Running Procedure. VAroughneck. voestalpine Tubulars GmbH & Co KG Rev.: 0

Similar documents
Running Procedure. VAxplorer. Rev.:1.

Running Procedure. Rev.:2 VAGT.

Running Procedure. VAsuperior. Rev.:2.

JFETIGER RUNNING MANUAL. Downloaded From JFETC.COM Thu, 20 Sep :15: JFETIGER. * valid at time of download * JANUARY 2015

JFEBEAR RUNNING MANUAL

RECOMMENDED PRACTICE TKC FJ-150

VAGT STill GoinG STronG. voestalpine Tubulars GmbH & Co KG

RECOMMENDED PRACTICE SEAL-LOCK FLUSH/SEMI FLUSH CONNECTIONS

U. S. STEEL TUBULAR PRODUCTS PROPRIETARY THREAD CONNECTION MANUAL

OCTG Mill RUNNING AND PULLING PROCEDURE FOR TPS-MULTISEAL (ALL TYPES & GRADES) QP 05-16E Revision No. 7 Page 1 of 11

RECOMMENDED PRACTICE SEAL-LOCK HT

RECOMMENDED PRACTICE TKC-4040 V.I.T. and HO-I

Wedge TenarisHydril Running Manual.. Premium connection approved thread compounds TSH-MD

U. S. STEEL TUBULAR PRODUCTS PROPRIETARY THREAD CONNECTION MANUAL

DRILL PIPE CARE AND HANDLING Complete Group AVENUE Leduc AB T9E 0W1 +1 (780) CG.ENG.

Benoit Premium Threading, LLC Recommended Practice. Approved By: Benoit Quality Assurance Department Date: May 1, 2013

. Recommended guidelines for the field inspection of TenarisHydril connections, FSOG Equipment, Material & Documents

ER Connection. . Recommended guidelines for the field inspection of TenarisHydril connections, FSOG Equipment, Material & Documents

Blue Quick Seal Connection

Benoit Premium Threading, LLC Recommended Practice. Approved By: Benoit Quality Assurance Department Date: January 6, 2017

22. TenarisHydril Blue Thermal Liner Connection

Wedge 533 / 503 / 553

SEC Connection. . Recommended guidelines for the field inspection of TenarisHydril connections, FSOG Equipment, Material & Documents

MS & MS XT/XC Connections

Drill Collars. Drill collars from VAM Drilling are available with the following features:

SEAL-LOCK APEX ANCILLARY

. Recommended guidelines for the field inspection of TenarisHydril connections, FSOG Equipment, Material & Documents

3SB Connection. . Recommended guidelines for the field inspection of TenarisHydril connections, FSOG Equipment, Material & Documents

2. The power tong snub line should be attached to a back up post, leveled and positioned at a 90 angle to the power tongs.

FIELD INSPECTION OF JFETIGER THREAD. Downloaded From JFETC.COM Fri, 16 Nov :49: * valid at time of download * JFETIGER.

TKC CONVERTIBLE: 8 RD / NUE / EUE / BUTTRESS 4040 / 4040 HO / 4040 HO-B FS-150 ANCILLARY SPECIFICATION

SEAL-LOCK HT-S (TIMED) ANCILLARY SPECIFICATION

1. Use slip type elevators for flush, near flush, integral, special clearance and special bevel coupled connections.

OIL COUNTRYTUBULAR GOODS

TenarisXP Buttress 4 1/2" TO 16"

Running Procedure for Casing with GB Drilling with Casing Connections

GB Connection Performance Properties Sheet Rev. 3 (10/07/2015) E N G I N E E R I N G T H E R I G H T C O N N E C T I O N S TM

SEAL-LOCK HT ANCILLARY SPECIFICATION

Drill Pipe Connection Care and Handling

Fishing Bumper Sub. Manual D450

Contents. RE PS Revision 5

Сontents. RE PS Revision 5

Blue 2 3/8" TO 13 5/8"

