A Case Study on Aggregate Load Modeling in Transient Stability Studies

Similar documents
ECEN 667 Power System Stability Lecture 19: Load Models

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience

NERC Load Modeling Activities. Ryan D. Quint, PhD, PE Senior Engineer, System Analysis, NERC MRO Fall Reliability Conference November 2016

Load Modeling for Power System Studies

Composite Load Model Sensitivity Study

Distributed Energy Resources

Inverter-based DER Ride Through and IEEE Standard 1547

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Load. Yan Ma. A Thesis Presented in Partial Fulfillment of the Requirements for the Degree Master of Science

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

STATCOM Application to Address Grid Stability and Reliability: Part II. D.J. SHOUP, N.W. TENZA Mitsubishi Electric Power Products, Inc.

Ancillary Services & Essential Reliability Services

Targeted Application of STATCOM Technology in the Distribution Zone

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

Essential Reliability Services Engineering the Changing Grid

Transient Stability Analysis Tool (TSAT) Update April 11, Hongming Zhang EMS Network Applications Manager

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

S o u t h w e s t P o w e r P o o l D i s t u r b a n c e P e r f o r m a n c e R e q u i r e m e n t s. Revision 3.0

Large Scale Solar Integration

DER Impacts on Bulk Grid Dynamic Performance

Interconnection System Impact Study Report Request # GI

Impact of Distributed Energy Resources on Transmission System Reliability

Dynamic Study of Bonaire Island Power System: Model Validation and Project Experience

LOW-VOLTAGE TECHNOLOGY SCOPING STUDY: IMPACT OF SMALL AIR CONDITIONING UNITS ON ELECTRICAL SYSTEM VOLTAGE RECOVERY

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

Integration of Large Wind Farms into Electric Grids

Power Grid Stability: The Perils and Potential of Power Electronic Load

Generator Interconnection System Impact Study For

Session 10 NERC Interconnection Requirements

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Statcom Operation for Wind Power Generator with Improved Transient Stability

Western Electricity Coordinating Council Modeling and Validation Work Group

Electric Power System Under-Voltage Load Shedding Protection Can Become a Trap

Advanced Protective Relay Training

Project #148. Generation Interconnection System Impact Study Report

Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

Midway/Monument Area TTC Study

Using Hosting Capacity Methodology to Develop Simplified Screens for New Solar PV Interconnections

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Falcon-Midway 115 kv Line Uprate Project Report

Islanding of 24-bus IEEE Reliability Test System

TRANSMISSION PLANNING CRITERIA

Experience with Model Validation of PV Power Plants. Abraham Ellis, Ryan Elliott, Ray Byrne Sandia National Laboratories

Project #94. Generation Interconnection System Impact Study Report Revision

Georgia Transmission Corporation Georgia Systems Operations Corporation

Grid Operations & Planning R&D Area Overview

LESSONS LEARNED IN IMPLEMENTING BATTERY INVERTER SYSTEM CONTROLS IN LOW-INERTIA SYSTEMS

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Gateway South Transmission Project

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Next Steps in Load Modeling. Dmitry Kosterev, BPA, NERC LMTF Meeting August 2017

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

Grid Stability Analysis for High Penetration Solar Photovoltaics

DP INNOVATION. A Novel Solution to Common Mode Failures in DP Class 2 Power Plant

Implementation of Under Voltage Load Shedding for Fault Induced Delayed Voltage Recovery Phenomenon Alleviation

ATTACHMENT Y STUDY REPORT

Modelling and Control of Highly Distributed Loads

Synthetic Inertia from Wind Turbine Generation

Distributed Energy Resources

Comments on the Solar Alliance Proposal for Changes to New Jersey Interconnection Rules

The University of New South Wales. School of Electrical Engineering and Telecommunications. Industrial and Commercial Power Systems Topic 6

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Islanding of 24-bus IEEE Reliability Test System

Designing and Maintaining a Pollution-Resilient Electric Power System. Managing Pollution Issues

Battery Energy Storage System addressing the Power Quality Issue in Grid Connected Wind Energy Conversion System 9/15/2017 1

Electrical grid stability with high wind energy penetration

4-Day Power System Analysis, Coordination, System Studies

responsible for maintenance and upkeep) Web URL: Previous name/number (if any)

Anupam *1, Prof. S.U Kulkarni 2 1 ABSTRACT I. INTRODUCTION II. MODELLING OF WIND SPEED

Variable frequency transformer for asynchronous power transfer

Simulation and Visualization of Power Grid Operations with High Renewable Penetration

Integrating Large Supplies of Wind Power - System Performance and Maintaining Quality of Supply in the Transmission Network

Fuzzy based STATCOM Controller for Grid connected wind Farms with Fixed Speed Induction Generators

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian

Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008

Use of Microgrids and DERs for black start and islanding operation

Industry Recommendation Loss of Solar Resources during Transmission Disturbances due to Inverter Settings - II

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Distribution System Analysis for Smart Grid

DNV GL enables right decision making in a complex world MARITIME OIL & GAS ENERGY BUSINESS ASSURANCE

Stability Study for the Mt. Olive Hartburg 500 kv Line

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

Renewable Grid Integration Research in the U.S.

