Boston Scientific Energy Storage Project. Final Report (PUBLIC) November 2016

Similar documents
City of Philadelphia Renewable Energy Power Purchasing RFP Pre-Proposal Meeting

TORONTO TRANSIT COMMISSION REPORT NO.

Solar-Wind Specific Request for Proposals

Hutchinson WWTF Solar PV EP4-41

JEA Distributed Generation Policy Effective April 1, 2018

2012 INSTALLERS MEETING UES INSTALLER S MEETING

MassDOT Highway ROW Solar PV Energy Program. Hongyan (Lily) Oliver Massachusetts Department of Transportation Office of Transportation Planning

RENEWABLE ENERGY IN JORDAN What had to be done 8 Oct 2017

1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS

2018 Customer generation rates

Battery & Energy Storage

Minnesota Power s Community Solar Garden Program. Minnesota Senate Legislative Energy Commission 7/12/2018

SOLAR DISTRIBUTED GENERATION PROGRAM UPDATE

Metal Bulletin Conference

PART 2 GUIDELINES. To be eligible to receive a financial incentive, the following conditions must be met:

PG&E California Solar Initiative (CSI) & Net Energy Metering (NEM) Interconnection Webinar. March 26, 2009

INTERCONNECTION STANDARDS FOR CUSTOMER-OWNED GENERATING FACILITIES 25 kw OR LESS PUBLIC UTILITY DISTRICT NO. 1 OF CHELAN COUNTY

The Isle of Gigha Flow Battery Project

24. SOLAR INCENTIVE PROGRAM II

Project Title: Contract Number: Milestone Number: Report Date: Contract Contact: Phone: Congressional District: Executive Summary:

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng

Electric Rates. For Michigan customers

The Regional Municipality of York. Purchase of Six Battery Electric Buses

4-6 October 2016 The NEC, Birmingham, UK. cleanenergylive.co.uk

Solar Power. Demonstration Site. Annual Performance Report 2017

Schedule GS-2 INTERMEDIATE GENERAL SERVICE

THE CONNECTICUT LIGHT AND POWER COMPANY, DBA EVERSOURCE ENERGY. PARTIAL STREET LIGHTING SERVICE RATE 117 Page 1 of 5

SERVICE CLASSIFICATION NO. 1

Umatilla Electric Cooperative Net Metering Rules

Presentation to IAPSC 9 th June Tim Irwin Deputy Director Environmental Policy Division Department of the Environment

CHOPTANK ELECTRIC COOPERATIVE, INC. DENTON MARYLAND TERMS AND CONDITIONS

ILLINOIS SUPPLEMENTAL PV PROCUREMENT PROGRAM (ROUND 3) JANUARY 13, 2016

Residential PV-the City of Cape Town s experience Brian Jones Head: Green Energy/Electricity Services City of Cape Town South Africa

Illinois and Renewable Energy

DEMAND RESPONSE EMERGING TECHNOLOGIES PROGRAM SEMI-ANNUAL REPORT 2015

2019 BQDM Extension Auction Frequently-Asked Questions Updated January 29, 2018

Part 3 Agreement Programs for 2017 and Greenhouse Gas Reduction (Renewable and Low Carbon Fuel Requirements) Act

2019 Summary of Eastern Massachusetts Electric Rates for Greater Boston Service Area Rates Effective: January 1, 2019

City-wide LED Street Light Conversion Program

Impact of Distributed Generation and Storage on Zero Net Energy (ZNE)

Move with the SUN All DC Solar Systems. Green Power Outsourcing. GSMA SEA working group. July 24-25, Mr. TK Shih.

2016 UC Solar Research Symposium

Genbright LLC. AEE Technical Round Table 11/15/2017

THE PUBLIC SERVICE COMMISSION OF WYOMING

STATE OF NEW HAMPSHIRE PUBLIC UTILITIES COMMISSION DE LIBERTY UTILITIES (GRANITE STATE ELECTRIC) CORP. d/b/a LIBERTY UTILITIES

Merger of the generator interconnection processes of Valley Electric and the ISO;

End-Customer Owned Decentralized Storage as a Part of the Smart Grid Volker Wachenfeld, SMA Solar Technology AG

Street Address. City-Village-Township

Greening the Grid: USAID GTG-RISE Initiative in India and Ancillary Services from Battery Energy Storage Systems

Electricity Network pricing schedule. Module 15 Effective April 1, 2011 for Electricity line charges. Version

SCHEDULE NO. ACG33 NET METERING SERVICE

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

THE EMPIRE DISTRICT ELECTRIC COMPANY P.S.C. Mo. No. 5 Sec. 4 1st Revised Sheet No. 23

ONCOR ENERGY STORAGE and MICROGRID

MISSOURI SERVICE AREA

Participation of Beacon Power s Flywheel Energy Storage Technology in NYISO s Regulation Service Market

THE NARRAGANSETT ELECTRIC COMPANY LARGE DEMAND RATE (G-32) RETAIL DELIVERY SERVICE

Considerations for Municipal Solar Projects. Ben Frevert Larsen Engineers November 16, 2016

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE

Creating A Greener Energy Future For the Commonwealth. Massachusetts RPS Solar Carve-Out: Overview & Program Basics.

Energy storage investment in APAC Energy Storage Strategy Paper

Electrovaya Provides Business Update

Oncor Electric Delivery Distributed Storage and Microgrid Demonstration Projects

Portland General Electric Company Eleventh Revision of Sheet No. 7-1 P.U.C. Oregon No. E-18 Canceling Tenth Revision of Sheet No.

Rwanda Biofuels Limited. Powering Rwanda s Development

Street Address. City-Village-Township

EXHIBIT A ORDINANCE NO. O CITY OF LAURINBURG, NORTH CAROLINA SCHEDULES OPR RESIDENTIAL TIME-OF-USE SERVICE

NSTAR ELECTRIC COMPANY M.D.P.U. No. 28 EASTERN MASSACHUSETTS CAMBRIDGE SERVICE AREA GENERAL SERVICE

Engineers Ireland Site Visit 23 rd March 2010

Grasshopper Vision. Accelerate the adoption of sustainable practices by creating accessible and affordable products for everyone.

Clarifications Note 2 ITB GP

Biogas Hybrid Buses in Bergen

Renewable Energy System Tariffs and Pricing

Project Title: Lowertown Ballpark (CHS Field) Solar Arrays Contract Number: EP4-34 Milestone Number: 1 Report Date: June 21, 2016

Edmond Electric Standard Pricing Schedules

Rate Schedules. Effective 1/1/2019

Creating A Greener Energy Future For the Commonwealth. Massachusetts Solar Carve-Out (SRECs): Overview & Program Basics.

sun systemizer High-performance battery storage for a safe power supply

Solar & Storage the Opportunity

TABLE OF CONTENTS. 1. Territory to Which Schedule Applies Application for Service Customer Obligation 15

Technical Series, Edition 16

Iowa Statewide Solar Readiness Initiative

Request for Qualifications. for

Edmond Electric Standard Pricing Schedules

CDOT RFP NM DTR ADA Cutaway Vehicles Contract Offerings Order Process. October 3, 2018

MEMORANDUM. TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit. Date: May 24, Summary

Kotzebue Electric Association Flow Battery Storage Systems Quarterly Report 7/2012 Prepared by Jesse Logan (KEA)

Purple Line Light Rail P3 Project

PATH Integrated Railcar and Signal System Replacement Program

Bihar Electricity Regulatory Commission Vidyut Bhawan, J.L.Nehru Marg, Patna

LANCASTER CHOICE ENERGY S BIENNIAL ENERGY STORAGE PROCUREMENT COMPLIANCE REPORT

Rapidly Deployable Plug & Play Energy Storage Solutions

TELL CITY ELECTRIC DEPARTMENT RATES AND CHARGES

STAFF REPORT ACTION REQUIRED

UM1716 Resource Value of Solar Docket Due: December 22, 2015

REQUEST FOR PROPOSALS (RFP) FOR THE PURCHASE OF SOLAR ENERGY

Power Supply Cost Recovery

Introducing the world's most reliable solar panel. Company presentation / Solar panels

RFP No. P3010 New l.i ght Rail Vehicles

The Gambia National Forum on

Transcription:

Boston Scientific Energy Storage Project Final Report (PUBLIC) November 2016

Executive Summary Kingspan ESB Limited applied for Energy RD&D funding for the Boston Scientific Solar PV Energy Storage Project in April 2016. In July 2016 the project was successful in it s application for approximately 45% of the budgeted capital cost of the project 1. This grant was for the installation of Ireland s largest co-located solar PV and energy storage system, and will be a critical test bed for embedded energy storage in Ireland. The project was to be an extremely challenging an innovative co-location of Solar PV and battery energy storage. Due to the tight project timelines the agreement of necessary legal contracts was not possible. These contracts preclude the grantee from progressing the solar PV element of the project, but do not preclude the progression of the battery energy storage element. A scope change was agreed with SEAI in October 2016 and the grant amount reduced as a result of this scope change. The battery energy storage element, a 190kWh / 100kW Tesla Powerpack, will deliver a number of functions during operation, namely: - Time shifting of demand to take advantage of lower retail electricity prices (arbitrage) - Delivery of system services within the new DS3 system service ancillary market as part of the ISEM market restructuring The project will be installed by end of November 2016, with some commissioning and testing continuing through December 2016 and January 2017. 1 Award letter received from SEAI on 28 th July 2016

