PSCo 10-Year Transmission Plan/20-Year Scenario Assessment

Similar documents
Public Service Company of Colorado Transmission Projects Status. CCPG May 5, 2016

Public Service Company of Colorado Transmission Projects Status. CCPG August 18, 2016

PUBLIC SERVICE COMPANY OF COLORADO SENATE BILL DESIGNATION OF ENERGY RESOURCE ZONES AND TRANSMISSION PLANNING REPORT PROCEEDING NO.

RULE 3206 REPORT PROPOSED CONSTRUCTION OR EXTENSION OF TRANSMISSION FACILITIES 2013 THROUGH Docket No. 12M-165E

Interconnection Feasibility Study Report Request # GI

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

System Impact Study Report Request # T MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado

Black Hills Project Summary

Interconnection System Impact Study Report Request # GI

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Tri-State December 2013 Board Meeting

Appendix D Black Hills Project Summary

Falcon-Midway 115 kv Line Uprate Project Report

West Station-West Cañon 115 kv Transmission Project

2012 LOCAL TRANSMISSION PLAN:

WestConnect Regional Planning Update

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Wholesale Power Supply Socorro Electric Cooperative, Inc. Rob Wolaver, P.E. Senior Manager, Energy Resources

Proposed New Construction for

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Transmission Planning Attachment K Public Input Meeting

2011 LOCAL TRANSMISSION PLAN:

2018 Annual Progress Report to WECC Pacific Gas and Electric Company

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

GENERAL DIRECTION SOUGHT AND SPECIFIC QUESTIONS TO BE ANSWERED

VERMONT ELECTRIC POWER COMPANY (VELCO)

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Public Service Company of Colorado System Impact Study Load Interconnection Request for a 50 MVA Load Near Collbran

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF COLORADO DIRECT TESTIMONY AND EXHIBITS OF CHRISTOPHER E. PINK TABLE OF CONTENTS

Pacific Gas and Electric Company s 2013 Annual Progress Report

Merger of the generator interconnection processes of Valley Electric and the ISO;

New Mexico Transmission Expansion Concepts For Wind Resources

Attached is Idaho Power s 2013 WECC Annual Progress Report. Please contact me if you have any questions.

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

SPS Planning Criteria and Study Methodology

COLORADO SPRINGS UTILITIES RESPONSE TO Xcel ENERGY INTERCONNECTION SYSTEM IMPACT STUDY REQUEST # GI , RESTUDY 1 (August 6, 2009)

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow

Ameren Missouri. AMENDED Renewable Energy Standard Compliance Report Prepared in Compliance with 4 CSR

Updates and Modifications to Report

GENERATOR INTERCONNECTION REQUEST. BHCT-G11 Interconnection System Impact Restudy PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING

APPENDIX F: Project Need and Description

Updates. Pat Reiten President and CEO, PacifiCorp Transmission

THE TRES AMIGAS PROJECT

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

welcome to the BC Hydro community open house

Transmission Planning for Wind Energy Resources in the Eastern United States. Dale Osborn

100 MW Wind Generation Project

Arizona Transmission Challenges

City of Palo Alto (ID # 6416) City Council Staff Report

SunZia Southwest Transmission Project

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Illinois State Report

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Salt Lake County Electrical Plan Task Force October Douglas N. Bennion, P.E. Vice President Rocky Mountain Power

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017

SunZia Southwest Transmission Project

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

PSE Attachment K Puget Sound Area Transmission Meeting

NEU Electric and Natural Gas Price Update

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Supplemental Report on the NCTPC Collaborative Transmission Plan

MILLIGAN SOLAR PROJECT

P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676)

Western Area Power Administration Rocky Mountain Region (LAPT) Network Integrated Transmission Service. Designated Network Resources

Minnesota Biennial Transmission. Zone Meeting 8

Market Efficiency Planning Study

Burlington Lamar 345/230 kv Impact and 2013 Post TPL Assessment Study

Moving Renewable Energy to the User

Overview of ISO New England and the New England Wholesale Power Markets

MEETING AGENDA. Western Area Power Administration Rocky Mountain Region. Transmission Planning Stakeholder Meeting

