EC Forum on Model Approaches to Distribution Pricing. June 2009

Similar documents
AURORA ENERGY LTD NOTIFICATION OF ELECTRICITY DELIVERY PRICES

Group 3: Pricing from 1 April 2018 and load management

Powerco Limited Pricing Guide 2015 ANNUAL REPORT 2015

Appendix 6.7 January 23, 2015 SURPLUS ENERGY PROGRAM PROPOSED TERMS AND CONDITIONS

Demand Charges to Deal With Net Energy Metering: Key Considerations

Electricity Transmission network charging

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Statement of Expected Price Trends

Marlborough Lines Limited Electricity Line Charges from 1 April 2014

Aurora Energy Limited. Network Connection Requirements (NS5.1)

United Energy Tariff Criteria (effective 1 January 2019)

MYPD3 tariff restructuring plan use-of-system charges. Brochure

Annual Distribution Pricing Proposal For 1 July 2018 to 30 June 2019 Overview

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-27 CUSTOMER GENERATION PRICE PLAN FOR RESIDENTIAL SERVICE

Tariffs Charges 2017/2018

Relative Power Factor Correction costs

Introduction to Charging: Which Parties Pay Which Charges?

Price Schedule for the Northpower Electricity Distribution Network

Cost Reflective Tariffs

New Rate Structure Encouraging greater efficiency

Customers with solar PV units in NSW producing and consuming electricity

Electricity Network pricing schedule. Module 15 Effective April 1, 2011 for Electricity line charges. Version

For the purpose of this Schedule the following words and phrases shall have the same meanings as assigned to them herein:

Cost of Service and Rates. Marty Blake The Prime Group, LLC

City of Lethbridge ELECTRIC UTILITY. Electric Distribution Tariff Rate Schedule

UK Power Networks Use of System Charging Methodology

APRIL 2011 FINAL RATES

Tariff Design Issues: Approaches for Recovering Grid and System Costs

THE NARRAGANSETT ELECTRIC COMPANY LARGE DEMAND RATE (G-32) RETAIL DELIVERY SERVICE

10% SIGNPOSTING THE FUTURE INCREASE. Implications of evolving technology for the pricing of New Zealand s distribution services

a) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load

Connecting your home or small business generation

National Grid. Narragansett Electric Company INVESTIGATION AS TO THE PROPRIETY OF COMPLIANCE TARIFF CHANGES. 2 nd Amended Compliance Filing

energy price fact sheet - electricity

216B.164 COGENERATION AND SMALL POWER PRODUCTION.

POWER NETWORKS Electricity Network Tariffs and Charges

Customers with solar PV units in NSW producing and consuming electricity

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-21 PRICE PLAN FOR RESIDENTIAL SUPER PEAK TIME-OF-USE SERVICE

The Electricity Grid Scottish Power Energy Networks Overview

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Reforming the TAC and Retail Transmission Rates. Robert Levin California Public Utilities Commission Energy Division August 29, 2017

Michigan Renewable Energy Case Study

JEA Distributed Generation Policy Effective April 1, 2018

ELECTRIC POWER BOARD OF THE METROPOLITAN GOVERNMENT OF NASHVILLE AND DAVIDSON COUNTY. TIME-OF-USE GENERAL POWER RATE--SCHEDULE TGSA (November 2018)

Introduction to Cost of Service Studies and Rate Design

Designing retail electricity tariffs for a successful Energy Union

Utility Rate Design for Solar PV Customers

Net Metering & Compensation Seminar

For the purpose of this Schedule the following words and phrases shall have the same meanings as assigned to them herein:

SSE Guide to the Energy Industry. Guide

The financial impact of residential rooftop PV on local governments in South Africa

Analysis of Impact of Mass Implementation of DER. Richard Fowler Adam Toth, PE Jeff Mueller, PE

ACTEWAGL DISTRIBUTION SCHEDULE OF ELECTRICITY NETWORK CHARGES

NEWFOUNDLAND AND LABRADOR BOARD OF COMMISSIONERS OF PUBLIC UTILITIES AN ORDER OF THE BOARD NO. P.U. 17(2017)

Decision on Merced Irrigation District Transition Agreement

Draft Guideline for the connection of smallscale inverter based distributed generation. EEA Asset Management Forum 22 June 2016 Dr Richard Strahan

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

Advanced Rate Design. Smart Electric Power Alliance Grid Evolution Summit. David Littell Principal The Regulatory Assistance Project (RAP)

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

Utility Distribution Planning 101

DG system integration in distribution networks. The transition from passive to active grids

Charging Delivery Body. 29 th January 2018

OVERVIEW OF UNIFORM TRANSMISSION RATES

RATE ORDER 2015 UNIFORM ELECTRICITY TRANSMISSION RATES January 08, 2015

Pricing Guide A guide to Orion s pricing for 2017/18

Load profiling for balance settlement, demand response and smart metering in Finland

Indicative Gas Transportation Charges from 1 April 2012 for East of England, London, North West and West Midlands Distribution Networks

Street Address. City-Village-Township

Connecting your business diesel generation

Tariff cover sheets reflecting all rates approved for April 1 in Dockets 4218 (ISR) and 4226 (Reconciliation Filing).

Zero Emission Bus Impact on Infrastructure

Wind Interconnection and Net-Metering in MA. Tim Roughan - National Grid Joe Feraci - NStar

White Paper. P13008 Net-metering concept for Small Scale Embedded Generation in South Africa. prepared for

Basic tariff guiding principles

Smart Non-Residential Rate Design

Methodology of Cost Allocation

Level 7 Post Graduate Diploma in Engineering Power System Economics and Planning

Powerco Limited. Electricity Price Schedule. Effective 1 April 2011

SERVICE CLASSIFICATION NO. 7. Also optional for: This option is not available to Service Classification No. 2 customers, effective December 3, 2002.

Power Supply Cost Recovery

Monitoring report. Solar feed-in tariff report

3 Existing National Grid

Agricultural Service Rate Schedule AG

Utility Operator Model

Docket 50-ER-108 Algoma Utilities. Final Form Rate and Rule Tariff Sheets Amendment 78. Filed By: Public Service Commission of Wisconsin

January 1, 2018 RATE SCHEDULE. 395 Southgate Drive, Guelph, ON N1G 4Y1. Billing: Admin: Fax:

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

Understanding Impacts of Distributed Solar Generation on Cost Recovery and Rates IAMU Annual Energy Conference Preconference Seminar

Ratemaking Trends in the Utility Industry. Jeff Wernert The Prime Group, LLC

Electric Rate Design Introductory Principles Residential Rate Design

Merger of the generator interconnection processes of Valley Electric and the ISO;

Making electricity billing fair

Incentives and Opportunities Signalled by Transmission Charges in Scotland. Iain Wright 03 September 2018

Impacts and integration of PV in LV networks

GLOBAL ELECTRICITY PRICES

Distribution Code Part 4: Distributed Generation Requirements

Agenda. Industry Rate Trends Summary of Financial Targets Cost of Service Information. Valuation of Solar

ENMAX POWER CORPORATION ( EPC ) DISTRIBUTION TARIFF RATE SCHEDULE

A Guide to the medium General Service. BC Hydro Last Updated: February 24, 2012

Manitoba Hydro Customer Consultation. Industrial Rates Workshop

Transcription:

EC Forum on Model Approaches to Distribution Pricing June 2009

Session Explain Aurora UoS Pricing and fit with the Retail Model Approach Discuss how we transitioned a Demand tariff structure to Aurora standard structure Some interim comments on aspects of the consultation paper.

Opening Comments Whilst Aurora pricing is based upon the Retail model, Aurora believes in choice and there should be model approaches Aurora not aware of any evidence which says Retail provides better outcomes compared to Wholesale for asset utilisation

Aurora Pricing Objectives Obtain sufficient revenue to Meet transmission costs Meet distribution operation & maintenance costs Comply with statutory requirements on public safety, environmental matters & quality of supply Provide an appropriate return on funds

Aurora Pricing Objectives (2) Efficiency Promote efficient investment in and operation of network by correctly signaling fixed and variable costs of delivery - improve network utilisation New or increased connections need to be economic based on future income from the new connection plus others need to make contributions towards the use of upstream assets. Fairness Recover costs fairly with respect to all users of network

Standard Aurora Pricing Methodology Has evolved over the years ESANZ Guide to Derivation of Line Charges MED Electricity Disclosure Guidelines PAWG work Publicly disclosed in Aurora document Use of System Pricing Methodology available from Aurora website at www.auroraenergy.co.nz

Pricing Areas 3 Pricing areas based upon the markedly different cost drivers using the ratios below Distribution - $ORC/MW of demand Transmission - $/MW of demand Dunedin GXPs average transmission cost low distribution cost Frankton GXP hi transmission cost medium dist cost Clyde & Cromwell GXPs average transmission cost very high distribution cost

Most Network Costs are Asset Specific Costs are collected and allocated to the main groups of network assets and by area - Dunedin, Central (Frankton and Cromwell/Clyde) Subtransmission 66 & 33 kv Lines & Cables Zone Substations 33/11 kv or 33/6.6 kv HV Lines & Cables 11 kv or 6.6 kv Distribution Substations LV Lines & Cables

Load Groups Network connection points are placed in load capacity groups eg Unmetered 1 kva, 8-15 kva, 16-149 kva, 150-249 kva, 250 to 499 kva, 500 to 2499 kva, 2500+ kva, Street Lighting. Costs are allocated to load groups on basis of use of different assets and on each groups mix of anytime maximum demand and congestion period demand in line with model eg HV consumers do not pay for LV costs

Distribution Components of Delivery Charges Fixed $ Capacity $ / kva Transformer kva, Circuit Breaker setting or Fuse size kva - Km Product of Capacity and km from connection to Transpower grid exit point for large connections with capacity > 150 kva Congestion Period Demand kw - $ / kw Average kw at peak network loads during dynamic congestion period Dedicated asset charge $ may apply

Connection Charges Transmission Costs (approx 19% of delivery costs) Recover Transpower costs relating to grid exit point assets dedicated spur lines Interconnection Charges Recover Transpower core grid costs using top 100 half hour demands Recover avoided interconnection charges paid to embedded generators

Transmission Components of Delivery Charges Capacity $ / kva based on transformer kva, circuit breaker or connection fuse size Congestion Period Demand kw - $ / kw based on average kw at peak network loads same dynamic congestion period as distribution

Standard Structure in both Dunedin & Central Otago A) Non Domestic and Non Standard Domestic Applies to all connections except Std Domestic Five main load groups L1 to L5 6,000 connections Central Otago 6,700 connections Dunedin Charge structure components - Fixed, Capacity kva, kva-km, Congestion Period kw (posted prices with dynamic congestion period) as discussed earlier

Standard Structure in both Dunedin & B) Standard Domestic Central Applies to connection with capacity L1 (8 or 15 kva) 21,600 connections Central Otago 46,400 connections Dunedin Charge Structure to met Low Fixed Charge Regs - Low fixed charge per ICP - Variable c/kwh charge based on register contents provided by the retailer metering configuration at ICP

A.1 STANDARD DOMESTIC CONNECTIONS Registry Code Distribution Per Annum Transmission Fixed Annual Charge (15 kva) Fixed Annual Charge (8 kva) (note 6) Uncontrolled Variable Charges SHSD15 $54.73 SHSD8 $15.00 Tariff Code ( /kwh) General Purpose All day Summer 010S 4.92 1.10 General Purpose All day Winter 010W 5.40 3.62 Controlled Variable Charges General Purpose + 16 hour water heat General Purpose + 16 hour water heat ( /kwh) All day Summer 017S 2.69 1.33 All day Winter 017W 3.96 2.07 Night + 3 hours 11 hour service 024 1.46 0.50 Night rate 8 hour service 028 0.56 0.00

Combination of capacity charge and congestion period demand charge structure provides strong incentives Size capacity (the size of the electrical pipe) to meet anytime maximum demand Meter as much load off peak as possible balance against creating anytime peaks Spread consumption over as many hours as possible this improves the load factor of the installation and connections with a better than average load factor will have lower energy delivery costs on a cents per kwh basis

Connections with capacity greater than 150 kva These connections generally large (ie sophisticated) enough for consumer to look after themselves. They make the choice when they wish to be controlled and what load will be controlled rather than be controlled by network. Dynamic Congestion Period Demand Signal Likely to occur on Cold winter days 8am 12 pm & 5pm to 10.00 pm May to September with most activity June & July Total hours on 150 to 250 per year

Dynamic Congestion Period Demand Signal Signal sent via ripple control - isolated relay contact can be used by consumer to operate a warning device input into a load management system or BMS directly control deferrable load start up a standby generator Email and SMS messages of status sent to consumers status on website See http://www.auroraenergy.co.nz/content/demandmanage ment.php for more detail on congestion periods

Typical Congestion Period Hours

Under 150 kva capacity connections Off peak retailer tariff options currently available for calculation of lower effective CPD kw 8 hour service uncontrolled or controlled loads - kwh discount = 100% any night rate metered load 11 hour service controlled loads - kwh discount = 75% normally nightstore heating but can be any load night hours plus 3 hour day boost 13 hour service controlled loads - kwh discount = 60% normally under floor heating but can be any load night hours plus 3 two hour day boosts 14 hour service controlled loads kwh discount = 100% Irrigation control regime but can be any load night hours plus ON 11am to 3pm and on at 9pm 16 hour service controlled loads - kwh discount = 50% normally water heating but can be any load target maximum of 8 hours control normally less than 4 hours

Transition of Price Structure Used in transitioning the Central Electric pricing to Aurora standard capacity pricing CE Structures HHR metered Demand tariff Distribution Fixed annual charge (small) Annual Demand charge $/kw per mth demand reset monthly Variable c/kwh Transmission Annual Demand charge $/kw per month Demand reset annually after winter Profile metered small fixed charge - variable c/kwh

Why Change Inconsistent with Dunedin area pricing added complexity to our processes Existing structure recovered insufficient from some seasonal loads such as irrigators and fruit packing houses, holiday homes, large Demand structure over recovered for some connections, frequent requests for dispensations for single high peaks in a month Revenue stream was less predictable being so dependent on variable kwh Low load factor 50% due to seasonal high loads for skiing and July school holidays

Process Steps Taken From 1999 began process of improving the information base of phases/ fuse size/ transformer size supplying each ICP Concentrated on high usage ICPs Grandfathered some small kwh usage multiphase ICPs as if they were single phase Installed two rate meters on ICPs above 150kVA if not HHR metered to collect congestion period usage during congestion period. (Fewer issues with meter compliance 2000) Added congestion period ripple channel to operate when managing load in Central Otago areas

Process Steps Taken 2001 Introduced capacity based pricing structure for new connections in Central Otago 2001 and 2002 consulted with retailers re transition process for existing connections, kept improving the information data base All agreed that transition should be over 2 or 3 years. Aurora settled on a period of 3 years

Transition Structure Standard capacity based pricing modified as follows commenced 2003 Full fixed charge and congestion period demand charge 1/3 rd of standard capacity charge price 1/3 rd of standard kva-km charge price Balance of revenue requirement via variable c/kwh Second year 2004 moved to 2/3rds capacity price and smaller balance requirement c/kwh Third year 2005 standard capacity based prices

EC Model Approach Distribution Pricing some interim comments High level principles generally OK but some devil in the detail Insufficient time to analyse fully some of the detail When Distributors consider changing pricing structures they significant time to gather data and update information base on which to structure new pricing

EC Model Approach Distribution Pricing some interim comments Aurora does not believe that an ICP that is HHR metered compared to a ICP that is profile metered should be on a different pricing structure Capacity based load groups provide a better basis. Eg HHR metered connection using the LV network (say 3ph 60 amp) should not be on the same pricing as a HHR 1000kVA connection kva km distance component is economically rational especially for large loads overcomes artificial regions based on a set km distance but restrictions around urban / rural cross subsidy for lower loads Is the low fixed charge regime achieving its targeted objectives

EC Model Approach Distribution Pricing some interim comments Transmission cost recovery Lower South Island region Year 0 Top 100 Demands in Winter Year 1 Top 100 Demands April & May 08 no load control Year 2 Top 100 demands Nov 08 (to date) no load control Operation of Tiwai smelter (60%) of regional load has huge impact on regional load - Result - difficult to predict when regional loads will peak EC model pricing approach recommendations for recovery of transmission costs will result in price volatility to the consumer due to the different seasonal movements.