NorNed. Europe s link for the future

Similar documents
The Electric Power System

Power import, transboundary connections, Market Coupling. Grzegorz Onichimowski President of the Board, TGE S.A.

Transmission Grid Development & Investment Planning on EHV Level in Germany

The Strategic reserve - why and how? Joakim Cejie Miljö- och energidepartementet

HVDC Interconnectors Benefits and Challenges

PCR Project Main features

Security of Supply. on the European Electricity Market

MARKET INFORMATION REGARDING COBRACABLE

eng_fakta_2005_kap5_ :16 Side 48 6Gas Management System

Explanatory document for the Nordic synchronous area proposal for ramping restrictions for active power output in accordance with Article 137(3) and

The role of Transmission System Operator in Belgium and in Europe. Vlerick Alumni Event 26 January 2016

Technical Assistance to support the AFUR

Click to edit title 18. Fachforum Netzbau und Betrieb

Old Markets - New Markets: an Internal Energy Market beyond 2014?

PCR Project Main features

Cooperation between EXAA, PXE and TGE. Workshop on the Organized Electricity Market in Central East Europe Vienna, 12. April 2010

European Power Markets. Jukka Ruusunen President and CEO

Nordic co-operation when meeting System challenges

RENEWABLE ENERGY TRANSMISSION INTERCONNECTION. Line Tveter

Jointly towards a long term sustainable energy supply

Northern European power system scenarios for EMPS 2010 to 2030

The Baltic Sea Regional Power Market Escape from Isolation! Taavi Veskimägi. CEO Elering AS

MANAGING CRITICAL GRID SITUATIONS A MARKET ANALYSIS

Towards a sustainable market design

Electricity industry structure and key players

THE BALTIC SEA POWER RING CONNECTED: A GLANCE AT NORDBALT AND LITPOL LINK TODAY AND OUTLOOK FOR TOMORROW

Lessons learnt from deregulation in Western Europe on the example of energy storage

Project Overview. Nick Pittarello Client Relationship Manager

7 th REGIONAL ENERGY CONFERENCE Konstantin Konstantinov, CEO, IBEX

Georgia Transmission Corporation Georgia Systems Operations Corporation

Power Engineering - Egill Benedikt Hreinsson. Lecture 15a. HVDC Transmission. 2 November 2011

The future role of storage in a smart and flexible energy system

Overview. 1. The cutting edge 2. Getting the infrastructure right 3. Evolved system operation 4. Opening up the power market 5. Integration economics

NWE /PCR Day-Ahead Price Coupling

Improving the integration of electricity networks: Prospects of the European Network of Transmission System Operators for Electricity (ENTSO-E)

Overview of ISO New England and the New England Wholesale Power Markets

Basics of the European Electricity Market Dr. Achim Ufert

The Global Grid. Prof. Damien ERNST

The Proposed Electricity Directive and Regulation: Market Design for a Low-Carbon Electricity Sector

the power to be transmitted; the length of the connection; the characteristics and the accessibility of the route; environmental constraints.

SEEV4-City. Smart, clean Energy and Electric Vehicles 4 the City

Drivers, Building Blocks (Cables, Offshore), EU and US Examples, Grid- Enabled HVDC, LCC-MTDC

LITGRID: TOWARDS BALTIC STATES SYNCHRONISATION WITH CONTINENTAL EUROPEAN NETWORKS

Experiences with the international trade of biofuels in Europe

SSE Guide to the Energy Industry. Guide

Regional Cooperation Infrastructure Development and Operation. EU Energy Governance. Olaf Ziemann Member of ENTSO-E s System Operations Committee

Availability of transmission capacity in the Nordics Q1/2017

C a b l i n g s o l u t i o n s a t t h e c o r e o f Po w e r Tr a n s m i s s i o n N e t w o r k s

April 25 Demand Response Resources Electricity Market Impacts

TRANSPOWER PLANS, BUILDS, MAINTAINS AND OPERATES NEW ZEALAND S HIGH VOLTAGE ELECTRICITY TRANSMISSION NETWORK THE NATIONAL GRID.

