Drivers, Building Blocks (Cables, Offshore), EU and US Examples, Grid- Enabled HVDC, LCC-MTDC

Similar documents
Drivers, Building Blocks (Cables, Offshore), EU and US Examples, Grid- Enabled HVDC, LCC-MTDC

Offshore Wind Connections HVDC for Offshore Grids

Raphael Görner, Head of Marketing & Sales, Grid Systems Germany Building bridges with HVDC Solar Energy for Science

Peter Lundberg, Product Manager HVDC Light, Guangzhou, Sept New Solutions for Transmission Systems HVDC Light ( 轻型直流 )

Mikael Dahlgren, ABB Corporate Research, 02 December 2011 ABB Technology providers perspective Energidagen Chalmers Energyinitiative

CMU Electricity Conference, 9th March 2011

ABB Roger Rosenqvist: August 30, 2012

Peter Lundberg, Global Product Manager, November 2016 ABB Power Systems Offshore wind connection

Offshore Wind: Grid Connection & Technology Options. Dietmar Retzmann Focus on. CO 2 Reduction Green Energy Megacities Security of Supply

Peter Lundberg, ABB HVDC, Nov 2016 HVDC Light - Power from shore. ABB Group November 16, 2016 Slide 1 1JNL A

HVDC Solutions. for Integration of the Renewable Energy Resources. Marcus Haeusler HVDC Lead Engineer. siemens.com/energy/power-transmission

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

ABB Group August 27, 2010 Slide 1

Dr.-Ing. Ervin Spahi, Wadden Sea Forum, Bremerhaven Electric grid on and off-shore: current status, obstacles and new developments

Ambra Sannino, ABB FACTS, May 2011 Keynote Speech PCIM 2011 The Role of Power Electronics in Smart Grids and Renewable Integration

Peter Leupp, Head of Power Systems, ABB Group, Namibia, 11 Nov 2011 HVDC power technology A key enabler for evolving trends

Long distance bulk transmission

Innovative technologies ready for the Supergrid

The Smart Way HVDC PLUS One Step Ahead Answers for energy.

ABB Wind Power Solution

ABB POWER SYSTEMS CONSULTING

ABB, November 2012 The high voltage DC breaker The power grid revolution. ABB 07 November 2012 Slide 1

Power Systems On the growth path

Click to edit title 18. Fachforum Netzbau und Betrieb

ECE 421 Project 1, Group 3 HVDC. Brian Beilstein, Robert Germick, James Haney, Alexander Joss, Matt Murphy, Shutang You

Transmission Grid Reinforcement with Embedded VSC-HVDC. Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui

Grid Integration of Large Scale Wind and Solar

HVDC Technology. Phil Sheppard Head of Network Strategy

Chapter 1. Overview of HVDC applications

ABB Next Level Big shift in power attractive opportunities

Power Transmisson Division Erlangen, April 15, Siemens receives major order for BorWin3 North Sea grid connection from TenneT

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

HVDC-Flexible in China. Sep

Cigre SC B4 Activities Towards HVDC Grids. HVDC Grid Workshop Belgium

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

IEEE PES General Meeting, Minneapolis, July 25-29, 2010 HVDC & FACTS Subcommittee. latest Technology Developments and Projects Dietmar Retzmann

HVDC POWER FROM SHORE. B. WESTMAN* K. ERIKSSON* G. PERSSON* A. MÆLAND** ABB Sweden*, Norway**

The Smart Way. HVDC PLUS One Step Ahead. Answers for energy.