State Regulatory Affairs and Local Relations Update. ATC Customer Meeting November 19, 2009

CUSTOMER/ TWIN ARROWS PROJECT

NJ Solar Market Update As of 6/30/15

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

Energy Policy Implications: PJM Planning

GENERATOR INTERCONNECTION REQUEST. BHCT-G11 Interconnection System Impact Study PREPARED BY BLACK HILLS CORPORATION TRANSMISSION PLANNING

Decision on Merced Irrigation District Transition Agreement

Distribution Capacity Impacts of Plug In Electric Vehicles. Chris Punt, P.E. MIPSYCON 2014

Transmission Planning using Production Cost Simulation & Power Flow Analysis

WIRES University Overview of ISO/RTOs. Mike Ross Senior Vice President Government Affairs and Public Relations Southwest Power Pool

The Development of Competitive Renewable Energy Zones in Texas

2016 SDG&E Grid Assessment Results

Updates and Modifications to Report

Michigan Thumb Loop Transmission Line Project

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Draft Results and Open House

Clean Energy Transmission Summit. Stephen Beuning Director Market Operations 1/9/13

Market Efficiency RTEP Proposal Window

Effects of Smart Grid Technology on the Bulk Power System

March 7, Subject: Southern California Edison 2011 Annual Progress Report

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

BC Hydro System 2016 Annual Progress Report

PREPARED DIRECT TESTIMONY

Local Transmission Plan. Rev. 1: April 2018

Transcription:

PSCo 10-Year Transmission Plan/20-Year Scenario Assessment May 2009 This report contains transmission planning data that may be conceptual in nature and is subject to change. The transmission projects listed may change scope or not be constructed.

Executive Summary 10-Year Transmission Plan Five Year Capital Budget(2009-2013) High Plains Express Initiative Total Cost Approx. $5.13 billion (may extend into 20 year time period) SB-100 Transmission Plan FERC Generation Interconnection Studies 23,970 MW, 81 Requests, Wind (51), Solar (10) SB-100. PSCo has initiated the Pawnee Smoky Hill 345 kv line (ISD 2013) and the Missile Site Switching station (ISD12-2010) High Plains Express is starting stage 2 feasibility 2

10-Year Plan Key Messages Coordinated and open transmission planning strategy that involves the electric utilities in the Rocky Mountain region and interested stakeholders Developed eight (8) unique transmission projects for the five (5) energy resource zones under Senate Bill - 100. Created an approved five year capital budget (2009 2013) for transmission reliability and import of renewable energy. 20-Year Transmission Scenario Assessment 20-year scenario assessment is a conceptual plan PSCo evaluated 6 unique transmission scenarios Scenarios include various levels of renewable energy that match the PSCo environmental strategy including an export strategy High Plains Express Initiative (HPX) develops a transmission expressway for moving renewable energy across the Rocky Mountain States 3

Scope and Purpose The purpose of this study is to document the transmission additions needed on the PSCo transmission system looking forward 10-20 years. The study is based on the most recent set of WECC approved 10 year powerflow models. Perform an assessment of the PSCo transmission assets based on current load forecast, resource plan, renewables, the SB-100 proposed plan and the High Plains Express project. 4

Transmission Ownership Colorado 5

PSCo System Statistics 2008 4153 Miles of Transmission 245 Substations Served 25 Generators Served 7 Wind Generators (1075 MW) PSCo Operating Company Peak Load 6701 MW PSCo Balancing Authority Peak Load 7912 MW 6

PSCo Transmission System PSCo Transmission Assets Located Entirely in CO and Within the Western Electric Coordinating Council Connected to Southwestern Public Service Company (SPS) Through the Lamar HVDC Interconnection Major Utility Interconnections Western Area Power Administration, TSG&T, Colorado Springs Utilities, Platte River Power Authority and Black Hills Power Major Wholesale Customers Intermountain REA, Black Hills, Holy Cross Energy, Yampa Valley REA and Grand Valley Electric, City of Center, Burlington, Julesburg 7

Planning Process Calendar 2009 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 5 year capital budget studies SB100, CPCN Filing SB100 Studies 5 year budget approved SB100 Biannual Filing 10 year plan completed CCPG Long Range Resource Plan WestConnect Generation Interconnect, Load Interconnect & Transmission Service Studies FERC 890 3/6/09 FERC 890 12/10/09 CCPG 4/23/09 CCPG 8/19/09-8/20/09 CCPG 12/16/09 WestConnect Annual Meeting 1/14/09 WestConnect Annual Stakeholder Meeting 8/20/09 8

Transmission Planning Drivers Regulatory/Environmental Considerations State Renewable Portfolio Standards Colorado Resource Plan (PSCo) SB -100 Transmission Plans to Energy Resource Zones 5-Year Capital Budget for Transmission Asset Management FERC - Generation Interconnection Studies Queue 23,970 MW, wind (51), solar (10) Transmission Service Studies Wholesale/retail Load Interconnections NERC reliability compliance and planning criteria Load Forecast (Feb 2009) 10-Year Colorado Long Range Planning Group (CLRPG) Studies (Jan 2009) High Plains Express (HPX) Initiative 9

PSCo Load (MW) 7000 6900 PSCo FERC Form #1 Peak Load 2004-2008 PSCo Retail and Wholesale customers 6927 6910 MW 6800 6700 6600 6500 6641 6701 6400 6421 6300 2004 2005 2006 2007 2008 2009 Year 10

PSCo Load (MW) MW 7400 7300 7200 7100 7000 6900 6800 6700 6600 6862.8 6710.5 PSCo Projected Peak Loads 2009-2019* PSCo Retail and Wholesale customers Red Line Indicates 2005 Peak Load (6927 MW) Green Line Indicates 2007 Peak Load (6910 MW) 6842.1 6648.2 6735.6 6827.3 6914.2 7012 7114.6 7231.1 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 7353.4 Year *Forecast Feb. 2009 Wholesale customers reduced by 250 MW in 2010 with Comanche #3 ownership 11

Generation Interconnection Map Legend X X X Wind Interconnection on PSCo Transmission Solar Interconnection on PSCo Transmission Gas/Coal Interconnection on PSCo Transmission 17 16 24 9 37 13 1819 36 4 33 14 11 15 1 6 20 3435 3940 8 27 43 2 22 2629 49 10 23 25 31 3 46 47 51 52 53 54 2850 3244 48 7 5 12 3041 42 21 45 Updated November 7, 2008 SJG 12

Active FERC Generation Interconnection Studies (2006-2009) Arapahoe 587 MW Boone 500 MW Wind Fort St. Vrain 300 MW Gas; 256 MW Combined Cycle Green Valley 400 MW Wind Hartsel 100 MW Solar Walsenburg 300 MW Wind Comanche 700 MW Wind Keensburg 250 MW Wind Ault 1600 MW Wind Jackson Fuller 601 MW Wind Missile Site 800 MW Wind; 270 MW Gas Lamar 2686 MW Wind San Luis Valley 150 MW Wind; 1730 MW Solar Pawnee 1170 MW Combined Cycle; 2820 MW Wind 13

Generation Interconnection Process PSCo Interconnection Queue Total Requests since 2003: 81 Total MW: 23,970 Requests by Generation Type: Wind: 52 Solar 10 Coal: 6 Gas: 12 Biomass: 1 14

Senate Bill 07-100 Upon recommendations by the 2006 Transmission Task Force on Reliable Electricity Infrastructure, the 66th General Assembly passed Senate Bill 07-100. Under SB 07-100, PSCo must meet the following requirements: Designate Energy Resource Zones (ERZ) Develop plans for the construction or expansion of transmission facilities necessary to deliver electric power consistent with the timing of the development of beneficial energy resources located in or near such zones Consider how transmission can be provided to encourage local ownership of renewable energy facilities Submit proposed plans, designations, and applications for certificates of public convenience and necessity to the commission for simultaneous review 15

Current SB-100 Transmission Plan 3-13-2009 New Ault-Cherokee 230 kv ~ISD 2015 New Midway- Waterton 345 kv ~ISD 2011 New San Luis Valley-Calumet- Comanche 230 & 345 kv lines ~ ISD 2013 San Luis Valley Zone 4 Ault Cherokee Daniels Park Waterton Calumet New Pawnee-Smoky Hill 345 kv, ISD 2013 Zone 1 Keensburg Smoky Hill Fuller Zone 2 Midway Comanche Zone 5 Pawnee Missile Site Zone 3 Vilas Lamar 230kV 345kV New Pawnee- Daniels Park 345 kv -2 nd circuit ~ISD 2016 New Missile Site 230 kv ISD 2010) & 345 kv (ISD 2013) New Lamar Vilas 345 kv ISD 2016 New Lamar-Comanche 345 kv & Lamar - Missile Site 345 kv ISD 2016 16

Proposed SB-100 Projects Project Pawnee - Daniels Park 345 kv Line Ault - Cherokee 230 kv Line Missile Site Lamar - Comanche and Lamar - Missile Site 345 kv Lines Description Second circuit 345 kv line in Energy Resource Zone 1 New 230 kv line in Energy Resource Zone 1 345/230 kv switching station on the Pawnee - Daniels Park line in Energy Resource Zone 2 New 345 kv lines to access Energy Resource Zone 3 New 345 kv line In Energy Lamar - Vilas 345 kv Line Resource Zone 3 to access wind rich area Double circuit 230 kv line (SLV to San Luis - Calumet - Calumet) and double circuit 345 Comanche Line kv line (Calumet to Comanche) Midway - Waterton 345 kv Line Needed for system reliability and utilization resources in Energy Resource Zones 3,4 and 5. Must file modification to CPCN received 9/07 in order to construct. Generation Injection Tenative ISD Energy Zone 300-500 MW 2016 1 300-600 MW 2015 1 200-500 MW 2010 (230 kv) - 2013 (345 kv) 800-1000 MW 2016 3 2 2016 3 600-1000 MW 2013 4&5 2011 3&4&5 Pawnee - Smoky Hill 345 kv Line 345 kv line from Pawnee to the Denver load center. Received CPCN in January 2009. *Generation values are not simultaneous 500 MW 2013 1 17

System Plans 18

5-Year Capital Budget (2009-2013) Planning Zones Denver/Boulder Foothills Western Colorado Front Range (I-25 Corridor) 19

Proposed Transmission Projects Denver/Boulder, 2009 2013 Denver/Boulder Area # Project Comments 1 Sandown Leetsdale Line New 115kV underground line for reliability 2 Valmont #2 230/115 kv Auto XFMR Add second 230/115 kv 280 MVA auto transformer at Valmont 11 2 4 3 4 IREA Happy Canyon Todd Creek 115 kv Delivery Point Construct a new 115 kv substation for IREA Provide a load delivery interconnection for TSG&T on Cherokee-Ft. Lupton 115 kv Todd Creek Substation 7 10 5 6 Distribution Powhaton Distribution Marcy New Powhaton substation on the Spruce Smoky Hill 230 kv line Add third 230/13.8 kv transformer at Marcy substation 8 7 Eldorado Plainview Replace existing 115 kv line with new single circuit, 115 kv structures and line rated for 150 DENVER 1 5 8 Chambers Final phase of transmission infrastructure upgrades tying the 230 kv outer belt network to the 115 kv load serving transmission system between the Tower substation and the Cherokee East 115 kv lines 9 Daniels Park 230/115 kv 280 MVA Replace existing 230/115 kv 150 MVA transformer with 230/115 kv 280 MVA transformer 6 9 3 10 11 Valmont Ridge Line GunBarrel Niwot 230 kv Rebuilding 115 kv line for higher capacity Underground 230 kv to Niwot to serve IBM, second circuit 20

