Study of Fault Currents and Relay Coordination of a Chemical Industry After Integrating with PV Generation and Simulation with a Software.

Similar documents
A Review on Grid Connected 100 kw Roof Top Solar Plant

String Monitoring and Control System for Solar Photo Voltaic Power Plants

Comparative Analysis of Integrating WECS with PMSG and DFIG Models connected to Power Grid Pertaining to Different Faults

Analysis of Grid Connected Solar Farm in ETAP Software

(by authors Jouko Niiranen, Slavomir Seman, Jari-Pekka Matsinen, Reijo Virtanen, and Antti Vilhunen)

Switchgear and Distribution Systems for Engineers and Technicians

Power System Stability Analysis on System Connected to Wind Power Generation with Solid State Fault Current Limiter

INTERNATIONAL JOURNAL OF ELECTRICAL ENGINEERING & TECHNOLOGY (IJEET)

Statcom Operation for Wind Power Generator with Improved Transient Stability

Performance Analysis of 40 KW Solar Photovoltaic System at DTU

INTERNATIONAL JOURNAL OF ELECTRICAL ENGINEERING & TECHNOLOGY (IJEET)

International Journal of Advanced Research in Electrical, Electronics and Instrumentation Engineering. (An ISO 3297: 2007 Certified Organization)

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

GRID CONNECTED 400kWp SOLAR ROOF TOP POWER PLANT NET METERING AT KARNATAKA STATE CRICKET ASSOCIATION M. CHINNASWAMY STADIUM, BENGALURU

Study of Fault Clearing by A Circuit Breaker In Presence of A Shunt Capacitor Bank

Figure 1 I-V characteristics of PV cells. Meenakshi Dixit, Dr. A. A. Shinde IJSRE Volume 3 Issue 12 December 2015 Page 4687

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

Impacts of distributed photovoltaic generation on Jenin distribution network: voltage level, power losses, power factor and power quality

Design and Simulation of Grid Connected PV System

Control Strategies for Supply Reliability of Microgrid

Hybrid Energy Powered Water Pumping System

Intelligent Control Algorithm for Distributed Battery Energy Storage Systems

Recent Trades in Distribution System

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

Cost Benefit Analysis of Faster Transmission System Protection Systems

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

Grid Stability Analysis for High Penetration Solar Photovoltaics

DYNAMIC BEHAVIOUR OF SINGLE-PHASE INDUCTION GENERATORS DURING DISCONNECTION AND RECONNECTION TO THE GRID

6545(Print), ISSN (Online) Volume 4, Issue 2, March April (2013), IAEME & TECHNOLOGY (IJEET)

Characteristics of LV circuit breakers Releases, tripping curves, and limitation

Dynamic Behaviour of Asynchronous Generator In Stand-Alone Mode Under Load Perturbation Using MATLAB/SIMULINK

FAULT ANALYSIS FOR VOLTAGE SOURCE INVERTER DRIVEN INDUCTION MOTOR DRIVE

Guidelines for connection of generators:

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

PLC Based ON-Grid System for Home Appliances

Interruption Technology of Breakers for High-voltage Direct Current

APPLICATION NOTE TESTING PV MICRO INVERTERS USING A FOUR QUADRANT CAPABLE PROGRAMMABLE AC POWER SOURCE FOR GRID SIMULATION. Abstract.

An Alternative to Reduce Medium-Voltage Transient Recovery Voltage Peaks

Journal of American Science 2015;11(11) Integration of wind Power Plant on Electrical grid based on PSS/E

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

Policy for Net-Metering based Renewable Energy Applications, Madhya Pradesh, DRAFT

Solar Photovoltaic Inverter Current Distribution during Fault on Distribution and Transmission System

The hierarchical three layer protection of photovoltaic generators in microgrid with co-ordinated droop control for hybrid energy storage system

Performance Analysis of Transient Stability on a Power System Network

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

ETAP Implementation of Mersen s Medium Voltage Controllable Fuse to Mitigate Arc Flash Incident Energy

Implementation of FC-TCR for Reactive Power Control

Modelling of PV Array with MPP Tracking & Boost DC-DC Converter

Net +Plus Connection Code

Power Quality and Power Interruption Enhancement by Universal Power Quality Conditioning System with Storage Device

PSNH INTERCONNECTION REQUEST

Diversifying into Marine Energy. ABB March 2015

Minnesota Dept. of Commerce, Division of Energy Resources. Distributed Generation Workshop Interconnection Standards

Novel Design and Implementation of Portable Charger through Low- Power PV Energy System Yousif I. Al-Mashhadany 1, a, Hussain A.