REFERENCE LIST. HVDC Light The original VSC technology

What can HVDC Light do for you it s time to connect Applications Key Components

Experience on Technical Solutions for Grid Integration of Offshore Windfarms

Status and Trends of HVDC

Modern Power-Electronic Converters for High-Voltage Direct-Current (HVDC) Transmission Systems

Smart Grid, Long term planning for a sustainable energy system, from source to socket

Curriculum Vitae Fredrik Rüter 19 December 2013

HVDC Systems in India

Renewable energy HVDC - the enabling transmission

TSTE25 Power Electronics. Lecture 14 Tomas Jonsson ISY/EKS

POWER TRANSMISSION OF LOW FREQUENCY WIND FIRMS

Power Engineering - Egill Benedikt Hreinsson. Lecture 15a. HVDC Transmission. 2 November 2011

The Role of Offshore Wind

Offshore Wind Farm Projects

Introduction CONTENT Future of offshore wind energy in Europe Offshore wind energy in Spain Alternatives to the transmission system to the grid Compar

Dr. Brice Koch, Head of Power Systems, Member ABB Group Executive Committee, Hanover April 23, 2012 HVDC a key technology enabler Shaping the

High Voltage Direct Current Systems

European technology leadership to address infrastructure bottlenecks

EPRI s HVDC & FACTS Conf. Oct , 2010, Palo Alto, CA

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

The Application of Power Electronics to the Alberta Grid

High Voltage Direct Current and Alternating Current Transmission Systems Conference. August Nari Hingorani

Gunnar Asplund HVDC R&D Manager Sweden. Latest HVDC Light developments. IEEE Montreal

Diversifying into Marine Energy. ABB March 2015

RGI Workshop on The Need for Grids

HVDC Enabling a stronger, smarter and greener grid

SVC Light For electrical transmission grids

Karl Elfstadius, ABB Smart Grid Program Mmanager / SMART GRID TAIWAN, Smart Grid Overview. ABB SG_Presentation_V4.

Power From Shore: An introduction to HVDC Light Offshore

An overview of HVDC market and future outlook. Saqib Saeed Principal Analyst Power Technology Research LLC (PTR)

Prospects of HVDC and FACTS for Sustainability and Security of Power Supply

MVDC PLUS Managing the future grid

Power Electronics for Medium Voltage Grid Applications Topologies and Semiconductors

Modular Multilevel Submodules for Converters, from the State of the Art to Future Trends

HVDC Interconnectors Benefits and Challenges

Tibin Joseph Marie Curie Early Stage Researcher Institute of Energy Cardiff University

Longevity of Power Electronic Solutions in the Macro Grid historical perspective of AC (FACTS) and DC (HVDC) installations

Power Transmission Division Erlangen, April 29, 2014

Enabling the power of wind. Competence and expertise for wind power customers

Power Flow Control in Meshed DC Grids. 29_03_17 Dr Jun Liang Cardiff University

DC Arc-Free Circuit Breaker for Utility-Grid Battery Storage System

Paradigms in Power System Planning & Operation Contemplating the HVDC Technological Evolution

the power to be transmitted; the length of the connection; the characteristics and the accessibility of the route; environmental constraints.

Infrastructure and Offshore Wind: Delivering Energy for an Industry at Scale

Power Transmission Solutions Grid Access

Case study The impact of variable Renewable Energy Sources on the European Power System

Substation Concepts for the Future

Benefits of HVDC and FACTS Devices Applied in Power Systems

ABB s hybrid HVDC breaker, an innovation breakthrough enabling reliable HVDC grids

Transmission s Future Today. High Capacity High Efficiency Low Profile

The role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016

Targeted Application of STATCOM Technology in the Distribution Zone

Overview Gas Insulated Switchgear Modular and flexible, kV. ABB Group May 15, 2013 Slide 1

Solutions for Smart Transmission Panel Session

Case 13-M Edic to New Scotland 345 kv Transmission Line and Hurley Avenue PARs Project (ED-NS/HA) Article VII Filing ED-NS/HA

SYSTEM INTEGRATION. Railway and urban transport electrification Energy-efficient and reliable solutions

OBJECTIVES LCC HVDC SYSTEMS VSC HVDC SYSTEMS COMMON EQUIPMENT DIFFERENT OPTIONS ECONOMIC IMPACTS CONCLUSIONS

APPLICATIONS: TECHNOLOGIES: KEY MARKET FORECASTS: GEOGRAPHIES:

Benefits of HVDC for System Interconnection. Energy Sector

Shunt reactors Proven history for future success

ABB Transformers For reliability, efficiency and minimum environmental impact

Achievement and experience in service of long length HV DC electrical links by insulated power cables

