Geomagnetic Disturbance Power System Study in Maine

Similar documents
THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Georgia Transmission Corporation Georgia Systems Operations Corporation

Interconnection Feasibility Study Report GIP-222-FEAS-R3

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Session 10 NERC Interconnection Requirements

Gateway South Transmission Project

Reactive Power Compensation for Solar Power Plants. Andy Leon IEEE PES Chicago Chapter December 12 th, 2018

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-369-FEAS-R1

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Project #148. Generation Interconnection System Impact Study Report

Generator Interconnection System Impact Study For

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

EPRI HVDC Research. Gary Sibilant, EPRI. August 30, 2011

Stability Study for the Mt. Olive Hartburg 500 kv Line

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

Interconnection System Impact Study Final Report February 19, 2018

Terry Blackwell Page 1 of 5. Education North Carolina State University BS, Electrical Engineering Power Systems emphasis

Interconnection Feasibility Study Report GIP-157-FEAS-R2

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

Interconnection System Impact Study Report Request # GI

ECEN 667 Power System Stability Lecture 19: Load Models

PSNH INTERCONNECTION REQUEST

Experience on Technical Solutions for Grid Integration of Offshore Windfarms

Electric Power Research Institute, USA 2 ABB, USA

Grid Operations & Planning R&D Area Overview

Transient Stability Analysis Tool (TSAT) Update April 11, Hongming Zhang EMS Network Applications Manager

CHAPTER 3 TRANSIENT STABILITY ENHANCEMENT IN A REAL TIME SYSTEM USING STATCOM

TransWest Express Project

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

ATTACHMENT Y STUDY REPORT

Project #94. Generation Interconnection System Impact Study Report Revision

Q217 Generator Interconnection Project

Rocky Mountain Power Exhibit RMP (RAV-4SD) Docket No Witness: Rick A. Vail BEFORE THE PUBLIC SERVICE COMMISSION OF THE STATE OF UTAH

Feasibility Study Report

Dynamic Scheduling NI A F S NI S. Where:

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Voltage Sag Mitigation in IEEE 6 Bus System by using STATCOM and UPFC

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Feasibility Study Report

100 MW Wind Generation Project

Technical & Regulatory Standards Development

Large Scale Solar Integration

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Power System Economics and Market Modeling

Simulated Switching Transients in the External Grid of Walney Offshore Wind Farm

Analysis of Grid Connected Solar Farm in ETAP Software

An Introduction to Completing a NERC PRC Study

Feasibility Study for the Q MW Solar Project

Targeted Application of STATCOM Technology in the Distribution Zone

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA

Q95 Vicksburg 69kV. System Impact Study. APS Contract No Arizona Public Service Company Transmission Planning.

THE TRES AMIGAS PROJECT

15 Nelson-Marlborough Regional Plan

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

Power System Economics and Market Modeling

ABB POWER SYSTEMS CONSULTING

2015 Minnesota Power Systems Conference Managing Bakken Oil Field Load Growth From a Transmission Perspective

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

PES Cook Islands KEMA Grid Study Final Report

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by:

15 Nelson-Marlborough Regional Plan

Interconnection. Maine Public Utilities Commission

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Transmission Planning using Production Cost Simulation & Power Flow Analysis

El Paso Electric Company

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Western Area Power Administration Sierra Nevada Region

Appendix D Black Hills Project Summary

Midway/Monument Area TTC Study

CHAPTER I INTRODUCTION

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

SPS Planning Criteria and Study Methodology

TRANSMISSION LOSS MINIMIZATION USING ADVANCED UNIFIED POWER FLOW CONTROLLER (UPFC)

ABB Inc. Public Service Company of New Mexico Broadview Full Buildout Affected PSLF Study

Composite Load Model Sensitivity Study

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

New 115 kv Disconnect Switches at Bloomsburg MTS

STATE OF MINNESOTA OFFICE OF ADMINISTRATIVE HEARINGS FOR THE PUBLIC UTILITIES COMMISSION PUC DOCKET NO. E002/TL OAH DOCKET NO.

