 2005 November 2005 November 2006 $98.5M Project approved and under construction Temporary line in service; reconstruction of permanent double-circuit line underway Rebuild/conversion underway Scheduled to start when A1 and A2 are complete. B: Indian Lake Hiawatha 69 kv to 138 kv Rebuild Phase 1 Rebuild Indian Lake Glen Jenks Phase 2 Rebuild as double circuit 138 kv, operate at 69 kv Phase 3 Convert to 138 kv operation TLR mitigation; voltage support; physical condition; local load-serving in Manistique area; required operating guide that splits the U.P. system August 2004 June 2006 2009 $6.1M $45.0M Under review Phase I complete; Phase II in progress Complete Construction underway Scheduled for 2009, but need and scope is being reviewed C: Morgan Stiles 138 kv Rebuild as double circuit Transfer capability August 2005 $7.0M Project approved and under construction 14

Project Status Summary Project Key Need Drivers Projected In-Service Date Projected Cost Status D: Morgan White Clay 138 kv uprate (eventual rebuild as part of Element H) Transfer capability March, 2005 $0.4M No PSCW approval required. Project Complete. E: Add 2 nd Plains transformer (250 MVA 345/138 kv) Transfer capability 2008 $5.4M No PSCW approval required. Scheduled for 2008. F: New Werner West Substation with 345/138 kv transformer TLR mitigation, system security December, 2006 $15.3M CA approved by the PSC in June 2005, awaiting real estate transactions resulting in a 6 month delay. G: Cranberry - Conover Plains Project Rebuild 69 kv Conover - Plains to 138 kv New 115 kv Cranberry - Conover Transfer capability; Transmission service; Reliability, physical condition December 2009 2009 2007 $118.2M CPCN submitted to PSCW in Nov 2005 Work scheduled to begin in 2008 Work scheduled to begin in 2007 H: New Morgan Werner West 345 kv line & Clintonville Werner West 138 kv line Transfer capability, reliability 2009 $132.3M CPCN submitted to PSCW in March 2005 I: New Gardner Park Central Wisconsin 345 kv line & Central Wisconsin 345 kv switching station Required for new Weston 4 generation 2009 $131.5M CPCN submitted to PSCW in March 2005 15

Northern Umbrella Plan Rollup Summary Current estimated cost for all projects is $559.7 million Total project spending to date is approximately $140 million (through January 2006) Of the 9 projects 1 is complete and in-service 3 are greater than 50% constructed 5 are in various stages of regulatory approval/permitting and design Construction and completion of all projects is expected in late 2009 if all goes according to plan 16

Wrap Up QUESTIONS & FEEDBACK