Transcription:

Björn Jacobson, ABB Power Systems HVDC, Oct. 4, 2011 Developments in Multiterminal HVDC Drivers, Building Blocks (Cables, Offshore), EU and US Eamples, Grid- Enabled HVDC, LCC-MTDC IEEE EPEC 2011 Winnipeg, Manitoba Slide 1

Why multi-terminal? Saving cost and conversion losses Providing enhanced reliability and functionality Combining purposes AC/DC Converter station Cable or Overhead line Breaker Slide 2

Why multi-terminal? Adding to an eisting point-to-point 4 converters 3 converters 3 breakers 3 converters AC/DC Converter station, eisting and additional Slide 3 Cable or Overhead line Breaker

Why multi-terminal? A node in a DC network 4 converters 1 converter 5 breakers AC/DC Converter station, eisting and additional Slide 4 Cable or Overhead line Breaker

Why multiterminal? Sectioning into sub-systems Without multi-terminal approach Protecting each object Slide 5

Pan-continental Grid in Planning Now We know where to go, but how? Wind -driven Solar-driven Hydrobalanced Hydro Generation changes Massive renewables North & South Europe, e.g. 30B (CAD 42B) North Sea wind, 6B (CAD 8B) Mediterranean solar grids New sites for conventional power Transmission changes East-West and North-South power flows meet in central Europe Balancing by hydro Loads change Urbanization, feeding large cities Slide 6

Similar transmission scenario emerges in North America New transmission capacity will be needed retire older fossil fuel based power plants epand (remote) renewable generation resources maintain reliability Public opposition to overhead transmission line and legal and permitting barriers can cause severe delays Common factors against overhead transmission lines: Aesthetics, Land use constraints, EMF HVDC cable transmission system used in eisting infrastructures can release these permission barriers AC cables have significant length limitations due to capacitive charging that requires shunt compensation DC cable systems are proven technology Slide 7

Polymer cables are proven technology for HVDC since 1999 In use for AC since 1970:s. HVDC voltage and power increase by factors of 4 and 20 times, respectively, over ten years Slide 8

Solid Dielectric Cables for HVDC transmission Slide 9

Land Cable Project Laying Slide 10

Eample of Cable Trenching Proven Efficient and Fast Process Slide 11

Eisting infrastructure corridors (such as overhead transmission lines, railway, highways) can be used to host cable transmission systems 500 kvac US transmission corridor Multi GW DC transmission can be trenched in parallel Slide 12

New ABB land cable factory in Huntersville, NC Fits supply-chain requirements Slide 13

Mid-Atlantic Power Pathway Project Slide 14

Champlain Hudson Power Epress Project Using cables and eisting infrastructure 1000MW, 600kV (±300kV) 320 miles all HVDC cable route (210 miles in water and 110 miles underground) The HVDC cable circuit will be laid in the Hudson River from Yonkers to a landing site south of Albany, New York. From the landing site south of Albany, the HVDC cable circuit will be installed underground within eisting railroad rights of-way to the southern shore of Lake Champlain The HVDC cable circuit will then be laid in Lake Champlain to the Canadian border. Slide 15

Can HVDC Grids be built today? Regional and interregional HVDC Grids At least two different types of HVDC transmission schemes involving more than two converter stations can be identified: Regional HVDC grids, which are possible to build already today. Interregional HVDC grids, where new developments are required. Slide 16

What is a Regional HVDC grid? Regional DC Grid with optimised voltage level. Slide 17 A typical regional HVDC Grid is defined as a system that constitutes of one protection zone for DC earth faults. To temporarily and rarely lose the whole HVDC system has a limited impact on the overall power system. Fast restart of the faultless part of the system HVDC breakers are not needed Normally radial or star network configurations Limited power rating To enable multi-vendor approach, standardized high level control interface needed Are built today with proven technology