Blue Series and Legacy Series Make up Acceptance

USS-LIBERTY FJM. A True Flush Connection for Clearance-Critical Applications

Casing & Tubing Running Services

Wedge /8" TO 13 5/8"

Blue 2 3/8" TO 13 5/8"

Handling / Lift Plugs

Innovative Landing String system for ultra-deep offshore

HYDRAULIC WORKOVER SERVICES

Initial Running Guidelines

Сontents. RE PS Revision 8

RENTAL TOOL SERVICES. Megaton Impact Tools

NO.2311 AN API Q1, 8C AND ISO 9001:2008 REGISTERED COMPANY

Oil Country Tubular Goods

NEW & USED TUBING, CASING, DRILL PIPE SPECIFICATIONS AND COLOR CODE SHEETS

Installation Instructions

Seamless. Oil Country Tubular Goods (OCTG)

T&C connections VAM 21 / VAM 21 HT. Connect with Confidence Vallourec Oil and Gas France

At the TOP in Fatigue Performance

ENGINE MEASUREMENTS ENGINE MEASUREMENTS AND SPECIFICATIONS CYLINDER HEAD. Measure Cylinder Compression. Using Telescoping Gauges and Hole Gauges

RENTAL TOOL SERVICES. Megaton Impact Tools

Internal Cutters. Manual E535

VAM FIELD PROCEDURE. VAM Field Procedure. Vallourec - VFP VAM CDS V , June 21 st Page 1 of 29

VAM SLIJ II TM The Semi-Flush connection from a name you trust

Tube Fitting Installation Instruction

PINS & BUSHINGS METRIC

Health, Safety and Environment: Product Performance: Proven Quality: Presence: Client Focus: Tried and Tested:

SHARKBITE INSTALLATION GUIDE

TECHNICAL UNIT DAVIS-LYNCH INC. TYPE 778-MC & 777-HY STAGE COLLAR JCE 02/17/03. FILE: 778-MC TECH NEW.doc REV. 1 Page 1 of 6 DAVIS

SKiM 63/93 IGBT Modules. Content. Mounting Instruction

Blohm+Voss. BVE / BVS /8 7.5/8 250 metric tons

SHARKBITE INSTALLATION GUIDE

INDEX. PAGE Adjustment mechanism for radial position of block on rotating

Fluid-O-Tech ROTOFLOW ROTARY VANE PUMP REBUILD MANUAL

VERLON No Swell Wear Rings

DRILLING MOTOR HANDBOOK

KINGS COLLEGE OF ENGINEERING DEPARTMENT OF MECHANICAL ENGINEERING

Installation Manual for Rear Park Assist

EST GROUP DC /96 REV 8 03/03 PAGE 1 OF 11 THROUGH-THE-TUBE PLUGGING WITH CPI / PERMA PLUGS

Hydraulic Release Overshots. Manual A115

DIAMOND ROLLER CHAIN. For Agricultural and Construction Equipment

type r remote drive for auxiliary

Operating Procedures for 2 SCH 160 through 10 SCH 120 GripTight Long Radius Elbow Test Plug

LOOKOUT LED LIGHT BAR INSTALLATION MANUAL 7900 SERIES

Custom Sizing Available

THROUGH-THE-TUBE PLUGGING WITH CPI / PERMA PLUGS

NOTICE: Section 1.22 Connecting Rod

LOAD SAFETY SERIES Information Sheet

Interlocks 200 Series

GH-BETTIS SERVICE INSTRUCTIONS DISASSEMBLY & REASSEMBLY FOR MODELS HD521-M4, HD721-M4 AND HD731-M4 DOUBLE ACTING SERIES PNEUMATIC ACTUATORS

Kits 75559, & Universal Air Spring-Over-Strut

ENGINEERING & SERVICES PVT LTD

Custom LitePad Handling & Mounting Guide

Atlas Copco Oil and Gas Rigs. The Predator Advantage

Z Type Hydraulic Fishing Jar. Manual D430

Mounting SySteMS ApplicAtionS overview version 1.2 March 2013

Casing Running Tools (CRTi2-8.63)

