Dynamic Scheduling NI A F S NI S. Where:

Similar documents
Facilities Study for Alberta to US Available Transfer Capability

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

SPS Planning Criteria and Study Methodology

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Stability Study for the Mt. Olive Hartburg 500 kv Line

VARIABLE TRANSFERS 2/11/2014. DTC Task Force. Ramu Ramanathan 2/10/2014 1

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Distributed Energy Resources

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

NorthernLights HVDC Project

Gateway South Transmission Project

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Essential Reliability Services Engineering the Changing Grid

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Project #94. Generation Interconnection System Impact Study Report Revision

Interconnection Feasibility Study Report GIP-226-FEAS-R3

TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC)

Steady-State Power System Security Analysis with PowerWorld Simulator

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

Session 10 NERC Interconnection Requirements

Targeted Application of STATCOM Technology in the Distribution Zone

Connection Engineering Study Report for AUC Application: AESO Project # 1674

TransWest Express Project

Cargill Power Markets LLC Transmission Service Study (OASIS # TSR and )

Interconnection System Impact Study Final Report February 19, 2018

Transmission Planning using Production Cost Simulation & Power Flow Analysis

i-pcgrid Workshop 2017

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

Power System Economics and Market Modeling

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

Benefits of Reducing Electric System Losses

Q217 Generator Interconnection Project

Hamdy S. K. El-Goharey, Walid A. Omran, Adel T. M. Taha

Islanding of 24-bus IEEE Reliability Test System

Experience on Technical Solutions for Grid Integration of Offshore Windfarms

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

EFFECT OF SOLAR PV ON VOLTAGE MANAGEMENT IN NEW ZEALAND

Research on Transient Stability of Large Scale Onshore Wind Power Transmission via LCC HVDC

Midway/Monument Area TTC Study

Western Area Power Administration Sierra Nevada Region

Western Area Power Administration Sierra Nevada Region

100 MW Wind Generation Project

CHAPTER I INTRODUCTION

Cross Cascades North Study Team Report

Grid Stability Analysis for High Penetration Solar Photovoltaics

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

POWER SYSTEM OPERATION AND CONTROL YAHIA BAGHZOUZ UNIVERSITY OF NEVADA, LAS VEGAS

Feasibility Study Report

Update to the 2004 Puget Sound Area Study Group ( PSASG ) Report: Assessment of Puget Sound Area / Northern Intertie Curtailment Risk

Proposed Solution to Mitigate Concerns Regarding AC Power Flow under Convergence Bidding. September 25, 2009

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Georgia Transmission Corporation Georgia Systems Operations Corporation

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

Grid code Compliance and Renewable Energy Projects. Mick Barlow, Business Development Director, S&C Electric, United Kingdom

April 30, Michael Schilmoeller, Senior Power Systems Analyst

WECC Regional Planning Review. Canada/Pacific Northwest Northern California Transmission Line Project. Technical Analysis Committee Report

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

Integration of Large Wind Farms into Electric Grids

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Islanding of 24-bus IEEE Reliability Test System

Lab Validation of PV Solar Inverter Control as STATCOM (PV-STATCOM) Rajiv K. Varma and Ehsan Siavashi

PES Cook Islands KEMA Grid Study Final Report

APPENDIX E: Project Need and Description

Geomagnetic Disturbance Power System Study in Maine

Dynamic Control of Grid Assets

Steady-State Power System Security Analysis with PowerWorld Simulator

APPENDIX E: Project Need and Description

Supplemental Report on the NCTPC Collaborative Transmission Plan

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006

300 MW SOLAR PHOTOVOLTAIC PLANT, GENERATOR INTERCONNECTION FEASIBILITY STUDY

REPORT. System Impact Assessment Report. Thierry Mine Development CONNECTION ASSESSMENT & APPROVAL PROCESS CAA ID

Dynamic Control of Grid Assets

XXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

BC HYDRO REAL TIME OPERATIONS OPERATIONS SUPPORT SYSTEM OPERATING ORDER 7T-13

Introduction to PowerWorld Simulator: Interface and Common Tools

Power System Economics and Market Modeling

Interconnection System Impact Study Report Request # GI

WESTERN EIM BENEFITS REPORT Second Quarter 2018

COMPARISON OF STATCOM AND TCSC ON VOLTAGE STABILITY USING MLP INDEX

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

BC Hydro OATT - Balancing Area Transmission Service Workshop. January 20, 2014

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

PSE Attachment K Puget Sound Area Transmission Meeting

Index Terms: Dynamics, reactive power capability, time domain simulation, voltage stability,

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Relative Power Factor Correction costs

