McNary Northshore Fishway Hydro Project. History & Lessons Learned

Similar documents
Generator Rebuild and Unit Refurbishment for the Wells Hydroelectric Project. NWHA Spokane October 30, 2014

Douglas County PUD. Wells Dam Turbine Refurbishment

The Magazine of the North American Hydroelectric Industry HYDRO REVIEW. NHA Annual Conference details pg. 69

Annual Fish Passage Report 2012 Columbia and Snake River Projects

Artesis MCM Case Studies. March 2011

Inventory Levels - All Prices. Inventory Levels - By Price Range

Primary Heat Transport (PHT) Motor Rotor Retaining Ring Failure

ILLINOIS COMMERCE COMMISSION

Inventory Levels - All Prices. Inventory Levels - By Price Range

Simson Haulofu Divisional Manager. NamPower Namibia

Project Description - 1 -

Inventory Levels - All Prices. Inventory Levels - By Price Range

Alternative Delivery as a Form of Risk Mitigation

Ameren Missouri. AMENDED Renewable Energy Standard Compliance Report Prepared in Compliance with 4 CSR

LAKE CHELAN ANNUAL FLOW AND WATER TEMPERATURE REPORT Final

No. CONSUMER PRICE INDICES. Information bulletin. Moscow 2019

Rocky Reach Bridge Crane Repair. Commission Presentation February 1, 2016

TECHNICAL SERVICE BULLETIN

August 26, Project No Holt Project Turbine and Generator Nameplates by electronic filing

Crane Inspection Log. Mailing Address: P.O. Box Tulsa, OK Phone: (918) Fax: (918)

Large Air Cooled Generator Failure

Sulzer Dowding & Mills

STAFF REPORT ACTION REQUIRED

A REPORT TO. Electrical. Mechanical. Civil. Protection & Control. Transmission & Distribution. Telecontrol. System Planning

WHAKAMARU POWER STATION REHABILITATION PROJECT. Author: Glen Twining, PMP, RMU Program Manager - Whakamaru, Mercury NZ Ltd, New Zealand.

Engineers Ireland Site Visit 23 rd March 2010

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Government of Canada Hopper Car Fleet

Electric Utility Power Systems. Generation of Electricity

Customer Service, Operations and Security Committee. Information Item III-A. January 12, 2017

PET(S) FIRST & LAST NAME: January 2019

Appendix N. The 2006 Fish Passage Implementation Plan

Inspection Testing Repair

Appendix G Examples and Recommended Methods

Metal Bulletin Conference

Appendix E Water Supply Modeling

2019 NWHA Annual Conference Cryptocurrency Mining

FINAL LICENSE APPLICATION Exhibit A Description of Project

SEAPA Board of Director s Meeting Director of Special Projects Report Petersburg, Alaska September 14, 2015

AN OUTLINE HISTORY OF DANISH WIND TURBINE PRODUCTION: Output and Longevity from 1977 to 2014.

up the formulas. You can copy/paste the formulas for the days within the same October 2017 Jan 1, 2 & 5 Student Christmas Break April 2018

Algebra II Pacing Guide

Boston Scientific Energy Storage Project. Final Report (PUBLIC) November 2016

Airworthiness Directive Schedule

Total Production by Month (Acre Feet)

2015 WDC Disturbance and Protection Standards Overview

Urban Construction Initiative Certification Program Update

Overview of hydro electric dams and how they work Provide background on basic principles of hydropower and its history. Explain features that all

Our Adventure in Securing Carbon Credits

Review of U.S. market reforms for renewable integration, flexibility, and storage

Capacity Market Rules for Energy Storage Resources

2017 EXTENDED LOCK MAINTENANCE CLOSURE ON THE COLUMBIA SNAKE RIVER WATERWAY

Bulk Storage Containers

Docket No. DE Dated: 05/04/2015 Attachment CJG-1 Page 1

MARSHFIELD STATION REHABILITATION

Rebuilding A 70-YearOld Rural. Alaska Hydro. David Lockard AEA

LEAP - Life Expectancy Analysis Program For Electrical Rotating Machines. Marcio Gennari ABB Brazil Automation Products Machines Service Osasco

Metropolitan Domestic Water Improvement District Board of Directors Meeting. August 8, July 2011 Report

Virginia Offshore Wind Port Readiness Study

CUSHMAN HYDROELECTRIC PROJECT. Pat McCarty, Generation Manager

Sano Milti Khola Hydropower Project, Fulasi VDC, Ramechhap (3 MW)

