Light and invisible. Underground transmission with HVDC Light Dag Ravemark, Bo Normark. Grid flexibility

Similar documents
What can HVDC Light do for you it s time to connect Applications Key Components

Gunnar Asplund HVDC R&D Manager Sweden. Latest HVDC Light developments. IEEE Montreal

Title: Advanced power electronics for cable connection of offshore wind Paper to be presented at Copenhagen Offshore Wind 2005

ABB POWER SYSTEMS CONSULTING

OVERVIEW OF UNDERGROUND POWER CABLES AT HIGH/EXTRA HIGH VOLTAGE LEVELS

JCP&L Verbatim Response to Middletown Township s Questions

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Power From Shore: An introduction to HVDC Light Offshore

Generators for the age of variable power generation

Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven Electric grid on and off-shore: current status, obstacles and new developments

Transmission Grid Reinforcement with Embedded VSC-HVDC. Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Final Written Examination.

Experience on Realizing Smart Grids. IEEE PES conference, Gothenburg

Peter Lundberg, ABB HVDC, Nov 2016 HVDC Light - Power from shore. ABB Group November 16, 2016 Slide 1 1JNL A

SUMMARY OF THE IMPACT ASSESSMENT

Smart Grid 2.0: Moving Beyond Smart Meters

Ecodesign Directive for Batteries

Shunt reactors Proven history for future success

environment briefing02

Long distance bulk transmission

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

The Smart Way. HVDC PLUS One Step Ahead. Answers for energy.

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

ABB Group August 27, 2010 Slide 1

Benefits of HVDC and FACTS Devices Applied in Power Systems

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

The Grid Link Project. Summary of the Report for the Independent Expert Panel

Energy Management for Regenerative Brakes on a DC Feeding System

Chapter 1. Overview of HVDC applications

Integration of Large Wind Farms into Electric Grids

Cables Connect, cover and forget

Targeted Application of STATCOM Technology in the Distribution Zone

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

OPF for an HVDC feeder solution for railway power supply systems

Electromagnetic Fully Flexible Valve Actuator

HVDC Back-to-Back Interconnections Enabling reliable integration of power system

Transmission s Future Today. High Capacity High Efficiency Low Profile

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

Western Alberta Transmission Line (WATL) HVDC Project

Improving Roadside Safety by Computer Simulation

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar

Stora Enso Helping Stora Enso achieve big energy savings

Question Question 1.2-8

Location of Noise Sources in Fluid Power Machines

SVC Light For electrical transmission grids

Full-Scale Medium-Voltage Converters for Wind Power Generators up to 7 MVA

Improvements of Existing Overhead Lines for 180km/h operation of the Tilting Train

OPF for an HVDC Feeder Solution for Railway Power Supply Systems

Robert L. Mitchell CEO and Co-Founder Atlantic Wind Connection

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

The cement and minerals industry

NRECA Cooperative Research Network. Modern Grid Initiative Southeast Summit August 10, 2006 Nashville, TN

Power Engineering - Egill Benedikt Hreinsson. Lecture 15a. HVDC Transmission. 2 November 2011

Breaking new ground. A circuit breaker with the capacity to switch 15 large power plants

Technical Guide No. 7. Dimensioning of a Drive system

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

Steel solutions in the green economy FutureSteelVehicle

Tibin Joseph Marie Curie Early Stage Researcher Institute of Energy Cardiff University

Microgrid solutions Delivering resilient power anywhere at any time

OTAHUHU-MANGERE-ROSKILL- HEPBURN ROAD 110 KV CIRCUITS

MVDC PLUS Managing the future grid

ADF. Restoring the perfect wave

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Electrical. Earthing & Bonding. Installation Techniques. Learning Notes MODULE 2.2 UNIT PHASE:2

When Grids Get Smart - ABB s Vision for the Power System of the Future

HVDC Light Grid friendly and ecological technology

HVDC Solutions. for Integration of the Renewable Energy Resources. Marcus Haeusler HVDC Lead Engineer. siemens.com/energy/power-transmission

THE PROTEAN AND POC-MAST DESIGN

Congestion relief. FACTS the key to congestion relief Rolf Grünbaum, Peter Lundberg, Göran Strömberg, Bertil Berggren. Powering the economy

INDUSTRY'S PERSPECTIVE ON THE COMPLIANCE WITH THE LOW SULPHUR REQUIREMENTS. Pulp and paper industries' views and assessment

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.