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

Battery Energy Storage System addressing the Power Quality Issue in Grid Connected Wind Energy Conversion System 9/15/2017 1

CHAPTER 5 FAULT AND HARMONIC ANALYSIS USING PV ARRAY BASED STATCOM

NYCA LOLE Violations (Methods D and E )

INSTALLATION OF CAPACITOR BANK IN 132/11 KV SUBSTATION FOR PARING DOWN OF LOAD CURRENT

Electric Power System Under-Voltage Load Shedding Protection Can Become a Trap

OPTIMUM ALLOCATION OF DISTRIBUTED GENERATION BY LOAD FLOW ANALYSIS METHOD: A CASE STUDY

A SIMPLE CONTROL TECHNIQUE FOR UNIFIED POWER FLOW CONTROLLER (UPFC)

DYNAMIC LOAD FLOW STUDIES OF DISTRIBUTION FEEDS IN THE SAN JOAQUIN VALLEY REGION

PSAT Model- Based Voltage Stability Analysis for the Kano 330KV Transmission Line

Transcription:

Dynamic Scheduling FERC Order 888 defines dynamic scheduling: which is the electronic transfer of the time-varying electricity consumption corresponding to a load or the time-varying generation associated with a generator from one control area to another. Dynamic scheduling moves the control requirements associated with one (or more) physical entity from one control area to another.

Dynamic Scheduling For example, in the Southwest, four control areas use their Hoover rights for regulation. WAPA receives every 4 seconds (normally 2-4 seconds) from four different control areas request for timevarying amount of generation (up to their contractual allocations). WAPA aggregates the four requests and sends the total to the control system and Hoover Dam. DS has application for both load and generation. Generation applications have higher DS than load

ACE Where: NI A F A β I ME = NI S F S ( NI NI ) 10β ( F A Dynamic Scheduling S A F actual and scheduled net interchanges actual and scheduled frequencies frequency bias setting (MW/0.1Hz) meter error correction factor S ) I ME ACE was required to cross 0 at least once every 10 minutes(a1). Average ACE (energy imbalance) should be within Ld (0.2-0.5% of peak demand) every 10 minutes (CPS1&CPS2)

Dynamic Scheduling Portion of ACE Dynamically allocated L d (0.2-0.5% of peak demand, e.g. BCH Ld ~ 50 MW)

Dynamic Scheduling How to determine the maximum DS? A quick search of the subject yielded no available methodology! There are two possible approaches: Steady-State (powerflow based). A series of snap shots, less accurate in capturing dynamic interaction Time domain (longer term transient analysis). AGC and other controls can be modeled. Requires dynamic data,specially for switchable shunts, ULTCs, ACE- AGC model, SPS, etc.

Dynamic Scheduling Amount of Dynamic Scheduling may be restricted due to: TTC (voltage/transient security limits) Ramp rate (e.g. 100 MW/min) Frequent switching of shunts Frequent Arming/Disarming of RAS Etc.

Dynamic Scheduling Voltage Schedule and Shunt Switching: The 500 kv system voltages should be generally maintained at 525 kv. In general, 550 kv is the upper continuous limit acceptable on any 500 kv bus, 570 kv is acceptable for up to 5 minutes. During heavy transmission loadings voltages should be maintained in the 525 kv to 535 kv range to minimize losses and increase stability margins. During lighter loadings voltages should be reduced to 520 kv, or lower if practical, to reduce VAR generation from the lightly loaded transmission. Sequentially timed tripping of most 500 kv circuits at voltages between 570 kv and 585.

Dynamic Scheduling Voltage Schedule and Shunt Switching: Sub Min kv Max kv Min p.u. Max p.u. CBN 530 547 1.06 1.094 CK5 515 545 1.03 1.09 ING 530 545 1.06 1.09 MSA 515 540 1.03 1.08 KLY 525 540 1.05 1.08 CUSTER * 515 540 1.03 1.08 MONROE * 525 550 1.05 1.10 ING 239 243 1.037 1.054 MDN 238 243 1.035 1.057 * From BPA s KVSCHED08_24Mar08.xls

Dynamic Scheduling Possible Remedial Schemes to Address DS problems: SVCs Other FACTS devices (e.g. STATCOM) Considering AUTO RAS arming Etc.

Summary of 2008 DS Limit Study With the addition of large amounts of wind generation in the Pacific Northwest it is expected that the need for regulation and other ancillary services will increase in the coming years. It is possible that BC could help meet part of this demand. However, the transmission between BC and the Pacific Northwest would need to support higher levels of Dynamic Schedules. Currently, the Northern Inter-tie Dynamic Scheduling limit is 300 MW. In a 2008 study the voltage issues related to increasing DS limit on the Northern Inter-tie to 750 MW were explored.