Dissecting California s Electricity Industry Restructuring Process. Outline

Monthly Market Detail - June 2018 Single Family Homes Miami-Dade County

Monthly Market Detail - June 2018 Townhouses and Condos Miami-Dade County

Summary Statistics. Closed Sales. Paid in Cash. Median Sale Price. Average Sale Price. Dollar Volume. Median Percent of Original List Price Received

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report

Action Requested From AMWG

Steam Turbine Seal Rub

FOR IMMEDIATE RELEASE

FOR IMMEDIATE RELEASE

ROANOKE ELECTRIC COOPERATIVE RATE SCHEDULES

Sacramento Municipal Utility District s EV Innovators Pilot

TOTAL PROPOSED CONTRACT PRICE Ring Power Corporation $4,875,951

ELECTRIC SERVICE RATE SCHEDULES. Effective November 1, 2017

Derrick Boltt Southern Region Hydro Generation Eskom South Africa

City of Beverly Hills North Santa Monica Blvd Reconstruction. Traffic & Parking Commission June 04, 2015

Making Electricity since December Melody Collis Facilities Engineering Assistant Manager Toyota Motor Manufacturing Canada

Units of Instruction MISD Pacing Guide Days Date Range Test Date

*iiiii. May 31, 2017 VIA ELECTRONIC FILING

SWANTOWN MARINA MARINE FUELING FACILITY. Ed Galligan Executive Director

Regulatory Status and Road Map for Wind Energy in Namibia

RESIDENTIAL WASTE HAULING ASSESSMENT SERVICES. January 10, 2011 Presentation to Arvada City Council

2015 Fish Passage Plan

Decision on Merced Irrigation District Transition Agreement

Energy Markets in Turmoil The Consumer Perspective

FOR IMMEDIATE RELEASE

Section 10. Renewable Energy

Anatomy of a Kaplan blade weld repair. In Place Repair of a 9000Lb Section Broken During Generating Operations

CALENDAR OF FILING DEADLINES AND SEC HOLIDAYS

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

FOR IMMEDIATE RELEASE

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES

Guide to the Niagara Falls Power Company Photographs

Steam Turbine Generator Core Isolation Issues at the Redhawk Combined Cycle Plant

Hinkley Point C our approach to Health and Safety Iain Graham Head of Health & Safety

FOR IMMEDIATE RELEASE

STEAM TURBINE MODERNIZATION SOLUTIONS PROVIDE A WIDE SPECTRUM OF OPTIONS TO IMPROVE PERFORMANCE

Predict Future Failures From Your Maintenance Records

IOWA MOLD TOOLING CO., INC. BOX 189, GARNER, IA TEL: IMT PART NUMBER

Operational Overview. Operational Forum, 24 th March 2010

Transcription:

McNary Northshore Fishway Hydro Project History & Lessons Learned May 6, 2017

21 th Annual TECHNICAL SEMINAR Machines, Maintenance, and Management: Keeping Hydro Facilities Up and Running History & Lessons Learned McNary Northshore Fishway Hydro Project McNary project history McNary re-powering project aka Runner install (part 1) Powerhouse crane failure & repair Rewind Project Runner install (part 2) Commissioning Lessons learned

McNary Lock and Dam

5

Brief Project History On September 30, 1991, the Federal Energy Regulatory Commission (FERC) issued a 50-year license to North Wasco County Peoples Utility District (NWCPUD) to construct, operate and maintain a hydroelectric project at the McNary Dam. Originally, BPA entered into a power purchase agreement with NWCPUD in 1993. BPA withdrew from the agreement in 1994. Klickitat PUD then joined with NWCPUD to develop the McNary Project. The PUD s entered into an Ownership Agreement in August of 1995 The McNary North shore hydroelectric project was completed and started production on October 17th 1997. The total cost of the project was $29 million.

7 Project Design The project uses attraction water from the north shore fish ladder on the McNary Dam for power generation. Attraction water flow is diverted through penstocks, runs through the turbine and is then routed back to the entrance of the fish ladder to attract migrating fish and lamprey. The intake structure at McNary is located at the bottom of the dam and draws water from about 80 ft below the surface of the dam forebay. The generator at McNary produces approximately 10 MW of power, which is split equally between NWPCUD and KPUD. Over a year, this amounts to approximately 80,000 MWh of energy enough power to provide electricity to about 8,000 homes

Construction Photos

Kurt 9 Conger, NWCPUD

McNary Fishway Hydro Project Unit Cross Section

McNary Re-powering Project Runner Install - Part 1 Review repair history of turbine blade cracks Review welding procedures from past blade repairs. Evaluate failure risk and cost associated with a blade failure Recommend remedial protection measures, e.g. vibration monitoring, startup/shutdown timing, other, that may mitigate damage if a blade failure occurs. Make recommendations for repair or replacement of turbine runner or other in-water equipment.

