BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

Similar documents
Energy storage - two Canadian Case Studies ESA Annual Conference, Washington, June 4th. Alex Bettencourt Managing Director

In the mountainous town of Field, Canada, the completed NaS battery energy storage installation went into service in May 2013.

American Electric Power s Energy Storage Deployments

EPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010

PROJECT OUTREACH REPORT

Glendale Water & Power Smart Grid Project

Smarter Network Storage UK first multi-purpose application of grid scale storage. Dr. Panos Papadopoulos, PhD, CEng

ADB Knowledge Partnership Week. Hirokazu Yamaguchi May, 2015

FINAL FACILITY STUDY. 230/69/13.8 kv Transformer Addition(s) at Badwater Substation 2009 T1. September 10, 2010

Decision on Merced Irrigation District Transition Agreement

O&M Requirements for Utility-Scale Solar PV and Energy Storage. Nicholas Jewell, Ph.D., PMP Sr. Research Engineer Research & Development LG&E and KU

Battery Electric Bus Technology Review. Victoria Regional Transit Commission September 19, 2017 Aaron Lamb

RESILIENT SOLAR CASE STUDY: SUNY New Paltz NYPA Integrated Grid Pilot

ENERGY STORAGE DEPLOYMENTS IN ONTARIO APPRO NOVEMBER 18, 2014 TORONTO

Off-Grid Renewable Energy Program in Myanmar. Pradeep Tharakan, PhD Senior Energy Specialist (Climate Change) Asian Development Bank

GRID INNOVATION CAUCUS CO-CHAIRS

Generation Interconnection Facilities Study For

Overview of Energy Storage Technologies For Renewable Integration. Jamie Patterson Sr. Electrical Engineer R&D Division California Energy Commission

Evaluating Batteries: Deployment, Integration and Market Drivers

Battery Energy Storage for Increasing Renewable Energy

Update on the Philippine Wholesale Electricity Spot Market

NEC Energy Solutions. Energy Storage for Grid Stabilization in Electricity Grids. with high Penetration of Renewable Energies

PDR Energy Baseline Alternative. Proposal for Discussion October 27, 2015

Large Scale Storage and Demand Resources - Enabler of Transmission Delivery? Paper Number: 14PESGM2398

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective

2009 Wind-Diesel Workshop. Microgrid Control System Technology GE Digital Energy, Markham Ontario

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

Portland General Electric

Unalakleet Update: Lessons learned & continual improvement. Alaska WWG

Review of U.S. market reforms for renewable integration, flexibility, and storage

May 2017 Pei Sue Ong, Capital Accounting Advice Manager Pacific Gas and Electric Company

BC Hydro System 2017 Annual Progress Report

The Smarter Network Storage Project

Application of Battery Energy Storage for Frequency Regulation. Alexandre Oudalov

Fleet Management & Planning

Distributed Energy Storage John Steigers Generation Project Development Energy / Business Services

successful integration of distributed generation in rural areas

SERVICES INNOVATION. Montreal Symposium March 29, Jack Simpson Director, Generation & Capacity Planning

NAS batteries for Technical Challenges with Renewable Energy

Experience on Realizing Smart Grids. IEEE PES conference, Gothenburg

Micro-Grid and Battery Energy Storage Technologies for Large Scale Renewable Energy Integration

Facilities Study for Alberta to US Available Transfer Capability

MILESTONE SUMMARY REPORT Project funding provided by customers of Xcel Energy through a grant from the Renewable Development Fund

MONTHLY PERFORMANCE DASHBOARD

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada

Battery Energy Storage System Pilot Project, Puducherry Power Grid Corporation of India Limited. Manish Kumar Tiwari

Smart- Grid Ready PV Inverter

Store Energy, Green Future

MONTHLY PERFORMANCE DASHBOARD

Smart Grid Automation and Centralized FISR

THE TRES AMIGAS PROJECT

Smart Grid Subcommittee Report

NTPC RENEWABLE ENERGY PROJECTS SUCCESS, CHALLENGES AND PERSERVERANCE

Brad Roberts. & Jeff Palermo KEMA High Plains Transmission Summit Topeka Lawrence, Kansas November 3, 2009