What is an interregional HVDC Grid? Regulatory issues such as how to manage such new grids need to be solved. An interregional HVDC grid is defined as a system that needs several protection zones for DC earth faults. Developments focus: HVDC breakers and fast protections Grid Power flow control/primary control: automatic control Master control: start/stop, redispatching Long-term development, e.g. High voltage DC/DC converters for connecting different regional systems On-going Cigré WG B4.52 HVDC Grid Feasibility study Slide 18

Borwin 1, Dolwin 1-2 Summary Main data Borwin 1 Dolwin 1 Dolwin 2 Commissioning year: 2012 * 2013 2015 Power rating: 400 MW 800 MW 900 MW No of circuits: 1 1 1 AC Voltage: 170 kv (Platform) 155 kv (Platform) 155 kv (Platform) 380 kv (Diele) 380 kv (Dörpen W) 380 kv (Dörpen W) DC Voltage: ±150 kv 320 kv 320 kv DC underground cable: 2 75 km 2 75 km 2 45 km DC submarine cable: 2 125 km 2 90 km 2 90 km Main reasons for choosing HVDC Light: Length of land and sea cables. *) when all Bard 1 wind generation is in operation. Transmission since 2010 Slide 19

BorWin1 The first HVDC project to connect offshore wind Customer Tennet, Germany Customer s need Connection of 400 MW from offshore wind farm to the German transmission grid 125 km distance to coast 75 km from coast to connection point Robust grid connection Customer s benefits Environmentally friendly power transport Reduce CO 2 emissions by nearly 1.5 million tons per year by replacing fossil-fuel generation Supports wind power development Slide 20

BorWin1 The first HVDC project to connect offshore wind ABB s response 400 MW HVDC Light system at ±150 kv 125 km sea cable route 75 km land cable route Turnkey delivery including platform Full grid code compliance Slide 21

BorWin1 Single Line Diagram 1 km Bard platform 400 kv Scope Diele1 HVDC Light Cable +150 kv Offshore1 Future shunt reactor(s) ma 40 MVar? km OWP Future 1 AC Breaker + preinsert. Resistor Power Transformer Converter Valve Phase Reactor DC Capacitor DC Chopper? km OWP Future 2 AC Filter HVDC Light Cable -150 kv GIS 154 kv SLD March 2008 JL Future HVDC Transmission Link 1 Future HVDC Transmission Link 2 Slide 22

DolWin2 Germany Customer: TenneT Year of commissioning: 2015 Customer s need 135 km long subsea and underground power connection Robust grid connection ABB s response Turnkey 900 MW HVDC Light system ± 320 kv etruded cable delivery Customer s benefits Environmentally sound power transport Low losses and high reliability Reduce CO 2 -emissions by 3 million tons per year by replacing fossil-fuel generation Grid connection 90 km inland Slide ABB 23 Group PowDoc Slide 23 id

DolWin2 Germany SylWin BorWin 1 DolWin HelWin Customer: TenneT Country: Germany Scope of works: design, supply and installation of HVDC Light ±320 kv 900 MW system Two converter stations - one offshore and one onshore Offshore platform 135 km ±320 kv etruded cables 45 km sea cable 90 km land cable Order value: 1 BUSD In service: 2015 Slide ABB 24 Group PowDoc Slide 24 id 2 1. DolWin beta DC platform 2. Dörpen-West substation

HVDC Light grid connection concept by ABB New platform concept developed together with a Norwegian off-shore firm for Dolwin 2 Slide ABB 25 Group PowDoc October id 20 Slide 25

View from Scandinavian TSO (Svenska Kraftnät) Prepare for multiterminal operation: Grid enabled P-t-P Southwest link VSC Tendering: 1000-1200 MW 2 3-terminal in parallel Gotland VSC in planning: 2 500 MW Support 1000 MW wind FUTURE possibility: Connect DC point-to-point terminals into HVDC grids connection. The first MTDC? Planning / discussion Awarded / tendering Nordbalt VSC Order received: 700 MW Security of supply, market integration Commission end 2015 Slide 26

