Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis

Similar documents
Market Efficiency Update

Transmission Expansion Advisory Committee

Market Efficiency Update

Market Efficiency RTEP Proposal Window

FTR Modeling Enhancements for Future Transmission Expansions

Market Efficiency RTEP Proposal Window

Market Efficiency Update

Illinois State Report

Transmission Expansion Advisory Committee

Market Efficiency Update

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

Transmission Expansion Advisory Committee Meeting. April 23, 2008

Generation Deactivation Notification Update

Manual 3: Transmission Operations Updates Version 52

Manual 3: Transmission Operations Updates Version 52

Transmission Expansion Advisory Committee

PJM Regional Transmission Expansion Planning (RTEP) Process

Sub Regional RTEP Committee Mid-Atlantic

100 MW Wind Generation Project

Sub Regional RTEP Committee Mid-Atlantic

SERTP rd Quarter Meeting

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Distributed Solar Generation in the Long-Term Load Forecast

2013 SERTP. Welcome. SERTP rd Quarter Meeting. 2 nd RPSG Meeting

COORDINATED SYSTEM CONGESTED FLOWGATE STUDY SCOPE MISO, PJM, SPP AND TVA January 2010

The Transmission Lay of the Land

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

PSE Attachment K Puget Sound Area Transmission Meeting

2015 Grid of the Future Symposium

Supplemental Report on the NCTPC Collaborative Transmission Plan

2017 Indiana State Infrastructure Report (January 1, 2017 December 31, 2017)

SECTION 3 - ENERGY MARKET, PART 2

CIL/CEL Values and Study Timeline

Sub-Regional RTEP Committee PJM South

Sub Regional RTEP Committee Mid-Atlantic

Highly Constrained Elements Within ATC Footprint

Sub Regional RTEP Committee - Southern. August 19, 2011

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

New Jersey State Report

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Sub Regional RTEP Committee South

Reliable Integration of Inverter-Based DER

Minnesota Biennial Transmission. Zone Meeting 8

Pennsylvania State Report

Transmission Expansion Advisory Committee

Sub Regional RTEP Committee Western Region ATSI

SERTP rd Quarter Meeting

Reliability Analysis Update

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee - Southern

Impacts of MISO DPP-2016-February (West, ATC, MI, South) Projects on PJM Facilities

Sub Regional RTEP Committee South

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

Designated Entity Pre-Qualification Materials. Exelon Corporation

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Distributed Solar Generation Update

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Subregional RTEP Committee Mid-Atlantic Area. September 9, 2008

How Storage Will Transform Electric Power Emissions and Markets. Roger Lueken & Jay Apt

Market Efficiency Planning Study

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

Sub Regional RTEP Committee Mid-Atlantic First Energy MAAC Solution Meeting

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

High Plains Regional Transmission Summit. Timelines for Planning Processes / Policy

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

IMM Quarterly Report: Summer 2017

LOCAL TRANSMISSION PLAN

February 10, The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, DC 20426

Reliability Analysis Update

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Energy Policy Implications: PJM Planning

ATTACHMENT Y STUDY REPORT

MTEP13 SPM #2- Central Region. March 25, 2013

Transmission Expansion Advisory Committee. Reliability Analysis Update

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

2018 PJM BASELINE RELIABILITY ASSESSMENT

15 Nelson-Marlborough Regional Plan

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

2010 SERTP. Welcome. SERTP rd Quarter Meeting. 2 nd RPSG Meeting 9:00 AM 3:00 PM

PJM SRTEP Meeting Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge:

Appendix D Black Hills Project Summary

New Service Queue Update 2017 (Study reports located at:

Overview of ISO New England and the New England Wholesale Power Markets

Reliability Analysis Update

1. Administrative Items... SPP. 2. Stakeholder Web-Presentation... ABB

Sub Regional RTEP Committee Mid-Atlantic

Market Congestion Planning Study (South)- Robustness Analysis. Economic Planning Users Group Meeting August 11 th, 2017