Summary of 2008 DS Limit Study The study was designed to: Assess the impact of up to 750 MW of DS on regional voltages during Summer Heavy Load Hour (HLH) conditions for North-South with full PSE generation, and for South-North with light PSE generation; Assess the relative performance of possible system reactive reinforcements in BC; Test a study methodology to quantify the impact of mid-term dynamic phenomena such as DS. The simulations were performed using the Voltage Security Assessment Tool (VSAT) of Powertech s DSATools TM

Furthermore, the sensitivity of the results to all switched shunts and ULTC controls was examined when reactive reinforcement was assessed. Reactive reinforcement in the form of continuously controlled Static VAr Compensator (SVC) was examined at four different locations, namely, Ingledow and Meridian 500 and 230 kv buses. No reinforcements were investigated on the US side Summary of 2008 DS Limit Study The switched shunt controls, as well as Under Load Tap Changers (ULTC) were locked at first; subsequently the AutoVar controls at MDN230 and ING230 were turned on to find out if any reactive switching was required and how the key bus voltages changed.

Summary of 2008 DS Limit Study It was assumed that increases in the Northern Inter-tie DS limit would be staged in small increments of up to 100 MW. These were grouped into six stages: Stage 1: 50 MW BCTC-NWE & 200 MW BCTC-CAISO Stage 2: 100 MW BCTC - BPA plus Stage 1 Stage 3: 100 MW BCTC - BPA plus Stage 2 Stage 4: 100 MW BCTC - Washington plus Stage 3 Stage 5: 100 MW BCTC - Portland Area plus Stage 4 Stage 6: 100 MW BCTC - BPA plus Stage 5

Summary of 2008 DS Limit Study BC - US Additional Flow 800 600 400 200 0 Stage 6: Profile A 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Minute (Note: DSmax = 512.5 MW due to diversity in schedules.) BC - US Additional Flow 800 600 400 200 0 Stage 6: Profile B 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Minute

Summary of 2008 DS Limit Study Future DS commitments would likely have different maximum ramp rates. Consequently, for the purposes of this study some ramp rates were assumed. Two potentially stressed profiles were developed to try and quantify how the ramp rates could be factored into the time-stepped power flow studies. Profile A results from each DS ramping continuously at its maximum ramp rate (i.e., Saw-tooth Profile). Profile B results from each DS ramping to its limit at its maximum ramp rate, holding there until every other DS in that stage has reached its corresponding limit, and then all ramping back in the opposite direction to their other limit (i.e., Max-Min Profile).

Summary of 2008 DS Limit Study CKY500 500. 530.94 kv 50045 MDN230 230. 50018 240.31 kv ING230 230. 240.58 kv 50183 0.0 MDN T1 12.6 51175 122.3 MDN T3 12.6 51182 0.0 ING T4 12.6 50588 0.0 ING T2 12.6 51190 ING T5 12.6 51208 0.0 MDN500 500. 524.87 kv 50047 0.0 CBN500 500. 523.96 kv 50860 533.67 kv 50703 NIC500 500. 50194 ING500 500. 524.60 kv -279.1 0.0 NLY230 230. 50784 237.15 kv 0.0 1008 MW -168 MVAr 992 MW -167 MVAr 300 MW -24 MVAr 40323 CUSTER W 500. 526.81 kv NLYPHS 230. 50822 238.89 kv Case 1:Summer HLH 2300 MW N-S ALIS 40749 752.6 MONROE 500. 545.61 kv 40145 239.00 kv BOUNDARY 230.

Summary of 2008 DS Limit Study Case 1: Summer HLH 2300 MW N-S ALIS PV Plot for Stage 6 of Profile B Without Shunts Switching.

Summary of 2008 DS Limit Study Case 1: Summer HLH 2300 MW N-S ALIS PV Plot for Stage 6 of Profile B With Shunts Switching.

Summary of 2008 DS Limit Study Case 1: Summer HLH 2300 MW N-S ALIS PV Plot for Stage 6 of Profile B Without Shunts Switching.

Summary of 2008 DS Limit Study Case 1: Summer HLH 2300 MW N-S ALIS PV Plot for Stage 6 of Profile B With Shunts Switching.

Summary of 2008 DS Limit Study

Conclusions of 2008 DS Limit Study DS study up to 750 MW for a wide range of conditions/scenarios Worst case: All Lines In Service with 2300 MW of N-S transfer Northern Inter-tie DS exacerbated potential voltage stability problems around Custer and Ingledow Maximum increased switching frequency: 16 on/off per hour With 1900 MW S-N flow: No switching up to 750 MW DS SVC examined at ING500, MDN500, ING230, MDN230: