New Jersey State Report

Similar documents
Illinois State Report

2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017)

4.7: New Jersey RTEP Overview

Sub Regional RTEP Committee Mid-Atlantic

Energy Policy Implications: PJM Planning

Transmission Expansion Advisory Committee

Reliability Analysis Update

2016 Load & Capacity Data Report

PJM Regional Transmission Expansion Planning (RTEP) Process

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

SECTION 3 - ENERGY MARKET, PART 2

Sub Regional RTEP Committee Mid-Atlantic

Transmission Expansion Advisory Committee Meeting. April 23, 2008

Reliability Analysis Update

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Sub Regional RTEP Committee Mid-Atlantic

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Merger of the generator interconnection processes of Valley Electric and the ISO;

Overview of ISO New England and the New England Wholesale Power Markets

2018 Load & Capacity Data Report

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

Decision on Merced Irrigation District Transition Agreement

Interconnection and Net Metering Service in Ohio

The Transmission Lay of the Land

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

West Virginia Energy Plan and Becoming an Electric Generator

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

Distributed Solar Generation in the Long-Term Load Forecast

Supplemental Report on the NCTPC Collaborative Transmission Plan

SPP OVERVIEW. Mike Ross Senior Vice President, Government Affairs and Public Relations

Wholesale Electric Market Economics

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position Y Linden 138 kv & 230 kv

Sub Regional RTEP Committee Mid-Atlantic

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

Sub Regional RTEP Committee - Southern. August 19, 2011

Sub-Regional RTEP Committee PJM South

ERCOT Overview. Paul Wattles Senior Analyst, Market Design & Development. Solar Energy Industries Association July 11, 2012

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Feasibility Study Report

Distributed Solar Generation Update

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Pennsylvania State Report

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Sub Regional RTEP Committee South

Sub Regional RTEP Committee Western Region ATSI

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

Reliability Analysis Update

Feasibility Study Report

Market Efficiency Update

Transmission Expansion Advisory Committee. Reliability Analysis Update

Interconnection System Impact Study Report Request # GI

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

PSE Attachment K Puget Sound Area Transmission Meeting

IMM Quarterly Report: Summer 2017

21st Century Power Grids: Reliable, Controllable and Resilient

Transmission Expansion Advisory Committee

Impact of Distributed Energy Resources on Transmission System Reliability

Feasibility Study Report

Robert L. Mitchell CEO and Co-Founder Atlantic Wind Connection

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

Implications of Alberta s Evolving Electricity Market for Solar

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

100 MW Wind Generation Project

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

COMPANY AND WORKFORCE

2018 PJM BASELINE RELIABILITY ASSESSMENT

New 115 kv Disconnect Switches at Bloomsburg MTS

PLANNING TO START OR EXPAND A BUSINESS?

Market Efficiency Update

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources

Reliability Analysis Update

Sub Regional RTEP Committee Mid-Atlantic

Power Systems Fundamentals

STATE OF NEW JERSEY BOARD OF PUBLIC UTILITIES

Electric Vehicles and the Power Grid. October 29, 2010 Biloxi, MS

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK

NJ Solar Market Update As of 10/31/15

Market Efficiency Update

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

FTR Modeling Enhancements for Future Transmission Expansions

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Local Transmission Plan. October 11, 2013 Revised August 25, 2014

Sub Regional RTEP Committee South

PUBLIC SERVICE ELECTRIC AND GAS COMPANY PROPOSAL FOR BASIC GENERATION SERVICE REQUIREMENTS TO BE PROCURED EFFECTIVE JUNE 1, 2016

System Impact Study Report

What is the Future of Competitive Markets? Some Fundamental Preliminaries and View from Events in the PJM Market

Market Efficiency RTEP Proposal Window

MILLIGAN SOLAR PROJECT

MINIMUM OIL BURN/AUTOMATIC FUEL SWAPPING CAPABILITY

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Energy Storage at PG&E

May 11, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Post Office Box Lansing, MI 48909

Transcription:

New Jersey State Report July 2017

Table of Contents 1. Planning Generation Portfolio Analysis Transmission Analysis Load Forecast 2. Markets Capacity Market Results Market Analysis 3. Operations Emissions Data 2