Reliability Analysis Update

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

2013 ANNUAL PROGRESS REPORT

West Station-West Cañon 115 kv Transmission Project

New Mexico Transmission Expansion Concepts For Wind Resources

Western NY Public Policy Transmission Planning Report

15 Nelson-Marlborough Regional Plan

Transmission Planning & Engineering P.O. Box MS 3259 Phoenix, Arizona

Transcription:

Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis September 02, 2014

Objectives To review simulated congestion results for all Market Efficiency study years To provide an explanation of the drivers of congestion based on transmission topology and economic fundamentals To discuss next steps 2

Congestion Analysis: All Study Years 2015 and 2019 for study of approved RTEP projects for accelerations and modifications. - Compare market congestion for near term vs. future topology - Estimate economic impact of accelerating planned upgrades 2019, 2022, and 2025 for study of new enhancements. - Review results to identify future constraints causing significant congestion All base congestion results posted on Market Efficiency website at below link: - http://pjm.com/~/media/planning/rtep-dev/market-efficiency/2014-market-efficiencyanalysis-base-congestion-results.ashx 3

2015 Load, Generation and Economic Assumptions Top 25 Market Efficiency Constraints 2015 Input Assumptions with 2015 Topology 2015 Input Assumptions with 2019 Topology Facility Name AREA TYPE Frequency (Hours) Market Congestion ($ Millions) Frequency (Hours) Market Congestion ($ Millions) AP SOUTH L/O BED-BLA PJM INTERFACE 1627 $103.6 1448 $79.4 Braidwood to East Frankfort 345 kv CE LINE 147 $18.0 215 $26.0 Monticello to East Winamac 138 kv M2M LINE 2569 $99.0 65 $2.9 Hennepin to Hennepin 138 kv M2M LINE 570 $5.9 1374 $12.6 AEP-DOM L/O BED-BLA PJM INTERFACE 706 $26.7 587 $19.3 Miami Fort to Willey 138 kv DEO&K LINE 310 $20.0 308 $25.0 Oak Grove to Galesburg 161 kv M2M LINE 3281 $60.0 Crescent 345 kv DLCO XFMR 9 $2.6 4 $0.5 Elliot to Elliot 138 kv AEP LINE 338 $30.0 27 $2.0 Cordova to Nelson 345 kv CE LINE 333 $9.9 817 $21.1 Worcester to Ocean Pines (I) 69 kv DP&L LINE 42 $4.7 88 $11.9 Graceton to BAGLEY 230 kv BGE LINE 826 $22.0 Dravosburg to West Mifflin 138 kv DLCO LINE 1275 $14.4 937 $8.5 Cloverdale to Lexington 500 kv AEP - DVP LINE 631 $37.0 Wurno to Claytor Lake 138 kv AEP LINE 84 $11.0 99 $5.0 Woodville to 15USAP 138 kv DLCO LINE 449 $5.0 431 $6.0 Hunterstown 230 kv ME XFMR 254 $18.0 WESTERN INTERFACE PJM INTERFACE 257 $7.1 6EDFERRY to Dickerson Station "D" 230 kv PEPCO - DVP LINE 39 $6.3 Staley North to Lafayette 138 kv M2M LINE 283 $4.0 Tiltonsville to Windsor 138 kv AP - AEP LINE 36 $12.4 7 $0.4 Cherry Valley to Cherry Valley 138 kv CE LINE 119 $5.3 15 $0.2 Cherry Valley 345 kv CE XFMR 119 $4.0 Belvidere to Marengo Tap 138 kv CE LINE 227 $8.0 Alpine to Belvidere 138 kv CE LINE 62 $4.0 Total Congestion (Top 25) $538.9 $220.8 Total Congestion (All Facilities) $593.0 $285.0 4