Review paper on Fault analysis and its Limiting Techniques.

CHAPTER 4 PROTECTION REQUIREMENTS

HOMER OPTIMIZATION BASED SOLAR WIND HYBRID SYSTEM 1 Supriya A. Barge, 2 Prof. D.B. Pawar,

New York Science Journal 2017;10(3)

Regenerative Utility Simulator for Grid-Tied Inverters

Power Electronics

Recent trends and Importance of Power Electronics: Dr. Siva Kumar K IIT Hyderabad

DRAFT. Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY

2000 Cooper Bussmann, Inc. Page 1 of 9 10/04/00

Power Flow Simulation of a 6-Bus Wind Connected System and Voltage Stability Analysis by Using STATCOM

Modal analysis of Truck Chassis Frame IJSER

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

Design Modeling and Simulation of Supervisor Control for Hybrid Power System

Design of an off Grid Photovoltaic system for New Office Buildings

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

Renewable Energy Systems 14

Xcel Energy Guidelines for Interconnection of Electric Energy Storage with the Electric Power Distribution System

ANFIS CONTROL OF ENERGY CONTROL CENTER FOR DISTRIBUTED WIND AND SOLAR GENERATORS USING MULTI-AGENT SYSTEM

School of Electrical and Information Engineering. ELEC High Voltage. University of Sydney. Dr Keith Mitchell. Engineering

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

CUSTOMER / ACCOUNT INFORMATION Electric Utility Customer Information (As shown on utility bill)

A Transient Free Novel Control Technique for Reactive Power Compensation using Thyristor Switched Capacitor

Interconnection System Impact Study Report Request # GI

Grounding Of Standby & Emergency Power Systems

Protection for 2500KVA High Tension Transformer Ankita S.Kulkarni 1, Priyanka S.Dhayarkar 2, Harsha H.Ambure 3, Ashwini S.Shinde 4

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

ABB Switzerland Ltd High Voltage Products PTHG-V / Marta Lacorte Business Development LAM High Current Systems. Generator Circuit- Breaker Systems

Power System Solutions (PSS)

Power Management with Solar PV in Grid-connected and Stand-alone Modes

A flywheel energy storage system for an isolated micro-grid

DESIGN CONSIDERATIONS FOR APPLICATION OF SHUNT CAPACITORS IN HEAVY HATER PLANT (TUTICORIN)

CHAPTER 1 INTRODUCTION

Battery Energy Storage

Onix Structure Private Limited. Solar PV Power Generation System Detailed Project Report

A Study of Suitable Bi-Directional DC-DC Converter Topology Essential For Battery Charge Regulation In Photovoltaic Applications

NORTH CAROLINA INTERCONNECTION REQUEST APPLICATION FORM. Utility: Duke Energy Progress

Increasing the Battery Life of the PMSG Wind Turbine by Improving Performance of the Hybrid Energy Storage System

PQC-STATCON. PPHVC-Power Quality Solutions. Instantaneous and stepless power quality compensation for dynamic reactive power and unbalanced loads

Hardware Testing of Photovoltaic Inverter Loss of Mains Protection Performance

Analyses of the grid resistance measurement of an operating transformer station

/12/$ IEEE. M. Bashir M.Sc student, Student Member, IEEE Ferdowsi University of Mashhad Mashhad, Iran

APPLICATION OF VARIABLE FREQUENCY TRANSFORMER (VFT) FOR INTEGRATION OF WIND ENERGY SYSTEM

Design and Control of Hybrid Power System for Stand-Alone Applications

Computer Aided Transient Stability Analysis

Transcription:

Study of Fault Currents and Relay Coordination of a Chemical Industry After Integrating with PV Generation and Simulation with a Software. B. Ramakoti #1, S. Hari Prasad Babu #2, K. Aravinda Swamy #3, K. Ramakrishna #4, B. Koti Reddy #5 # Dept. of Electrical Engineering, JNTU, Kakinada, India Abstract In the present de-regulation and distributed generation era, most of the large industries are adopting various distribution generators with the use of Renewable energy resources like solar, wind etc. The main purpose of this paper is to discuss the basic principle of solar photo-voltaic system, its integration with the existing utility grid and protection issues. As all are aware, solar power generation is being encouraged globally with the tag of Green Power, but there are certain issues like synchronisation, power- flows, harmonics and especially protective relay coordination. Later has been discussed thoroughly in this paper. A continuous chemical Industry, whose incoming grid power is integrated with solar PV power, has been selected for the case study. In the selected industry, a part of electrical net-work, which covers with point of coupling (POC) and detailed fault calculations are done as per the available literature for both the scenarios of pre-pv integration and post-pv integration. Also similar fault calculations are done with e-tap software and compared both the results. Then the relay coordination or Time Current Characteristics (TCC) of both pre and post PV integration scenarios are simulated with the software and the both results are compared to arrive a final conclusion of Relay coordination. Key words: Solar Photo Voltaic, Relay co-ordination, PV integration, Fault currents, Point of coupling. I. INTRODUCTION The power industry across the globe is experiencing a radical change in business as well as in operational model when the vertically integrated utilities are being un-bundled [1] and opened up for competition in power generation area which ends up the monopoly era of power system generation, with the advancement in Power Electronic Devices (PED), the integration of distributed generation in to the existing power network has increased rapidly. Business community, both state and private, are adopting renewable energy generations [2] either to meet the regulatory norms like respective geo-graphical Electricity Regulation Commissions in the form of Renewable Power Purchase Obligation (RPPO) or to reduce power bills. One of the major distributed integration facilities [3] is solar power, with the help of solar photo-voltaic (SPV) cells. The basic schematic diagram of a solar power plant is shown in Fig. 1. and described briefly as follows: Fig 1: Schematic diagram of a solar power plant The PV module, consisting of PV cells, converts the solar radiation in to DC electricity which again will be converted in to AC by inverters. The PV modules are first formed into strings by connecting in series to get the required voltage and then strings are connected is parallel to get the required power capacity. Then the output is fed to a Power Conditioning Unit (PCU) where it is converted in to AC. The PCU is not only acting as an inverter but also doing the functions of voltage regulation, maximum power point tracking (MPPT), synchronisation with grid, auto sleep and wake up functions and as a protective device. Also it monitors the power-flow at the Point Of Coupling and faults occurring in system. II. DESCRIPTION Keb Chemicals, The industry under study, is a chemical industry whose power schematic diagram is diagram is shown in Fig. 2. ISSN: 2231-5381 http://www.ijettjournal.org Page 208

All the circuit Breakers (CB) are of Vacuum circuit breakers. The HT switchgear is standard indoor type with all interlocks. Transformer, TR-3 : 3 winding, 340 V/340 V/6.6 kv, 50Hz, Dy5y5, 6 %, 1.25MVA, 1061A/ 1061A/ 109A. The detailed schematic diagram of PV assembly is shown in Fig. 4. Fig 2: Power Schematic diagram of industry The brief technical particulars of the Transformers are given in Table-I TABLE I TRANSFORMERS DATA Parameters TR-1 TR-2 MVA Rating 10 1.6 Primary voltage - KV 33 6.6 Sec. voltage- KV 6.6 0.415 % Z 8.75 6 Amps-primary 175 140 Amps-secondary 875 2130 Vector group Dyn 11 Dyn 11 Grounding Through a 3.8ohms resistor Solid Even though the total electrical network is large in size, the present study is restricted to 6.6 kv SWGR i.e., POC and its power in and out connections for fault currents calculations and simulations. The total load of the industries was 4 MW which was totally met from the utility grid. In the recent past, the unit was decided to go for a 1 MWp solar power plant and installed the same to meet the legal requirements. The power schematic diagram of main electrical power net work after PV integration is shown in Fig. 3. and the details of PV equipment given below. Fig 3: Power Schematic diagram post-pv integration Each PV module: 255W, 30 V (Vmp), 37 V (Voc), 8.5A (Imp), 8.9A (Isc) Each String: 21 nos of modules in series to give 340 V, 5.355 kw, 8.5 A Total Strings in parallel: 2 arrays X 94 nos to give 630 V, 2 x 0.5 MWp, 790 A Inverter (in PCU): 630 V DC/ 630 V AC, 50Hz, 3ph. Loads are mostly induction motors. Fig 4: Schematic diagram of PV Assembly III. PV System Integration Issues These are certain issues encountered by the industry due to SPV integration [4] like over voltages, Bidirectional power flow, power quality, harmonics, power fluctuations, protections, synchronisation etc.. However the scope of this paper is restricted to protection issues. Power system analysis reviews [5] the study of the various faults currents, rating of equipment [6] to with stand these faults [7] and protective relay settings accordingly. Since the protective device provides a form of insurance [8] for vital electrical equipment which reduces the equipment damage and en danger to human in the vicinity. Whenever an equipment or distributed generation is added, proper relay coordination [9] to be ensured so as to protect the entire network as intended and to meet the overall objective of coordination of protection and switching devices. Fault current for various faults, play a significant role in electrical protection system. Their magnitude varies from grid to grid. The integration may cause of loss of sensitivity of over current and earth fault relays [10]. Hence a detailed analysis is required to avoid mal operation and unwanted trips. When a fault occurs in grid, the fault is additionally supplied by distributed generators and may change operating sequence of circuit breakers [11]. Hence it is to be ensured that during any fault in system, the distributed generators like PV generation should be isolated as quickly as possible so that conventional protection system will isolate the faults as intended. IV. Calculation of Fault Currents and Methodology Fault currents of a utility grid are very high in magnitude and all the electrical equipment is suitably designed to with stand these fault currents. In this ISSN: 2231-5381 http://www.ijettjournal.org Page 209

