Western Alberta Transmission Line (WATL) HVDC Project

Similar documents
PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Bohn to Kettle River Transmission Project

City of Palo Alto (ID # 6416) City Council Staff Report

Part 3 Agreement Programs for 2017 and Greenhouse Gas Reduction (Renewable and Low Carbon Fuel Requirements) Act

ABB life cycle services Uninterruptible power supplies

FORTISBC INC. PRUDENCY REVIEW KETTLE VALLEY SUBSTATION EXHIBIT A2 5

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Kettle River Transmission Project

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Currant Lake Transmission Project

TORONTO TRANSIT COMMISSION REPORT NO.

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L82

RE: Regulatory Proposal under the Condominium Act, 1998 (17-MGCS021)

Umatilla Electric Cooperative Net Metering Rules

ABB POWER SYSTEMS CONSULTING

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Interconnection Process for Generation Systems

Reliable, economical and safe siemens.com/rail-electrification

Inactive Well Compliance Program (IWCP)

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

welcome to the BC Hydro community open house

Electric system improvements near you

Low and medium voltage service. Power Care Customer Support Agreements

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Decision D ATCO Electric Ltd. Decommissioning of Transmission Line 6L79. October 18, 2016

TRANSFORMER SERVICE. ABB Ability inspection for transformers TXplore Oil-filled transformer internal inspection service

Presentation of the European Electricity Grid Initiative

ABB in primary aluminium From mine to market

Willingdon Substation Decommission

REGIONAL TRANSMISSION ORGANIZATIONS / INDEPENDENT SYSTEM OPERATORS AND THE ENERGY IMBALANCE MARKET: AN OVERVIEW OF THE PICTURE IN THE WEST

Evaluating Stakeholder Engagement

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

AT A GLANCE GRID /2014

Making Electricity since December Melody Collis Facilities Engineering Assistant Manager Toyota Motor Manufacturing Canada

conversation SHAPE the May 2015 The AUC

PUD ELECTRIC SYSTEM INTERCONNECTION

GRID CONSTRAINT: OPTIONS FOR PROJECT DEVELOPMENT

Solar Farm Electrical Control Buildings & Substation Build Project

Transit Vehicle (Trolley) Technology Review

Chirmorie Wind Farm Grid Connection

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Rocky Reach Bridge Crane Repair. Commission Presentation February 1, 2016

Industry Recommendation Loss of Solar Resources during Transmission Disturbances due to Inverter Settings - II

Centerwide System Level Procedure

California Energy Storage Policies. Carla Peterman Commissioner, California Public Utilities Commission December 2016

Joint Operating Procedures for First Nations Consultation on Energy Resource Activities

The Capital Grid Project:

Impact of Distributed Energy Resources on Transmission System Reliability

Looking Towards the Future: Advantages of 765-kV Transmission Technology

Included in this Stakeholder Information Package:

ABB Services for Low Voltage equipment Your choice, your future

Modernising the Great Western railway

Welcome. Green Line in Your Community

Electric Power Research Institute, USA 2 ABB, USA

SUBSIDY SCHEME FOR GRID CONNCTED AND OFF GRID SOLAR SYSTEMS AT IOCL PETROL PUMPS

ELECTRIC TRANSMISSION 101: Operational Characteristics. Wayne Galli, Ph.D., P.E. Executive Vice President Clean Line Energy Partners LLC

EUROPEAN COMMISSION ENTERPRISE AND INDUSTRY DIRECTORATE-GENERAL

STAFF REPORT ACTION REQUIRED

Tunney s Pasture Station Bus Loop and Lay-up Area Design

Unitil Energy Demand Response Demonstration Project Proposal October 12, 2016

Converting BRT to LRT in the Nation s Capital Ottawa, Canada. John Manconi City of Ottawa Ottawa, Canada

2015 Grid of the Future Symposium

15 Nelson-Marlborough Regional Plan

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Small Generator Interconnection Program Interconnection Technical Requirements

2018 AER Social Research Report

Grid Impacts of Variable Generation at High Penetration Levels

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

BASF SE. Particulars. RSPO Annual Communications of Progress About Your Organisation. Membership. Particulars Form Page 1/1.

JCP&L Verbatim Response to Middletown Township s Questions

Civil Engineer. Tasks

Robert L. Mitchell CEO and Co-Founder Atlantic Wind Connection

SUBSIDY SCHEME FOR GRID CONNCTED SOLAR ROOFTOP POJECT IN ASSAM UNDER THE 14 MW RESCO AND CAPEX MODEL

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

Straight Talk. About the Smart Grid. Introduction

Transmission Grid Reinforcement with Embedded VSC-HVDC. Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui

Alternatives for meeting the need for transmission improvement described

Request for Assistance (RFA)

Oil Palm Growers Operational Profile 1.1 Please state your main activities as a palm oil grower Palm oil grower & miller Palm oil mill/palm kernel cru

