Fund and 2015 revenue bonds Est. State and Local Taxes: $2,810,000

Similar documents
MOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Recommend to Board. Final Action

The purpose of this report is to respond to the Notice of Motion CS-16-51, Generators for Fire Halls and Recreation Facilities, including:

City of Palo Alto (ID # 6416) City Council Staff Report

MOTION NO. M Purchase of Thirty-two Double Deck Buses for Increased Passenger Capacity, Bus Replacement and Service Expansion

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

The Regional Municipality of York. Purchase of Six Battery Electric Buses

TORONTO TRANSIT COMMISSION REPORT NO.

The Boston South Station HSIPR Expansion Project Cost-Benefit Analysis. High Speed Intercity Passenger Rail Technical Appendix

Michigan Renewable Energy Case Study

DEBBIE COMIS, CHIEF ADMINISTRATIVE OFFICER AERIAL LADDER FIRE RESCUE APPARATUS REPLACEMENT PURCHASE

The Case for. Business. investment. in Public Transportation

National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA )

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

Merger of the generator interconnection processes of Valley Electric and the ISO;

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

COMMUNITY DEVELOPMENT BLOCK GRANT DISASTER RECOVERY (CDBG-DR) PROGRAM SUBSTANTIAL AMENDMENT NYS CDBG-DR 2013 ACTION PLAN

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF DECEMBER 11, 2017

Board 8/24/2017 Final Action Bonnie Todd, Executive Director of Operations Martin Young, Commuter Rail Manager

SUBJECT: CONTRACT C080S, HOIST REPLACEMENT AT BUS MAINTENANCE DIVISIONS 3, 5, 9, 10, AND 18, PETERSON HYDRAULICS AND ROTARY LIFT, A JOINT VENTURE

MOTION NO. M Light Rail Vehicle Oil-less Rotary Scroll Air Compressor Upgrade PROPOSED ACTION

May 2017 Pei Sue Ong, Capital Accounting Advice Manager Pacific Gas and Electric Company

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

ISO on Background. Energy-efficiency forecast. Anne George. Stephen J. Rourke VICE PRESIDENT, SYSTEM PLANNING DECEMBER 12, 2012

STAFF REPORT ACTION REQUIRED

Review of Electric Utility Hurricane Preparedness and Restoration Actions ORLANDO UTILITIES COMMISSION RESPONSES TO STAFF'S SECOND DATA REQUEST

Form Revised: February 2005 TORONTO TRANSIT COMMISSION REPORT NO. MEETING DATE: August 30, SUBJECT: Scarborough Rt Strategic Plan

The Regional Municipality of Halton. Chair and Members of the Planning and Public Works Committee

CITY OF VANCOUVER ADMINISTRATIVE REPORT

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

DES MOINES AIRPORT AUTHORITY BOARD SUMMARY OF REGULAR MEETING Des Moines International Airport Board Room May 13, 2014

Annual KRTA Report for the Year 2016

Smart Grid Update Supplier Conference. Kevin Dasso Senior Director Technology & Information Strategy. October 27, 2011

Proposed FY Capital Improvement Program (CIP) March 5, 2018 Capital Planning Committee 1

CANTON COMMUNITY REQUEST FOR BOARD ACTION

City of Grand Island

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001

O-Train Confederation Line Stage 1

CTA Capital Construction Update December 12, 2006

7000 Series Railcar Program Overview

HONOLULU AUTHORITY FOR RAPID TRANSPORTATION CITY AND COUNTY OF HONOLULU ADDENDUM NO. 1 TO THE REQUEST FOR INFORMATION FOR THE

SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE JULY 17, 2014 PURCHASE OF HYBRID SEDANS APPROVE CONTRACT AWARD ACTION: RECOMMENDATION

Balancing the Transportation Needs of a Growing City

City of Kingston Report to Council Report Number Jim Keech, President & CEO, Utilities Kingston

DART Priorities Overview

AGENDA ITEM 1 G Consent Item

City of Grand Forks Staff Report

State/Local Governance

TORONTO TRANSIT COMMISSION REPORT NO.

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY

Demystifying Distributed Energy Resources and Microgrids Implications for Louisiana

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH ROCKY MOUNTAIN POWER. Exhibit Accompanying Rebuttal Testimony of Dana M.