Proposed Transmission Projects Foothills Area (2009-2013) # Project Comments 1 FSV G5 & G6 Transmission upgrades required to install two new gas turbines at Ft. St. Vrain. CPCN was acquired from the CPUC 3 2 1 2 4 Distribution Kelim Sub Distribution College Lake New distribution substation required for customers in the area north of Denver, interconnecting at PRPA s Airport substation New 230/138 kv distribution substation required for customers in the area west of Fort Collins (CSU Campus) interconnecting/ sectionalizing PRPA's Rawhide Dixon 230 kv line 21

Proposed Transmission Projects Western Colorado Area (2009-2013) 4 # Project Comments 1 IREA Hartsel New Hartsel 230 kv substation delivery point for IREA 2 Uintah 230 kv Cap Bank Install one 45 MVAR capacitor bank at Uintah 3 Collbran 115/12.3 kv Bank 1 Replacement Replace existing bank 1 115/12.5 kv 2.8 MVA transformer with a 115/12.5 kv 7.5 MVA transformer 4 Clear Creek Starkey Substation and Line New Clear Creek 345 kv substation and 230 kv transmission line from Clear Creek to Starkey Gulch to serve gas processing retail customer 5 Uintah Sub 230-69 kv Install 67 MVA 230/69 kv transformer at Uintah to serve PSCo load 6 Shoshone Install new 69kV transformer at Shoshone due to catastrophic failure of penstock 7 Fruita Sub 24.9 kv Delivery New 69/24.9 kv 7.5 MVA transformer and related equipment at Fruita substation to serve Grand Valley Rural Power load 8 Distribution New Castle New 115/69/24.9 kv distribution substation 9 Distribution Poncha Jct. #3 Add new 25 kv main and transfer buses and two 25 kv feeders to existing 115/25kV transformer 8 6 2 3 1 9 22

Proposed Transmission Projects Front Range (I-25 Corridor) Area (2009-2013) 3 1 Year Project Comments 2010 Comanche Reader Line #2 Construct a new underground Comanche Reader 115 kv line 2010 Replace Comanche 230/115 kv Auto transformer Install 2 new 280 MVA auto transformers to replace the existing ones 2012 Midway Waterton 345 kv Line New 345 kv Line 2 23

High Plains Express Initiative Two 1,280 mile, 500kV, AC lines through WY, CO, NM and AZ 3,500 4,000 MW of transmission capacity Cost approximately $5.13 billion Regional Projects Spans both Ten Year Plan & Twenty Year Scenario Assessment 24

Studies Cost Estimate Two separate 500 kv AC lines Approx. 3,500 MW Capacity $1.5 Mil/mile for 1,280 miles x 2 = $3.84 billion Substations (10 new / 5 upgraded): $640 million Series compensation: $512 million SVC: $140 million Total Costs: $5.13 billion 25

PSCo 20-Year Scenario Assessment 26

Scenario Index Scenario 1 Scenario 2 Scenario 3 Scenario 4 Scenario 5 Scenario 6 Low Renewables Growth (1600 MW) Intermediate Renewables Growth (2400 MW) High Renewables Growth, SB-100 Full Build Out to Five Energy Zones (4400 MW) High Plains Express Initiative with Integrated Wind Projects Wind Export Scenario, Interconnect With Southwest Power Pool HPX Initiative with Solar Integration 27

Scenario 1: Low Renewables Growth (1600MW) PAWNEE SMOKY HILL 28

Scenario 2: Intermediate Renewables Growth (2400MW) PAWNEE SMOKY HILL COMANCHE SAN LUIS VALLEY CALUMET 29

Scenario 3: High Renewables Growth, SB-100 Full Build Out 230kV Ault Zone 1 345kV Daniels Park Cherokee Arapahoe Smoky Hill Zone 2 Pawnee Missile Site Zone 4 Zone 5 Calumet Comanche Zone 3 Lamar Vilas 30

Scenario 4: High Plains Express Integration Project 4 31

Scenario 5: Wind Export Scenario, 765kV System to Interconnect with Southwest Power Pool 32

Scenario 6: HPX Initiative with Solar Integration 33