An ISO 9001 Company. BOP 1KW-MG FIRMWARE RETROFIT KIT

Similar documents
10260 Retrofit to 10260A Non-Contact Sensor Instructions Kits through -512

PM-200 POWER SUPPLY MODULE v3.2 ASSEMBLY & INSTALLATION INSTRUCTIONS

In addition to this instruction sheet, the following are included in this kit (some additional parts are included for future maintenance):

SYSTIMAX 360 FTP Evolve Panel Instructions

Installation Instructions for the PowerCommand 3100 FT-10 Network Genset Communications Module (GCM) Kit

Installation Instructions. PowerFlex 700 Drive - Frame 8 Components Replacement

802C System Controller Original and SMD Version

Installing the Flame Ionization Detector EPC Flow Control Manifold

5 Removal and replacement

Installation Guide. Volatiles Interface for 6890 Gas Chromatograph Accessory G2319A

Carousel Unit User Manual Replacing the Check Stand Motor

Please complete customer details above so that we can ensure all customers can be given prior notification of future upgrades and product status.

ST 3000 R300 Smart Meter & R300 Smart Meter with ZS Option Installation Instruction

160S Rewind Option Kit Installation Instructions

Part Name/Description Part Number Quantity Instruction Kit Metalfor Flow Sensor

Replacing the Gear Drive Motor Assembly and GFCI Module for Operation with the Chain Drive Motor Assembly

HercuLine 2000 Series Gear Kit Replacement Instructions

Installation Instructions 1812 Folder Disk Clutch Retrofit Kit Martin Yale #WRA

PFadvantage Metalfor Araus 1360

PFadvantage MF 6850/6855; Ideal 9080/9090

Flow Sensor

* * Inside Toyota Avalon. Tools Required IMPORTANT

PowerFlex 700H and 700S AC Drives Frame 9 Main Fan Capacitor Replacement Kit

TOYOTA TACOMA XM SATELLITE RADIO Preparation

TOYOTA TUNDRA SKID PLATE Preparation

2-row and All-row systems included.

Combine Kit Parts List New Holland Late TR89, Late TR99 (Yield Monitor Ready)

(2 DPDT 2 4 X

TOYOTA COROLLA LOWERING SPRINGS Preparation

TOYOTA TUNDRA BUMPER STEP ASSIST Preparation

Installation Instructions for John Deere cotton picker models: 9986 & 2-row and All-row systems included.

Agilent G1554A On-Column Capillary Inlet with EPC

ELECTRICAL POWER-STATIC INVERTER - BRIDGE ASSEMBLY R170 RELOCATION

INSTALLATION INSTRUCTIONS

ELECRAFT KX3 Application Note

TOYOTA TUNDRA BUMPER STEP ASSIST Preparation

Second Stage Regulator - 1/4 Turn

Installation Instructions. PowerFlex 700 Drive - Frame 7 Components Replacement

Instructions for 2-row monitoring only

PFadvantage JD 3300/4400/6600/7700; 4420

THIS GUIDE IS INTENDED FOR DEALERS AND SOLAR COMFORT TECHNICIANS ONLY AND IS NOT MEANT OR INTENDED TO BE REPRODUCED OR DISTRIBUTED TO THE CONSUMER

70001 and Clutch Rebuild Instructions

2001 F-650/750 Workshop Manual

Instructions for 2-row monitoring only

TOYOTA 4RUNNER CROSS BARS Preparation

TECHNICAL SERVICE BULLETIN: TSB

Ag Leader Technology. Parts List for Combine MF , 8780, White 9700

INSTALLATION & OWNER S MANUAL

TABLE OF CONTENTS I. SERVICE & MAINTENANCE PROCEDURES. 1) Opening and closing of door latch. 2) Latch assembly and adjustment

SCION tc LOWERING SPRINGS Preparation

PowerFlex 700S and 700H Fan Inverter Upgrade Kit (Frame 10-11)

LEXUS LC/LCh CARBON FIBER LOWER GRILLE Preparation

SS & SS SOFT-START v3.0 ASSEMBLY & INSTALLATION INSTRUCTIONS

920 Remote Control Switches

MODEL 2604 WARNING <THESE INSTRUCTIONS MUST BE GIVEN TO THE END USER> Custom 5th Wheel Hitch Mounting Rail Installation Instructions

Field Service Bulletin: S3U/Y Console V5 P/N Installation

N/S= Not Shown Bold = Part available for purchase. Italic = Part not available for purchase, listed and shown for reference only.