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

From: Tito R. Nagrampa Jr, P.E. Approved by: /s/ General Manager Juan M. Ulloa, P.E. Engineering Supervisor

PGE Sustainability Report Key Metrics FISCAL YEAR 2017

Overview of S.L Competitive Energy Solutions for North Carolina

WINDOM ELECTRIC UTILITY: RATE STUDY. Tim Miller Manager, Financial Analysis & Rates Missouri River Energy Services December 30, 2015

Electric Purchased Power Costs BACKGROUND AND CURRENT STATUS OF THE CITY S ELECTRIC FUND

Summer Reliability Assessment Report Electric Distribution Companies Perspective

Review of Reliability Must-Run and Capacity Procurement Mechanism BBB Issue Paper and Straw Proposal for Phase 1 Items

Energy Technical Memorandum

AGENDA INTERCITY TRANSIT AUTHORITY WORK SESSION January 20, :30 P.M. 1) APPROVAL OF AGENDA 1 min.

100 MW Wind Generation Project

Policy Note. Vanpools in the Puget Sound Region The case for expanding vanpool programs to move the most people for the least cost.

Port of Long Beach. Diesel Emission Reduction Program

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report

Fuel for the Frozen North Alaskan Fuel Consortium Adds Capacity at Anchorage Airport

Late Starter. Tuesday, November 6, 2018

The Capital Grid Project:

US 29 Bus Rapid Transit Planning Board Briefing. February 16, 2017

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

Proposal Concerning Modifications to LIPA s Tariff for Electric Service

HONORABLE CHAIRPERSON AND MEMBERS OF THE AZUSA UTILITY BOARD

78th OREGON LEGISLATIVE ASSEMBLY Regular Session. House Bill 4036

Emergency Generation Options

Contract Awards for Tender Calls and for the Construction of Works Associated with the City's Basement Flooding Protection Program

Modernization of Afipsky Refinery. The Russia and CIS Project & Equipment Forum RPEF 2015 April 21-22, 2015, Moscow

REPORT TO THE CHIEF ADMINISTRATIVE OFFICER FROM THE DEVELOPMENT AND ENGINEERING SERVICES DEPARTMENT COMPRESSED NATURAL GAS TRANSIT FLEET UPDATE

MMP Investigation of Arthur Kill 2 and 3

4 COSTS AND OPERATIONS

Item #14. DATE October 12, GCTD Board of Directors. Reed C. Caldwell Director of Engineering & Construction

Washington Metropolitan Area Transit Authority Recommended Contracting Actions For Up To 217 Hybrid Electric & Clean Diesel Buses

PEC is continuously experiencing growth in its service territory. Weather and member growth are primary drivers for increased kwh sales.

City Council Report. Mayor and City Council

The Gambia National Forum on

Electrical District No. 3 SOLAR Q & A

July 28, 2009 Presentation to the Illinois Statewide Smart Grid Collaborative

CITY OF AMES, IOWA CAPITAL IMPROVEMENTS PLAN

CITY OF LOS ANGELES INTER-DEPARTMENTAL MEMORANDUM

California Energy Storage Policies. Carla Peterman Commissioner, California Public Utilities Commission December 2016

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Interconnection System Impact Study Report Request # GI

APPROVE CONTRACT MODIFICATION AWARD

Tel metro. net

CITY OF LOS ANGELES DEPARTMENT OF AIRPORTS

Comprehensive project bid to grant in concession GTS Project 220 Kv Tintaya - Azangaro Transmission Line. GTS: Guaranteed Transmission System

RECOMMENDATION PAPER TO THE DULLES CORRIDOR COMMITTEE

TORONTO TRANSIT COMMISSION REPORT NO.

Transcription:

PORT OF SEATTLE MEMORANDUM COMMISSION AGENDA Item No. 6b ACTION ITEM Date of Meeting August 4, 2015 DATE: TO: FROM: Dave Soike, Director, Aviation Facilities and Capital Programs Wayne Grotheer, Director, Aviation Project Management Group SUBJECT: Utility Emergency Backup/Standby Power Project (CIP #C800538) Amount of This Request: $36,998,308 Source of Funds: Airport Development Est. Total Project Cost: $37,200,000 Fund and 2015 revenue bonds Est. State and Local Taxes: $2,810,000 ACTION REQUESTED Request Commission authorization for the Chief Executive Officer to: (1) develop, advertise, and execute a Public Works Building Engineering Systems Contract for the Utility Emergency Backup/Standby Power Facility Project with a total project cost estimated at $37,200,000; and (2) authorize the use of Port crews for preliminary work in support of the project. SYNOPSIS The project will provide an enclosed, dual fuel standby power facility that is functionally complete, fully integrated, and capable of supplying 25 megawatts (MW) of power. This wattage is 100 percent of the Airport s peak electrical demand over the existing power distribution system. Upon the unexpected loss of normal utility power, the standby power facility will provide stable backup power to the Airport within five minutes. The standby power facility will have sufficient fuel storage capacity to operate the Airport continuously for up to 24 hours with ability to use aviation fuel as a backup source should diesel fuel become unavailable. The total value of this request is $36,998,308 of an estimated total project cost of $37,200,000. This improvement will not be impacted by future development recommended as part of the Sustainable Airport Master Plan (SAMP). BACKGROUND Almost all functions at the Airport rely on electricity. The Airport currently has back-up power only for life/safety functions, which is three (3) megawatts or ten percent of the Airport s electrical demand. These functions are primarily based on passenger egress requirements or getting passengers and staff out of the Airport safely. During an extended electrical power outage, the Airport will not be able to operate. Template revised May 30, 2013.

Page 2 of 6 The Airport has had experiences with power outages and has taken past actions to mitigate such threats to operations. In 2009 and 2010, the Airport was faced with the prospect of a long-term area power outage that might result from the failure of the Howard Hansen Dam. With support from tenants and airlines, the Airport spent $3.5 million to rent and install 18 MW of temporary backup generators at that time. The generators were returned when the risk from the dam failure was mitigated. In 2008, a car accident caused the Airport s south main substation to lose power for several hours. In 2006, a windstorm knocked out power to the region and portions of the Airport. This project was submitted to the airlines for a majority-in-interest vote. The project was approved. PROJECT JUSTIFICATION AND DETAILS During a utility power outage, the Airport is unable to operate normally. An extended loss of utility power at the Airport impedes the Port s, airlines and tenants ability to utilize the Airport. Loss of electrical power shuts down airline and concession electronic communications, jet bridge operations, flight information displays, ticket printers, security checkpoints, electric ground support equipment (egse) chargers, baggage conveyors, lighting for legal occupancy within the terminal, heating/cooling systems, and other functions. The continued reliable operation of Sea- Tac Airport is vital to meeting the needs of the region and the airlines. This project will provide the Airport with a permanent standby power source and enable the continued operation of Sea- Tac Airport during a short or long-term power outage event. Project Objectives Provide 25 megawatts of stable power to Sea-Tac Airport within five minutes System able to expand as Airport demands grow System to run continuously for up to 24 hours without refueling System to be able to run on multiple fuel types When conditions dictate (e.g. major storm approaching, dam bursting), the ability to isolate the Airport utility from the Puget Sound Energy electrical grid so that the Airport is not affected by regional electrical outages Scope of Work This project will provide a complete, useable, and fully integrated standby power facility capable of supplying 25 megawatts of power to the Airport. The standby power facility will be sited on Port property next to the Port s South Main Substation and Puget Sound Energy s Sea-Tac substation (see Attachment A site vicinity map). This is an ideal location due to the proximity of existing electrical infrastructure that minimizes the cost and complexity of power distribution to aviation facilities. The project has been coordinated with the Construction Logistics Expansion Project.

Page 3 of 6 All generators or generation equipment will be installed in a weather-tight building or structures of suitable size and design capable of expanding to house an additional generator. Any contaminated soil disturbed or removed shall be abated, appropriately handled, and properly disposed of. Fuel storage and associated piping will be above ground with appropriate containment and monitoring systems for compliance with State and Federal regulatory requirements. Preliminary work includes actives such as site investigation, electrical room escorting, remediation efforts, limited fiber optic cable installation or other ancillary activities to support the project. Procurement method The Standby Power Facility will be competitively procured as a Public Works building engineering system contract. Per RCW 39.04.290, the Port may award contracts of any value for the design, fabrication, and installation of building engineering systems by using a competitive process where bidders are required to provide final specifications and a bid price for the design, fabrication, and installation of building engineering systems, with the final specifications being approved by an appropriate design, engineering, and/or public regulatory body. The procurement strategy was chosen because an industry standard turnkey solution is available and a large percentage of the cost is equipment. Schedule Commission Authorization for Procurement: 3 rd Quarter 2015 Award Contract 2 nd Quarter 2016 Issue Notice to Proceed: 3 rd Quarter 2016 Construction Complete: 3 rd Quarter 2017 FINANCIAL IMPLICATIONS Budget/Authorization Summary Capital Expense Total Project Original Budget $36,400,000 $800,000 $37,200,000 Previous Authorizations $201,692 $0 $201,692 Current request for authorization $36,198,308 $800,000 $36,998,308 Total Authorizations, including this request $36,400,000 $800,000 $37,200,000 Remaining budget to be authorized $0 $0 $0 Total Estimated Project Cost $36,400,000 $800,000 $37,200,000 Project Cost Breakdown This Request Total Project Procurement/Construction $33,388,308 $33,590,000 Soil Abatement $800,000 $800,000 Sales Tax $2,810,000 $2,810,000 Total $36,998,308 $37,200,000

