Customer Services, Operations, and Safety Committee Board Information Item III-D May 13, 2010 Rail Fleet Plan

Similar documents
Customer Services, Operations, and Safety Committee Board Information Item III-E May 13, 2010 Bus Fleet Plan

7000 Series Railcar Program Overview

Capital Needs Assessment Riders Advisory Council July2, 2008

Capital and Strategic Planning Committee. Item III - A May 10, FY2018 Third Quarter Capital Program Updates

Transit Maintenance Equipment. Maintenance Facilities FY

Briefing on Metro Matters Projects

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1

Proposed FY2015 Budget and Fare Increase

Authorize Public Hearing To Discontinue Non- Regional Metrobus Routes 2W, 12A-S and 20F-Y in Fairfax County

Briefing on Metro Matters Projects

CEDAR AVENUE TRANSITWAY Implementation Plan Update

Report by Planning, Development & Real Estate Committee (B) Washington Metropolitan Area Transit Authority Board Action/Information Summary

Bi-County Transitway/ Bethesda Station Access Demand Analysis

Update on Transportation Activities in Fairfax County

Safety Performance Indicators

Washington Metropolitan Area Transit Authority

Washington Metropolitan Area Transit Authority

Balancing the Transportation Needs of a Growing City

Washington Metropolitan Area Transit Authority Board Action/Information Summary

Precision Station Stopping Progress Update

Improving Accessibility of Regional Bus Stops and Pathways

Update on Bus Stop Enhancements

Customer Service, Operations and Security Committee. Information Item III-A. January 12, 2017

Washington Metropolitan Area Transit Authority Board Action/Information Summary. MEAD Number:

Customer Services, Operations, and Safety Committee Board Information Item III-A May 13, 2010 Safety Report

MOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion

Safety and Operations Committee. Action Item III-A. December 13, 2018

Maryland Gets to Work

Minnesota Avenue Station Parking Garage Repair Project

Adhoc Planning Commission Committee Review of the Virginia Square Sector Plan. Virginia Square Site

Dulles Corridor Air Rights Study Investigation

Increase Rail Service to the Mid City Green Line Stations

UCLA Lake Arrowhead Conference. October 18, 2010

Letter EL652 City of Mercer Island. Page 1. No comments n/a

Semi-Annual Status Report on Railcar Programs

CLRP. Performance Analysis of The Draft 2014 CLRP. Long-Range Transportation Plan For the National Capital Region

UCLA Lake Arrowhead Conference. October 18, 2010

UCLA Lake Arrowhead Conference. October 18, 2010

Capital Needs Inventory

Status Report Metrobus Capital Improvement Program FY06-11

Appendix B. Tier 2 Final Environmental Assessment I-66 Transit/TDM Technical Report

RTSP Phase II Update

METRONext. Vision & Moving Forward Plans. Board Workshop. December 11, DRAFT For Preliminary Discussion Only

REPORT CARD FOR CALIFORNIA S INFRASTRUCTURE WHAT YOU SHOULD KNOW ABOUT CALIFORNIA S TRANSIT FACILITIES

Leadership NC. November 8, 2018

Overview of Transit Funding and Planning in the PACTS Region

ConnectGreaterWashington: Can the Region Grow Differently?

Link LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion

DART Priorities Overview

Capital Metro Plans & Projects Update NASWC July 27, capmetro.org

Transit in Bay Area Blueprint

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

MWAA FY /16/2008 NORTHERN VIRGINIA TRANSPORTATION IMPROVEMENT PROGRAM CAPITAL COSTS (in $1,000) Source Source Total Fed/St/Loc.

Valley Metro: Past, Present and Future. September 11, 2014

Customer Service, Operations and Safety Committee. Rail Car Deployment Strategies

West Broadway Reconstruction/LRT Design. March 19, 2015

Chapter 6 - Capital Improvement Program

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Commuter Rail Vehicle Technology Analysis

The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report

TRANSPORTATION EFFECTS

Executive Summary October 2013

Metropolitan Council Budget Overview SFY

5. OPPORTUNITIES AND NEXT STEPS

Commuter Rail Vehicle Technology Analysis

Basic Project Information

Metrorail Line Load Application

Georgia Department of Transportation 2006 Fact Sheet Lovejoy to Atlanta Rail Line visit the website at

Needs and Community Characteristics

Washington Metropolitan Area Transit Authority Board Action/Information Summary

The Future of Rail in Maryland. Kevin B. Quinn, Jr. Administrator

Durham-Orange (D-O) Light Rail Transit (LRT) Project

Response: The comment reflects the final recommendations of the Project Team and the evaluation of the two Build Alternatives in the Final EIS.