2019 Input Assumptions with 2015 Topology Facility Name AREA TYPE Frequency Market Congestion (Hours) ($ Millions) 5 2019 Input Assumptions with 2019 Topology Frequency Market Congestion (Hours) ($ Millions) AP SOUTH L/O BED-BLA PJM INTERFACE 1705 $99.0 1535 $87.3 Braidwood to East Frankfort 345 kv CE LINE 271 $32.0 452 $51.0 Monticello to East Winamac 138 kv M2M LINE 1736 $79.0 13 $0.4 Hennepin to Hennepin 138 kv M2M LINE 596 $7.0 2016 $29.2 AEP-DOM L/O BED-BLA PJM INTERFACE 508 $19.0 552 $21.4 Miami Fort to Willey 138 kv DEO&K LINE 347 $23.0 267 $17.0 Oak Grove to Galesburg 161 kv M2M LINE 2987 $66.0 Crescent 345 kv DLCO XFMR 123 $29.0 67 $18.3 Elliot to Elliot 138 kv AEP LINE 497 $44.0 104 $9.0 Cordova to Nelson 345 kv CE LINE 201 $6.0 538 $15.2 Worcester to Ocean Pines (I) 69 kv DP&L LINE 28 $4.0 76 $13.8 Graceton to BAGLEY 230 kv BGE LINE 3080 $54.0 8 $0.0 Dravosburg to West Mifflin 138 kv DLCO LINE 1456 $19.0 894 $8.3 Cloverdale to Lexington 500 kv AEP - DVP LINE 435 $32.0 Wurno to Claytor Lake 138 kv AEP LINE 136 $8.0 158 $7.0 Woodville to 15USAP 138 kv DLCO LINE 541 $8.0 364 $6.0 Hunterstown 230 kv ME XFMR 372 $25.0 WESTERN INTERFACE PJM INTERFACE 958 $25.0 270 $3.3 6EDFERRY to Dickerson Station "D" 230 kv PEPCO - DVP LINE 792 $11.0 125 $0.2 Staley North to Lafayette 138 kv M2M LINE 453 $12.0 Tiltonsville to Windsor 138 kv AP - AEP LINE 4 $1.0 Cherry Valley to Cherry Valley 138 kv CE LINE 89 $3.0 44 $0.4 Cherry Valley 345 kv CE XFMR 156 $6.0 Belvidere to Marengo Tap 138 kv CE LINE 46 $1.0 Alpine to Belvidere 138 kv CE LINE 57 $4.0 Total Congestion (Top 25) $617.0 $287.8 Total Congestion (All Facilities) $671.0 $395.0 2019 Load, Generation and Economic Assumptions Top 25 Market Efficiency Constraints

Upgrades responsible for Congestion Reduction 2015 and 2019 Simulations Facility Name Area Upgrade Responsible for Congestion Decrease Monticello to East Winamac 138 kv M2M MISO MVP Project: Reynolds to Greentown Oak Grove to Galesburg 161 kv M2M MISO MVP Project: Fargo-Galesburg-Oak Grove 345 kv Line Graceton to BAGLEY 230 kv BGE PJM Project: Rebuild Graceton - Bagley 230 kv as double circuit line using 1590 ACSR Cloverdale to Lexington 500 kv AEP - DVP PJM Project: Rebuild line, add 765 kv XFMR, replace 6A/6B Xfmr Hunterstown 230 kv ME PJM Project: Install 2nd Hunterstown XFMR and reconductor Hunterstown- Oxford Line Elliot to Elliot 138 kv AP SOUTH L/O BED-BLA WESTERN INTERFACE AEP PJM PJM No upgrade Identified 6EDFERRY to Dickerson Station "D" 230 kv PEPCO - DVP Reconfigure Line #203 to feed Edwards Ferry sub radial from Pleasant View 230 kv Dravosburg to West Mifflin 138 kv DLCO Projected Congestion rises in future year simulations Staley North to Lafayette 138 kv M2M MISO Project: Reconductor Lafayette 230 to Staley Tiltonsville to Windsor 138 kv AP - AEP Projected Congestion in 2015/2019 reduced per removal of LTE rating Operational derate (2014) Crescent 345 kv DLCO Projected Congestion expected to rise without 3rd XFMR Cherry Valley 345 kv Belvidere to Marengo Tap 138 kv Alpine to Belvidere 138 kv Cherry Valley to Cherry Valley 138 kv CE CE CE CE PJM Project: Construct a new Byron to Wayne 345 kv circuit 6