Technical & Regulatory Standards Development

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study

Performance Analysis of Transient Stability on a Power System Network

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Optimizing Energy Efficiency for DP Vessels for Variable Operational Risks

PMU-based Wide Area Protection System Concept and application in a large longitudinal system

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

An Introduction to Completing a NERC PRC Study

Distributed Energy Resources

Transcription:

A Case Study on Aggregate Load Modeling in Transient Stability Studies Presented by: Daniel Feltes Siemens PTI Coauthors: Carlos Grande-Moran, Bernardo Fernandes, James Feltes, Ming Wu and Robert Wells Unrestricted Siemens AG 2017 siemens.com/power-technologies

Overview Discussion on practical applications of detailed load models in transient stability analyses, including: Fault Induced Delayed Voltage Recovery (FIDVR) Transient Voltage Response Criteria Load Models Typical Model Parameters Case Study Next Generation of Load Models Conclusions and Recommendations Page 2

Fault Induced Delayed Voltage Recovery (FIDVR) NERC defines FIDVR as a voltage condition initiated by a fault and characterized by: Stalling of induction motors Post-contingency voltage recovery to less than 90 percent of precontingency voltage Slow recovery (more than two seconds) to post-contingency voltage levels FIDVR is caused or aggravated by large amounts of single phase air conditioners. This type of load plays a main role in FIDVR because of its low inertia and proneness to stall Page 3

Fault Induced Delayed Voltage Recovery (FIDVR) Studies using traditional models have not been able to accurately reproduce FIDVR events FIDVR analysis requires simulation models that represent a wide variety of Figure From: 2013 FIDVR Events Analysis on Valley Distribution Circuits. Richard Bravo and Steven Robles. December 30, 2013. load dynamics Page 4 (Available at https://certs.lbl.gov/sites/default/files/2013-fidvr-valley-distribution-circuits-events-analysis.pdf).

Transient Voltage Response Criteria Load lost due to disturbances can be divided into two categories: Consequential load loss - Load disconnected as a result of transmission being removed to isolate the fault or lost due to the voltage dip caused by the fault Non-consequential load loss - Loss of additional load due to FIDVR The objectives of a dynamic voltage criteria are to ensure the fault ridethrough by the generators and the majority of the loads, and to minimize the risk of additional motor stalling, generator tripping or voltage collapse. Page 5

Transient Voltage Response Criteria A typical example of a short term dynamic voltage criteria: For category P1 and P2 (single contingencies), voltages should recover to above 80% of nominal within 2 seconds of the initial fault For categories P3 to P7 (multiple element contingencies), voltages should recover to above 80% of nominal within 4 seconds of the initial fault (some loss of load acceptable) For long term dynamic voltage criteria, a common practice is: Voltages should return to at least 90% of nominal in 10 seconds Page 6

Voltage Criteria The utilities and ISO s criteria should be consistent with PRC-024 to ensure generating units remain connected during voltage excursions Page 7

Historical Load Models Since loads are the driving force in the dynamic response of power grids to FIDVR events, the load models need to include representation of: Sensitivity to voltage and frequency variations Inertial and machine flux dynamics of induction motor loads Dynamic response of motor protection systems (thermal and undervoltage) The magnitude, composition and dynamics of loads change with season, month, week, day and hour of the day This seasonal and random nature of the loads makes its modeling difficult in power system studies Page 8

Historical Load Models Static Models Algebraic equations known as ZIP load models Do not represent any load dynamics Typical dynamic simulations uses a combination of : o 100% constant I for active power loads o 100% constant Z for reactive power load ZIP load coefficients are often specified on a control area basis Page 9

Historical Load Models - CLOD Developed to simulate some of the dynamic behavior of aggregate loads Easy to use in power system studies: inputs are component percentages of the total load at the bus Page 10

Historical Load Models - CLOD The use of this model is recommended for initial voltage screenings to identify voltage performance issues No voltage, frequency or thermal protection Not fully represented if the system includes large amounts of residential heating, refrigeration and air conditioning loads In this case, a detailed model is required to represent 3-phase induction motors, single phase motor loads and dynamic effects of frequency variation Page 11

Load Model - CMLD Load Bus High Voltage (System Bus) Substation LTC Low Side Bus Distribution Feeder Equivalent 3-ph Motor A 3-ph Motor B 3-ph Motor C Bf1 Bf2 1-ph Motor D Substation Shunt Bss Feeder Compensation Electronic Load Static Load A comprehensive model developed to simulate the dynamic behavior of loads connected to a distribution bus through an equivalent feeder Page 12