Executive Summary (July 2017) Existing Capacity: Natural gas represents approximately 58 percent of the total installed capacity in New Jersey while coal represents approximately 11 percent. This differs from PJM where natural gas and coal are relatively even at 35 and 34 percent respectively. Interconnection Requests: Natural gas represents more than 97 percent of new interconnection requests in New Jersey. Deactivations: Approximately 10 MW of capacity in New Jersey retired in 2016. This represents less than 3 percent of the 392 MW that retired RTO-wide in 2016. 1,600 MW announced retirement to occur 2017. 1,200 MW retired on June 1, 2017. RTEP 2016: New Jersey RTEP 2016 projects total more than $63 M of investment. Approximately 78 percent of that represents supplemental projects. Load Forecast: New Jersey load growth is nearly flat, averaging between - 0.4 and 0.3 percent per year over the next 10 years. This aligns with PJM RTO load growth projections. 3

Executive Summary (July 2017) 2020/21 Capacity Market: Compared to the PJM footprint, New Jersey s distribution of generation, demand response and energy efficiency is similar. 6/1/14 5/31/17 Performance: New Jersey s average daily locational marginal prices were consistently at or below PJM average daily LMPs. Nuclear resources represented 41 percent of generation produced in New Jersey while natural gas averaged 29 percent. Emissions: 2016 carbon dioxide and sulfur dioxide emissions are slightly up from 2015; nitrogen oxides continue to hold flat from 2015. 4

PJM Service Area - New Jersey (December 31, 2016) PJM operates and plans the bulk electric system in New Jersey, including facilities owned and operated by Atlantic City Electric Co., Jersey Central Power & Light, Linden Variable Frequency Transformer (VFT), Neptune Regional Transmission System, Public Service Electric & Gas Co. 5

Planning Generation Portfolio Analysis 6

New Jersey Existing Installed Capacity (Capacity Rights, December 31, 2016) Summary: Natural gas represents approximately 58 percent of the total installed capacity in New Jersey while coal represents approximately 11 percent. Overall in PJM, natural gas and coal are relatively even at 35 percent and 34 percent respectively. * Gas Contains Natural Gas Other Gas 9,731 MW 44 MW 7

PJM Existing Installed Capacity (Capacity Rights, December 31, 2016) In PJM, natural gas and coal make up nearly 70 percent total installed capacity. * Gas Contains Natural Gas Other Gas 62,941 MW 405 MW 8

Natural gas represents more than 97 percent of new interconnection requests in New Jersey. Total MW Capacity by Fuel Type New Jersey Interconnection Requests (Requested Capacity Rights, December 31, 2016) MW # of projects Active 4,842 52 Under Construction 1,354 43 Suspended 1,259 20 Total 7,455 115 Fuel as a Percentage of Projects in Queue 9

NJ Interconnection Requests Active In Service Suspended Under Construction Withdrawn Total Sum MW # of Projects MW # of Projects MW # of Projects MW # of Projects MW # of Projects MW # of Projects Biomass 10.0 1 10.0 1 Coal 24.0 1 15.0 1 39.0 2 Diesel 0.0 1 0.0 1 Hydro 20.5 2 1,001.1 2 1,021.6 4 Methane 45.3 16 40.6 9 85.9 25 Natural Gas 4,787.5 17 6,993.0 63 1,246.0 4 1,234.0 13 45,167.0 138 59,427.5 235 Nuclear 381.0 6 381.0 6 Oil 35.0 2 945.0 8 980.0 10 Solar 54.0 25 163.5 81 10.1 7 95.7 27 1,214.2 364 1,537.5 504 Storage 0.0 10 0.0 2 0.0 7 0.0 2 20.0 25 20.0 46 Other 45.5 7 45.5 7 Wind 0.0 1 3.3 2 601.7 17 605.0 20 Total 4,841.5 52 7,638.3 174 1,259.3 20 1,353.7 43 49,060.2 572 64,153.0 861 10

New Jersey Progression History Interconnection Requests (Requested Capacity Rights, 1999-2016) Final Agreement Final Agreement Following Final Agreement execution, 1,302 MW of capacity withdrew from PJM's interconnection process. Another 2,574 MW have executed agreements but were not in service as of December 31, 2016. Overall, 13 percent of requested capacity MW reaches commercial operation. 11