Spring Brake Application

Transcription:

Running Procedure VAroughneck Rev.: 0 www.voestalpine.com/tubulars

Table of Content Proprietary connections Proprietary grades VAroughneck Technical data sheet Running and handling Visual inspection and field repair Transportation, handling and storage This document contains the recommended practices for the installation of voestapline tubulars proprietary connections. This is not comprehensive and is meant only as general guidance, based on best industry practices. The user assumes all responsibility for the safe and effective implementation of these practices. Further, it is the user s responsibility to provide competent and knowledgeable personnel, as well as appropriate and well maintained equipment.. 2 11/21/2017 Running procedure VAroughneck Rev.: 0

Proprietary Connections Overview VAGT VAsuperior VAxplorer VAroughneck Fields of application Casing Tubing Casing Tubing Casing Casing CAL * II IV IV IV I Efficiency Tension 100** 100 100 100 100 (% of pipe Compression 100** 100 100 100 100 body) {Uniaxial Internal pressure 100 100 100 100 100 Loads} External pressure 100 100 100 100 100 Sealability (% of efficiency) {Combined Loads} Conditions of combined load tests Tension 100 100 100 100 100 Compression 50 (for fluids: 100) 100 100 100 100 Internal pressure 100 100 100 100 100 External pressure 30 (for fluids: 100) 100 100 100 100 Medium GAS GAS GAS GAS FLUID Von mises (%) 95 95 95 95 95 Bending 20 20 20 20 20 Applications High torque NO NO*** N.A. YES YES * tested acc. to customer specifications ** exception for heavy walls *** on request enhanced torque available Visit www.voestalpine.com/tubulars for detailed information 3 11/21/2017 Running procedure VAroughneck Rev.: 0

Grades overview voestalpine Tubulars Proprietary Grades SPECIFIED SOUR SERVICE DEEP WELL MILD SWEET GAS MINIMUM YIELD GRADE API SPEC 5CT HIGH COLLAPSE ENHANCED PROPERTIES EXTREME PROPERTIES with high collapse with enhanced properties with high collapse Low Temperature Ferrite Pearlite Quenched & Tempered STRENGTH psi 55 000 J55 VA-HC-J55 VA-LT-J55 VA-FP-55-1CR K55 VA-HC-K55 VA-LT-K55 75 000 VA-FP-75-1CR 80 000 N80-Q VA-HC-N80-Q VA-EP-N80-Q VA-XP-N80-Q VA-LT-N80-Q VA-FP-80-1CR L80-1 VA-HC-L80-1 VA-EP-L80-1 VA-XP-L80-1 VA-LT-L80-1 VA-L80-1-1CR / VA-L80-1-3CR VA-SS-80 VA-SS-80-HC VA-SS-80-EP 90 000 C90-1 VA-HC-C90-1 VA-EP-C90-1 VA-XP-C90-1 VA-LT-C90-1 VA-SS-90 VA-SS-90-HC VA-SS-90-EP 95 000 R95 VA-HC-R95 VA-EP-R95 VA-XP-R95 VA-LT-R95 110 000 T95-1 VA-HC-T95-1 VA-EP-T95-1 VA-XP-T95-1 VA-LT-T95-1 C110 VA-HC-C110 VA-EP-C110 VA-SS-95 VA-SS-95-HC VA-SS-95-EP VA-SS-110 VA-S-110 VA-SS-110-HC VA-S-110-HC VA-SS-110-EP VA-S-110-EP VA-LT-C110 P110 VA-HC-P110 VA-EP-P110 VA-XP-P110 VA-LT-P110 VA-P110-1CR / VA-P110-3CR 125 000 Q125-1 VA-HC-Q125-1 VA-EP-Q125-1 VA-XP-Q125-1 VA-LT-Q125-1 VA-S-125 VA-S-125-HC VA-S-125-EP VA-D-125 VA-D-125-HC 140 000 VA-D-140 VA-D-140-HC 150 000 VA-D-150 VA-D-150-HC On request in combination with : LOW TEMPERATURE Enhanced/Extreme Properties HIGH COLLAPSE Visit www.voestalpine.com/tubulars for detailed information 4 11/21/2017 Running procedure VAroughneck Rev.: 0