2014: North East - Agra: Multiterminal Classic UHVDC* 8 000 MW World Record Power Transmission NEA800: 1 728 km transmission 15 km wide corridor Bhutan Nepal Bangladesh 800 kv Converter Valve, Shanghai HVDC connection of multiple remote hydro power regions in NE India Low losses, reliability, fleibility North East - Agra (NEA 800) Hydro resources NE locally 13 m of rainfall per year 15 km narrow Chicken Neck Transmission Corridor, between Buthan, Nepal & Bangladesh Electricity to 90 M people ABB:s second Multiterminal HVDC 1. New England Hydro Quebec 1992 Three terminal, 2000 MW ABB:s second 800 kv HVDC 1. Xiangjiaba Shanghai 2010 2000 km, 6400 MW UHVDC Slide 27 * Classic UHVDC = Line-commutated converters ultra-high voltage direct current

NEA800 Four station Multiterminal HVDC Simplified Single Line Diagram +800 kv DC 400 kv AC 400 kv AC 400 kv AC 400 kv AC -800 kv DC Agra Alipurduar Biswanath Chariali Slide 28 Customer India Power Grid Corp. Value $1 190 M Distance 1 728 km Power 8 000 MW Terminals Four (22 bipoles) Voltage 800 kv In operation 2014-2015 Delivery time 39-42 months

Multiterminal HVDC emerges as the first steps towards HVDC Grids Slide 29 Significant loss reduction Increased power capacity per line/cable vs. AC Stabilized AC & DC grid operation Less visual impact and lower electromagnetic fields Easier acceptance of new DC projects if lines can be tapped DC = only solution for subsea connections > 60 km Connection of asynchronous AC Networks Circumvent right of way limitations Technology required for visions like Desertec & North Sea Offshore Grid, but can be built today for smaller grid e.g. for efficient power balancing

Hybrid DC Breaker Basic Design Modular design of Main DC Breaker for improved reliability and enhanced functionality Fast DC current measurement for control and protection Disconnecting residual DC current breaker isolate arrester banks after fault clearance Slide 30

IGBT DC Breaker IGBT DC Breaker Cell IGBT DC Breaker Position IGBT DC Breaker Cell 80kV IGBT DC Breaker cell consists of four IGBT stacks, two stacks required to break fault current in either current direction Compact design using reliable 4.5kV Press-pack IGBTs Resistor-Capacitor-Diode snubbers ensure equal voltage distribution Optically powered gate units for independent DC Breaker operation Slide 31

IGBT DC Breaker IGBT DC Breaker Test Circuit Breaking Tests continue capability on verification of 1GVA verified of Hybrid for DC 80kV Breaker IGBT DC concept Breaker cell Slide 32

Hybrid DC Breaker Basic Functionality Normal operation: Current flows in low-loss bypass Slide 33 Proactive control: Load commutation switch transfer current into Main DC Breaker switch, the Ultra Fast Disconnector opens with very low voltage stress Current limitation: Main DC Breaker switch commutates fault current into parts Fault of clearance: the sectionalized Main DC arrester Breaker bank switch commutates fault current into arrester bank

Hybrid DC Breaker Main Features Very low transfer losses in bypass, < 0.01% of transmitted power Fast protection without time delay if opening time of Ultra Fast Disconnector is within delay of selective protection (< 2ms) Immediate backup protection in DC switchyard Self protection due to internal current limitation Slide 34 In-service functional tests allow for maintenance on demand

IGBT DC Breaker Conclusions With breaking times of less than 2ms and a current breaking capability of 16kA, the proposed Hybrid DC Breaker is well suited for DC grids The modular concept is easily adapted to different voltage and current ratings Protective current limitation and in-service functionality tests enhance system reliability Transfer losses are less than 0.01% related to the transmitted power DC Breakers are no longer a showstopper for large DC grids Slide 35

Summary Key equipment status Status today we can offer complete Multi-Terminal systems Converter monopolar or bipolar Cable system IGBT breaker Conventional mechanical DC Breaker Future Hybrid DC Breaker will enhance functionality Regional DC Grids can be built without DC Breakers Several HVDC projects in Europe are built Multi-terminal enabled Slide 36