New Jersey 2016 Generation Deactivations (Capacity, As of December 31, 2016) Unit Columbia Dam Hydro (Columbia NJ) MW Capacity TO Zone Age Actual Deactivation Date 0.5 JCPL undetermined 10/3/2016 Warren County Landfill 1.5 JCPL 10 6/1/2016 BL England Diesel(s) {IC1, IC2, IC3, IC4} 8.0 AE 51 5/31/2016 Summary: Three generating units in NJ deactivated in 2016 11 generating units totaling 392 MW of capacity deactivated in PJM in 2016 12

New Jersey 2016 Announced Generation Deactivations (Capacity, As of December 31, 2016) Unit MW Capacity TO Zone Age Projected Deactivation Date B.L. England 2 155 AE 52 *4/30/2017 B.L. England 3 148.9 AE 42 *4/30/2017 Hudson 2 617.9 PSEG 47 6/1/2017 Mercer 1 321 PSEG 55 6/1/2017 Mercer 2 320.3 PSEG 55 6/1/2017 Note: There are additional generators in NJ slated to deactivate in future years see deactivation maps *B.L. England notified PJM of its intent to deactivate effective 4/30/2017 but due to reliability reason both B.L. England units will continue to operate under an RMR arrangement until the required upgrades are completed Summary: In 2016 five generating units in NJ announced their intention to deactivate, all in 2017. In 2016 there were a total of 23 PJM generating units that announced their intent to deactivate, ranging in date from 2016-2020. 13

New Jersey 2016 Actual and Announced Generation Deactivations (Capacity, As of December 31, 2016) 14

Planning Transmission Infrastructure Analysis 15

NJ RTEP Baseline Projects 16

Baseline Load Growth/ Deliverability & Reliability Congestion Relief - Economic Operational Performance Generator Deactivation TO Criteria Violation NJ RTEP Baseline Projects NJ Baseline Project Driver Map ID Project ID Project 1 b2722 Reconductor the 1 mile Bergen Bergen GT 138 kv circuit (B-1302) Required Date 10/30/20 16 Cost ($M) Designated Entity* 2016 TEAC Review $6.50 PSEG 12/8/2015 2 b2755 Build a third 345 kv source into Newark Airport 6/1/2018 $43.00 PSEG 7/14/2016 Note: Baseline upgrades are those that resolve a system reliability criteria violation. 17

NJ RTEP Network Projects 18

Generation Interconnection Merchant Transmission Interconnection Long-term Firm Transmission Service NJ RTEP Network Projects NJ Network Project Drivers Map ID 1 2 Project ID n4940 n4985 Project Reconductor the 2.1 mile Lake Nelson-Kilmer (I1023) 230kV line w/ single 1590 kcmil ACSS conductor, replacing the existing 1590 kcmil ACSR conductor Horseshoe Road Substation: Construct a 115 kv three breaker ring bus interconnect substation between Raritan River and Werner substations for AA2-128 Interconnection. Required Date Cost ($M) TO Zone(s) 2016 TEAC Review AA2-128 6/30/2017 $8.00 JCPL 10/6/2016 AA2-128 6/17/2016 $5.92 JCPL 10/6/2016 Note: Network upgrades are new or upgraded facilities required primarily to eliminate reliability criteria violations caused by proposed generation, merchant transmission or long term firm transmission service requests. 19

NJ TO Supplemental Projects 20

NJ TO Supplemental Projects Ohio Supplemental Project Driver Map ID 1 2 3 Project ID Project s0879.1 Relocate the Bergen 138kV 40P and 90P breakers to the Bergen generation station and install additional one 138 kv breaker s1151 s1177 Build a new 13 kv class-h substation in Kingsland with two new 230/13 kv transformers Install Stop Joints on South Mahwah - Waldwick 345 kv circuit J-3410 Required Date Cost ($M) TO Zone(s) 2016 TEAC Review 12/31/2017 $6.16 PSEG 7/26/2016 5/31/2019 $29.60 PSEG 7/26/2016 5/23/2017 $6.00 PSEG 11/3/2016 Note: Supplemental projects are transmission expansions or enhancements that are used as inputs to RTEP models, but are not required for reliability, economic efficiency or operational performance criteria, as determined by PJM. 21