The Case for. Business. investment. in Public Transportation

Item #14. DATE October 12, GCTD Board of Directors. Reed C. Caldwell Director of Engineering & Construction

MOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses

ITEM 9 Information October 19, Briefing on the Performance Analysis of the Draft 2016 CLRP Amendment

Proposal for September 2006 Start of Commuter Rail from Lovejoy on the Macon Line to Atlanta

Developing Toronto s Transit Network Plan to Public Information Meeting June 21, 2016

AWARD CONTRACT FOR LINE BREAKERS

Federal Gas Tax Program. Transportation Committee May 7, 2014

Waco Rapid Transit Corridor (RTC) Feasibility Study

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000.

TRANSIT IDEA STRATEGIC INITIATIVE On BUS RAPID TRANSIT (BRT)

congestion management program

congestion management program

FY 2018 I-66 Commuter Choice Program Presentation to the Northern Virginia Transportation Commission May 3,

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT

Regional Inventory of Projects Planned High Capacity Surface Transit Improvements in the WMATA Service Area. DRAFT Project Summaries

TORONTO TRANSIT COMMISSION REPORT NO.

Metropolitan Council Transit Capital Improvement Plan. September 23, 2009

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

TBARTA USF to Wesley Chapel Express Bus Service Operating Plan. Draft 3/25/2014

Green Line Long-Term Investments

FREQUENTLY ASKED QUESTIONS

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE

Feasibility Study. Community Meeting March, North-South Commuter Rail Feasibility Study

Central City Line Locally Preferred Alternative (LPA) Amendment Public Hearing. July 24, 2014

Transcription:

Customer Services, Operations, and Safety Committee Board Information Item III-D May 13, 2010 Rail Fleet Plan Page 54 of 96

Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: Resolution: Yes No TITLE: 2010 Metrorail Fleet Management Plan PURPOSE: To present the 2010 Metrorail Fleet Management Plan, which was last updated in 2006, and to seek feedback and direction on the needs for rail cars and facilities to support future growth of the existing system and the Metrorail Extension to Dulles Airport and Loudoun County. DESCRIPTION: The updated Metrorail Fleet Management Plan will be a tool that provides proper planning for future Metrorail vehicle and facility needs, taking into consideration current and future ridership demand, approved expansion projects, scheduled and unscheduled maintenance, and the rail car rehabilitation program. The plan complies with the Federal Transit Administration`s (FTA) new requirements effective December 2009 for a 15-year fleet plan. By adopting the plan, the Board does not make any formal commitment to any project or funding for any fleet expansion. The following is a summary of the improvements included in the Plan. Rail Car Growth: This plan includes the needs for 128 cars for a two-phased extension to Dulles and proposed growth of 130 rail cars for running 75% peakperiod 8-car trains by FY2015, as well as, growth of 90 rail cars for running 100% peak-period 8-car trains by FY2020. The summary is as shown below: Page 55 of 96

Total Fleet Current Fleet 1,142 With new 7000-series vehicles Dulles Extension Phase I & II: + 128 cars 1,270 New cars for growth - 75% peak period 8-car trains: 1,400 + 130 cars New cars for growth - 100% peak period 8-1,490 car trains: + 90 cars Rail Car Storage Needs: The Dulles Extension project anticipates the need for an additional 128 rail cars and will provide up to 226 additional storage spaces. This fleet plan shows that there is currently adequate storage to accommodate the rail cars needed for system growth of 130 cars for running 75% peak-period 8-car trains. However, it is not adequate for system growth of 90 cars for running 100% peak-period 8-car trains. In addition, storage capacity by location does not meet service train dispatching needs, creating operation inefficiency. Existing/Planned Capacity Storage Needed Difference Current Fleet 1,316 1,258 58 With new 7000-series vehicles Dulles Extension Phase I & II: + 128 cars 1,538 1,398 140 New cars for growth - 75% peak period 8-car trains: 1,538 1,540-2 + 130 cars New cars for growth - 100% peak period 8-car trains: + 90 cars 1,538 1,640-102 Page 56 of 96

Rail Car Maintenance Facility Needs: The fleet plan identifies the need for a total of 222 maintenance bays, 48 more than currently exists. The Dulles project includes 36 new maintenance bays to support the 128 rail cars for the Dulles Extension, as well as the growth at West Falls Church facility. When the fleet is expanded for system ridership growth by FY2020, there will be a need for 12 additional maintenance shop spaces. The exact yard expansion locations are not specified in the plan. This would be done as part of an overall fleet expansion and funding agreement. FUNDING IMPACT: The adoption of the Metrorail Fleet Management Plan is for planning purposes only and does not obligate Metro or its Board of Directors to the Plan`s projected requirements; therefore there is no funding impact. RECOMMENDATION: Provide feedback and direction on the 2010 Metrorail Fleet Management Plan. Page 57 of 96

2010 Metrorail Fleet Management Plan Update Customer Service, Operations and Safety Committee May 13, 2010 Page 58 of 96

Purpose Good business practice Complies with Federal Transit Administration s s (FTA)new requirements effective December 2009 for a 15-year fleet plan Assesses current operation and capacity needs Identifies the gap between fleet demand and supply Assists in our capital program review process Page 59 of 96