Welcome to Breckenridge. T&D Research Stem Meeting Tuesday August 11, :00 5:00 pm

Wind Power Plants with VSC Based STATCOM in PSCAD/EMTDC Environment

Management of Congestion in the Deregulated Energy Market

HVDC POWER FROM SHORE. B. WESTMAN* K. ERIKSSON* G. PERSSON* A. MÆLAND** ABB Sweden*, Norway**

Brochure. Wind turbine generators Reliable technology for all turbine applications

A COMPARISON OF THE PERFORMANCE OF LINEAR ACTUATOR VERSUS WALKING BEAM PUMPING SYSTEMS Thomas Beck Ronald Peterson Unico, Inc.

STABILIZATION OF ISLANDING PEA MICRO GRID BY PEVS CHARGING CONTROL

1 Faculty advisor: Roland Geyer

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Use of High-Power Thyristor Technology for Short-Circuit Current Limitation in High Voltage Systems

Introduction to transmission network characteristics - technical features. Slobodan Markovic EKC Athens,

30 top tips to tackle HVAC challenges No.09 - Energy efficiency

Department of Energy Analyses in Support of the EPA Evaluation of Waivers of the Renewable Fuel Standard November 2012

NORTH SLOPE BOROUGH Department of Public Works P.O. Box 350 Barrow, Alaska 99723

Control System for a Diesel Generator and UPS

Power stability for manufacturers

Raphael Görner, Head of Marketing & Sales, Grid Systems Germany Building bridges with HVDC Solar Energy for Science

Practices for Energy Sustainability Enhancement in Metro Systems

CHAPTER 8 - GAS AND ELECTRICITY TRANSMISSION COMPARATIVE CASE STUDY

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Printed on elementary chlorine-free bleached paper.

Implementation of FC-TCR for Reactive Power Control

Power Voltage Transformers for Air Insulated Substations

ABB Next Level Big shift in power attractive opportunities

Electric Networks/Ina Lehto Updated Original 12/2011

EPRI HVDC Research. Gary Sibilant, EPRI. August 30, 2011

Looking Towards the Future: Advantages of 765-kV Transmission Technology

Transcription:

Light and invisible Underground transmission with HVDC Light Dag Ravemark, Bo Normark When power must be transmitted over long distances, overhead lines (OHL) have long been the prevailing technology. The costs and performance of buried cables made them unattractive as an alternative. The advent of HVDC Light is bringing about a huge change. Whereas buried cables are not suitable for long-distance high-voltage AC transmissions, the different behavior of DC fundamentally changes this. The high costs of burying cables which has long made this mode unattractive is also losing ground as an argument. The combination of environmental concerns over the impact of overhead lines and the availability of new cost-saving technologies is leading to a re-think. Underground cables are now more attractive than ever before. 25

