Wisconsin Public Utility Institute. June 28, Minimum Distribution Charges. Larry Vogt. Director, Rates Mississippi Power

Similar documents
MINIMUM DISTRIBUTION SYSTEM CONCEPTS AND APPLICATIONS. Larry Vogt. Manager, Rates

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

9. Non-Residential Services (Commercial, Industrial, and Agricultural)

BUSINESS PROCEDURE. January 1, 2015

Methodology of Cost Allocation

AMENDMENT ELECTRIC SERVICE MANUAL 2014

34.00 METERING GENERAL LABELING MULTIPLE METER ENCLOSURES ON A SINGLE PREMISE

FROM B.C. HYDRO ENCLOSURE (SEE NOTE 4) RIGID CONDUITS (SEE NOTE 8) ALTERNATIVE TO LOAD BARRIER (SEE NOTE 7) SERVICE ENTRANCE ENCLOSURE

WPS SERVICE MANUAL. Section 7 Clearances. 7-1 Basic Electric Clearances - Services Miscellaneous Clearances Antenna Clearances...

10 Commercial, Industrial, Agricultural Services

SYSTEM PROTECTION SYSTEM PROTECTION. Underground Electric Distribution Standards I. FUSE COORDINATION

Max value Max life Range from. ($000) (Years) Pole Type

Transmission & Distribution Glossary of Electrical Terms

Jefferson County PUD Pole Attachment Rate Model Assumptions Exhibit A

AGRICULTURAL UNDERGROUND SERVICE 500 HP OR LESS

TABLE OF CONTENTS. Important Notices Underground Plant Protection Information. Commercial/Industrial Information Sheet

OEB's Appendix 2-B: Fixed Asset Continuity Schedule

Customer Requirements Clearance Requirements for Overhead Joint Utility Construction

WPS SERVICE MANUAL. Section Amp and Smaller - Common

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

SECTION 300 OVERHEAD SERVICE

SPECIFICATIONS FOR COMMERCIAL CONSTRUCTION

Approved Meter Sockets and Cabinets

Pretest Module 29 High Voltage Unit 1


ELECTRIC SERVICE RULES DISTRIBUTED GENERATION Issued Jan 2016

Item Code Description Unit Qty Total

Approved Contractor Construction e-guide Residential Commercial

$ homes in a subdivision. The Fee includes an S-1 Pedestal. $ homes in a subdivision. The Fee includes an S-2 Pedestal.

Customer Requirements Downtown Secondary Network Service

LIST OF EDD DESCRIPTION/ SPECIFICATION AS 19 TH OCTOBER 2016

Pretest Module 24 Three-phase Service Entrance

SPECIFICATIONS FOR RESIDENTIAL CONSTRUCTION

Associated equipment As related to metering equipment: such as the current transformers, CT wiring and test switches.

Pentahead bolts See note 2. Conduit run as specified. Company facility. Refer to drawing SS8.6-2 or SS8.6-3 STANDARD SERVICE INSTALLATION

2. DEFINITIONS. 2.3 APPROVED Acceptable to the authority enforcing the National Electric Code

COMMERCIAL QUICK REFERENCE

Commercial Electric Policy

Index Section 103 Joint Use. General Requirements for Installation of Attachments on Oncor Poles

STOUGHTON UTILITIES ELECTRIC SERVICE RULES AND INFORMATION

New Commercial Service Request-Job Process

Service Requirements

ELECTRIC SERVICE RULES UTILITY/CATV SERVICES Issued Jan 2016

3.1 Overview of ATCO Electric s URD System Design

Spring Test 10 due 05/11/2013

CONDUCTOR CONDUCTOR. Overhead Electric Distribution Standards INTRODUCTION

Electric Service Rules

201 S. Anaheim Blvd. Page No Anaheim, CA RULE NO. 2 DESCRIPTION OF SERVICE

7. Residential Single-Family and Duplex Buildings (Dwellings)

SINGLE PHASE WIRING SPECIFICATIONS

See NT POWERCOS , Classification Based On Service Size.

RATE APPLICATION MANUAL. Kansas City Board of Public Utilities

THREE PHASE WIRING SPECIFICATIONS

Table of Contents. Electrical Service Requirements. 1. General Requirements

DYNAMIC LOAD FLOW STUDIES OF DISTRIBUTION FEEDS IN THE SAN JOAQUIN VALLEY REGION

DS-1 (Residential) Customer Charge Per electric service account $ 8.23 $ 8.23 $ 8.23 Meter Charge Per electric service account $ 6.06 $ 6.06 $ 6.