Strategy and Roadmap for PV Systems in Japan

Electricity Storage: A multi valued technology opportunity

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

BYD Battery Energy Storage Solution. BYD Design Center

2015 Grid of the Future Symposium

System Status Briefing

International Approaches for an Integrated Grid

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017

Power Purchase and Grid Connection Procedures

Solar-Wind Specific Request for Proposals

ERCOT Overview. Paul Wattles Senior Analyst, Market Design & Development. Solar Energy Industries Association July 11, 2012

Case Studies and Benchmarking: Canadian DER Integration Projects Tarek EL-Fouly, PhD

MONTHLY PERFORMANCE DASHBOARD

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

2016 UC Solar Research Symposium

Energy Storage Workshop. Hosted By: The UK Energy Storage Operators Forum

Non-network solutions

C PER. Center for Advanced Power Engineering Research C PER

King Island Renewable Energy Integration Project. Isolated Power System Connect 2015 Simon Gamble Manager Hybrid Off-Grid Solutions

15 Nelson-Marlborough Regional Plan

Generator Interconnection System Impact Study For

Breakthrough in Vanadium Flow Batteries regarding Cost and Performance

Battery & Energy Storage

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Texas A&M Microgrid and Electrical System Study. Cushing Memorial Library & Archives

Operational Opportunities to Minimize Renewables Curtailments

BC Hydro System 2011 Annual Progress Report

Distributed Generation

Summer Reliability Assessment Report Electric Distribution Companies Perspective

Facilitated Discussion on the Future of the Power Grid

Islands challenges and R&D activities funded by HEDNO. Nikos Hatziargyriou Chairman of the Board and CEO of HEDNO ETIP SNET Vice-Chair

The Isle of Gigha Flow Battery Project

SCE's Experience Distribution Volt/VAR Control:

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

welcome to the BC Hydro community open house

SAFT approach to on-grid Energy Storage Intensium Max and ESS experiences Javier Sánchez

MIPSYCON 2014 Can a Grid be Smart without Communications? A Look at an Integrated Volt Var Control (IVVC) Implementation

Energy Storage Options for the Electricity Network

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK

MCE Napa County Cleaner energy and lower rates. Honig Winery, Rutherford

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.

MONTHLY PERFORMANCE DASHBOARD

Small Scale Generation Connections

15 Nelson-Marlborough Regional Plan

BROCHURE. End-to-end microgrid solutions From consulting and advisory services to design and implementation

Irrigation energy efficiency How to analyse your energy costs. Nick Bullock The Energy Guys

Transcription:

1 BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada IEEE PES Meeting July 2014

General BC Hydro Overview Crown Corporation Serving about 95% of province and 1.9 million customers ~10,500 MW demand Generation 13,800 MW capacity 41 Dam sites, 30 Hydro facilities and 9 Thermal units > 90% renewable Wind under contract 790MW, installed 480MW Transmission 500kV series-compensated backbone 18,000 km of transmission lines, 22,000 steel towers 260 substations One primary control center + one backup Interconnected to Alberta and US part of WECC Distribution 56,000 km of Distribution lines Approx. 900K poles, over 300K of transformers Serve 17 Non-integrated areas 2

Battery Energy Storage Project Opportunity Issue Golden substation near-capacity Served via single 69kV transmission line Peak load ~28MVA 2 x 25kV transformers Poor reliability indices for Field Single 55km 25kV distribution circuit from Golden substation Peak load ~550kVA Proposal Add 2MW battery energy storage to Golden distribution network to reduce peak load on substation Defer transformer upgrades at substation for 2 years Locate 1MW of the battery energy storage at Field to supply power during feeder outages 3