The Swedish Government Inquiry on Smart Grids

Tallinn. CEO, AS Nordic Energy Link

Running the Electric Power Grid

Electric energy storage Elia Group Approach

Demand Response in Nordic countries Seppo Kärkkäinen, VTT. Workshop on Demand Side Management April 18, 2007 Seoul Palace Hotel, Korea

Electricity Networks Inter-regional market co-ordination (Session 8)

Value of the interconnectors in the Nordic countries

Regional Market Integration

Decision on Merced Irrigation District Transition Agreement

GRID INNOVATION CAUCUS CO-CHAIRS

Proposed Incorporation of Merced Irrigation District into ISO Balancing Authority Area in Stakeholder Webconference February 28, 2013

Innovative technologies ready for the Supergrid

HVDC Innovative Technology for Smart Grids and Super Grids. Wilfried Breuer CEO Power Transmission Solutions, Siemens Energy Sector

2010 National Report of Energiekamer to the European Commission

The Electric Power System

SET Plan The 10th Year Anniversary Central European Energy Conference 2017

Vattenfall Capital Markets Day 2009

The oil fields in the NCS are located in the North Sea, Norwegian Sea, and Barents Sea.

Integration of intermittent renewable generation. The case of Denmark

Tibin Joseph Marie Curie Early Stage Researcher Institute of Energy Cardiff University

Curriculum Vitae Fredrik Rüter 19 December 2013

Europe s % Interconnection Target:

Power Transmisson Division Erlangen, April 15, Siemens receives major order for BorWin3 North Sea grid connection from TenneT

Landfall and Converter Station Site Selection Report Non-Technical Summary

PETROLEUM EQUIPMENT & TECHNOLOGY Magazine, July 1998

Power Transmission Division Erlangen, April 29, 2014

Passenger cars in the EU

Cost Reflective Tariffs

Power grid operator requirements to the solar stormsciense society

Kettle River Transmission Project

France-Spain. Public participation leaflet. across the Bay of Biscay. August interconnection.

Bohn to Kettle River Transmission Project

Contents. Solar Select TM Frequently Asked Questions

Merger of the generator interconnection processes of Valley Electric and the ISO;

CYPRUS ENERGY REGULATORY AUTHORITY REGULATION OF RENEWABLE ENERGY SOURCES FOR THE FUTURE

Innovation in electricity retailing for EVs in New Zealand

&DVH 1R, <'52 6$*$ 5(*8/$7,21((&1R 0(5*(5352&('85( Article 6(1)(b) NON-OPPOSITION Date: 05/07/1999

The Electric Power System

Elia System and market overview 2010

DG system integration in distribution networks. The transition from passive to active grids

The Electric Power System

Increase of the sales by 33% mainly due to the Safelite acquisition

The Energy Market 2004

Flounder (Platichthys flesus) in Subarea 4 and Division 3.a (North Sea, Skagerrak and Kattegat)

Power Transmission Division Erlangen, April 29, Siemens Completes Installation of Second HVDC Converter Platform for TenneT

Retail competition Experiences from Scandinavia. Harvard Electricity Policy Group September 22, 2005 Bo Andersson, PhD

The Role of Offshore Wind

How the Nordic countries accommodates for new renewable energy and overcame the challenges

Peter Lundberg, Product Manager HVDC Light, Guangzhou, Sept New Solutions for Transmission Systems HVDC Light ( 轻型直流 )

HOW NET METERING OF ELECTRICITY WORKS

Transcription:

NorNed Europe s link for the future

We take electricity for granted in our everyday lives. Without thinking about it, we switch on the lights, leave the coffee maker on and turn the vacuum cleaner on to full power. However, these routine actions would not be possible without somebody to supply the power. In both the Netherlands and Norway we meet the demand for energy by means of an efficient electricity grid. TenneT and Statnett are responsible for the highways in the electricity grid that connect all regional grids to each other and to the European grid. As national grid administrators also known as transmission system operators (TSOs) of the grids in their respective countries, both TenneT and Statnett rapidly respond to developments in the energy market in Northwestern Europe. A connection between the Netherlands and Norway is in line with the European Union s policy of interconnecting markets and enhancing the free market system.