Load Model - CMLD In the Power Flow model, the load is represented at the high voltage bus as a ZIP load (typically constant P and Q) During initialization of a dynamic simulation, the model replaces the load with an aggregate model of induction motors, electronic loads, etc. The model is responsive to load shedding signals from undervoltage and underfrequency relays applied at the high voltage bus Reasonably represents 1-ph induction motor stalling and restart Reasonable indication of A/C loads tripping by thermal protection Data requirement is significant 133 parameters Page 13

Load Model - CMLD 1-ph induction motors stall and thermal relay characteristics stall curve run curve Page 14

Case Study The study area includes: Voltage levels range: 115, 138, 161 and 345 kv On-line generation: 4200 MW Total load: 4331 MW Load consisted of: 3-ph and 1-ph induction motors, heating, electronic devices, etc. Zones A (%) B (%) C (%) D (%) E (%) F (%) Industrial 11 0 46 19 21 40 Commercial 51 67 28 17 44 25 Residential 38 33 26 64 35 35 Agriculture 0 0 0 0 0 0 Page 15 Load Type A (%) B (%) C (%) D (%) E (%) F (%) Motor A 11 11 11 10 11 11 Motor B 10 9 15 10 11 14 Motor C 5 3 9 5 6 8 Motor D 26 28 16 26 23 18 Electronic Load 18 17 21 18 19 21 Static 31 32 28 31 30 28

Other Key CMLD Parameters CONs Oringinal No Trip Values NERC Values Values Used in Case Study EPRI Trip Settings WECC Trip Settings Description J+47 0.6 0.7 0.65 0.65 0.6 Vtr1A - U/V Trip1 V (pu) J+48 999 0.02 0.1 0.1 0.033 Ttr1A - U/V Trip1 Time (sec) J+49 0.2 0.2 0.2 0.2 0.3 Ftr1A - U/V Trip1 fraction J+50 999 1 0.1 0.1 1 Vrc1A - U/V Trip1 reclose V (pu) J+51 999 999 999 9999 9999 Trc1A - U/V Trip1 reclose Time (sec) J+52 0.4 0.5 0.5 0.5 0.5 Vtr2A - U/V Trip2 V (pu) J+53 999 0.02 0.02 0.02 0.033 Ttr2A - U/V Trip2 Time (sec) J+54 0.15 0.7 0.75 0.75 0.7 Ftr2A - U/V Trip2 fraction J+55 999 0.7 0.65 0.65 0.65 Vrc2A - U/V Trip2 reclose V (pu) J+56 999 0.1 0.1 0.2 0.2 Trc2A - U/V Trip2 reclose Time (sec) Page 16

Case Study The transient voltage response criteria used in the case study is: 1. Bus voltages shall not dip below 70% of the nominal voltage for more than 83.3 ms (5 cycles) after fault clearing 2. Bus voltages shall recover to the acceptable steady state low voltage limit within 5 seconds after fault clearing. The steady state low voltage limit is 0.93 pu for all 100 kv and above buses. Page 17

Case Study Comparison of Voltage Response with Different Load Models Page 18

Case Study Motor A Component P and Q Page 19

Case Study Comparison of Voltage Response with Different Load Models (extended time scale) Page 20

Case Study Rotor Speed for Motor A, B and C Components Page 21

Case Study Bus Voltage Comparison With and Without Additional Reactive Resources and Transmission Upgrade Page 22

Case Study Bus Voltage Comparison With and Without Additional Reactive Resources and Transmission Upgrade Page 23

Next Generation of Load Models Adaptation of the CMLD to incorporate DER. Work in progress The DER_A model: represents U-DER and R-DER by a simplified version of generic PV models with a reduced set of parameters Load Bus High Voltage (System Bus) Substation LTC Low Side Bus 3-ph Motor A 3-ph Motor B 3-ph Motor C Bss Bf1 Bf2 Electronic Load 1-ph Motor D Utility Scale DER - Large Scale - large Commercial U-DER R-DER Retail DER - Residential Rooftop PV - Behind-the-Meter Generation Static Load Page 24

Conclusions This presentation aids system planners in making decisions on when simplified or detail load representations are required in stability studies Insufficiently detailed load models can result in studies that do not adequately identify potential FIDVR events The current CMLD model represents a wide variety of load dynamics, but requires a large amount of data. There is a trade-off between the effort of collecting data and the need for detailed load models Comparisons between simulation results and recorded system events are strongly recommended to calibrate the detailed load models. Even then, the seasonal and randomness of loads must be accounted for. Page 25

For further questions, comments and inquires Siemens Power Technologies International 400 State Street, Schenectady NY 12305 Daniel Feltes Phone: +1(518) 395-5170 E-mail: daniel.feltes@siemens.com siemens.com/power-technologies Page 26