Pump Station 7 Improvements

Competitive Power Procurement

CITY OF MINNEAPOLIS GREEN FLEET POLICY

Service and Rehabilitation Electrical Power Systems

A day in the Life... stories

Renewables from a TSO Perspective. M.BENA, SmartGrids Director, RTE, French TSO Vienna, 18 May 2015

CUSTOMER/ TWIN ARROWS PROJECT

Comhairle Cathrach Chorcaí Cork City Council

New Ulm Public Utilities. Interconnection Process and Requirements For Qualifying Facilities (0-40 kw) New Ulm Public Utilities

SOUTHWEST CALGARY RING ROAD (SWCRR)

GE Energy Management. GE s electrification and automation business

Modular Standardized Electrical and Control Solutions for Fast Track Projects

Summary of survey results on Assessment of effectiveness of 2-persons-in-the-cockpit recommendation included in EASA SIB

15 Nelson-Marlborough Regional Plan

Interconnection System Impact Study Report Request # GI

Running the Electric Power Grid

DC Substation Solutions For Metal Processing Applications

AEP Ohio Distribution Reliability and Technology Programs

Battery Electric Bus Technology Review. Victoria Regional Transit Commission September 19, 2017 Aaron Lamb

APPENDIX F: Project Need and Description

Transcription:

Submission for the ACEC Canada Canadian Consulting Engineering Awards 2016 Western Alberta Transmission Line (WATL) HVDC Project Submitted by Teshmont Consultants LP as a Consultant to AltaLink

Attachment 1 Confirmation Receipt from the online Official Entry Form & Project Outline ACEC Canada Canadian Consulting Engineering Awards 2016

Phase 2 Bid Evaluation and Contract Award After a three month tendering period, Teshmont performed a comprehensive and detailed review of the bids submitted to evaluate conformance to the specifications and to assess the different offerings from a technical standpoint in order to provide AltaLink with a ranking of the bidders on a technical merit and value basis. The review also included a series of clarification questions and associated responses. Once a preferred bidder was identified, Teshmont supported AltaLink through the contract negotiations and prepared a conformed specification at the end of negotiations, which encapsulated all of the changes to the original specification that were agreed upon during the negotiations. The final contract for the converter stations was awarded to Siemens of Germany. Phase 3 Design, Manufacture, Installation, and Commissioning The third phase of the project was broken down into four distinct stages as follows: Stage 1: Design Review During the design review stage, Siemens was required to submit study reports, drawings, equipment specifications, schedules, plans, and other documents. Teshmont s job was to not only review these documents, checking for conformance to specified requirements but also to manage the flow of these submittals within the AltaLink/Teshmont team to ensure timely responses, which were critical in maintaining the project schedule. Teshmont also reviewed the design of the transmission line, which was being built under separate contracts managed by SNC Lavalin. The line design review included conductor and insulator selection, tower design, as well as minimum electrical clearances. Stage 2: Manufacturing During the manufacturing phase, Teshmont monitored Siemens progress and reviewed factory test plans and subsequent test results of major components. For the most critical components, Teshmont staff attended factory acceptance tests together with AltaLink staff to ensure the quality of the delivered equipment. Stage 3: Installation During site installation of the equipment, Teshmont supported AltaLink by providing feedback to any questions or concerns that arose. Teshmont staff, while not permanently on-site, did make site visit at key times to view progress. Stage 5 Commissioning During final energization and commissioning of the system, Teshmont reviewed the commissioning plan and was on-site for critical first energization and subsequent system testing up to achievement of full power transmission readiness on December 10, 2015. In addition to the above, Teshmont provided project management support and coordination throughout the lifecycle of the project, overseeing the effective and time critical flow of information between the various stakeholders. This involved management of the massive amounts of data flowing through the project SharePoint portal between all of the project stakeholders in a timely manner so as not to delay the project 5

schedule. Teshmont also had the responsibility of reviewing, vetting, and coordinating comments from various teams of subject matter experts involved in the project. Teshmont worked together with key AltaLink personnel throughout the project for training and technology transfer purposes. This was seen from the outset as a key factor to having a successful project, as this would be the first HVDC project for AltaLink and they would be ultimately be responsible for ongoing operation and maintenance of the system after it was commissioned. Project Complexities and Challenges The WATL Project was a $1.65 billion dollar project with multiple parties involved over a span of five years. Teshmont had to ensure that the technical specifications were clear and concise and that the contractors adhered to the technical specifications while remaining on schedule and within budget. In order to accomplish this, information exchange between stakeholders in a well-organized and timely manner was essential. Teshmont was responsible for setting up and managing a process and system for document submittal and review utilizing Microsoft SharePoint that ultimately was used on over 32,000 documents shared amongst a number of stakeholders over the course of the five year project. WATL also brought particular technical challenges as it was the first HVDC system to be energized in Alberta. Thorough study was essential to ensure that the initial 1000 MW line embedded in the heart of the existing Alberta electric system would not have any adverse effects. Some of the particular technical issues that had to be examined for WATL included: - Effects of commutation failures - Effects of transformer energization - Effects of transient overvoltages - Possible control interactions and power voltage instability - Effects on the rating of existing harmonic filters in other substations Another challenge was the potential impact of the transmission line on the countless pipelines found in the surrounding area. In many instances, HVDC systems are developed utilizing ground electrodes, which allow for the HVDC system to operate in ground current return mode for short periods of time during certain operating conditions. Utilization of a ground electrode allows for a much simpler, smaller, and less expensive design of the HVDC transmission line towers. However, operation utilizing a ground electrode may have undesirable impacts on nearby infrastructure, which would need to be examined and possibly mitigated. Due to the possible safety and operating concerns with the numerous oil and gas pipelines in the region, it was decided to develop the HVDC line with a metallic return conductor and avoid the use of ground electrodes. 6