2019 Input Assumptions with 2019 Topology Facility Name AREA TYPE Frequency Market Congestion (Hours) ($ Millions) Market Efficiency Simulation Results 2019, 2022, and 2025 Simulation Years 2022 Input Assumptions with 2019 Topology Frequency Market Congestion (Hours) ($ Millions) 2025 Input Assumptions with 2019 Topology Frequency Market Congestion (Hours) ($ Millions) AP SOUTH L/O BED-BLA PJM INTERFACE 1535 $87.3 1326 $117.3 915 $83.8 Braidwood to East Frankfort 345 kv CE LINE 452 $51.0 284 $36.0 176 $22.0 Hennepin to Hennepin 138 kv M2M LINE 2016 $29.2 2276 $55.1 2169 $49.5 AEP-DOM L/O BED-BLA PJM INTERFACE 552 $21.4 577 $31.4 544 $39.6 Miami Fort to Willey 138 kv DEO&K LINE 267 $17.0 251 $27.0 210 $30.0 Crescent 345 kv DLCO XFMR 67 $18.3 82 $38.7 73 $31.2 Elliot to Elliot 138 kv AEP LINE 104 $9.0 151 $13.0 176 $15.0 50045005 L/O RCKSPG-KEENY PJM INTERFACE 858 $17.6 730 $29.6 798 $38.9 Cordova to Nelson 345 kv CE LINE 538 $15.2 483 $21.6 408 $18.2 Worcester to Ocean Pines (I) 69 kv DP&L LINE 76 $13.8 96 $19.6 128 $30.8 Dravosburg to West Mifflin 138 kv DLCO LINE 894 $8.3 889 $10.8 916 $13.7 Sub 56 (Davenport) to East Calamus 161 kv M2M LINE 247 $4.2 704 $19.7 971 $30.7 Wurno to Claytor Lake 138 kv AEP LINE 158 $7.0 205 $12.0 110 $7.0 Woodville to 15USAP 138 kv DLCO LINE 364 $6.0 371 $10.0 306 $10.0 Peach Bottom 500 kv PECO XFMR 117 $5.0 139 $7.0 206 $22.0 CENTRAL INTERFACE PJM INTERFACE 118 $0.9 616 $7.7 659 $11.2 Krendale to Shanor Manor 138 kv AP LINE 513 $3.0 783 $13.0 810 $15.0 Brunner Island to Yorkana 230 kv ME - PPL LINE 315 $8.8 243 $9.2 269 $15.7 Claytor Lake to South Christiansburg 138 kv AEP LINE 145 $3.0 355 $16.0 205 $9.0 Fieldale to Thornton 138 kv AEP LINE 135 $4.0 170 $9.0 224 $11.0 Conastone to Northwest 230 kv BGE LINE 56 $3.1 50 $4.4 76 $20.3 Safe Harbor to Graceton 230 kv PPL - BGE LINE 800 $8.8 671 $8.2 433 $5.6 Taneytown to Carroll 138 kv AP LINE 532 $10.2 419 $5.9 163 $2.8 CLEVELAND INTERFACE PJM INTERFACE 4 $0.3 17 $1.9 107 $11.6 Dooms to Crozet 230 kv DVP LINE 12 $1.0 26 $3.0 16 $11.0 Total Congestion (Top 25) $353.4 $527.1 $555.6 Total Congestion (All Facilities) $395.0 $575.0 $639.0 7