FlexJet Carriage Circuit Board (PCB) Replacement

TECHNICAL INSTRUCTIONS

Installation Guide. Kennedy Technology Group, Inc.

Switching DC Power Supply

M40e and M160 Cooling System Installation Instructions

PowerFlex DC Drive - Frame A Pulse Transformer Circuit Board

LIMITED SLIP DIFFERENTIAL INSTALLATION

TOYOTA PRIUS PLUS LOWERING SPRINGS Preparation

ILD LOCK CYLINDER CHANGE-OUT INSTRUCTIONS REVISION 2_012505

TOYOTA PRIUS XM SATELLITE RADIO Preparation

Installation Guide. Auxiliary Pressure Control Manifold on 6890 GC Accessory G1570A

(2) Universal Light Brackets. Passenger/Right Mounting Bracket. Driver/Left Mounting Bracket

Replacing the Meter Body / Process Head Parts

TOYOTA im INTERIOR LIGHT KIT Preparation

Flow Sensor Deflector Deflector

INSTALLATION INSTRUCTIONS FOR PART

NA-Tune Installation Procedure

Parts List. Item Qty. Part # Description Item Qty. Part # Description Torque. 1 1 Bumper Replacement Shell 10 4 ½ x 1 ½ Hex Bolt 65 Ft.

LEXUS GS 350/450h ILLUMINATED DOOR SILLS Preparation

SCION xa 2004 SATELLITE RADIO TUNER Section I Installation Preparation

Instruction Sheet. 7 x 22 (178 x 559 mm) Rear Roller Brush Product No WARNING Rev A

INSTALLATION INSTRUCTIONS

Overview. Chassis Packaging

General Applicability Note: Recommended Tools. Personal & Vehicle Protection Safety Goggles Seat Covers Floor Covers Special Tools. Installation Tools

SCION tc STRUT TIE BAR Preparation

920i Programmable HMI Indicator/Controller Deep Enclosure Installation Instructions PNs 82455, 82456, 82457, 82458, 82459, 82460

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS

BehringerMods.com. Instructions for modification of Behringer DCX analog inputs and outputs

Feeder Circuit Breaker Units Secure Support Pan and Change Door Latch

CO₂ Sensor Replacement (RF598 and RF602) Installation Instructions

Lower Adjuster Small Black Header Sensor Reversed

MOTHMAN FUZZ ASSEMBLY INSTRUCTIONS RECOMMENDED TOOL AND SUPPLY LIST MOTHMAN FUZZ KIT PARTS LIST

Service Manual Air Tech Second Stage

Remove Air Cleaner Cover and. Filter

ESA II. I - Revive Slider Conversion Kit. Installation instructions

Product Guide: Series III Pump Control Board Set (RoHS)

SX-16 Nightsun Searchlight Safety and Service Bulletin # SL

Primus Wind Power. AIR Circuit Replacement Instructions

RECOMMENDED SEQUENCE OF APPLICATION

INSTALLATION INSTRUCTIONS

PowerFlex 700 Drive - Frame 8 Components Replacement

SCION xb 2004 SATELLITE RADIO TUNER Section I Installation Preparation

Transcription:

INSTRUCTION MANUAL 1. DESCRIPTION KEPCO An ISO 9001 Company. BOP 1KW-MG FIRMWARE RETROFIT KIT BOP 1KW-MG RETROFIT KIT 219-0562 Kepco KIT 219-0562 contains the PROMs used to upgrade the firmware for BOP 1KW-MG power supplies. The upgraded firmware supports faster serial communication and faster measurement rate 2. APPLICABILITY This KIT applies only to model revisions listed under Applicable Revs in Table 1. Two components designated C49 are included in this Kit. Newer/Older revisions listed in Table 1 specify the correct part number and installation location, depending on the BOP revision. TABLE 1. APPLICABILITY BOP MODEL APPLICABLE REVS NEWER REVS These Revs require C49, P/N 117-1122 to be added to A4A3 per PAR. 3.6, step 3. OLDER REVS These Revs require capacitor assembly P/N 117-0999 to be added to A6A1 per PAR. 3.7, step 1. BOP 6-125MG Rev 0 to Rev 10 Rev 2 to Rev 10 Not applicable BOP 10-75MG Rev 3 to Rev 23 Rev 15 to Rev 23 Rev 3 to Rev 14 BOP 20-50MG Rev 1 to Rev 31 Rev 22 to Rev 31 Rev 1 to Rev 21 BOP 25-40MG Rev 0 to Rev 10 Rev 2 to Rev 10 Not applicable BOP 36-28MG Rev 7 to Rev 33 Rev 24 to Rev 33 Rev 7 to Rev 23 BOP 50-20MG Rev 1 to Rev 30 Rev 21 to Rev 30 Rev 1 to Rev 20 BOP 72-14MG Rev 0 to Rev 26 Rev 18 to Rev 26 Rev 0 to Rev 17 BOP 100-10MG Rev 0 to Rev 29 Rev 21 to Rev 29 Rev 0 to Rev 20 NOTE: For revisions not listed above, please consult factory. Kepco can provide firmware that has been pre-configured for a particular unit. The serial number of the unit is added to part number of the kit to indicate the unit to which the kit applies. 3. INSTALLATION INSTRUCTIONS 3.1 MATERIAL REQUIRED (See Table 2.) TABLE 2. MATERIAL REQUIRED MATERIAL LOCATION QUANTITY PROM, Kepco P/N 250-0840; replaces U2 on Digital Board A1 Provided in this Kit 1 PROM, Kepco P/N 250-0841; replaces U24 on Digital Board A1 Provided in this Kit 1 PROM, Kepco P/N 250-0839; replaces U1 on Front End Control Board A4A3 Provided in this Kit 1 PROM, Kepco P/N 250-0842; replaces U9 on Keypad Interface Board A6A1 Provided in this Kit 1 Resistor, Kepco P/N 115-2511, metal film, 8.66K Ohms, 1%, 1/8W, replaces R9 on A4A3 Provided in this Kit 1 2015, KEPCO, INC 1 Data subject to change without notice 228-1789 REV 5