The cable The longest submarine high voltage cabel In this brochure you can read all about NorNed - the extraordinary project to install a 580 kilometre cable along the seabed of the North Sea, between Norway and the Netherlands. A joint initiativ of two TSO s Statnett and TenneT. Converter station in Feda, Norway Eemshaven Feda NorNed is a submarine high voltage cable which interconnects the Dutch and Norwegian electricity grids. The cable enables Statnett and TenneT to transmit electricity from the Netherlands to Norway and vice versa. With a capacity of 700 megawatts (MW) the cable can supply, half of Amsterdam or Oslo s demand of power. Where is the cable located? The high voltage interconnection is installed along the shortest possible route between the two countries. The connecting points are situated in Feda, on Norway s south coast, and Eemshaven in the very north of the Netherlands. The TSOs are responsible for the connection between the cable and the national high voltage grid in both countries. When did the project start? The NorNed project has been hailed as a major success. The preparations started back in 1994, and the decision to build the interconnector was made at the end 2005. The cable was completed in May of 2008. Why install a new interconnection? The Dutch electricity grid already had interconnections to Germany and Belgium before the completion of the NorNed project, while Statnett had cables linked to Sweden, Finland, Denmark and Russia. As such, some of the power supplies of Norway and the Netherlands already originated from abroad. The NorNed cable links the Dutch and Norwegian national grids to markets to which they were not previously connected. The cable contributes to the overall security of supply. The cable laying ship C/S Nexans Skagerrak Converter station in Eemshaven, The Netherland 4 NorNed NorNed 5

Technique 580 kilometres and 47.000 tonnes in total The NorNed cable is either buried in the seabed or covered by rock. It was installed with the help of a special cable ship. Converters on the mainland convert the cable s direct current to alternating current and vice versa. Production of single core cable, Nexans Halden, Norway The cable was rolled out in sections measuring 75 kilometres in length, except for the Waddenzee section, which is 47 kilometres long. The sections were connected to one another at sea. A considerable layer of sand and rock covers the cable in order to protect it. The cable could only be installed in favourable weather conditions, for example, when the sea was calm. Facts and figures Out of the 580 kilometres of cable, 420 kilometres lay in shallow water up to 50 metres deep. The remaining 160 kilometres of cable have been installed at a depth of up to 410 metres. The double core cable weighs around 85 kg per metre; the single core cable weighs 37,5 kg per metre. The cable has a total weight of 47.000 tonnes. It was manufactured at factories in Sweden and Norway. The first 270 kilometres of the route from Eemshaven to Norway comprises a double core cable, partly for environmental reasons and partly because this has been agreed upon by the Dutch and German authorities. For the remainder of the route, two single cables have been opted for, mainly as these are easier to maintain. Facts and figures Cable length: 580 km Cable capacity: 700 MW (megawatt) Total project costs: EUR 600 million, 495 for the cable it self 24 licences in four countries includes substations and connections to the mainland grid From direct current to alternating current The NorNed cable is a direct current connection. Due to energy losses, the use of alternating current is not efficient when transmitting power across a distance of several hundreds of kilometres. However, the mainland high voltage grids in 22 agreements with existing cable and pipeline owners Converter stations in Feda (Norway) and Eemshaven (Netherlands) Weight: single-core cable: 37,5 kg per metre; two-core cable: 85 kg per metre Voltage level: +/- 450 kv (kilovolt) Maximum sea depth: 410 metres Norway and the Netherlands transmit alternating current. As a consequence, large converters are required to convert the alternating current into direct current. Both in Feda (Norway) and in Eemshaven (the Netherlands), these converters are set up as high voltage sub-stations or converter stations. Each converter occupies a large area, about the size of three football pitches. Because of the weather conditions in Eemshaven, it has been necessary to place the whole new station indoors, as salty wind and windblown sand may damage the equipment. The converter in Feda is mainly set up outdoors, as Feda is located inland. Doble layer of steel wire Outside layer of plastic The valve hall at the converter station in Eemshaven Plastic Hundrets of layers of paper Lead Copper Two-core cable utilised at 270 km of the cable connection 6 NorNed NorNed 7