Current Fleet 26% of the fleet (1000-series) is over 30 years Manufacturer Series Number Years Number Purchased Purchased in Service Rohr Industries 1000 300 1974-1978 282 Breda Construzioni Ferroviarie Construcciones y Auxiliar de Ferrocarriles, S.A. (AAI/CAF) 2000 / 3000 76 / 290 1983-1988 358 4000 100 1992-1994 100 5000 192 2001-2004 184 Alstom 6000 184 2006-2008 184 Total 1,142 1,108 Page 60 of 96

Current Service and Maintenance Challenges 1000-series cars Belly operating configuration Strain the limits of yard operation Impact maintenance resources Requires additional yard transfers Manual train operation Increase maintenance demand i.e. wheel flats Impacts on-time performance Aging infrastructure Traction power system Signaling system Track and Structures Platform edges Page 61 of 96

Ridership Growth and Service Expansion Recent ridership growth rates are around 3% Future ridership growth is projected at 2%-3% up to FY2020 and 1% beyond FY2020, consistent with the projected job and population growth in the WMATA service area Dulles corridor extension will add 23 miles of track and 11 stations Phase I: to Wiehle Avenue, Reston, VA scheduled to be completed in FY2014 Phase II: to Dulles Airport, eastern Loudoun County scheduled to be completed in FY2017 Page 62 of 96

Ridership Peak Hour Load Impact without Growth Railcars Assuming no growth railcars: 50% 8-car trains through FY2025 Metrorail system to reach capacity starting FY2020 By FY2020, Orange/Dulles Rail will become highly congested By FY2025, Green Line will become highly congested Page 63 of 96

Ridership Peak Load Impact with Growth Railcars Assuming with growth railcars: 100% 8-car trains by FY2020 Bringing relief to peak crowding and keep peak passenger loads in line with capacity Page 64 of 96

Railcar Maintenance Needs Generally, the operating spare ratio of 20 22% has to be maintained to fulfill maintenance requirements: Scheduled (preventive) maintenance Unscheduled (corrective) maintenance Number of railcar maintenance shop spaces are required to conduct maintenance activities Industry practice is equal to 15% of the revenue fleet Page 65 of 96

Railcar Maintenance Space Needs Shop Year Location Line Opened Capacity Function Alexandria Blue Yellow 1981 20 Servicing, Inspection and Running Repair Branch Green 2002 8 Inspection and Running Repair Brentwood Red 1974 2009 Rehab 40 Heavy Repair, Overhaul, Inspection and Running Repair Greenbelt Green 1996 22 Servicing, Inspection Running Repair, Heavy Repair and Overhaul New Carrollton Blue Orange 1978 2006 Rehab 28 Servicing, Inspection and Running Repair Shady Grove Red 1983 36 Servicing, i Inspection and 2009 Rehab Running Repair West Falls Church Orange 1986 20 Servicing, Inspection and Running Repair Total Current Car Capacity 174 Future Maintenance Space Needs: Dulles Phase I: 8 maintenance shop spaces are planned at West Falls Church Dulles Phase II: 28 maintenance shop spaces are planned at Dulles Additional 12 maintenance shop spaces will be needed for all 7000-series growth railcars Page 66 of 96

Railcar Storage Needs Number of railcar storage spaces are required: Industry practice is equal to the number of total fleet plus 10% extra spaces for railcar movements Future fleet growth will consume all of the available storage capacity and demand more Storage capacity by location does not meet service train dispatching need; storage is not efficiently located Page 67 of 96

Railcar Storage Capacity Existing/ i Planned Capacity Storage Needed Net Capacity Current Fleet 1142 1,316 1,258 58 With 7000 Series: Dulles Phase I: 64 1,354 1,328 26 Dulles Phase II: 64 1,538 1,398 140 100% 8-car Trains: 220 1,538 1,640-102 Future Railcar Storage Needs: Dulles Phase I: 38 additional storage spaces are planned at West Falls Church Dulles Phase II: 184 additional yard storage spaces are planned at Dulles Additional 102 yard storage spaces will be needed for the 7000-series growth railcars Page 68 of 96

Proposed Railcar Procurement Manufacturer 7000 Series # Of Cars Funded TBD Dulles Phase I 64 Yes 1000-series replacement 300* Yes 4000-series replacement 100* No Dulles Phase II 64 No System expansion 75% 8-car trains System expansion 100% 8-car trains 130 No 90 No * The 1000-series and 4000-series railcars will be retired Page 69 of 96

Challenges to Meet the Demand Impacted by fleet size Railcar storage space / location ATC and signaling system Traction power system substation and tie breakers Track and structure Vertical transportation Faregates and fare machines Station design enhancements Page 70 of 96

Plan Summary Documents the processes and procedures for operating and maintaining the rail fleet and systems through FY2025 Identifies fleet and facility capacity shortages Assists with forecasting the Capital Needs Inventory (CNI) recommendations and the shortterm Capital Improvement Program (CIP) Page 71 of 96