3.2 PRELIMINARY PROCEDURE 1. Prior to upgrade, turn on unit and note the serial number when it is displayed during power-up. Record Serial number for configuration after upgrade is complete. 2. If pre-configured chip is provided, verify the serial number of the unit matches the serial number of the kit (KIT 2190562-[serial number] 3.3 DISASSEMBLY PROCEDURE TABLE 2. MATERIAL REQUIRED (CONTINUED) MATERIAL LOCATION QUANTITY Capacitor, Kepco P/N 117-1122, ceramic, 220pF, 10%, 100V, replaces C49 on A4A3 per Table 1 Provided in this Kit 1 Capacitor assembly, Kepco P/N 117-0999, ceramic, 1 F, 10%, 50V, with solder lug on A6A1 per Table 1 Provided in this Kit 1 Heatsink, Kepco P/N 136-0486, installed on A4A3U9 and A4A3U14. Provided in this Kit 1 Screw, Kepco P/N 101-0092, PHPH, 4-40 x 0.375 used to install heatsink P/N 136-0486 Provided in this Kit 2 Lockwasher, #4, Kepco P/N 103-0097, used to install heatsink.p/n 136-0486 Provided in this Kit 2 Nut, Hex, Kepco P/N 102-0003, 4-40 x 1/3 in. used to install heatsink.p/n 136-0486 Provided in this Kit 2 ESD (Electrostatic Discharge) wrist strap (Kepco P/N 114-0080) Provided in this Kit 1 IC Extractor (Kepco P/N 114-0079) Provided in this Kit 1 Instruction Manual Kepco P/N 228-1789 Provided in this Kit 1 Phillips Screw Driver Not Supplied N/A Chip Puller or small Flat Blade Screw Driver Not Supplied N/A 1. Turn power off, disconnect the unit from source power and remove line cord. 2. Remove the two mounting ears from the chassis by removing three screws from each. 3. Remove the top cover of the unit by removing 14 screws as follows: two at top of the front panel, four at each side, (one towards the rear, three at the bottom) and four at the top of the rear panel. 4. Observe back of front panel-mounted circuit breaker. If a Printed Circuit Board is present, skip this step. If not, tag and remove the four quick disconnect cables from circuit breaker. 5. Disconnect ribbon cable attached to Distribution board A6A1 (see Figure 1) going to Front End Control board A4A3 connector J1. 6. Disconnect ribbon cable attached to Distribution board A6A1 going to Digital board A1J2. 7. Disconnect two 4-pin connectors (or, on some units one 4-pin and one 6-pin connector) (J12, J15, Figure 4), and one 5-pin connector (J14, Figure 4) wired with twisted pairs from Distribution board A6A1. Pull on the twisted pair where it enters the connector; if necessary, a screwdriver can be used to apply enough pressure to front panel to slightly increase separation between front panel and Distribution board A6A1, enough for the connectors to be removed. CAUTION: Failure to pull the fan connector straight back can damage the connector. 8. Remove fan connector (J10, Figure 4) from Distribution board A6A1 by pulling connector straight back. CAUTION: Removing the outer screws first can result in damage to the front panel. 9. At the bottom of the chassis, first remove the two inner screws, then the two outer screws securing front panel to chassis and separate front panel and Distribution board A6A1 from the chassis. 10. For units without lug wires, carefully pull the front panel straight back from the chassis to disengage the circuit breaker pins and separate the front panel from the chassis. 2 228-1789 REV 5 102715

11. Pry black cover off front panel ADJUST knob. Then remove ADJUST knob by releasing the nut. A4A3 ASSEMBLY (SEE FIGURE 2) A1 ASSEMBLY (SEE ABOVE) A6A1 ASSEMBLY (SEE FIGURE 4) BOP -1KW CHASSIS (COVER REMOVED) FIGURE 1. ASSEMBLIES A1, A4A3 AND A6A1 LOCATIONS AND DIGITAL BOARD A1 PROM LOCATIONS KEPCO, INC. 131-38 SANFORD AVENUE FLUSHING, NY. 11355 U.S.A. TEL (718) 461-7000 FAX (718) 767-1102 http://www.kepcopower.com email: hq@kepcopower.com 102715 228-1789 REV 5 3

3.4 DIGITAL BOARD A1 COMPONENT REPLACEMENT (SEE FIGURE 1) NOTE: Steps 1 and 2 can be skipped if brief trigger pulses (less than one second) are used. 1. On Digital board A1, locate PROM, U2 (see Figure 1). CAUTION: FAILURE TO USE THE ESD WRIST STRAP MAY DAMAGE THE PROM! 2. Take the ESD wrist strap from kit and use the peel and stick area to connect the wrist strap to the chassis of the BOP. Place the wrist strap on your arm as indicated by the instructions for the wrist strap. 3. Touch the IC tube to the chassis of the BOP. Open one end. 4. Pry out the PROM U2 using an IC extractor. Insert the hook, first into one slot and then the other, and gently pry out the PROM. Place the PROM in the tube and close the tube. 5. Open the other end of the IC tube and remove the replacement PROM U2 from the tube. 6. Insert the PROM into the socket, insuring the dot on the chip is oriented as shown in Figure 1. 7. Pry out the PROM U24 using an IC extractor. Insert the hook, first into one slot and then the other, and gently pry out the PROM. Place the PROM in the tube and close the tube. 8. Open the other end of the IC tube and remove the replacement PROM U24 from the tube. 9. Insert the PROM into the socket, insuring the dot on the chip is oriented as shown in Figure 1. 10. Reclose the IC tube. Remove wrist strap and disconnect it from the BOP chassis. 3.5 A4A3 FRONT END CONTROL BOARD, PROM U1 REPLACEMENT 1. On Front End Control board A4A3, locate PROM, U1 (see Figure 2). 2. Take ESD wrist strap and connect the wrist strap to the chassis of the BOP. Place the wrist strap on your arm as indicated by the instructions for the wrist strap. CAUTION: FAILURE TO USE THE ESD WRIST STRAP MAY DAMAGE THE PROM! 3. Touch the IC tube to the chassis of the BOP. Open one end. 4. Pry out the PROM U1 using a chip puller (not supplied) or a small flat-blade screw driver to gently pry out the PROM. Place the PROM in the tube and close the tube. 5. Open the other end of the IC tube and remove the replacement PROM (P/N 250-0839 U1) from the tube. 6. Insert the PROM into the socket, insuring the indentation on the chip is oriented as shown in Figure 2. 7. Locate integrated circuits U9 and U14 (see Figure 2). 8. Attach heatsink (supplied in Kit) onto U9 and U14 as shown in Figure 3 using hardware supplied in Kit. 3.6 A4A3 FRONT END CONTROL BOARD, COMPONENTS R9, C49 REPLACEMENT 1. On Front End Control board A4A3, locate resistor R9 (see Figure 2). 2. Replace resistor R9 with the replacement R9 supplied in this kit. 3. Perform this step only for models listed under Newer Revs in Table 1. a. On Front End Control board A4A3, locate capacitor C49 (see Figure 2). b. Replace capacitor C49 with the replacement C49 P/N 117-1122 supplied in this kit. 4 228-1789 REV 5 102715

FIGURE 2. FRONT END CONTROL BOARD, A4A3, COMPONENT LOCATIONS FIGURE 3. A4A3 HEATSINK INSTALLATION KEPCO, INC. 131-38 SANFORD AVENUE FLUSHING, NY. 11355 U.S.A. TEL (718) 461-7000 FAX (718) 767-1102 http://www.kepcopower.com email: hq@kepcopower.com 102715 228-1789 REV 5 5

3.7 DISTRIBUTION BOARD A6A1 PROM REPLACEMENT (SEE FIGURE 4) CAUTION: Note which screws do not use flat washers and tag for reassembly. 1. Perform this step only for models listed under Older Revs in Table 1; for all other models, skip to step 2. a. Remove screw in upper left hand corner of front panel securing A6A1 to the front panel. b. Install the screw just removed through the lug of the capacitor assembly supplied, and reinstall the screw (hand tight); refer to Figure 4, Detail A. c. Solder the other end of the capacitor to pin 2 of J12 as shown in Figure 4, Detail A. 2. Remove seven screws, seven lockwashers and five flat washers securing the Distribution board A6A1 to the front panel. Carefully separate the Distribution board A6A1 from the front panel. The PROM on the Distribution board A6A1 is now accessible for replacement (it is not necessary to disconnect the ribbon cables between the front panel and Distribution board A6A1) to replace the PROM. 3. Place Distribution board A6A1 on an ESD mat (if an ESD mat is not available, place the Distribution board on the top cover) and locate PROM U9 (see Figure 4). DISTRIBUTION BOARD (FAR SIDE) DETAIL A: CAPACITOR ASSEMBLY INSTALLATION DOWN DOWN TO REASSEMBLE: INSERT RIBBON CABLE INTO J4 (PUSH DOWN AT ARROWS IF NECESSARY). FIGURE 4. DISTRIBUTION BOARD A6A1 COMPONENT LOCATION CAUTION: FAILURE TO USE THE ESD WRIST STRAP MAY DAMAGE THE PROM! 4. Use the peel and stick area of the wrist strap to connect the wrist strap to an ESD mat (or to the top cover if an ESD mat is not available). Place the wrist strap on your arm as indicated by the instructions for the wrist strap. 5. Touch the IC tube to the ESD mat or top cover. Open one end of the IC tube. 6. Pry out the PROM U9 using an IC extractor. Insert the hook, first into one slot and then the other, and gently pry out the PROM. Place the PROM in the tube and close the tube. 7. Open the other end of the IC tube and remove the replacement PROM U9 from the tube. 8. Insert the PROM into the U9 socket, insuring the dot on the chip is oriented as shown in Figure 4. 9. Reclose the IC tube. Remove wrist strap and disconnect it from the BOP. 6 228-1789 REV 5 102715