Synergy Water savings in Norway and green energy for the Netherlands From the market s point of view, TenneT and Statnett are located at the edge of Europe. With the completion of the NorNed cable, both countries occupy a more central position within Europe. In effect, we are an electricity node connected to other high voltage grids and electricity markets. Norway and the Netherlands have different methods of generating electricity. In Norway, 99 percent of all electricity is generated through hydro-electric power, an environmentally friendly production method. Hydro-electric power plants convert the energy of falling water into renewable green electricity. In the Netherlands, electricity is mainly generated by means of fossil fuels such as natural gas and coal. Via the NorNed cable, Dutch market parties will be able to import renewable electricity. This will mainly be done during the day, when electricity consumption is at its peak. Complementary Norway and the Netherlands complement each other when it comes to the production and consumption of electricity. In the Netherlands, less electricity is consumed at night than during the day, while the energy consumption in Norway is relatively high during the night. The two countries also have different patterns of energy consumption: Norway has an electric heating system, while the Netherlands uses gas heating. At night, Norway is self-sufficient in its electricity production. However, it prefers importing the cheaper electricity produced by the Netherlands during the night. This also allows Norway to save the limited water resources in its reservoirs for use during the day, so that it can in turn supply electricity to the Netherlands during expensive daytime peak hours. Optimum use of production capacity Because of the limited amount of electricity used in the Netherlands during the night, Dutch power plants are operated at a limited load during these night-time hours. Electricity cannot be stored, and the generators cannot be switched off because the power plants have to be ready in time for the daily morning peak in electricity consumption. Thanks to the NorNed cable, power plants in the Netherlands are able to make better use of their production capacity at night by exporting their electricity to Norway. Norway The Netherland Electricity consumption in summer and winter Water Gas Coal Nuclear power Wind Otherwise Songa water reservoire, South-Norway 7 January 2008 7 July 2008 MW 20000 18000 16000 14000 12000 10000 8000 6000 4000 2000 0 HOUR Norway 1 3 5 7 9 11 13 15 17 19 21 23 MW The Netherlands 20000 18000 16000 14000 12000 10000 8000 6000 4000 2000 0 HOUR 1 3 5 7 9 11 13 15 17 19 21 23 8 NorNed NorNed 9

Trading A strong European electricity market Steps in the explicit day - ahead NorNed Auction The NorNed cable links the electricity grids of the Netherlands and Norway. In the near future, this submarine cable link will also make a significant contribution towards a robust European electricity market comprising central Western Europe and the Nordic countries. This new electricity highway allows exchange of electricity to and from Norway and the Netherlands. To begin with, allocation of capacity will be organised by an explicit, day-ahead auction. The explicit auction will later be replaced by an implicit auction. Explicit auction links Norway and the Netherlands The explicit auction implies that qualified market parties first purchase capacity on the NorNed connection (i.e. space on the highway ) and thereafter electricity on the power exchanges. Market parties purchase capacity in an auction jointly organised by Statnett and TenneT: NorNed Auction. All the 700 MW capacity of NorNed is available for the day-ahead explicit auction. At the day-ahead auction, participants obtain capacity per hour for the next day. A day-ahead auction is electronic; bids come in through a special secured system. Statnett and TenneT inform the participating parties of the auction results and publish them on the website www.norned-auction.org. Linking together Norway and the Netherlands is expected to ensure security of supply, make more efficient use of power systems and make prices converge. More available capacity and expanded trade between Norway and the Netherlands will not only influence prices on the APX (Dutch power exchange) and Nord Pool Spot (Norwegian power exchange), but will also positively influence the electricity prices in neighbouring countries. Almost 20 qualified market parties take part in the explicit auction; this ensures a good competition in the market. Towards market coupling In June of 2007, responsible ministers, regulators, TSOs, power exchanges and industry associations in five European countries (Belgium, Germany, France, Luxembourg and the Netherlands) signed a joint memorandum of understanding (MOU). The MOU deals with the coupling of electricity markets and security of supply in Central Western Europe by means of an implicit market coupling. In an implicit auction, a market party simultaneously buys or sells capacity and electricity in one of the electricity markets. An implicit auction implies harmonisation of Gate Closure Times (GCTs), which is a precondition to the market. The GCT is the deadline for submitting bids on the day-ahead market. Market coupling between the Central Western European market and the Northern European spot market can be realised once the Central West European regional market has been established. Statnett, control room Nord Pool Qualified participant in the Dutch and/or Norwegian electricity market Participant acquires cable capacity, through the NorNed Auction TSOs inform participants and publish auction results on website Participant purchases or sells power at APX and Nord Pool Spot TSOs schedule next day electricity flow programs TSOs manage transmission of electricity, day after trading 10 NorNed NorNed 11