For over a century electrical transmission systems have been based mainly on overhead transmission lines (OHL). The main reason for this has been the cost advantage when compared to highvoltage underground transmission. Recent studies suggest the cost premium of underground transmission is in the range of 5 15 times the traditional overhead transmission alternative. But this comparison is already dated. Two main factors are affecting the paradigm: Environmental restrictions are increasing the costs and implementation time for overhead transmission. Technological development significantly reduces the cost of underground transmission. Consequences of environmental restrictions There are several reasons why underground HVDC cables have a better environmental profile than overhead HVAC lines. Land use An HVDC cable uses significantly less land than an overhead HVAC line. The right-of-way for a 400 kv OHL can be a 60 m wide strip 1 where no buildings/high trees are allowed whereas an underground DC cable needs at most a 4 m wide inspection road on top of it. For AC OHL the amount of land required for a 400 km transmission is 2,400 hectares (1 hectare = 10,000 m 2 ). However only 160 hectares are required for DC cable (< 6 percent). Audible noise Restrictions on land use stretch beyond the immediate right-of-way. Audible noise from transmission line corona most noticeable when conductors are wet in foggy weather conditions might restrict buildings close to OHL. The width of this noise corridor depends on local noise ordinance as well as on the design and voltage of the line. Noise objections from neighbors make it more difficult 1 Land use comparison for HVDC Light and AC OHL transmission. to obtain permits. An underground DC cable naturally has no audible noise emission. EMF Magnetic and electrical fields can also restrict the use of land close to an OHL. In several countries a precautionary policy vis-à-vis magnetic fields is in force. The Swedish National Electrical Safety Board and the Dutch Ministry of Housing and Environment 2 Property devaluation (%) Table 1 AC OHL DC AC right of way 60 m AC noise clearance 100 m (commercial) AC noise clearance 200 m (residential) AC EMF clearance 360 m (school) Effect of proximity of overhead line on property values (in Finland). 0-4 -8-12 -16 Comparison of material usage Material DC AC underground OHL Aluminium 3.3 kg 2.1 kg Copper 1.4 kg PVC 2.3 kg PEX 6.1 kg Steel 100.0 kg Ceramics 0.3 kg Concrete 376.3 kg Total 13.1 kg 478.8 kg DC underground right of way; a 4m inspection road 0 500 1000 1500 2000 2500 Distance from line (m) both suggest a 0.4 µt safety level for 50 Hz magnetic fields from transmission lines. This level corresponds to field levels normally encountered in city environments today. In contrast to an AC line, the field for a DC cable is static (non-radiant). Applying the same precautionary policy as for AC would not call for the provision of any EMF corridor around an underground DC cable. The field immediately above the cable is far less than the earth s natural magnetic field. Right-of-way as a loss of CO 2 sink Growing forests are considered CO 2 sinks because trees convert carbon dioxide from the atmosphere into carbon stored in the form of wood and organic soil matter. A forest can absorb 9.2 tons of CO 2 per hectare per year. Building a 400 km, 400 kv overhead transmission line through an area that is 75 percent forest represents a loss of a carbon sink of 16,780 tons of CO 2 per year. HVDC Light technology was introduced in 1997 with a small test installation of 3 MW. Since then, both cables and converters have progressed dramatically in both size and performance. Material use The material intensity of an AC OHL is higher than a DC cable. The statistical material use per meter of transmission is compared in Table 1. Using lifecycle assessment (LCA) to analyze the cradle to grave material impact, the DC cable has an environmental impact of 64.5 kg of CO 2 - equivalents per meter and the AC OHL has an impact of 365.4 kg of CO 2 -equivalents per meter. In other words, the material used in the DC cable has only 17.6 percent the environmental impact of the AC OHL. 26

