TACOMA PUMP STATION 4103 FORCE MAIN HDD PROJECT: A SHORT BORE WITH TALL CHALLENGES

Similar documents
INNOVATION IN HDD CONSTRUCTION AND ENGINEERING: AN 8,850-FOOT 32-INCH SINGLE DRILL HDD

Presentation Objectives Provide a description of how Directional Boring works Cover the basics for planning a Directional Bore Discuss the advantages

St. Clair River Replacement Project Execution Plan. Appendix 1 Contractor s Drilling Execution Plan

An innovative solution for water and sewer installation AXIS. Guided Boring System

********************PROJECT OWNER******************** **** River Crossing West Siphon Horizontal Directional Drilling Operations. TIME: 4:30 p.m.

Monitoring of Shoring Pile Movement using the ShapeAccel Array Field

Build-A-Box Modular Trench Shielding System

Build-A-Box. Modular Trench Shielding System. Tabulated Data Effective January 4, Revised: April 21, with CHANGE THREE

GUIDED BORING APPLICATION VARIETY: PAIRING THE RIGHT TOOLING WITH THE CHALLENGE

Bid Summary Still Creek Wastewater Improvements Phase III City Job No. 411-D November 21, 2013

HDD ASSIST OVERCOMING DIFFICULT SITUATIONS

PERMANENT RESIDENTIAL UNDERGROUND SERVICE

5. Underground Requirements

BID FORM PART A. Total Quantity 1 LS $ - 2a Surveying, Layout, and Field Staking 1 LS $ - 2b Maintenance of Traffic 1 LS $ -

RESOURCE CENTRE GUIDELINES IMPACT MOLING AND RAMMING

A New High Temperature Pressure Rated HDPE Pipe Resin Expands the Capability of Polyethylene Pipe

CHAPTER 9: VEHICULAR ACCESS CONTROL Introduction and Goals Administration Standards

CAT-1 Series 3. Installation Guide. The Valley Group, Inc. 871 Ethan Allen Hwy. Suite 104 Ridgefield, CT 06877

For Conduit Inspections

Ambient Magnetic Field Compensation for the ARIEL (Advanced Rare IsotopE Laboratory) Electron Beamline. Gabriela Arias April 2014, TRIUMF

Presenter s Notes SLIDE 1. Before darkening the room, offer a welcome and overview. Begin by introducing the program and its topic:

#366. Gate Operator Pre-Installation and Site Planning. Introduction

A BURIED MAZE OF PIPES PUTS THE FASTBACK SYSTEM TO THE TEST

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona, USA

Horizontal Alignment

JCP&L Verbatim Response to Middletown Township s Questions

Septic Tanks. Effluent Screen Cleaning. Effluent Screens. Surveying Abbreviations. Installation Keys. Septic Tanks, Holding Tanks & Pump Tanks

DESIGN STANDARDS SECTION DS 3 STREETS

CRISIS: WORLDWIDE DETERIORATING INFRASTRUCTURE SOLUTION: PIPE BURSTING, PROVEN METHOD OF REPLACEMENT PIPE BURSTING ADVANTAGES:

OVERVIEW ENVIRONMENTS. Structures

Cam Motion Case Studies #1 and # 2

Traffic Engineering Study

Public Works Operations Manual Standard Operating Procedures for Water and Sewer WS - B311 Sanitary Sewer Connection Repair

MONTANA TEEN DRIVER CURRICULUM GUIDE Lesson Plan & Teacher Commentary. Module 2.2 Basic Control and Vehicle Location

THOMAS. Unifit Premier Series. Couplings & Flange Adaptors Non Restrained Products PIPE PRODUCTS

1. INTRODUCTION 2. PROJECT DESCRIPTION CUBES SELF-STORAGE MILL CREEK TRIP GENERATION COMPARISON

Atlas Copco Geotechnical Engineering Products. Pipe roofing solutions

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

CLEANING, INSPECTION AND REPAIR. Valve Spring Compressor (Part No. HD-34736B) Figure Compressing Valve Springs