Benefits Ensuring reliable supply of electricity and stable prices The NorNed cable has not only created a physical connection between the Netherlands and Norway, it also has great benefits for all of us. Environment Responsibility towards society During the installation of the NorNed cable, Statnett and TenneT have been taking careful account of the vulnerable natural environment in which the submarine high voltage cable is being laid, for instance with regard to the plant and animal life in the Waddenzee area. The great advantage of the NorNed cable for Norway and the Netherlands is that the cable enhances security of supply of electricity. The cable has also strengthened TenneT s and Statnett s positions as transmission system operators (TSOs) in the Norwest European electricity market and the Nordic region. Benefits for the market Thanks to the NorNed cable, more international trading can take place. The NorNed cable will introduce more traders and competition to the market places and as such contribute to enhanced liquidity. the seasons: higher prices during the summer and lower prices during winter. Whilst in the Netherlands prices in general are expected to come down. In The Netherlands, this will be most noticeable on peak consumption hours during the day, while in Norway during the winter. Additionally, in Norway, profits on NorNed will provide end users with reduced tariffs. TenneT and Statnett are aware of their responsibility towards society. All new high voltage lines and cables have been integrated into their environment as well as possible. When installing the NorNed cable, they took into account the wishes of government bodies, interest groups, businesses and local residents. Preconditions The route and location of the NorNed cable depended on various aspects: Environmental planning/preconditions: environmental considerations, locations of nature reserves, shipping routes Electrical/technical preconditions: strength of the magnetic field, soil condition Organisational preconditions: costs, timeline Policy frameworks defined by the government: spatial planning, legislation Consultation Part of the NorNed cable runs through Waddenzee. This is a marine area where plant and animal life receive a great deal of attention. The exact route of the submarine high voltage cable is determined in consultation with government bodies and interested parties. Eight transformers have been produced for the NorNed project each weighing about 250 tonnes As a result of NorNed, the electricity prices determined on an hourly basis by APX and Nord Pool Spot is expected to fluctuate less. This will in turn result in a more stable overall electricity price. Benefits for end users In Norway, the prices are expected to become more stable between Benefits for the society Dutch production plants are as a result of how the cable s operation is planned, able to make better and more efficient use of their production capacity during the night. This can reduce CO2 emissions from power production. Laying of the first 45 km of the cable outside Eemshaven, the Netherlands 12 NorNed NorNed 13

14 NorNed NorNed 15

Photos: Trond Isaken/Erik Thallaug/Knut Kollanrud/TenneT/Statnett/ABB/Nord Pool/ScanStockPhoto Design: Gro Berglund Eemshaven Feda For more information about NorNed Statnett SF P.O. Box 5192 Majorstuen NO-0302 Oslo, Norway T: +47 22 52 70 00 F: +47 22 52 70 01 firmapost@statnett.no www.statnett.no