SPECIFICATIONS FOR RESIDENTIAL CONSTRUCTION

SECTION 27 - PAD-MOUNTED TRANSFORMERS TABLE OF CONTENTS

Underground Distribution Construction Manual

UGI UTILITIES, INC. ELECTRIC DIVISION

320A Single Phase URD Meter Loop Installations

Engineering Service Specifications. Commercial Single-Phase Current Transformer Metering Schemes

Meter Installation. -and- Padmount Transformer Guide

WIRING DESIGN & PROTECTION REQUIREMENTS CHECKLIST

Volume 2 Charts, Formulas, and Other Useful Information

Niagara Mohawk Power Corporation d/b/a National Grid

ENTRANCE EQUIPMENT ER D PAGE 1 OF 5

PWC SCHEDULE OF DEPOSITS, FEES AND CHARGES. Table of Contents

SECTION 500 METERING AND ASSOCIATED EQUIPMENT

Installing or Rebuilding Your Electric Service

Scale of Inspection Fees of Electrical Inspectorate Schedule. I. Fees for Initial Inspections:

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

PWC SCHEDULE OF DEPOSITS, FEES AND CHARGES. Table of Contents

TEMPORARY ELECTRIC WIRING FOR CARNIVALS, CONVENTIONS, EXHIBITIONS, FAIRS AND SIMILAR USES

PUBLIC UTILITY DISTRICT NO. 1 OF LEWIS COUNTY METERING SPECIFICATIONS

SERVICE ATTACHMENT ON A BUILDING WITH BUS DUCT SERVICE ENTRANCE AND INDOOR METERING

Clark Public Utilities Commercial Electric Service Handbook. This page left blank intentionally.

7 Single Family Service

PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

JACKSON ELECTRIC COOP METER LOOP CONSTRUCTION SPECIFICATIONS JUNE 2018

Demand Charges to Deal With Net Energy Metering: Key Considerations

SERVICE REQUIREMENTS COMMERCIAL & INDUSTRIAL CUSTOMERS

CHAPTER V RESIDENTIAL WIRING

Service Requirements

New Service. From... BARRON. Spooner Office: P.O. Box 261 Spooner, WI Barron Office: P.O. Box 40 Barron, WI

RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS SECTION VI RESIDENTIAL SUBDIVISION SERVICE REQUIREMENTS

For Conduit Inspections

SOUTHWEST LOUISIANA ELECTRIC MEMBERSHIP COORPORATION COMMERCIAL SERVICE REQUIREMENTS

TELL CITY ELECTRIC DEPARTMENT RATES AND CHARGES

PJM SRTEP Meeting Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge:

Corrections most seen on plan review October 18, 2017 David Rankin Seattle Department of Construction and Inspections

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Customer Substation Manual

Parkland Light & Water Co. ELECTRIC SERVICE REQUEST AND METER STANDARDS

TADP 548 Transmission Line Design- Electrical Aspects

CHAPTER 3. Basic Considerations and Distribution System Layout

Transformer Protection

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

ACTEWAGL DISTRIBUTION SCHEDULE OF ELECTRICITY NETWORK CHARGES

TEMPORARY ELECTRICAL SERVICE

Transcription:

Wisconsin Public Utility Institute June 28, 2017 Minimum Distribution Charges Larry Vogt Director, Rates Mississippi Power 1

Costs of Service vs. Cost Recovery Residential Service Example Assuming that all defined customerrelated costs are recovered through the Customer Charge. 2

Principal Cost-of-Service Study Cost Components The classification step of the cost-of-service study assigns all of the functionalized cost elements to the fundamental cost-causation components of Energy, Demand, and Customer. Energy-related costs variable costs which are dependent on kwh energy requirements. Demand-related costs fixed costs which are dependent on kw load requirements. Customer-related costs fixed costs which are independent of load or energy requirements. 3

Classification of Functional Costs Fuel Energy Costs: VARIABLE Demand Costs: FIXED Minimum Distribution System (MDS) Customer Costs: FIXED 4

