Pipe Support The Fast, Economical Solution for Low Pressure Pipeline Repair

Similar documents
HOT TAPPING & PLUGGING SOLUTIONS

Dimas Satya Lesmana S.T. 1

PIGGING PRODUCTS. Capex supply. PIG LAUNCHER and RECEIVER

Plastic and Composite Repair Student Handouts

Analysis of Aquawrap for use in Repairing Pipelines with a Dent / Gouge Defect

327. Repairing the bent and cracked fenders Tap out the dents from the back side of the fender with a fender hammer.

Tapecoat. Application Guideline

SUB SEA SYSTEMS INTERNATIONAL NIGERIA LIMITED CLOCKSPRING

PIPELINE CASING FILLING PROCEDURES. By Tom Weber-Trenton Corporation

A flexible solution for a tough problem: What are the solutions available for conveyor belt repair?

REVISION DESCRIPTION:

Southern Star Central Gas Pipeline Contractor Covered Task List Last updated 8/15/2018

Epic Consolidated Operations LLC Contractor Covered Task List Last updated 9/6/2018

Northern Natural Gas Contractor Covered Task List Last updated 4/26/2018

DONKIN ASSET PROTECTION SYSTEM WARRANTY UP TO 20 YEARS* DONKIN ASSET PROTECTION SYSTEM

PIPELINE REPAIR OF CORROSION AND DENTS: A COMPARISON OF COMPOSITE REPAIRS AND STEEL SLEEVES

mechanical coupling system

Contents. Preparing the motor Winding the rotating secondary Winding the primary... 8

Columbia Pipeline Group Contractor Covered Task List Last updated 1/8/2018

The aim is the detection of

Overhead transmission lines Spacers

CATALOGUE. Valid from 15 November Weldwide Solutions Limited Product Catalogue

Methodologies and practices for non-piggable lines Andreas Landsteiner Integrity Department - Transalpine Pipeline (TAL)

Williams Contractor Covered Task List Last updated 11/7/2017

EnLink Midstream Contractor Covered Task List Last updated 11/8/2017

PSI Model C or W End Seal. Link-Seal Modular Seals, when centered. Not drawn to scale. 2 Max. (0.6M) 8 Max. (2.44M) 8 Max. (2.44M) 2 Max. (0.

Dominion Energy Questar Pipeline LLC Contractor Covered Task List Last updated 10/3/2017

Black Hills Energy Contractor Covered Task List Last updated 10/10/2018

C I R R U S COWLING DESCRIPTION

3M Scotchkote Liquid Epoxy Coating 323+

High Pressure Access Systems

Howard Midstream Energy Partners LLC Contractor Covered Task List Last updated 10/11/2013

3-Way Ball Valve Type 23H

Ford Fabricated Steel Products

Noble Energy Contractor Covered Task List Last updated 2/20/2019

BiDirectionAll Pig. BiDirectionAll Pig. with optional brush wraps. Features

Thermoelectric Module Installation Guidance

Energy Transfer Partners LP Contractor Covered Task List Last updated 3/2/2018

DCP Midstream Contractor Covered Task List Last updated 7/11/2018

PRODUCT CATALOGUE DOUBLE PREINSULATED PIPES

DACON INSPECTION SERVICES I PIPESURVEY INTERNATIONAL MFL INSPECTION OF PIPELINES

Enbridge Gas Transmission and Midstream and Enbridge Liquid Pipelines (Express-Platte) Contractor Covered Task List Last updated 8/30/2018

TransCanada US Contractor Covered Task List Last updated 9/27/2018

Assembly Instructions for Bondstrand Fiberglass Flanges

Energy Transfer Partners LP Contractor Covered Task List Last updated 12/10/2018

PIPE LOG BOOK. Project no:... Project:... Construction section:... On behalf of:... Commissioned by:... Order no:... Date:... Construction period:...

CS Fiber Optic Splice Case. Instruction

The Use of Conduction Tracers Vs Bare Tracers Metric Version

TYPE 4 BEARING INSTALLATION IN COMPOSITE HULLS.

FR11A Fender, Welded-On

VRX Plunger. Advanced Control Valve

Boardwalk Pipeline Partners, LP Contractor Covered Task List Last updated 9/17/2018

PRODUCT DATA SHEET SP-1386

COMPRESSION COUPLINGS Exclusive Design Features Outer Shell and Bar Washer The unique design provides an equalized pressure seal.

THE APPLICATION OF LONG RANGE GUIDED ULTRASONICS FOR THE INSPECTION OF RISER PIPES

PRODUCT CATALOGUE. PisaFlex is Mexico s premier manufacturer of metallic expansion joints and braided hose assemblies.