City of Grand Island Tuesday, October 10, 2017 Council Session

Presenter s Notes SLIDE 1

Working in Proximity to Overhead Power Lines

Alberta Infrastructure HIGHWAY GEOMETRIC DESIGN GUIDE AUGUST 1999

UNDERGROUND CONDUIT SYSTEMS for Primary and Secondary Conductors (Rev. 7)

City Hall 539 Phoenix Street South Haven, Michigan Telephone (269) Fax (269)

Chapter 8.0 PROPOSED CAPITAL IMPROVEMENT PROGRAM

Electrical Safety Slide Show Presenter s Notes

2 Min. Min. Edge of. Edgeline See Note 3 PLAN VIEW. See Note 3. This distance may vary

TYPICAL SPECIFICATION ECP Steel Pier PPB-300 Utility Bracket System

NEW TECHNOLOGIES INCREASE DRILLING PERFORMANCE IN OMV PETROM. March 20, Bucharest

Wash Pipe. Survey Tool. Pilot String Bit Drill Profile. Pilot String. Wash Pipe Bit. Pot Holing for Utilities

Power Arc Testing on Insulator Sets

CLEARWATER FIRE & RESCUE TRAINING BUREAU

Cost Benefit Analysis of Faster Transmission System Protection Systems

Section 6H.01 Typical Applications

800 Access Control, R/W Use Permits and Drive Design

TABLE OF CONTENTS. Minimum Parallel Component Thickness, Type II...8. Minimum Perpendicular Component Thickness, Type III (40'-L, 9'-OC)...

2015 Grid of the Future Symposium

Robotic Inspection of Unpiggable Piping at Pump Station

Todd Carlson Program Coordinator Engineering MMSD PP I/I Summit 2.0 October 15,

Western Alberta Transmission Line (WATL) HVDC Project

Product manual Oil Streak Sensor INTRODUCTION CONSTRUCTION. Master Sensor

INFRASTRUCTURE RENEWAL FOR THE NEXT GENERATION PATCO High Speed Line Power Infrastructure Renewal

TR SERIES LŌDRIL LAD SERIES AERA. Foundation Drilling Equipment Manufacturing

Placement on the fireground simply refers to how and where an apparatus is placed at the scene.

Exhaust System Bypass Valves and Exhaust Valve Bypass Controller

Casing Spacers. An engineered equal to stainless steel casing spacers.

Module7:Advanced Combustion Systems and Alternative Powerplants Lecture 32:Stratified Charge Engines

Plan Check Policies and Guidelines

Craig Scheffler, P.E., PTOE HNTB North Carolina, P.C. HNTB Project File: Subject

INSTALL SERVICE- ENTRANCE SYSTEMS

MN Roads Low Volume Road Testing to Validate the Purdue TPTA Textures and Predicted Joint Effects

Fast-Track Design and Construction of Running Repair Shop for Metro-North Railroad

A Practical Guide to Free Energy Devices

This article discusses a tank

Plan Check Policies and Guidelines

Step 1. PLANNING FOR THE INSTALLATION TOOLS REQUIRED

Commercial Electric Service Handbook

Pump ED 101. Variable, Fixed Speed Control - - Float Switch Activation. Introduction

Research Results Digest 72

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR PAVEMENT RIDE QUALITY (MEAN ROUGHNESS INDEX ACCEPTANCE CRITERIA)

FABRICATION TR Flex Pipe & Fittings DUCTILE IRON

Bohn to Kettle River Transmission Project

ESCONDIDO FIRE DEPT TRAINING MANUAL Section Truck Module Page 1 of 6 Utilities - Controlling Revised

PASSING ABILITY OF SCC IMPROVED METHOD BASED ON THE P-RING

Comparison Between PE 4710 (PE 4710 PLUS) and PE 100 (PE 100+, PE 100 RC)

5. Contractor Information 3M Model 2300 Series System Layout Checklist

Section 5. Crude Oil and Natural Gas Resource Development

Overhead Concealed Door Closer DORMA RTS88

McCALLUM TESTING LABORATORIES, INC.