Distribution System Lines and Facilities Costs FERC Description 360 Land and Land Rights 361 Structures 362 Station Equipment S 336.4 MCM ACSR SUB M R N.C. 363 Storage Battery Equipment 364 Poles, Towers & Fixtures 365 OH Conductors & Devices Switches 4/0 CU NO. 2 AL C/N 75 N.C. N.C. 1,500 ckvar Reclosers & Sectionalizers 366 UG Conduit 367 UG Conductors & Devices 333-333-333 50-50-50 368 Line Transformers Regulators Capacitors Cutouts 15 1/0 CU Arresters 369 Services 370 Meters 25 37.5 N.O. 373 Street Lighting 5

Distribution System O&M Costs FERC Description 580-589 Operation 590-598 Maintenance Distribution Expenses (Excluding Substations) 901-905 Customer Account Expenses - Operation 906-910 Customer Assistance Expenses Operation 911-917 Sales Expenses Operation Administrative and General (A&G) Expenses (Allocated portion) 920-933 Operation 935 Maintenance 6

Cumulative 1-Phase Residential Customer Cost Components Revenue Requirement per Customer per Month MDS Customer Costs Minimal Customer Costs 7

Minimum Distribution System What is MDS? MDS is an analysis module of the cost-of-service study in which primary and secondary voltage distribution system investment and O&M costs are classified between demandrelated and customer-related cost components. Why is MDS important? MDS quantifies those fixed costs that are independent of load or energy usage and thus provides a cost-justification basis for inclusion in the Customer Charge portion of the rate structure. 8

The Access Function Of The Distribution System All primary and secondary voltage customers are connected to a distribution voltage source, i.e., a local substation. SUB There is a physical path which brings voltage to the customer s premise. Maintaining the voltage path ensures customer access to electrical power. 9

The Capacity Function Of The Distribution System Primary and secondary distribution system facilities and lines must be sized to adequately handle the customers demand for power. Electric service facilities are rated in terms of kva capacity (conductors rated in terms of ampacity). Customer Load Feeder Load 10

Objective of the Minimum Distribution System Analysis To assess each device utilized in the distribution system in terms of its mission in order to determine if its function is: Dependent on kw load requirements and therefore demand related, or Independent of kw load requirements and therefore customer related. 11

Customer or Demand? 12

Capacitor-Based Voltage Control MW SUB FEEDER 132 V +10% 120 V 108 V 10% TIME DISTANCE 13

Customer or Demand? 14

Protection Scheme Temporary Fault Condition SUB CB R 15

Protection Scheme Permanent Fault Condition SUB CB R 16

Protection Scheme Permanent Fault Condition No Load SUB CB R 17

Customer or Demand? 18

Classification of Distribution Plant for the Cost-of-Service Demand Customer Distribution Substations X Primary Lines* X X Line Transformers* X X Secondary Lines* X X Other Line Equipment* X X Service Lines Meters X X * Minimum Distribution System facilities. 19

Zero-Intercept Methodology Applied to: Line Transformers Conductors Poles THE Y-AXIS INTERCEPT UNIT COSTS IS THE UNIT COST OF ZERO CAPACITY COST OF A STANDARD SIZE UNIT CAPACITY 20

Line Transformers 21

Zero-Intercept Example Single-Phase Overhead Transformers 1. ZERO-INTERCEPT: $463.975/transformer Based on various kva sizes of 7.2 kv - 120/240 V, single bushing, polemount transformers 2. TOTAL NUMBER OF OVERHEAD TRANSFORMERS: 98,278 CUSTOMER COMPONENT = $ 463.975 98,728 = $45,807,307 3. TOTAL OVERHEAD TRANSFORMER COST: $109,960,813 DEMAND COMPONENT = $109,960,813 - $45,807,307 = $64,153,506 CUSTOMER COMPONENT = 41.7% DEMAND COMPONENT = 58.3% 22

Primary and Secondary Conductors and Poles PRIMARY NEUTRAL SECONDARY 23

UNDERGROUND PRIMARY CABLE CONCENTRIC NEUTRAL CONDUCTOR 24

CONDUIT FOR UNDERGROUND CABLES RIGID PVC FLEXIBLE 25

Distribution Poles Types Of Materials 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 1.0% 0.9% 0.8% 0.7% 0.6% 0.5% 0.4% 0.3% 0.2% 0.1% 0.0% ALUMINUM CONCRETE FIBERGLASS STEEL 0% ALUMINUM CONCRETE FIBERGLASS STEEL WOOD 26