Project Information 10 MW vertical unit commissioned in 1997 Orenco supplied Hangzhou turbine & generator, manufactured in China History of propeller runner blade cracking Runner casting quality poor with dimensional problems Initial McMillen Jacobs site visit on June 17, 2014 Annual outages with weld repairs

Early cracks near anti-cavitation fin

Cracks needing repair every 6 months

Cracks getting worse after each weld repair

Crack NDE

Recommendations Contract for additional engineering, including developing contract documents Perform generator detailed inspection early 2015 Bid and award new runner contract Bid and award runner install site work contract Action: Owners direct McMillen to develop runner procurement bid documents and runner installation bid documents.

Runner Procurement Bid documents prepared and issued to bidders Bids evaluated and recommendation for award February 2015 Weir American Hydro awarded contract effective March 31, 2015 Runner to be delivered within 311 days

New Runner

Old Runner

Runner Installation Contract Bid documents prepared and issued to bidders Bids evaluated and recommendation for award August 2015 HCMS awarded contract effective September 9, 2015 Runner to be installed by February 5, 2016 Outage begins October 2015

November 18, 2015 - Crane Failure During the last lift of major equipment from the turbine pit, a defective weld in the powerhouse crane failed. The old runner, shaft, bearings, brackets and head-covers dropped 18. Parts of the crane fell into the powerhouse damaging the stator and concrete. Nobody was injured!

Powerhouse Crane

Crane Failure Damage The crane failure damaged several major components of the project: Generator stator windings and core Turbine bearing bracket that supports the runner and shaft Lower guide bearing support bracket And the crane itself was no longer serviceable for the runner installation work

Other Component Defects Stator winding defects Loose wedges and missing side/depth packing Caused excessive wear, winding damage and reduced life expectancy Lack of strand transpositions or internal transpositions resulting in higher losses Tin/lead solder results in higher losses and increased outage risk Other (PD evidence, inadequate end winding clearances) Wicket gates, bearing surface degradation, runout measurements too high Multiple inner and outer head cover defective welds Upper and lower bearing bracket defective welds Possible defective rotor welds investigated need rewelding

Project Timeline Late 2015: HCMS Stabilized the Project Early 2016: Disassembly of Plant Components Feb-Aug 2016: Off-site Component Repairs May-June 2016: Crane Repair and Installation April 2016: Boards Authorized Stator Rewind May-July 2016: Stator Rewind June-October 2016: Reassembly of Plant Nov 2016 Feb 2017: Commissioning

Generator Rewind Based on inspections during repair of damage to stator core laminations a rewind was recommended Developed rewind bid documents and issued bid documents Evaluated bids and awarded a contract for stripping coils and installing new to National Electric Coil (NEC) After coils were manufactured HCMS took short break while installed new windings

Runner Install Part 2 While rewind was underway 300 ton mobile crane used to service work Meanwhile powerhouse crane components are repaired/replaced HCMS weld repairs rotor spider following EME fracture mechanics analysis HCMS begins reassembly of unit in July 2016 following rewind Other work included: headcover line bored for wicket gate bushings, discharge ring machined, wicket gate stems repaired, bracket weld repairs, etc. Unit alignment complete in November 2016 Unit water up attempted mid-november 2016, but leakage from wicket gate cartridges causes delay Corp of Engineers ladder outage (December 2016 through January 2017) delays commissioning to February 2017. Commissioning begins February 7 and is complete February 12, 2017

Commissioning

Turbine Output (MW) Turbine Power vs. Servo % 12.0 11.0 10.0 9.0 8.0 7.0 6.0 5.0 4.0 3.0 2.0 1.0 0.0 40 45 50 55 60 65 70 75 80 85 90 95 100 Servo %

Commissioning Conclusions Runner met guaranteed output Load rejection unit speed rise and pressure rise acceptable Generator temperature rise acceptable Bearing temperatures acceptable Vibration levels below maximum allowable

Lessons learned Purchasing Chinese equipment is risky extreme vetting is needed Weld repair of CA6NM castings very difficult Crane load testing isn t the final word Need a good team to recover from an extreme situation Be prepared to respond to changed conditions based on disassembly inspections Watch out for bad paint system specifications

Acknowledgements NWCPUD and KPUD staff HCMS American Hydro National Electric Coil Congratulations to Bob Guidinger on his retirement!

Questions?