USING INSPIRE AS AN UPFRONT DESIGN, OPTIMIZATION & SIMULATION TOOL FOR EXISITNG MANUAL GEARBOX COMPONENTS

Precision at work Purpose-built Piling Rigs

Completion Solutions Inc.

CHAPTER 140 DRIVEWAYS

Boring Unit Sitework Systems Attachment

Positioning Aerial Apparatus By: Joe Kroboth, III, PE, CFPS Emergency Services Instructor MFRI, Western Maryland Regional Office

Economic Impact of Derated Climb on Large Commercial Engines

Study Report. McCredie-Overton Transmission Line Right-of-Way Analysis. City of Columbia, Missouri. prepared for the (S49)

Table Existing Traffic Conditions for Arterial Segments along Construction Access Route. Daily

Billing Code: P. Petitions for Modification of Application of Existing Mandatory Safety Standards

Transcription:

North American Society for Trenchless Technology (NASTT) No-Dig Show 2011 Washington, D.C. March 27-31, 2011 Paper D-2-04 TACOMA PUMP STATION 4103 FORCE MAIN HDD PROJECT: A SHORT BORE WITH TALL CHALLENGES Christopher Price 1, Matthew Pease 1, Kimberly Kelsey 2, and David Koberstein 3 1 Staheli Trenchless Consultants, Bothell, Washington 2 Brown and Caldwell, Seattle, Washington 3 City of Tacoma Public Works, Tacoma, Washington ABSTRACT: The City of Tacoma has determined that an existing sanitary sewer force main that extends beneath the Hylebos Waterway requires replacement. The 1,060-foot Horizontal Directional Drill (HDD) crossing is located in the Port of Tacoma industrial area. An 18-inch HDPE pipeline is being installed in conjunction with upgrades to an existing pump station in order to achieve the desired design flows. This paper examines the challenges associated with the project design and construction. Challenges included very soft soils with blow counts of zero in the vicinity of the entry location, wooden piles within the waterway, and the presence of poorly graded gravel in sections of the bore. Additionally, the design incorporates steep entry and exit angles, conductor casings at entry and exit, and challenging site constraints requiring vertical and horizontal curves in order to achieve the fixed entry and exit points for the existing pipe system. 1. INTRODUCTION This paper presents a discussion of the design considerations and solutions along with the construction of an 18-inch HDPE sanitary sewer force main pipeline beneath the Hylebos Waterway. The project is located in the highly industrialized Port of Tacoma area with large volumes of heavy trucking and shipping traffic. Horizontal Directional Drilling (HDD) was selected as the preferred installation method due to the low construction impacts to surrounding businesses and the cost effectiveness of the method. Although the 1,060-foot HDD crossing is considered relatively short by comparison to the record breaking HDD lengths of today, this paper examines the challenges unique to the project along with solutions developed during the design and throughout construction. Paper D-2-04 - 1

TACOMA Figure 1. Vicinity map and project location (Brown and Caldwell, 2010). 2. DESIGN CONSIDERATIONS Physical constrains of the project during the design phase consisted of restricted construction areas both at the entry and exit locations, critical sensitive pump station structures including a wet and dry well, utilities both above and below ground, and impacts to the surrounding businesses. ENTRY EXIT Heavy Equipment Traffic Dry and Wet Well Overhead Power Figure 2. Plan View of the Hylebos Channel HDD Crossing EXIT Point Dry Well Pumps Wet Well Existing Sewer ENTRY Point Figure 3. Exit Site View (left) and Entry Site View (right) with HDD alignment as dashed line. Paper D-2-04 - 2