paper following methodology is followed by restricting to these major faults viz L-L-L (Symmetrical) and L-G (Un symmetrical) faults: 1. Calculation of L-L-L fault current at POC by power MVA method for pre-pv integrated system. 2. Calculation of L-G fault current at POC by power MVA method for pre-pv integrated system. 3. Repeating the steps (1) to (2) for post- PV integrated system to arrive a conclusion of variations in fault currents of pre and post integration scenario. 4. Simulation of L-L-L fault with e-tap software to know the fault currents for comparison purpose. 5. Estimation of fault clearing times (i.e. Trip time) for L-L-L and L-G faults, at POC of both pre and post PV integration scenario with TCC Curves of Relay. 6. Analysis and conclusions of calculations and review study done for final recommendations if any for post-pv integration scenario. A. Pre-PV Integration Scenario 1) L-L-L fault: Fault MVA diagram with simplified calculations [12] is shown in Fig. 5. with further simplification in the same figure itself. Fault diagram is shown in Fig. 6. Fig. 6 Here the Delta connected winding of TR-1 blocks the flow of zero sequence current from source. Also in motors, X0=50% of X1= 12.5%. MVA ZPS of HV motor= 15/0.125=120 and MVA ZPS of LV motor= 1.25/0.125=10 (But blocked by Delta connected winding of TR-2) MVA ZPS = 100 +27+120 = 247 Total fault MVA=38.4 X 3 = 115.27 or If=10.1 ka B. Post-PV integration scenario 1) L-L-L fault: Fault MVA diagram is shown in Fig. 7. Fig. 7.1 Fig. 5.1 Fig. 5.2 Fig. 5.3 SC MVA = = 71.43 + 19.22 = 90.65 or Short Circuit Current, If = 7.9 ka which is termed as Over Current. 2) L-G Fault: Fig. 7.2 Total fault MVA=91.84 or If=8.03 ka 2) L-G fault: Zero phase current flows from PV system is blocked by delta winding of transformer. Now the fault MVA diagram shown in Fig. 8. ISSN: 2231-5381 http://www.ijettjournal.org Page 210

Fig. 8 Total fault MVA= 3 X 38=114 or If=10.17 ka All the above calculated results are tabulated in Table- II. TABLE-II CALCULATION RESULTS SPAJ-140C of ABB make (fast acting Numerical Relay) 2) Settings made: Over current: IEC Curve of Very Inverse (VI) with 500% current setting and TMS (Time multiple settings) of 0.3 Earth fault: IEC Curve VI with 20% current and TMS of 0.1. For faults at F, the relay R1 will operate and isolates the faulty area from system by opening CB-2. Time of operation: For L-L-L fault of 7.9KA = 0.6 Sec. For L-G fault of 10.1KA = 0.18 Sec. Fault Current in ka L-L-L L-G Pre-PV integration 7.9 10.10 Post-PV integration 8.03 10.17 3) Inference: It is confirmed that there is not mush variation in fault currents post PV integration since their contribution to fault is an insignificant value of around 125% of their normal rating dislike 1000% to 2500% of conventional system s fault current. 4) Simulation: The L-L-L fault scenario is simulated in e-tap software and result of screen shot shown in Fig. 9 which indicates both the calculated and simulated values are almost same. Fig 10 : Protective schematic diagram: Pre-PV Fig 9 : e-tap simulation screen shot V. ESTIMATION OF FAULT CLEARING TIME A. Pre-PV integration: The protective schematic diagram is shown in Fig. 10. 1) Details of R1: Over current and earth fault relay, ISSN: 2231-5381 http://www.ijettjournal.org Page 211