The project schedule was another challenge. Despite the five year duration, a number of key activities throughout the project had very short timelines in order to meet key milestone dates. The initial front-end engineering study, design, specification, bid, review, negotiate, and award process for the converter stations was completed within six months compared with a more typical duration of eight to twelve months. Construction of the transmission line was also a challenge due to the relatively tight construction schedule. In order to expedite construction of the line, helicopters were used to assist with not only tower erection as shown in Figure 4, but also stringing of the line as shown in Figure 5. Figure 4: Tower Assembly Using a Helicopter Air Crane Figure 5: Conductor Stringing using a Helicopter 7

Innovation and Application of Technology The selection of HVDC transmission technology for interconnecting the major Alberta load centres of Calgary and Edmonton was made based on studies results that showed the technical advantages of HVDC over a similarly rated AC option were of higher benefit. Any HVDC project is technically complex and involves careful study and planning to ensure that the HVDC technology is properly applied and the WATL project was no exception. Power system analysis performed by Teshmont indicated that there were potential issues with interactions between the planned converter station and the Alberta interconnected electric system at the Crossings Converter Station near Langdon. In order to mitigate the identified issues, the project implementation required a STATCOM, which is a fast power electronic based regulating device used to provide precise voltage regulation. The STATCOM at Crossings Converter Station minimizes the impact on the AC system when the HVDC system s filter banks required to absorb the harmonics generated by the converters are switched in and out. The converters are controlled by state of the art high speed advanced control and protection systems, which are able to precisely regulate the amount and direction of power flow through the HVDC system. The control and protection systems are also able to quickly respond to disturbances in the adjoining AC network to help operators maintain system control and stability during outages. Another major application of advanced technology on the project was in the method of testing these control and protection systems in the factory. These tests took over two months and were performed in Siemens factory in Germany utilizing a power system real time digital simulator (RTDS). The RTDS is an advanced parallel processing super computer that, when loaded with a model of the power system, is able to simulate the response of a power grid to HVDC controls in real time. When connected to the simulator, the HVDC controls behave and respond as if they were in operation in the real power grid. This method allows for very accurate testing to be performed and modifications to be carried out on the HVDC controls without the risk of causing problems, including blackouts, in the real power system. While initially installed and commissioned for two terminal operation at 1000 MegaWatts (MW) maximum power transfer capability, the HVDC line has been designed to be upgraded to 3000 MW with no additional structures or conductors required. As well, the system has also been developed to support the potential future addition of more converter stations to form a multi-terminal scheme. Multi-terminal HVDC transmission is highly complicated from a HVDC control and protection perspective and currently there are only two such systems in operation in the world. Social/Economic/Environmental Impact As noted previously, HVDC technology was selected for a number of reasons, including the reduction of electrical power loses. As a result of these lower losses, the project is estimated to reduce carbon emissions by approximately 350,000 tonnes, which is the equivalent of removing 65,000 vehicles from Alberta s roads. 8

By selecting HVDC to interconnect the two largest load centres in the province, WATL will help to improve the overall reliability of electricity supply to consumers in these centres and in the province. Secure and dependable supply of electricity helps maintain a high quality of life, security, and productivity for the people of Alberta. The project also relieves transmission system congestion that existed in the existing AC network and that limited consumers access to the generator facility owners. As Alberta is the only truly deregulated energy market in North America, with consumers having choice in their electricity provider, unrestricted access to electricity generators results in increased competition and ultimately lower energy costs to consumers. The selection of HVDC also resulted in a transmission line whose towers are smaller in size and therefore take up less space than a similarly rated AC transmission line. This reduction in tower size results in less land being required for the line right-of-way and is less visually obstructive than a comparable AC transmission line. Finally, the application of HVDC has no observed negative effects on potential health impacts resulting from electric or magnetic fields. Conclusions The WATL project was significant and historic for both AltaLink, as well as the electric power system in Alberta. Teshmont was instrumental in helping AltaLink throughout the five years of development and implementation of the project by working closely to provide technical leadership, guidance, advice, and training for the successful operation of the WATL HVDC Project. Thanks in large part to Teshmont s extensive involvement in the project, the WATL HVDC Project will provide environmental, economic, and societal benefits for all Albertans throughout its life. 9

Attachment 4 Photographs ACEC Canada Canadian Consulting Engineering Awards 2016