The physical constraints were compounded by the geotechnical considerations which together shaped the design. Soils with low to zero blow counts were encountered to depths of approximately thirty feet below ground surface on both sides of the channel. Gravels intermixed with sand were also found throughout the upper 30 foot which pose a concern for bore hole stability or potential collapse. Geotechnical exploration revealed the groundwater at a depth of five feet below grade (Brown and Caldwell, 2010). The existence of abandoned wooden piles of unknown location and depth played a role in selecting bore alignment and geometry as well, with likely pile locations avoided altogether. The fill material near the surface consisted of gravels, sands, large amounts of wood and fully intact railroad crossties from an abandoned and buried rail line at the exit location. 3. DESIGN SOLUTIONS Steep entry and exit angles of 24 and 18 degrees, respectively, were chosen to quickly advance the bore path through the less desirable materials in order to limit the geotechnical risks presented by the soft soils and open graded gravels discovered in the geotechnical exploration. Due to the limited setback distances of the entry and exit locations from the channel, the steep angles also allowed the rapid development of ground cover, or depth, vital in preventing inadvertent returns along the planned alignment in addition to a decreased likelihood of encountering abandoned piles anticipated in the area. Conductor casings were incorporated into the design for both the entry and exit locations at lengths of 86-feet and 124-feet respectively. The casing was chosen as a means to contain the pressurized drilling fluid and to ensure borehole stability as the bore alignment at entry passed within 5-feet adjacent to the existing operational wet and dry wells of the City of Tacoma s existing wastewater pumping station. @ 248 Figure 4. Contractor s Approved Entry Side Profile with Wet Well Pump and Conductor Casings. The exit side conductor casing was utilized to mitigate the risk of inadvertent returns and moreover, to ensure the integrity of the bore and prevent catastrophic settlement due to over excavation in poor soils beneath the adjacent roadway and business driveway. Large volumes of daily traffic consisting of oversized heavy equipment deliveries cross the bore alignment within feet of the exit location where ground cover is at a minimum. Paper D-2-04 - 3

Figure 5. Exit Side Profile with Conductor Casing. The bore consisted of both vertical and horizontal curves chosen to adequately distance the alignment from the previously discussed critical structures, utilities, and obstacles, while achieving the proper pipe pullback angle to the pipe fusion and layout area. This ultimately proved beneficial during construction since the Contractor only had to contend with lofting the product pipe vertically due to the steep exit angle but required little adjustment laterally to align the fused pipe string with the bore. 4. CONSTRUCTION The Contractor elected to use a 900,000lb HDD rig for the crossing with the engineer s calculated maximum pullback force of 55,000lb (Staheli, K., Bennett, R.D., O Donnell, H., Hurley, T., 1998). This choice necessitated moving the entry point closer to the channel to accommodate the increased rig length and prevent the elevated end of the rig from encroaching on the nearby existing overhead power lines. A request to decrease the entry angle by four degrees was also approved to aid in distancing the rig from the overhead power during rig setup and drilling operation. The decreased entry angle shifted the bore closer to the below grade dry well, increasing risk to the structure that the Contractor offset with additional conductor casing (HDD Good Practices Guidelines, 2008). Overhead Power Lines Figure 7. Drill rig setup at 20 degrees. Paper D-2-04 - 4

Additional entry conductor casing was installed by the Contractor in order to reach the minimum depth of the bore required by the plans due to the decreased entry angle of 20 degrees. Figure 6. Installation of the 86LF entry conductor casing at 20 degrees. To provide additional protection of the adjacent wet and dry wells during drilling, the Contractor elected to install 120 feet of wash-over pipe, i.e., a smaller 12-inch diameter casing than that of the conductor casing, extending through and beyond the conductor casing by 40 additional feet. The wash-over pipe was used while drilling the pilot and removed when reaming the bore. Figure 8. Installation of 120 feet of 12-inch wash over casing. The Contractor extended the surface-laid TruTrack coil as far into the channel as possible during the low tide in order to increase the tracking distance during the pilot bore. Cement blocks were used to fix the coil wire along the channel floor. A second coil was placed at the exit side in a similar manner to track the pilot bore once across the channel. Due to the shortened crossing length from moving the entry point, along with the increased length of steel casing, the drill operator had only a few drill pipe to establish a heading before exceeding the limits of the entry side tracking coil. This proved inadequate on the first crossing attempt as the pilot bore was off both line and grade by 20-feet and 3-feet respectively, when reaching the exit side tracking coil. The operator was able to pull back and attempt a new heading that was successful on the second attempt and the pilot bore was completed within tolerance at the planned exit location. Paper D-2-04 - 5