3.8 REASSEMBLY 1. Carefully line up the 14-pin header on Distribution board A6A1 with the corresponding socket on the front panel, and the Distribution board LED s with the corresponding cutouts in the front panel and press the Distribution board into place. 2. Secure Distribution board A6A1 to the front panel using seven screws, seven lockwashers and five flat washers as noted during disassembly. 3. Slide the ADJUST knob over the shaft of the ADJUST control and secure using nut and washer. Press black cover onto front panel ADJUST knob. 4. Carefully line up circuit breaker pins with corresponding connectors on front panel and carefully mate front panel and chassis. If circuit breaker incorporates a Printed Circuit Board, it may be necessary to press the PCB onto the circuit breaker. CAUTION: Installing the inner screws first can result in damage to the front panel. 5. Attach front panel with Distribution board A6A1 to the chassis first using two outer screws at the bottom of the chassis, then two inner screws. 6. Connect two 4-pin connectors (or one 4-pin and one 6-pin connector), and one 5-pin connector attached to twisted pairs to connectors J12, J15 and J14, respectively on Distribution board A6A1 (see Figure 4). The 4- pin connectors can plug into either J12 or J15; holding the wires, line up the pins on an angle, then push until straight and press into place; if necessary a screwdriver can be used to apply enough pressure to front panel to slightly increase separation between front panel and Distribution board A6A1, enough for the connectors to be inserted. 7. Attach the fan connector (J10, Figure 4) by inserting the connector straight into the mating socket. 8. Connect ribbon cable from Distribution board A6A1 to Digital board connector A1J2. 9. Connect ribbon cable from A4A3 module to Distribution board A6A1 connector J11. 10. If Circuit breaker does not have a Printed Circuit Board, connect the four wires to the circuit breaker in accordance with the tags on the wires. 11. Attach the cover to the chassis using 14 screws. 12. Attach the two mounting ears to the chassis using three screws for each. 13. Install the power cord, connect the unit to source power, turn on power supply and proceed to Initialization, PAR. 4 KEPCO, INC. 131-38 SANFORD AVENUE FLUSHING, NY. 11355 U.S.A. TEL (718) 461-7000 FAX (718) 767-1102 http://www.kepcopower.com email: hq@kepcopower.com 102715 228-1789 REV 5 7

4. INITIALIZATION After the hardware upgrade has been completed it is necessary to configure the unit using the following procedure. NOTE: For KIT part numbers that have a unit serial number, the unit type, max/min settings and calibration have been pre-configured; perform ONLY steps 2 and 3 of the following procedure. 1. At the front panel, press % then use Y to highlight Unit Type. Press F1 to select unit type. Highlight applicable model (should match nameplate on front panel) and press $. 2. At the front panel, press % then use U to highlight Power Up Settings. Press! to display the Max/Min Settings menu. Press @ to set all the Power Up settings to the factory default. Then press $ to save the settings for power-up. 3. At the front panel, press % then use U to highlight Protected Settings. Press! to display the Protected Settings menu. Press @ to set all the Protected settings to the factory default. Then press $ to save the settings for power-up. 4. To establish the Serial Number use a remote interface to send the string DIAG:SER n where n is complete serial number recorded during the preliminary procedures (PAR. 3.2, step 1). 5. Cycle power to the unit, turning it OFF, then ON using the POWER ON/OFF circuit breaker. 6. Calibrate the unit in accordance with the applicable Technical Manual for BOP 1000W. 5. INSTRUCTION MANUAL CHANGES None. 8 228-1789 REV 5 102715