Fig 11: TCC OF SPAJ-140 C RELAY (VI) B. Post PV integration: The schematic diagram of protective system is shown in Fig. 12. VI. CONCLUSIONS For the industry selected as a sample, various protection issues that arise due to integrating of PV system in to the existing grid are discussed in detail. Equipment rating for fault currents post PV integrating is also checked and simulated for their adequacy and all the results are tabulated. From the results, it is concluded that there are no significant changes in the equipment rating and Time-current characteristics (TCC) of protection systems. This study implies that the electrical utilities, industries or consumers need not put much attention on their electrical systems adequacy post distributed generators integration especially PV generators in to their grid since their contribution during faults have a marginal impact. ACKNOWLEDGEMENTS The authors would like to extend their sincere thanks to the management of DPREC, JNTU (K) for extending the facilities to carry out this work; to the management of Keb Chemicals to gather the data from their works and to the management of DE Consulting firm for utilizing the simulation software. REFERENCES Fig 12 : Protective schematic diagram: Post-PV For fault at F, the relay R5 shall operate to open CB-6 before R1 opening CB2 so that the PV system s contribution to fault is less and also PV system will not suffer from transients of grid under faults. Details of R5: Relay SPAJ-140C of ABB make. 1) Relay coordination condition: For fault at F, the operating time of R5 shall be less than that of R1 i.e. less than 0.6 Sec for over current and less than 0.18 Sec for earth fault. 2) Settings made: Over current: R1=No change from pre-pv integration, R5 = 500% current with TMS of 0.1. Earth fault current: R1=No change, R5 = 20% current with TMS of 0.05. 3) Relay operation [13]: For L-L-L fault of 8.03 KA= R5 operates is 0.2 Sec; R1 operates in 0.58 Sec. For L-G fault of 10.17 KA = R5 operates in 0.095 Sec, R1 operates in0.17 Sec. 4) Inference: The above calculated results confirm that there is no much difference in fault clearing time for the pre and post PV integration scenario. 5) Final summary: It is confirmed that the relay coordination is not violated with PV integration and no significant changes are required as the equipment rating and relay settings post PV integration. [1] Ali Keyhani, Mohammad N.Marwali, Min Dai Integration of green and renewable energy in electric power system, Wilely publication 2010. [2] S.Eftekharnejad, V.Vittal, G.T. Heydy, B.Keel and J.Loehr,Impact of increased presentation of P.V. Generation on power systems, IEEE transactions as Power system vol- 28 Issue-2, PP-893-901, May 2013. [3] Noureding Hadsaid, Jean claude Sab onnadiere, Smart Grids,Wiley-2012. [4] Puladasu sudhakar, Dr.shushama, Dr.B.Sarresh, Protection issues of power system with PV system based distributed generation, IOSR Journal of Electrical Engineering vol-9 issue-3 May - June-2014. [5] Sunil S.Rao, Switchgear protection and power system, Khanna Publications, 2008. [6] BadriRam, D.Vishwakarma, Power System Protection and Switchgear, Tata Mc Graw Hill,2011. [7] Short Circuit Calculation Hand Book at ww.arcadvisor.com. [8] Distribution Automation Handbook, Section 8.2, Relay coordination, IMRS 757285, ABB Ltd. -2011, Finland. [9] Recommended practice for protection and coordination of industry and commercial power system, IEEE std: 242-1975, part 7.5.2. [10]A.Canova, L.Giaccase, F.Spertino and M.Tartag lior, Electrical impact of photo voltaic plant is distributed network, IEEE transactions on industry applications, vol-45 no:1 Pp 341-347, Jan-Feb- 2009. [11] Pedro Rodrignez, A drianv timbus, Flexible active power control of distributed power generation system during grid faults, IEEE transactions on industrial electronics vol-54, No:5 PP-2583-2592 oct- 2007. [12] IEC 60909-0 Short Circuit Currents in three phase a.c systems, Calculation of Currents-2001 [13] ABB Relay manual, SPAJ 140C. ISSN: 2231-5381 http://www.ijettjournal.org Page 212