EXIT Site Coil Wire (Falling Tide) Figure 9. Wire coil extending into the Hylebos Channel. Steel plates were placed directly over the bore where the alignment crossed beneath the adjacent roadway and business driveway at the exit site as added protection to the heavy traffic traversing the shallowest portion of the alignment. This measure was performed in lieu of installing the exit side conductor casing prior to completing the pilot bore. Once the pilot bore was completed, the Contractor installed the exit side conductor casing as planned and the steel plates were removed. Inadvertent returns were observed approximately 20-feet from the exit location when drilling the last 30-feet of the pilot bore. This was due to the Contractor drilling all but the last 30-feet of the pilot bore on one day, and then completing the bore the next morning after preparing the exit excavation. Increased fluid pressures were required to resume drilling the remaining 30-feet on the second day. The hydrofracture was minor and immediately contained and cleaned. Steel Road Plates EXIT Point Existing Sewer Figure 10. Exit Site with Existing Sewer and Steel Plates Over the Bore. One reaming pass was utilized from the pilot bore diameter of 9-7/8 inches to the final reamed diameter of 26 inches utilizing a fly cutter reamer that proved efficient through the ground conditions encountered. Given that this style of reamer could not be easily pulled into the entry side casing without damage, the reamer was placed on the drill string at the exit and back-reamed to the entry side conductor casing. A barrel swab was then placed on the drill string at the entry and the fly cutter with the newly placed barrel was pushed back through the bore along with the tail string. Paper D-2-04 - 6

The fly cutter was then removed from the drill string and the barrel swab was pulled back through the bore for a final swab and proof of the bore. Figure 11. Fly cutter and barrel assembly used for back reaming. Pullback of the product pipe was completed expediently once preparations for buoyancy control were made. Buoyancy control was accomplished with a 2-inch PVC tremie pipe run inside the length of the product pipe and adding water while pulling back the product pipe. The short exit side layout area for the product pipe necessitated two segments of pipe and a fuse mid pullback. After stopping to fuse the pipe and allowing time for it to cool, the pullback resumed without any appreciable increase in pullback forces and the remaining product pipe was installed successfully in less than an hour. The total duration for the pullback was approximately 5 hours, including the 3 hours required to fuse and cool the HDPE pipe. The total pullback force was approximately 22,000 lbs and varied only slightly over the duration of the pullback. 5. CONCLUSION This project presented challenges during the design that were overcome by weighing the available engineering solutions and tailoring these to balance the project risks with constructability issues. Although the channel crossing was relatively short, this fact magnified specific challenges that would constitute minor concern for lengthier crossings. Bore alignment and geometry were critically important given the geotechnical conditions and the site characteristics that constrained the design. The Contractor also brought solutions to issues that arose during construction and through active and thoughtful communication with the Engineer and Owner challenges during the drilling were resolved and construction progressed and culminated in the completion of a successful project. 6. REFERENCES ASTM F 1962 (2005). Standard Guide for Use of Maxi-Horizontal Directional Drilling for Placement of Polyethylene Pipe or Conduit Under Obstacles, Including River Crossings, American Society for Testing and Materials, 2005. Brown and Caldwell, City of Tacoma Department of Public Works, (2010). City of Tacoma Department of Public Works Pump Station 4103 Force Main Contract Drawings and Specifications. HDD Industry Consortium, Horizontal Directional Drilling Good Practices Guidelines, 2008, 2004, 300pp. Staheli, K., Bennett, R.D., O Donnell, H., Hurley, T., (1998). Installation of Pipelines Beneath Levees Using Horizontal Directional Drilling (HDD), CPAR-GL-98-1, April 1998. Paper D-2-04 - 7