Pole Heights Relative Frequency Distribution 40% 35% 30% 25% 20% 15% 10% 5% 0% 30' 35' 40' 45' 50' 55' 60' 65' 70' 75' 80' 85' 90' 95' POLE HEIGHTS 27

Clearance Requirements Poles lines must be designed to ensure proper safety clearances, such as specified in the National Electric Safety Code (NESC), Section 23. The NESC provides specific minimum clearances of power lines located over: Roadways, parking lots, driveways, pedestrian areas, railroad track rails, water ways, etc. Other electric conductors and services, trolley/electric train cables, communications cables, etc. 28

Pole Line Grading IMPROPER GRADING: POLES ALL HAVE THE SAME HEIGHT PROPER GRADING: POLES WITH VARYING HEIGHTS 29

Distribution Pole Classification Conclusion On Pole Height Pole height requirements are mainly a function of clearances and line grading, which are related to safety and mechanical design. In some situations, a pole height may need to be increased (e.g., from a 40 to a 45 ) to accommodate some facilities. Overall, pole height is not a predominant function of load. 30

Pole Class 31

Standard Pole Classes Example: 35 Wood Pole No. 1 39.0 No. 2 36.5 No. 3 34.0 No. 4 31.5 No. 5 29.0 No. 6 27.0 No. 7 25.0 MINIMUM CIRCUMFERENCE OF SOUTHERN YELLOW PINE POLES (@ GROUND LINE) 32

Pole Class Requirements Based On Transformer Capacity 0 TRANSFORMER kva 10 15 25 37.5 50 75 100 167 250 1 2 POLE CLASS 3 4 5 6 7 1 TRANSFORMER 2 TRANSFORMERS 3 TRANSFORMERS 33

Distribution Pole Classification Conclusion On Pole Class The physical sizes and weights of line transformers and conductors are related to their current carrying capabilities. Pole class must be increased in order to carry heavy mechanical loads caused by large line transformers and conductors. Overall, pole class is a predominant function of load. 34

Example MDS Analysis Results Poles, Transformers, and Conductors Customer Demand Poles Wood 66.4% 33.6% Concrete 47.3% 52.7% Steel 57.5% 42.5% Transformers 1Φ OH* 41.7% 58.3% 1Φ UG** 61.5% 38.5% 3Φ UG** 34.2% 65.8% Customer Demand Conductors Primary Bare ACSR OH 21.0% 79.0% 15 kv CN UG* 57.4% 42.6% Secondary WP AL OH 38.4% 61.6% Duplex OH 31.4% 68.6% 1-Conductor UG* 60.7% 39.3% * Basis for classifying transformer vaults ** Basis for classifying transformer pads * Basis for classifying conduit 35

Example MDS Analysis Results Distribution Line Devices Primary Secondary Customer Demand Customer Demand Regulators & Capacitors 100% Reclosers and Sectionalizers 100% Cutouts & Arresters Line Transformers (OH) 41.7% 58.3% Regulators & Capacitors 100% Reclosers & Sectionalizers 100% Line Protection 100% Bypass Switches Regulators 100% Reclosers & Sectionalizers 100% OH Line Switches* 21.0% 79.0% UG Line Switches* 57.4% 42.6% * Based on conductors 36

Example Cost-of-Service Results For Three Low Voltage Customer Classes 37

Q&A Larry Vogt 38

Appendix Materials 39

Weighted Linear Regression For Distribution Line Transformers m N nxy nxny 2 N nx nx 2 SLOPE N = Total number of all transformers of a given type, e.g., 59,800 7.2 kv - 120/240 V, single-bushing, polemount units n = Number of a given size transformer, e.g., 9,935 15 kva b y INTERCEPT ny m N nx N X = Transformer size in kva, e.g., 5, 7.5, 10, 15, etc. Y = Transformer unit cost in $ per unit, e.g., $724.48 (cost of a 15 kva unit) 40

Zero-Intercept Analysis The Problem With Vintage Costs $2,000 $1,800 $1,600 $1,400 Analysis of Pad-Mount Line Transformers Based on Booked Installed Costs Unit Cost $1,200 $1,000 $800 $600 $400 $200 3Φ 1Φ $0 0 10 20 30 40 50 60 70 80 90 100 kva 41