Installation Service INSTRUCTIONS

Style 234 Restrained Flexible Single-Gasket Coupling. System No. Submitted By Spec Sect Para Location Date Approved Date

Saddle Butte Rockies Midstream LLC Contractor Covered Task List Last updated 12/6/2017

British Standard Underground Hydrant Range

USA Headquarters. Dynex/Rivett Inc. 770 Capitol Drive Pewaukee, WI U.S.A. Tel: FAX:

Resimac Ltd. Engineered Polymer Solutions

USA Headquarters. Dynex/Rivett Inc. 770 Capitol Drive Pewaukee, WI U.S.A. Tel: FAX:

SECTION VIII. (Sub-section 430) Wastewater Valves and Appurtenances. 1. General thru Gate Valves thru 430-3

Pipeline Accessories. PSI Pigs. General Information Technical Data Type Selection

THOMAS. Low Pressure SS Couplings. Couplings & Flange Adaptors Non Restrained Products PIPE PRODUCTS

PSI HEAT SHRINK PRODUCTS -

INSTALLATION GUIDELINE -SARAN VAPOR RETARDER FILM AND SARAN VAPOR RETARDER TAPE ITW INSULATION SYSTEMS

Power Connection Kit installation instructions

Joint Technical Meeting

Val-Matic 3-Way Tapered Plug Valve

TECHNICAL SPECIFICATIONS OF METROPOLITAN WATERWORKS AUTHORITY OF THAILAND

Important: Please read these instructions carefully and completely before starting the installation. TITAN Fuel Tanks INSTALLATION GUIDE

CASING SPACERS DESIGNED FOR WATER, SEWER, OIL & GAS

Sealing Technologies & Solutions

GS-37 FLARE FLANGE SYSTEM

This article discusses a tank

Important: Please read these instructions carefully and completely before starting the installation. TITAN Fuel Tanks INSTALLATION GUIDE

Suggested Specifications

Energy Division. PCA Single Column Polymeric Surge Arrester

Maintenance Information

USA Headquarters. Dynex/Rivett Inc. 770 Capitol Drive Pewaukee, WI U.S.A. Tel: FAX:

PSI Anti-Corrosion Tape

contents MALLEABLE PIPE FITTINGS BUsHEs NiPPlEs PlUgs caps BENds BackNUTs UNioNs TEEs 171 cross PN25 p socket PN25 p socket PN25 p.

Florida City Gas Contractor Covered Task List

Appendix B Kinder Morgan Operator Qualification Program List of Covered Tasks Hazardous Liquid Pipelines Part 195 revised 8/24/2018

DUCTILE IRON FLANGED GATE VALVES for gas distribution DN40 DN300 PN16 max operating pressure MOP 16 bar

USA Headquarters. Dynex/Rivett Inc. 770 Capitol Drive Pewaukee, WI U.S.A. Tel: FAX:

WRSS Wraparound Repair Sleeve Installation Instructions

MILLCENTRIC FULL/100% POR T ECCENTRIC PLUG VALVE

THOMAS. PolyGrip Range. Couplings & Flange Adaptors Restrained Products PIPE PRODUCTS

Check Valve MODEL. Schematic Diagram. Product Dimensions Data:

INDUSTRIAL VACUUM SYSTEMS MADE AND MANUFACTURED IN GERMANY RANGE OF ACCESSORIES COMPETENCE CENTRE INDUSTRIAL VACUUMING. Valid from

Elcometer 506 Pull- Off Adhesion Gauge. elcometer.com 1

Appendix A Kinder Morgan Operator Qualification Program List of Covered Tasks - Natural Gas - Part 192 Revised 12/13/2017

REV READ BEFORE INSTALLATION OF KIT:

How to Make Realistic Roads & Parking Lots

Bondstrand 5000/5000C Product Data (Severely Corrosive Industrial Service and Oxidizing Acids)

PIPELINE INSPECTION SURVEY QUESTIONNAIRE

Water Treatment Pressure Vessel

Transcription:

CLOCK SPRING Pipe Support The Fast, Economical Solution for Low Pressure Pipeline Repair 3 x 18 repairs were made in support locations. The Pipe could not be raised so blocks were inserted and the supports were cut away. The pipe was then hand prepared to remove all traces of zinc paint and any corrosion scabs. The 3 repairs were completed within 2 hours. FOR FURTHER INFORMATION ON CLOCK SPRING REPAIR SOLUTIONS CONTACT: Clock Spring Company, L.P. UK, 4A The Causeway, Godmanchester Huntingdon, Cambs, PE29 2HA, England Telephone: 44 1480 414703 Facsimile: 44 1480 414705 Email:

Clock Spring Steel Works Tight Access Western Europe Steel Works 20 diameter 45.5 barg design pressure -20 to +50 C operating temperature Contents is oxygen gas 12.7 mm original wall thickness Defect and surrounding pipe cleaned to S.T. 3 Up to 50% internal wall loss in 2 patches with a maximum axial length of 200 mm. The existing epoxy coating was removed using sanding disks and the bare pipe metal was exposed, grit blasting was not suitable at this location. High compressive strength filler was placed in the defect area, to pass the loading from the defect to the Clock Spring. Repair installed using the hand spool method A 20 Clock Spring was installed under the supervision of a Clock Spring technician using the hand spool method which is used in areas with tight access. The repair is considered permanent with a 50 year validated lifetime. ½ a day including cleaning of the pipe using wire brushing and sanding disks. Repair tightened and taped while it cures