NJ Merchant Transmission Project Requests Queue Project Name MFO Status In Service Date TO U2-077 Linden 230kV 300 In-Service 06/01/11 PSEG W1-001 Linden VFT 230kV 15 In-Service 06/01/11 PSEG X1-078 Deans (Poseidon) 500kV 525 Under Construction 05/01/17 PSEG 22

Planning Load Forecast 23

PJM Annual Load Forecasts (January 9, 2017) 24

New Jersey 2017 Load Forecast Report Transmission Owner 2017 2027 Summer Peak (MW) Growth Rate (%) Winter Peak (MW) 2016/17 2026/27 Growth Rate (%) Atlantic City Electric Company 2,495 2,445-0.2% 1,630 1,565-0.4% Jersey Central Power and Light 6,056 6,108 0.1% 3,864 3,797-0.2% Public Service Electric and Gas Company 10,057 10,012 0.0% 6,821 6,754-0.1% Rockland Electric Company 404 404 0.0% 234 233 0.0% PJM RTO 152,999 155,773 0.2% 131,391 134,915 0.3% *PJM s 2017 forecast reflects methodology improvements implemented in 2016: variables to account for equipment and appliance saturation and efficiency, distributed solar generation adjustments and more refined treatment of weather data. 25

Markets Capacity Market Results 26

PJM 2020/21 Auction Clearing Prices (May 23, 2017) 27

New Jersey - Cleared Resources in 2020/21 Auction (May 23, 2017) Cleared MW (Unforced Capacity) Change from 2019/20 Auction Generation 12,631 (643) Demand Response 574 (164) Energy Efficiency 199 101 Total 13,403 (706) EMAAC Locational Clearing Price $187.87 28

PJM - Cleared Resources in 2020/21 Auction (May 23, 2017) Cleared MW (Unforced Capacity) Change from 2019/20 Auction Generation 155,976 882 Demand Response 7,820 (2,528) Energy Efficiency 1,710 195 Total 165,506 (1,450) 29

Generation Demand Response Energy Efficiency New Jersey Offered and Cleared Resources in 2020/21 Auction (May 23, 2017) Unforced Capacity Offered MW 13,647 Cleared MW 12,631 Offered MW 590 Cleared MW 574 Offered MW 203 Cleared MW 199 Total Offered MW 14,440 Total Cleared MW 13,403 30

Markets Market Analysis 31

LMP ($/MWh) New Jersey - Average Daily Load and LMP (June 1, 2014 - May 31, 2017) 300 New Jersey s average daily LMPs generally align with the PJM average daily LMP 18,000 250 200 150 15,000 12,000 9,000 Load (MW) 100 50 6,000 3,000 0 0 6/1/2014 12/1/2014 6/1/2015 12/1/2015 6/1/2016 12/1/2016 6/1/2017 NJ Average Real-time LMP PJM Average Real-time LMP NJ Average Real-time Load 32

LMP ($/MWh) New Jersey Hourly Average LMP and Load (June 1, 2014 May 31, 2017) New Jersey s hourly LMPs were at or above the PJM average. 60 12,000 50 10,000 40 30 8,000 6,000 Load (MW) 20 4,000 10 2,000 0 Hour Beginning 0 4 8 12 16 20 NJ Average Real-time Hourly LMP PJM Average Real-time Hourly LMP NJ Average Real-time Hourly Load 0 33

New Jersey Energy Production (June 1, 2014 May 31, 2017) Amount of energy produced by New Jersey generation Misc., 2% Coal, 2% Gas, 11% Nuclear, 41% Imports, 14% Natural gas, 29% 34

Operations Emissions Data 35

PJM - Average Emissions (lbs/mwh) (December 31, 2016) CO 2 (lbs/mwh) 1,350 1,300 1,250 1,200 1,150 1,100 1,050 1,000 950 PJM Average Emissions (lbs/mwh) Carbon Dioxide Nitrogen Oxides Sulfur Dioxides SO 2 and No x (lbs/mwh) 9 8 7 6 5 4 3 2 1 900 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 0 36

New Jersey - Average Emissions (lbs/mwh) (December 31, 2016) CO 2 (lbs/mwh) 700 650 600 New Jersey Average Emissions (lbs/mwh) Carbon Dioxide Nitrogen Oxides Sulfur Dioxides SO 2 and No x (lbs/mwh) 3.0 2.5 2.0 550 1.5 500 1.0 450 0.5 400 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 0.0 37