Observations for 2019, 2022 and 2025 Simulation Years Facility Name Area Observations AP SOUTH L/O BED-BLA PJM West to East transfers. North Anna #3 Nuclear Plant causes downward trend in congestion between 2019 and 2025, rises after 2025 Braidwood to East Frankfort 345 kv CE PJM owned facility near border with MISO - impacted by interchange and high wind output Hennepin to Hennepin 138 kv M2M Potential Network upgrades associated with new generator interconnections may help AEP-DOM L/O BED-BLA PJM Combination of West to East transfers, load growth, higher loop flows and higher gas prices causes an upward trend in congestion Miami Fort to Willey 138 kv DEO&K Crescent 345 kv DLCO Identified in Baseline Reliability analysis (Projects under consideration in Reliability Proposal Window) Elliot to Elliot 138 kv AEP Identified as overload in Winter Analysis 50045005 L/O RCKSPG-KEENY PJM Peach Bottom 500 kv PECO West to East transfers on 500 kv system associated with load growth and higher gas prices cause upward trend in congestion CENTRAL INTERFACE PJM Krendale to Shanor Manor 138 kv AP Higher gas prices drive higher coal output in western PJM Cordova to Nelson 345 kv CE Near border with MISO - impacted by interchange and loop flows Worcester to Ocean Pines (I) 69 kv DP&L Load growth with limited local re-dispatch options leads to very high shadow price Dravosburg to West Mifflin 138 kv DLCO Higher constraint sensitivity due to load growth and gas prices causes steady increase in congestion over time Sub 56 (Davenport) to East Calamus 161 kv M2M MISO owned facility Impacted by PJM/MISO interchange and loop flows Wurno to Claytor Lake 138 kv AEP Identified as overload in Winter Analysis Brunner Island to Yorkana 230 kv ME - PPL Higher gas prices cause higher constraint sensitivity Fieldale to Thornton 138 kv AEP Congestion and binding frequency grows steadily with load Conastone to Northwest 230 kv BGE Increase in constrained hours due to load growth Safe Harbor to Graceton 230 kv PPL - BGE Downward trend in congestion offset by higher congestion in Peachbottom area CLEVELAND INTERFACE PJM Load growth drives increase in number of constrained hours. Dooms to Crozet 230 kv DVP Constraint sensitivity rises significantly over time reflecting higher redispatch costs 8

Observations of Congestion in 2019, 2022 and 2025 Simulation Years Wind impacts local constraints in COMED region High efficiency gas-fired generation in MAAC and Southern PJM initially mitigate the rise in regional congestion Trend upwards for load and gas prices contribute to higher congestion regionally and for some local constraints in future years Higher gas prices beyond 2020 cause uptick in coal generation as some units become economic over greater number of hours Lower voltage (138 kv and below) tend to be more sensitive to small load changes especially when load pocket further electrically from inexpensive re-dispatch options Interchange rises steadily over period of 2015 to 2025 but doesn t appear to be a significant driver of congestion changes across PJM footprint 9

Next Steps Market Efficiency Next Steps: Stakeholder feedback on model 10/01/2014 Finalize Proposal Document and Criteria October criteria for project proposals PJM review of acceleration candidates September - October Proposal window November 1 March 1, 2015 10

Market Efficiency Data Posting Market Efficiency Web Page located at http://www.pjm.com/planning/rtep-development/market-efficiency.aspx Market Efficiency Case Files have been posted for all study years Access requires CEII confirmation Access requires Vendor (Ventyx) confirmation Access requires MISO approval confirmed through PJM No confidential data provided or used in analysis (i.e. actual bid data) XML Format Reference Files Input Assumptions Summary Updated Modeling Document provides details of setup and modeling methods Steps to run Model Document Market Efficiency Training Document Market Efficiency Questions Please send to the RTEP e-mail distribution (rtep@pjm.com) with Market Efficiency in the subject line header 11