Sheffield-Highgate Export Interface SHEI. VSPC Quarterly Meeting October 18, 2017

Renewable Energy Systems 14

CHAPTER 6 DESIGN AND DEVELOPMENT OF DOUBLE WINDING INDUCTION GENERATOR

Advanced Protective Relay Training

Transcription:

Geomagnetic Disturbance Power System Study in Maine Maine IEEE Joint Chapter PES/IAS Technical Meeting 7/22/2015 Presenter: Justin Michlig, PE

2

3

Overview NERC/FERC updates State of Maine Legislative updates Geomagnetic Disturbance (GMD) Theory GMD Power Flow data requirements Results of CMP GMD analysis Future Steps

NERC Standard TPL-007-1 Applicability: Planning Coordinator Transmission Planner Transmission Owner Generator Owner Scope of facilities: Facilities operated or connected at 200+ kv Specifically transformers with a 200+ kv grounded winding are included

NERC Standard TPL-007-1 High Level Summary: R1: Maintain Models for analysis R2: Run GMD Assessments every 5 years on peak and Off-Peak models Including reactive power device and other transmission facility contingences R3: If performance not acceptable, create Corrective Action Plan(s) R4: Must have criteria for acceptable steady state voltage R5: Coordinate responsibilities between PC and TP R6: Distribute assessment to neighbors R7: TO&GO to assess thermal impact to transformers R8: TO&GO to provide thermal assessment to PC and TP

NERC/FERC Updates FERC/NERC GMD Rulemaking activity: FERC Order 779: May 16, 2013 Directs NERC to develop GMD standards for Operations and Planning FERC Process started with Oct. 18, 2012 Notice of Proposed Rulemaking (NOPR) NERC GMD Taskforce scope started in 2010 FERC Order 797: June 19, 2014 Approves EOP-010-1 Enforceable Date April 1, 2015 May 14, 2015 NOPR to approve TPL-007-1 In addition send it back to NERC for edits Increase field strength to be tested Shorten implementation time if possible Enforceable date: TBD

Maine GMD Progress MPUC Docket: 2013-00415 Started with LD 131 via resolve Report delivered to PUC & passed onto Legislature Jan 20, 2014 This report gathered pertinent documentation on past GMD and EMP events highlighting potential mitigation technologies. No tools available to quantify system impacts Continued in 2014 after PUC request to acquire software and perform analysis Results delivered to PUC end of 2014 and passed to Legislature 2014 Maine GMD/EMP Impacts Assessment LD 1363 Efforts to require installation of mitigation technologies and liability transferred to utilities Did not pass

GMD Planning Study Model the Transmission system Calculate the Geomagnetic Storm s Geoelectric intensity to be modeled Run a Geomagnetic Induced Current (GIC) DC power flow calculation Incorporate the DC results into an AC power flow simulation Apply contingencies and review for system deficiencies

DC GIC Theory - Voltages induced on the power system are calculated by geographic location and field intensity. - DC Resistance form lines, transformers, shunts, and other devices are utilized to construct the impedance network Figure 1 from K. Patil, Modeling and Evaluation of Geomagnetic Storms in the Electric Power System, DIGRE 2014. Used with Permission.

DC GIC Theory - GMD event casts a Geoelectric Field over the power system creating a DC current flow in the AC transmission system - Greatest impact while the Geoelectric Field is parallel to transmission line N Sub 1 Sub 2 DC Induced Voltage 1 0.8 0.6 0.4 0.2 0-40 -0.2 60 160 260 360-0.4-0.6-0.8-1 270 DC Induced Voltage 1 0.75 0.5 0.25 0 0 180 90

GIC Specific Data Data required in addition to traditional Steady State model: Geolocation (ex. 44.3125690,-69.8173740) Ground Grid Impedance Transformer * DC Resistance K Factor [4] Winding Connections Transformer core type NERC Benchmark Geoelectric Field intensity calculation* Other devices with low DC resistance Path *Additional detail on following slide

Transformer DC Data Auto Transformer Data Sheet Examples High Side Winding tested to ground in mω. Chose a phase or average value in Ω. Model value =.276 Ω. 1.031 Old Test reports are not easy to read and may be reported in total resistance. Divide total impedance by 3. Model value =.344 Ω

Transformer K Factor The K Factor Relates Effective GIC through the transformer to var consumption/additional losses K-Factor @ 500 kv K-Factor @ 345 kv Three Phase Shell form 0.33 0.228 Single Phase (Separate Cores) 1.18 0.814 Three Phase Three Legs 0.29 0.2 Three Phase Five Legs 0.66 0.455 Example 345 kv Grounded Auto Mvar Loss Calculation K factor Effective GIC Mvar.2 100 A 20 Three Phase Seven Legs 0.66 0.455

NERC Reference GMD peak = 8 (V/km) peak = FERC NOPR directs NERC to update value Benchmark geoelectric field magnitude at System location Factor adjustment for geomagnetic latitude Factor adjustment for regional earth conductivity model

Lookup β Condensed Geoelectric Field Scaling Factors USGS Earth Model (β) AK1A 0.56 AK1B 0.56 AP2 0.82 FL1 0.74 NE1 0.81 PT1 1.17 SL1 0.53 BOU 0.28 FBK 0.56 PRU 0.21 Physiographic Regions of the Continental United States Figure 6 from NERC GIC Application Guide 2013

Calculation of α.001 e 0.115 L L Geomagnetic North Latitude 47 28 N 56.95 N.6979 Geophysical Geomagnetic α 42 58 N 52.46 N.4169

Example Benchmark Field Calculation peak = 8 (V/km) FERC NOPR directs NERC to update value.001 e 0.115 L L Geomagnetic North Latitude 0.81 2015 Geomagnetic conversion Latitude α Benchmark Field in Maine Northern ME 56.95N.6979 4.53 V/km Southern ME 52.46N.4169 2.7 V/km What does this calculation give me again? Electric Field to use in GIC power flow calculation Conservative value used in Maine 2014 study

Maine GMD Study Specifics Scope: Includes a GIC model within the Maine transmission system (a few buses into NB and NH) Focuses on 200+ kv Analyze Geoelectric fields from 4.53 V/km to 29 V/km in Maine Discuss system improvements and cost: Possible replacement of electromechanical relays Possible upgrades to capacitor banks to improve 5 min recovery time

2014 CMP GMD Analysis Review the transmission system per NERC GMD Planning Guide Establish the worst orientation of the Geoelectric Field Report the Effective GIC flows in transformers Report system impact to voltages

GMD Field Orientation 0.996 PU Voltage vs. Geoelectric Field Orientation Shunt Switching_Chester Offline w/ Step-up out 0.994 0.992 PU Voltage 0.99 0.988 0.986 Entire Study Area State of Maine 0.984 0.982 0 50 100 150 200 250 300 350 Degrees

GMD Field Orientation PU Voltage vs. Geoelectric Field Orientation Shunt Switching_Chester Offline w/ Step-up out 321 325329 337341345349353357 1 0.996 333 0.994 0.992 0.99 309 313317 305 0.988 301 0.986 297 293 0.984 289 0.982 285 281 0.98 277 0.978 273 0.976 269 265 261 257 253 249 245 241 237 233 229 225 221 217 213 209 205 201197 193189185 181 5 9 13 17 21 25 29 3337 41 4549 53 57 61 65 69 73 77 81 85 89 93 97 101 105 109 113 117 121 125 129 133 137 141 145 149 153 157 161 165 177173169 Entire Study Area State of maine

Results from GMD field orientation effects match the orientation of the transmission in Maine. 23

CMP Results Mvar 90 80 70 60 50 40 30 20 10 Transformer Mvar Consumption vs. Geoelectric Field Strength @ 88 Chester SVC 18/345 kv Yarmouth GSU 22/345 kv #4 Keene Road GSU 115/345 kv Orrington 345/115 kv #1 Orrington 345/115 kv #2 South Gorham 345/115 kv #1 South Gorham 345/115 kv #2 Mason 345/115 kv #1 Macguire Road 345/115 #1 Keene Road 345/115 kv #1 Coopers Mill 345/115 kv #3 Surowiec 345/115 kv #1 0 0 5 10 15 20 25 30 35 V/km Geoelectric Field Albion Road 345/115 #1 Larrabe Rd 345/115 #1

CMP Results 1.04 Maine 345 kv Transmission Voltage vs Geoelectic Field Strength @ 88 1.035 V PU 1.03 1.025 1.02 1.015 1.01 1.005 CHESTER SVC ORRINGTON COOPERS MILL RAVEN FARM MAINE YANKEE SUROWIEC YARMOUTH SOUTH GORHAM BUXTON MASON ALBION ROAD LARRABEE RD MAGUIRE ROAD KEENE ROAD 1 0 5 10 15 20 25 30 35 V/km Geoelectric Field

CMP Results Reactive Reserves vs. Geoelectric Field 1800 1600 1400 1200 1000 Mvar 800 Online Capacitive Reactive Devices 600 400 Total Installed Capacitive Reactive Devices 200 0 0 5 10 15 20 25 30 35 V/km *Excludes Generator Reactive Capability, which is a significant source of reactive power

GMD Field Orientation Effective GIC A/phase for Maine transformers Degree Amp Max 4.53 V/km 14 V/km 20 V/km 23.5 V/km 29 V/km NERC 1 in 100 year Benchmark Study team assumed 1 in 50 year event Study team assumed 1 in 100 year event Study team assumed 1 in 200 year event Study team assumed 1 in 500 year event 2 winding delta - wye Chester SVC 18/345 kv 162 76 235 336 395 487 Yarmouth GSU 22/345 kv #4 144 49 152 217 255 315 2 winding Auto Xfmrs Keene Road GSU 115/345 kv 160 32 98 140 165 204 Orrington 345/115 kv #1 64 4 14 20 23 29 Orrington 345/115 kv #2 64 4 12 17 20 25 South Gorham 345/115 kv #1[1] 60 1 3 5 6 7 South Gorham 345/115 kv #2 60 12 36 51 60 74 Mason 345/115 kv #1 111 6 20 28 33 41 Macguire Road 345/115 #1 30 27 83 120 139 172 Keene Road 345/115 kv #1 160 6 18 26 31 38 Coopers Mill 345/115 kv #3 30 35 109 155 182 225 3 winding Auto xfmrs Surowiec 345/115 kv #1 38 17 52 75 88 108 Albion Road 345/115 #1 30 60 186 266 313 386 Larrabee Rd 345/115 #1 135 48 149 213 250 308

CMP Results Transformer Effective GIC using Each transformers most Impactful Geoelectric Field Angle 600 500 Chester SVC 18/345 kv Yarmouth GSU 22/345 kv #4 Keene Road GSU 115/345 kv Orrington 345/115 kv #1 Effective GIC A/Phase 400 300 200 Orrington 345/115 kv #2 South Gorham 345/115 kv #1 South Gorham 345/115 kv #2 Mason 345/115 kv #1 Macguire Road 345/115 #1 Keene Road 345/115 kv #1 Coopers Mill 345/115 kv #3 100 Surowiec 345/115 kv #1 0 0 5 10 15 20 25 30 35 Geoelectric Field Magnitude V/km Albion Road 345/115 #1 Larrabe Rd 345/115 #1

CMP Assumptions Change Results PU Voltage vs. Geoelectric Field Orientation @ 15V/km 353357 1.01 337 341345349 325 329333 1.005 313 317321 309 1 305 301 0.995 297 293 289 0.99 285 281 0.985 277 273 0.98 269 265 261 257 253 249 245 241 237 233 229 225 221 217 213 209 205 201 197 193 189185 1 181 5 9 13 17 21 25 29 33 37 41 4549 53 57 61 65 69 73 77 81 85 89 93 97 101 105 109 113 117 121 125 129 133 137 141 145 149 153 157 161 177173169 165 Entire Study Area State of maine

CMP Assumptions Change Results PU Voltage vs. Geoelectric Field Orientation @ 15V/km_No Shunt Switching_Chester Offline w/ Step-up in-service 321 325329 353357 0.995 333 337341345349 0.99 0.985 309 313317 305 0.98 301 297 0.975 293 289 0.97 285 281 0.965 277 273 0.96 269 265 261 257 253 249 245 241 237 233 229 225 221 217 213 209 205 201197 193189 185 1 181 5 9 13 17 21 25 29 3337 41 4549 53 57 61 65 69 73 77 81 85 89 93 97 101 105 109 113 117 121 125 129 133 137 141 145 149 153 157 161 165 169 173 177 Entire Study Area State of maine

Maine Analysis Results Voltage performance of the Maine transmission system was very good Worst GMD storm angle ~88 degrees Each transformer had different angles which excited them the most Only Chester above 75 A/phase GIC recommended for thermal screening a 8 V/km benchmark event At 29 V/km field tested 8 transformers above thermal screening threshold

Not Covered But Important Harmonic Analysis May cause unintended tripping, but newer relays can filter No great method found to analyze GMD Harmonic effects

Maine Analysis Prospective Monitoring Chester Neutral current since 1991 GIC has been present and the power system has had voltage changes due to it Peak GIC neutral flow of 98 A (~33A/phase) Simulations of 75 A/phase during benchmark event @ 8 V/km Capacitors, SVC Filters, and potential UPS functionality issue during events No customer outages No associated customer equipment damage reported

Maine Analysis Next Steps Reassemble previous study team Perform recommended thermal assessments of transformers Scope GMD monitoring for installation

Questions? 35

References [1] NERC GMD Project Page TPL-007-1 GMD Task Force Planning Guide Benchmark Geomagnetic Disturbance Event Description Thermal Screening Criterion White Paper Transformer Thermal Impact Assessment White Paper Application Guide [2] Geomagnetic Location Calculator - http://wdc.kugi.kyoto-u.ac.jp/igrf/gggm/ [3] R. Horton, D. Boteler, T.J. Overbye, R. Pirjola, and R.C. Dugan, A Test Case for the Calculation of Geomagnetically Induced Currents, IEEE Transactions on Power Delivery, Vol. 27, No. 4, October 2012, pages 2368-2373. [4] X. Dong, Y. Liu, J. G. Kappenman, Comparative Analysis of Exciting Current Harmonics and Reactive Power Consumption from GIC Saturated Transformers, Proceedings IEEE, 2001, pages 318-322. [5] K. Patil, Modeling and Evaluation of Geomagnetic Storms in the Electric Power System, C4-306, CIGRE, 2014