Page 4 of 6 Budget Status and Source of Funds This project, C800538, was included in the 2015-2019 capital budget and plan of finance. The funding sources will include the Airport Development Fund and 2015 revenue bonds. This project will be incorporated into the Airport s electrical utility, so both capital and operating costs will be recovered through an internal utility charge allocated to the terminal. The costs therefore show up as operating costs. Financial Analysis and Summary CIP Category Renewal/Replacement Project Type Infrastructure Upgrade Risk adjusted discount rate N/A Key risk factors Project cost for analysis $37,200,000 Business Unit (BU) Electric Utility (allocate to Terminal Building) Effect on business performance NOI after depreciation will increase IRR/NPV N/A CPE Impact 0.08 in 2017 Lifecycle Cost and Savings The design life of the project is 30 years or more. Operations and Maintenance (O&M) costs of the recommended alternative will be approximately $125,000/year to include: periodic maintenance, testing, air permitting requirements, fuel, and training. It is anticipated that the system will need to be run once a week or 50 hours a year for maintenance and testing purposes. STRATEGIES AND OBJECTIVES The project supports the Port s Century Agenda objective of meeting the region s air transportation needs at Sea-Tac International Airport for the next 25 years by improving electrical reliability for continuous Airport operations. ALTERNATIVES AND IMPLICATIONS CONSIDERED Alternative 1) Maintain the status quo. Capital Cost $0 This is not the recommended alternative. Pros: No capital investment Cons: The Airport s operations continue to be subject to an electrical outage risk. Each hour of an electrical outage incurs significant costs to the airlines. In the last major outage, The

Page 5 of 6 Alaska Airlines Group lost their main computer network, which grounded flights nationwide. The airlines support going ahead with the project. Waiting for an extended outage to occur, and then trying to find and rent and temporarily install diesel backup generators will take time. The option is slow to implement as evidenced by earlier experience with flood risk from the Howard Hansen Dam. The regional power transmission systems feeding the Airport would have been flooded. It took over six months to set up the temporary system. In a regional power outage, the Port will be in competition for generator resources. Alternative 2) Install a new combined heat and power facility. Capital Cost $56+M O&M Cost $2.2M/year This is not the recommended alternative. This alternative would install a Gas Turbine Generator and associated infrastructure upgrades to provide both electricity and heat to the Airport. Pros: The Airport electrical utility would be able to operate independently of outside power suppliers. Heat can be recovered from the electrical generation process to heat the Airport. Cons: This project would double electrical costs for the Airport s Electric Utility customers. The option would not utilize the Port s contract for low-cost hydroelectric power from the Bonneville Power Administration. A continuously operating gas turbine would subject the Port to more stringent environmental regulations and oversight. Alternative 3) Install centralized dual fuel generators Capital Cost $37.2M O&M cost $125,000/year This alternative provides a centralized Standby Power Facility capable of supplying 25 megawatts of power over the existing Airport distribution system. This is the recommended alternative. Pros: The Standby Power Facility project will protect the Airport from an electrical outage and enable continuity of airport and airline operations.

Page 6 of 6 Industry standard fully equipped backup power facilities are available on the marketplace. The dual fuel generators will normally run on diesel fuel but in an emergency may be fueled by Jet-A fuel. Cons: The system will need to be monitored to ensure compliance with Airport s environmental operating permits. ATTACHMENTS TO THIS REQUEST Attachment A Site Vicinity Map PREVIOUS COMMISSION ACTIONS OR BRIEFINGS December 9, 2014 Presentation to Commission.