Project Activities Since September Progress Report Since the Progress Report was submitted in September 2016 the following activities have been undertaken by the project team. 1. Battery selection, payment and shipping of Tesla Powerpack battery 2. Site selection and site integration design 3. Installation of concrete foundation for Tesla Powerpack battery at site 4. Installation of Tesla Powerpack battery system, G10 protection panel, electrical and control interfaces. The following sections outline some of these activities in more detail Battery Selection and Design The battery system for the project was specified initially to have a storage capacity of around 100kWh. Kingspan ESB, through ESB Innovation, sent an RFP to four potential battery suppliers; Three responses were received and evaluated based on the following criteria - Cost - Performance - Delivery schedule (driven by grant timeline) A number of factors were evident from this RFP responses received - The market for battery energy storage systems does not readily deliver 100kWh batteries, a larger system would be required - Delivery time would be a challenge for all suppliers - There was a wide variation on price A Tesla 100kW/190kWh system was selected as the preferred battery for this project. The cost of this was higher than the original budgeted cost, but that is due to the capacity being almost double that of the budgeted system. The selection of Tesla as preferred supplier in June 2016 and they committed at this time to delivering by end September 2016, in line with the project schedule. As a deposit could not be paid until the SEAI grant agreement was received in late

July, Tesla adjusted their expected delivery date to end October 2016. This was outside the original agreed project schedule. This delivery date of the battery to site was achieved within October 2016. Below is the Tesla PowerPack layout for this project, it s location at the Boston Scientific Site, and a description of the main components Figure 1: Tesla Battery System configuration at Boston Scientific. 2 x Powerpack battery units, 1 x DC combiner, 1 x PCS (Power Conditioning System)

Figure 2: Typical Tesla Powerpack installation showing main components. Note only two Powerpack units installed at Boston Scientific. Figure 3: SLD of 100kW/190kWh Tesla battery system for Boston Scientific

Foundation Installation The final battery system location was agree between Boston Scientific, Kingspan ESB and Tesla. The area selected was within the Phase 3 Chiller Compound at Boston Scientific. Installation of the concrete foundation was undertaken in early November 2016 in line with Tesla s foundation specification. The foundation includes a service area for battery maintenance. Figure 4. Foundation pad during installation before concrete pour Installation of Powerpack, G10 relay The installation of all major components was undertaken in November 2016. This involved the installation of the below components at site over three days - 2 x 100kWh/50kW Tesla Powerpack batteries - 1 x DC Combiner panel - 1 x Power Conditioning System (nominal power 250kVA) - 1 x Tesla Master Controller - 1 x Frequency Meter - 1 x Battery Meter

- 1 x G10 Protection Panel - Associate DC, AC and Signal cables Photos of the installation in progress and final installation are shown below. The battery was installed by 28 th November 2016. Figure 5. Internal components of 100kWh/50kW Powerpack 2 of these installed at Boston Scientific

Figure 6. Installed major components on concrete foundation Figure 7. DC Link Box Internals

Figure 8. Completed Tesla Powerpack System Figure 9. Master Controller and Metering

Figure 10. Completed Tesla Powerpack System Figure 11. Completed Tesla Powerpack System

Next Steps The Tesla Powerpack system is now installed at the Boston Scientific site in Galway. This is the very first Tesla battery storage system in Ireland, and one of the first battery energy storage systems of any type in Ireland. Through December and January the final phases of commissioning and testing of the system will be undertaken with ESB Networks (Embedded Generation Interface Protection) and Tesla. The battery will be available for service following this test period. Over the initial year of operation it is expected that the battery system will deliver the following benefits to both Boston Scientific and ESB. - System arbitrage savings to Boston Scientific from a day/night shifting of energy (i.e. charging the battery at nigh-time rates, and discharging at daytime or peak rates) - Eirgrid DS3 Qualification Trials (2017) ESB have entered the battery system into the DS3 Qualification Trial tender for 2017. This will allow the demonstration of the battery providing Primary Operating Reserve (POR) as a system service. - DS3 Market (2018 on) ESB expect that when operation is demonstrated the battery will deliver DS3 services through a competitive auction from 2018 onwards. The Tesla PowerPack system will operate as a R&D test bed to understand the following - Operation and degradation effects of a Li-Ion battery system providing multiple functions (arbitrage and system services) - Demonstration of delivery of several DS3 system services including Fast Frequency Response, Primary Operating Reserve Secondary Operating Reserve, and Tertiary Operating Reserve - Demonstration of an embedded (behind the meter) energy storage system to trade within the DS3 market - Future addition of renewable energy, such as the originally planned rooftop solar PV system, to develop an understanding of the co-location of battery energy storage and renewable power generation on industrial energy consumer sites - Provision of real world operating data to universities and IT s to enable primary research into embedded energy storage operation within the electricity system