VAroughneck Bild neu? VAroughneck is designed for deviated wells, extendedreach wells and drilling-with-casing. Pin-to-Pin contact at least twice the torque capability of API Buttress Stresses Controlled stress distribution proven by FEA. Buttress thread design Compatible with API Buttress. Rotating of the string Offers the opportunity to rotate the string during installation. Cementing Rotating during cementing leads to improved the cement bond. Mechanical properties Tension and compression rating 100% of the pipe body 5 11/21/2017 Running procedure VAroughneck Rev.: 0

Dimensions and torque values Dimensions and torque values will be provided through our datasheet generator: http://www.voestalpine.com/tubulars/en -> Customer service -> Datasheet generator Torques are valid for dope with friction factor 1 at room temperature Max. torque: optimum +10% Min. torque: optimum -10% Torques for special clearance couplings on request Special clearance & 20 beveled couplings: slip type elevator strongly recommended due to lower load on coupling face 11/21/2017 6 Running procedure VAroughneck Rev.: 0

Running and handling Equipment Elevator If collar type smooth bearing face If slip type clean and sharp dies Derrick Blocks are centered over rotary table Power tong Correct size and calibrated Pipe handling Thread protectors in place No hooks to lift pipes No rough handling Use proper racks Preparation Cleaning Remove and clean protectors Clean pin and box Diesel and oil-based products are not recommended as cleaning solvent Prevent corrosion Drifting Drift on pipe rack Visual inspection Check each pipe (see page 11) Apply clean and dry protectors Pipe tally Running Lifting and stabbing Remove pin protectors just before stabbing Clean connection with compressed air Check for damages Apply thread compound pin & box API-modified running compound with known friction factor between 0,8 and 1,2 is recommended. Dope shall be applied uniform on pin and box (on pin including shoulder) 7 11/21/2017 Running procedure VAroughneck Rev.: 0

Running and handling Use a stabbing guide Lower carefully Maintain good alignment Make-up Start slowly in high gear with open back-up If connection jams (torque increases immediately) Stop and release tong Disengage connection / place back-up on coupling Clean connection / visual inspection If questionable - set aside If o.k. stab again If connection stabs correct Increase speed to spin-in (max. 25 rpm) Assemble until torque increase Stop rotation / close back-up Finish in low gear and with speed less than 10 rpm Approximately 1 to 2 turns before shouldering Acceptance Final torque between maximum and minimum Use correct friction factor of dope Friction factor might be affected by extreme temperatures. No plastic deformation Increase of torque shall be reasonable uniform and smooth 8 11/21/2017 Running procedure VAroughneck Rev.: 0

Running and handling TORQUE MAXIMUM OPTIMUM MINIMUM VAroughneck R RAPID TORQUE INCREASE AT THIS POINT INDICATES PIN TO PIN CONTACT Triangle stamp shall be used as rough indicator for the make-up progress only. DIAGRAM SHOULD SHOW PIN TO PIN CONTACT ( No specific DELTA TORQUE ) TURN After final make-up the coupling should be close to base line ( field make-up) 9 11/21/2017 Running procedure VAroughneck Rev.: 0

Running and handling Break-out Place back up tong on coupling mill side Set up power tongs to low gear Speed shall be less than 10 rpm Slowly lift the pin out of the box Handle with care / use protectors Clean all pipes Visual inspection / page 11 Apply appropriate dope Any problems during make-up or breakout should be reported immediately Used equipment, thread compound, torques used, assembly speed,. Any questionable joint, set aside for evaluation, shall be brought to a disposition or rejected If rejected it must be properly marked Mill-end coupling make-up Couplings to be changed have to be made-up to position Apex of the triangle ( +/- 1,5 mm = +/- 0,06 ) Thread lock compound Pin Thread lock compound shall be applied on the first two-thirds of the threads. No other compound on pin. Box No lock compound or dope compound on Box 10 11/21/2017 Running Procedure VAroughneck Rev.: 0