Aesthetics Property value Several studies have shown that property values are reduced close to OHL. For example, a study carried out in the United Kingdom showed the value of detached properties a distance of 100m from OHL were 38 percent lower than comparable properties. A Finnish study showed that the reduction is proportional to the distance from the line 2. Assuming that every 500 m along the 400 km line there is: One property 500 m from the OHL (with 8 percent value reduction). Two properties 1000 m from the OHL (with 4 percent value reduction). Three properties 2000 m from the OHL (with 2 percent value reduction). If an average property is valued at $ 150,000, the reduction in property value along the 400 km OHL then amounts to a staggering $25 million. Electrical losses When HVDC Light underground transmission is used inside an AC-grid, the transmission system can be operated in a more optimal way leading to lower electrical losses. The losses in the HVDC line are equivalent to the loss reduction of the AC grid, ie, the HVDC line is considered to transmit electricity without losses. The more efficient operation of a transmission system with HVDC can be attributed to two causes: the average higher voltage level in the AC grid and the reduction of reactive power flows. For example, on a 350 MW transmission (50 percent utilization) there are no HVDC losses whereas HVAC losses amount to 5 percent. This means the operator has 76,650 MWh more electricity to sell each year with an HVDC connection. The overall electrical losses 1) can be translated into 45,990 tons of CO 2 emitted per year. Power system stability HVDC systems can never become overloaded, and they offer additional benefits through their ability to con- trol power flow and voltage 3. HVDC the development of extruded cables can be very effective in damping for HVDC. The extruded cable has power oscillations, as well as avoiding some significant advantages over traditional mass impregnated cables. It: or limiting cascading system disturbances, particularly when connecting Is completely oil free. two points inside the same AC-grid, Has low weight. ie, in parallel with AC-lines: an HVDC Is very flexible and this simplifies Light converter is excellent at generating or consuming reactive power. Has very simple prefabricated handling during installation. joints. Technical characteristics of underground transmission system When planning traditional overhead transmission lines, it is better to choose high voltage lines for transmission over large distances because not only can transmission capacity be increased but losses are also reduced. However, for AC transmission in underground cables the situation is somewhat different. If the voltage is increased, the reactive power absorption of the cable increases so that its technical maximum length is reduced rather than increased. The laws of physics in this case then work against long AC transmission. Today s experience of cable transmission suggests a maximum transmission distance of about 60 km for a 345 kv AC underground cable. Reasons why underground HVDC cables have a better environmental profile than overhead HVAC lines include land use, audible noise, EMF, material use, and power systems stability. HVDC Light, a new transmission system designed for underground transmission This technology is based on some key components: Extruded cable technology Converter technology Control and protection technology Voltage source converters cause less stress on the cables than conventional HVDC converters and this has enabled Footnote 1) Using the OECD average of 600 kg CO 2 /MWh for electricity. 3 AC voltage 4 HVDC improves the stability of AC networks. Bus voltage 1.10 1.05 1.00 0.95 0.90 Maximum voltage 0 50 100 150 200 time HVDC Light product matrix. Available 2000 Available 2004 Available 2006 DC Voltage 500 A 1000 A 1500 A +/- 80 kv +/- 150 kv 90 MW 180 MW 170 MW 350 MW 280 MW 500 MW +/- 300 kv 350 MW 700 MW 1000 MW 27

5 Construction of Murraylink HVDC Light (Australia). Voltage source converters also show significant advantages over traditional HVDC converters such as: Dramatically smaller size. Typically they are half the height and their footprint is 25 percent smaller. Superior voltage and reactive power control reduces the risk of blackouts. They act as a firewall for network disturbances and block the cascading trips that occur in AC systems 2). They can operate in very weak networks and do not require network reinforcements. They reduce down time after outages with their black start capability. New high-speed control and protection technology makes it possible to fully utilize the inherent benefits of the voltage source converters. Technical development of HVDC Light systems HVDC Light technology was introduced to the market in 1997 with a small test installation of 3 MW. Since then, both cables and converters have progressed dramatically in both size and performance. Today the largest system in service is a 330 MW system operating at ± 150 kv. A 350 MW system is currently under construction. The converter design has been refined by the adoption of new switching schemes that reduce the number of components and cut the converter losses by 60 percent. In contrast to traditional HVDC, an HVDC Light system is highly modularized and makes greater use of semiconductors. The product matrix shown in 4 highlights available modules. Increased environmental pressure on overhead transmission lines is both raising total costs and increasing the risk for substantial project delays. Cable installation techniques A crucial element in underground transmission is the cable installation technique. In the Murraylink project in Australia, 5 and 6, a very successful installation was implemented using modified pipeline installation equipment. Up to 3km of cable was successfully installed per day. The total cost of laying the 170 km cable system amounted to the very reasonable sum of about AU$ 10 million ($ 7.6 million). HVDC Light cables have relatively low weight (typically <10 kg/m), making its installation similar to that of fibre-optic cables: the equipment used for trenching and the Footnote 2) See HVDC: A firewall against disturbances in high-voltage grids, Lennart Carlsson, ABB Review 3/2005 pp 42 46. depth at which the cables are laid is comparable (1 to 1.5 m below the surface). Cost comparison Overhead lines Underground transmission The new HVDC technology has, as already mentioned, some unique characteristics particularly when it comes to increasing network security. This means before a strict cost comparison is performed, a needs evaluation is required. Some key checkpoints are listed in Table 2. Table 2 HVDC suitability checklist Need for power transmission 50 1000 MW Need for accurate and fast control Distance more than 100 km Difficult to obtain permits for OHL Asynchronous networks Weak AC network Risk for dynamic instability Power quality issues Need for grid black start capability Need for high availability although occurrence of thunderstorms, wind storms/hurricanes or heavily icing conditions may apply Need for low maintenance Need for small footprint Risk of low harmonic resonances Need for fast voltage an reactive power control to enhance network security 28