Zero-Intercept Analysis Utilizing Current Costs $15,000 Analysis of Pad-Mount Line Transformers Based on Rebuild Costs $13,500 $12,000 3Φ Unit Cost $10,500 $9,000 $7,500 $6,000 $4,500 $3,000 $1,500 1Φ $0 0 10 20 30 40 50 60 70 80 90 100 kva 42

Zero-Intercept Example Primary Overhead Conductor 1. ZERO-INTERCEPT: $0.396/ft Based on various MCM sizes of bare ACSR conductors 2. TOTAL LENGTH OF PRIMARY CONDUCTORS: 15,708,000 ft PRIMARY CIRCUIT LENGTH: 15,708,000 2 = 31,416,000 ft CUSTOMER COMPONENT = $0.396 29,898,000* = $11,827,081 * Minimum Distribution System Length 3. TOTAL PRIMARY CONDUCTOR COST: $56,416,253 DEMAND COMPONENT = $56,416,253 - $11,827,081 = $44,589,172 CUSTOMER COMPONENT = 21.0% DEMAND COMPONENT = 79.0% 43

Determination Of Overhead Circuit Lengths For The MDS TOTAL POLE MILES PRIMARY SUB PRIMARY NEUTRAL COMMON NEUTRAL SECONDARY NEUTRAL SECONDARY UNDERBUILD SECONDARY TAPS 44

Weighted Linear Regression For Distribution Conductors m N nxy nxny 2 N nx nx 2 SLOPE N = Total feet of all conductors of a given type, e.g., 47,557,568 ft of ACSR conductors n = Number of feet of a given size conductor, e.g., 26,194,939 ft of #2 ACSR b y INTERCEPT ny m N nx N X = Conductor size in MCM (a #2 wire is 66.36 MCM), e.g., 26.24, 41.74, 52.62, 66.36, etc. Y = Conductor unit cost in $ per feet, e.g., $0.659/ft (cost of a #2 ACSR conductor) 45

Pole Capacity Poles have no electrical capacity component, but they do have a mechanical capacity (strength) component that can be viewed as a proxy for electrical loading. Pole class (or circumference) can represent loading capability for wood poles, but it does not work for steel or concrete poles since different classes can have the same physical dimensions. Ground line moment capacities do differ by class for all poles. Example: 35 5-C Pole Transverse Wind Load of 1,200 lb GLMC = 33,000 ft-lbs = 33 kips 46

Weighted Linear Regression For Distribution Poles m N nxy nxny 2 N nx nx 2 SLOPE N = Total feet of all poles of a given type, e.g., 55,642 ft of 40 ft wood poles n = Number of feet of a given size pole based on its GLMC, e.g., 21,137 ft of 76.80 kilopounds (kips) poles b y INTERCEPT ny m N nx N X = Ground Line Moment Capacity in kips, e.g., 48.0, 60.8, 76.8, 96.0, etc. Y = Pole unit cost in $ per feet, e.g., $12.05/ft (cost of a 76.8 kips pole) 47

Zero-Intercept Example Wood Poles 1. ZERO-INTERCEPT: $7.883/ft Based on various kip ratings of 40 southern pine poles 2. TOTAL LINEAR FEET OF WOOD POLES: 5,579,390 ft CUSTOMER COMPONENT = $7.883 5,579,390 = $43,982,773 3. TOTAL WOOD POLE COST: $66,254,744 DEMAND COMPONENT = $66,254,744 - $43,982,773 = $22,271,971 CUSTOMER COMPONENT = 66.4% DEMAND COMPONENT = 33.6% 48

Differentiated Cost Allocation Based on Voltage Magnitude & Phase 49

3-Phase vs. 1-Phase Customers Cost-of-Service Weighted Allocators CUSTOMER VOLTAGE CLASS 1Φ LV 3Φ LV 1Φ HV 3Φ HV 1Φ OH Line Transformers L 1 L 3 3 Services: 1Φ Lines L 1 3Φ Lines L 3 Meters: Watt-hour (non-demand) LN 1 1Φ Demand LD 1 H 1 3Φ Demand L 3 H 3 LV CT LD 1 L 3 3 LV VT LD 1 L 3 3 HV CT H 1 H 3 3 HV VT H 1 H 3 3 L 1 = # of 1Φ LV customers (LN 1 +LD 1 ); L 3 = # of 3Φ LV customers H 1 = # of 1Φ HV customers; H 3 = # of 3Φ HV customers 50