Contour Chemical Plant Leak Repair Western Europe 8 diameter straight pipe 7 barg operating pressure 30 C operating temperature 8.18 mm original wall thickness 1300 kn equivalent axial load Cooling water line contents Area to be repaired with 3 pinhole leaks present Wall thinning in the air to ground interface zone with pinhole leaks present, which were sealed using a clamp. A repair was designed by the Clock Spring Technical Centre using ISO 24817. The leak was sealed using a clamp and plastic steel was placed around the edges of the clamp. The pipe was then cleaned using water and sand blasting. Clamp applied over the leaks and sealed with plastic steel 12 layers of Clock Spring Contour were applied over the pipe. 3 days on-site using Clock Spring Contour trained and approved technicians. 12 layers of Clock Spring Contour applied, the leak has been completely stopped

Contour Chemical Plant Leak Repair & Flange Encapsulation Western Europe 30 diameter with 18 diameter tee 2 barg operating pressure 30 C operating temperature 9.53 mm original wall thickness Area to be repaired Wall thinning at the air to ground interface with some pinhole leaks. An encapsulation of the blind flange was also needed. A repair was designed by the Clock Spring Technical Centre in accordance with ISO 24817 guidelines. The pipe was cleaned using a slurry blast system. Pinhole leaks were then sealed with plastic steel and any sharp gradients were tapered out. Plastic steel used to seal leaks and taper any sharp gradients 19 layers of Clock Spring Contour were applied. 4 days on-site using Clock Spring Contour trained and approved technicians. Repair nearing completion

Contour Chemical Plant Mitre Bend Repair Western Europe 14 diameter bend 2 barg operating pressure 30 C operating temperature 9.53 original wall thickness Area to be repaired after sand blasting 3.2 mm of wall thickness remaining. A repair was designed by the Clock Spring Technical Centre using ISO 24817. The pipe was cleaned using water and sand blasting. First 4 layers installed and left to cure 15 layers of Clock Spring Contour were applied over the pipe. 3 days on-site using Clock Spring Contour trained and approved technicians. Completed repair

Clock Spring Pipeline Casing Spacers Atmore, Alabama, U.S.A. CLOCK SPRING 8 pipeline, X-52, double fusion bonded epoxy coating Operating pressure 975 psi Encased pipe under highway (HCA) Replacement with new pipeline. Pipe had defect from original pull where spacers failed to stay in place. Existing pipeline was cut and pulled through casing for removal. Almost all of the existing casing spacers were broken, showed significant corrosion at bolts, and many failed to hold during pipe removal. Clock Springs were custom cut to 5 ½ widths and used as casing spacers to provide protection of girth welds and pipeline during installation. 57 units, spaced 12 apart, were installed on new pipe sections in advance of installation. The crew of 10 installed all 57 units in 8 hours. Sections were then assembled on-site. Entire replacement of pipeline took approximately 4 days. Clock Springs pre-installed on pipe sections Casing spacers at girth weld joint Clock Spring cut to 5 ½ width and installed as casing spacer Spacers from old pipe, failed to stay in place when pipe removed with corrosion

Before After

Contour Chemical Plant Internal Corrosion Middle East Pipe Details Line contents is Naphtha 10 pipe diameter 7 Barg operating pressure 70 C operating temperature 9.27 mm nominal wall thickness 30 m repair length Training Delivered: A vertical, horizontal and 2 bends repaired with Clock Spring Contour A Clock Spring technician was mobilised to train the asset owners chosen contractors how to install the repair through a variety of classroom and practical sessions over 5 days. The contractors then had a test spool pressure tested to validate them to install the repair, prior to beginning installation on the main pipe. The pipe was grit blast in a series of stages to Sa 2 ½ and then preserved using CS 600 epoxy resin and peel ply. 5 layers were then installed across the 30 m of pipe including bends and tees with full installation taking around 5 days. A straight section of pipe wrapped with Clock Spring Contour Repair Designed: The repair was designed by the Clock Spring Technical Department in the United Kingdom to the standards set out in ISO 24817. The repair required 5 layers to seal a 100 cm 2 hole for a lifetime of 20 years. Vertical section of pipe, bend and horizontal section of pipe wrapped with Clock Spring Contour

Clock Spring Pipeline External Corrosion Benelux 10 natural gas pipeline 66.2 Barg design pressure 14.4 C operating temperature 5.56 mm original wall thickness 4.89 mm remaining wall thickness External corrosion due to a holiday in the corrosion coating which was spotted early due to regular pigging. A Clock Spring was applied to prevent further corrosion and reinforce the area of wall loss. Pipe cleaned to Sa 2 ½ and defect area marked and measured. Pipe was excavated and grit blast to Sa 2.5 prior to the application commencing. One 295 mm wide Clock Spring was placed over the defect with the installation taking 20 minutes. After 2 hours curing marker bands were installed, the repair was coated and the hole back filled. Installation of the Clock Spring Composite Sleeve using a trained technician. Repair Lifetime: The repair has a proven lifetime of > 50 years. Marker Bands: Clock Spring approved marker bands were applied to the edges of the repair, these highlight the repair area when future MFL pigging is used. Repair completed and marker bands applied.