Battery Energy Storage Project Opportunity Government of Canada Clean Energy Fund 2009 Up to $146M over 5 years to support renewable, clean energy and smart grid programs across Canada 50% matching funds for projects shown to reduce GHG emissions, demonstrate innovative technology and knowledge transfer to other applications, locations and organisations BC Hydro proposal awarded funding Jan 2010 Project Objectives Implement peak shaving and islanding functions Demonstrate use of battery to: Defer capital expense Be an alternative to diesel back-up Demonstrate deployment of battery power in Canadian climate conditions 11. Energy Storage and Demand Response for Near-capacity Substation Lead proponent: BC Hydro Strategic Area: Smart Grid/Electricity Storage Location: Golden and Field, British Columbia Purpose: This project demonstrates the integration of energy storage as a mechanism for reducing electricity demand at near-peak capacity substations. This type of solution has the ability to be used in other remote communities where the grid reliability is low and the cost of the transmission line upgrade is uneconomical. 4

Battery Energy Storage Design 5

Power Sodium-Sulphur Battery Technology Minimum Stored Energy Number of Modules Cycle life Round trip efficiency DC 85% Installed footprint / Enclosure Height Rated DC voltage of battery (full charge) 1 MW Nominal (1.05 MW 2hr Peak) 6.32 MWh DC 20 x 316 kwh 4500 cycles 25.1 m 2 / 4.6 m 640 V Battery Temperature 300 C Fast charge time of battery Expected life of battery Energy density Power density Power consumption of peripheral devices: Depends on ambient conditions Manufacturer 9-10 hours 15 years 59.6 kwh/m3 9.9 kw/m3 ~60 kw Battery Heaters (144 kw peak) NGK Insulators, Japan 6

Challenges Schedule delays: Procurement Permitting Fire Safety Design challenges: Canadian climate conditions Telecom options Operations challenges: Transitioning to operations Unexpected functionality 7

Schedule Delays Procurement (May 2010 Mar 2011) Two separate requests for proposal: Energy storage technology Systems integration Permitting (Mar 2010 Aug 2011) Funding from the Federal Government triggered CEAA (Canadian Environmental Assessment Application) process Parks Canada additional permitting requirements Fire Incident in Japan (Oct 2011 Aug 2012) Construction stopped NGK investigation and design changes BC Hydro risk assessment and business case review Reduce scope to 1MW in Field only 8

Design Challenges Civil Design Operating temperatures -50 C to + 40 C Maximum snow depth 1.2m Use metal building to provide snow protection and fans to cool in summer Outdoor installation at Balls Gap, Virginia, AEP 2010 Under cover installation, Field, BC, BC Hydro 2013 9

Golden 900 MHz radio peer-to-peer communication R T1 25 kv 240 V 1500 kva Field Peak Load 500 kw G Design Challenges Telecom Design Backhaul from Field to BC Hydro operations Satellite Field area network for battery site to intellirupter 900 MHz SpeedNet radio SMS (Inverter/Charger) +/- 1000 kw +/- 750 kvar ~ - Station Load and Battery Heaters NaS Battery (6.3 MWh, 1 MW) 10

Lessons Learned Combine the energy storage and integrator RFPs Time for procurement Control systems suitability Single contract negotiation and management Limitations of technologies in harsh environments Climate Terrain Balancing desire for in-house participation with timing constraints Traditional standards and specification approach Siloed approach to design The safe option still hasn t been around that long Operating non-standard equipment Operating orders SCADA screens and controls Testing for all scenarios 12

13 Battery Energy Storage Performance: Peak Shaving

Battery Energy Storage Performance: Islanding Date Duration Reason July 15, 2013 7.5 hours Tree July 19, 2013 9 hours Tree Sep 21, 2013 9.5 hours Vehicle accident Sep 27, 2013 8 hours Vehicle accident Oct 5, 2013 2 hours Vehicle accident Oct 11, 2013 3 hours Unknown Nov 15, 2013 Failed to activate Coordination between intellirupter and vista Nov 19, 2013 14.5 hours Tree, snow, wind March 8, 2014 23.5 hours Highway closure/avalanche June 3, 2014 3 hours Tree Total 80 hours Outage Prevented 14

THANK YOU Kunle Adeleye, BC Hydro adekunle.adeleye@bchydro.com Helen Whittaker, BC Hydro helen.whittaker@bchydro.com Aaron Ellis, BC Hydro aaron.ellis@bchydro.com Vlad Kositsky, BC Hydro vlad.kositsky@bchydro.com 15