If at least three of these conditions are fulfilled it is likely that an HVDC Light system will offer a very attractive solution. If, however, OHL permits are difficult to obtain, then this reason alone is sufficient to warrant an HVDC Light solution. In the following paragraphs, two examples currently being studied are presented. Case 1,700 MW over 400 km It is assumed this case fulfils at least five of the criteria outlined in Table 2, such as: The need for 50 1000 MW. Transmission distance is greater than 100 km. Difficulty to obtain permits for OHL. Risk of dynamic instability. Need for fast voltage and reactive power control to enhance network security. A comparison of the direct investment cost shows the following span: The direct investment cost for HVDC Light option including converters, cables and their installation is in the range of $ 275 $ 420 million. The breadth of this range is primarily due to differences in installation costs and local market conditions. For the AC overhead option there is an even greater span in cost. A study 6 HVDC Light valve. made by ICF consultancy in 2001 shows a huge variation in costs from country to country. Using these data, the direct investment cost for the AC overhead option gives a cost range of $ 130 $ 440 million for the line including installation and substations. At the direct investment cost level the price for the underground alternative is between 0.6 and 3.2 times the overhead option. This is quite a difference from the normally anticipated 5 15 times. Furthermore, other factors should also be considered, for example: Additional investments in equipment to manage voltage and reactive power control in the AC case. Losses (both cases). Costs for permitting the overhead solution. Cost for permission and construction time (both cases). Increased transmission capacity in the existing AC grid (HVDC case). Loss of property value. When these factors are included in the evaluation, the competitiveness of the HVDC alternative increases. Assume, for example, the following realistic additional factors for the overhead option: Additional reactive compensation: $ 25 million. Loss of property value: $ 25 million. Value of increased transmission capacity in existing AC grid: $ 50 million. Applying these factors raises the price tag of the AC alternative to between $ 230 million and $540 million, and that of the underground option to between $ 275 million and $420 million. The costs of the two alternatives are quite comparable and local factors determine which option is the most advantageous. Case 2,350 MW over 100 km A similar exercise for this case results in a direct investment cost for the HVDC option of between $ 110 million and $ 150 million, whereas the AC overhead version costs vary between $ 40 million and $ 90 million. The relative direct investment cost of the HVDC solution is in the range of 1.2 3.75 times that of an OHL. The application of the additional factors discussed above will again reduce the cost difference between the alternatives. Conclusions Increased environmental pressure on overhead transmission lines is both raising total costs and increasing the risk for substantial project delays. New HVDC technology in the form of HVDC Light has made underground options technically feasible and economically viable. This is especially so if the new grid investment is driven by security of supply issues. The conventional view that an underground link will cost 5 15 times its overhead counterpart must be revised. Depending on local conditions, it is realistic that the costs for an underground high-voltage line are equal to that of traditional overhead lines. Dag Ravemark ABB Cororate Research Västerås, Sweden dag.ravemark@se.abb.com Bo Normark ABB Power Technologies Zürich, Switzerland bo.normark@se.abb.com 29