Visual inspection and field repair 1 Shoulder 2 Internal bore 3 Cylindrical section 4 Perfect thread length 5 Non perfect thread length * * Not shown in sketch 11 11/21/2017 Running procedure VAroughneck

Visual inspection and field repair Element Area Rust Rust + Pitting Burrs Scratches Dent Shoulder 1 surface with N/A surface with surface with file and Pin Radius between Shoulder and Cyndrical section 1->3 surface with N/A surface with surface with file and Edge between shoulder and bore 1->2 Cylindrical section 3 N/A N/A Remove rust with. Pitting is accepted. N/A N/A surface with file and surface with file and Perfect Thread Length (measured from PIN end) PIPE OD mm inch 4 1/2 32,76 1,29 Internal bore 2 N/A 5 35,93 1,41 5 1/2 37,52 1,48 Perfect thread length (a*) Non-perfect thread length 4 5 surface with surface with surface with file and surface with file and 6 5/8 42,28 1,66 7 47,03 1,85 7 5/8 51,81 2,04 a* Up to 2 thread-turns may be imperfect if not more than ¼ of a turn is affected. If more than 2 thread-turns / or more than a half turn in total / are affected, hand-repair may be accepted after approval by voestaline Tubulars specialist. Abrassive fleece : 400 / 500 (superfine) Emery paper : 300-400 (superfine) 12 11/21/2017 Running procedure VAroughneck Rev.: 0

Visual inspection and field repair Box Element Rust Rust + Pitting Burrs Scratches Dent Shoulder (a*) Perfect thread length (b*) Non-perfect thread length Change coupling Change coupling Minor pitting, after removal of rust with abrassive fleece, is accaptable N/A Minor accepted Change coupling Change coupling General : The phosphated surface shall not be removed by hand repair (except area 3,4 and 5. If removed, it can be accepted after approval by voestalpine Tubulars specialist and application of phosphate spray. It is also recommended that after repair Moly-disulfide spray should be applied (*pin and box). a* This is only for accessoires b* Up to 4 thread-turns may be imperfect if not more than ½ of a turn is affected. If more than 4 thread-turns / or more than 2 in total are affected, hand-repair may be accepted after approval by voestalpine Tubulars specialist Mill-end make-up : Couplings to be changed have to be made-up to position. Apex of the triangle ( +/- 1,5 mm = +/- 0,06 ) 13 11/21/2017 Running procedure VAroughneck Rev.: 0

Transportation, Handling and Storage (As recommended by API 5C1) Transportation Handling Load pipe on bolsters and tie down with suitable chains or straps at the bolsters Load pipe with all couplings on the same end of the truck Do not overload the truck Before loading or unloading thread protectors should be in place Do not unload pipe by dropping Avoid rough handling which might damage the threads or the body of the pipe When rolling pipe, on the rack, keep pipe parallel and do not allow pipe to strike the ends Do not use hooks to lift pipes 14 11/21/2017 Running procedure VAroughneck Rev.: 0

Transportation, Handling and Storage (As recommended by API 5C1) Storage At least every six month some of the pin and box thread protectors should be removed at random and the threads checked for corrosion First tier of pipes should be no less than 1,5 feet (approximately 0,5m) from the ground Pipes should properly rest on supports to prevent bending and damages Between the successive layers of pipes you should provide wooden strips as separators Do not stack pipes higher than 9 feet (appr. 3 m) Only use thread protectors that correspond to the threaded pin/box ends Do not mix different pipes in the stack All protectors must be secured and should have no damage 0,5m 15 11/21/2017 Running procedure VAroughneck Rev.: 0