Y9. GEH2.3: FREEDM Cost Benefit Analysis based on Detailed Utility Circuit Models

Similar documents
An Integrated Grid Path for Solar. Thomas Key, EPRI Senior Technical Executive. ISES Webinar. April 22, 2016

Using Hosting Capacity Methodology to Develop Simplified Screens for New Solar PV Interconnections

Distribution System DER Hosting Capacity IEEE34 PV

Impact of Distributed Generation and Storage on Zero Net Energy (ZNE)

RESILIENT SOLAR CASE STUDY: SUNY New Paltz NYPA Integrated Grid Pilot

The FREEDM System: components, main functions, system control

STOCHASTIC ESTIMATION OF FEEDER-SPECIFIC DISTRIBUTED GENERATION (DG) HOSTING CAPACITY

Research Needs for Grid Modernization

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Targeted Application of STATCOM Technology in the Distribution Zone

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Residential Smart-Grid Distributed Resources

Radha Krisha (Pos. Doc.), M. A. Awal, Siyuan Chen, Hao Tu, Likhita Ravuri

Batteries and Electrification R&D

PV Grid Integration Research in the U.S.

Field Verification and Data Analysis of High PV Penetration Impacts on Distribution Systems

Model-Based Integrated High Penetration Renewables Planning and Control Analysis

Renewable Grid Integration Research in the U.S.

Energy Association of Pennsylvania Meeting. PECO Energy Utility Integrated Concord Microgrid Project. March 21, 2017

DYNAMIC LOAD FLOW STUDIES OF DISTRIBUTION FEEDS IN THE SAN JOAQUIN VALLEY REGION

Integrated System Models Graph Trace Analysis Distributed Engineering Workstation

Implementation of Distributed Generation

Distribution System Analysis for Smart Grid

Utility Distribution Planning 101

The Role of Electricity Storage on the Grid each location requires different requirements

EPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010

Analysis of Impact of Mass Implementation of DER. Richard Fowler Adam Toth, PE Jeff Mueller, PE

International Approaches for an Integrated Grid

Hardware Testing of Photovoltaic Inverter Loss of Mains Protection Performance

Electric Vehicles Coordinated vs Uncoordinated Charging Impacts on Distribution Systems Performance

GRID MODERNIZATION INITIATIVE PEER REVIEW

Energy Systems and Storage Integration R&D at NREL

Electric Vehicle Grid Integration Research Analyzing PHEV Impacts on Distribution Transformers in Hawaii

EV - Smart Grid Integration. March 14, 2012

TECHNICAL STRATEGIC CHOICE: POWER ELECTRONIC SYSTEMS AND APPLICATIONS

Impacts of Fast Charging of Electric Buses on Electrical Distribution Systems

Grid Impact of Electric Vehicles with Secondary Control Reserve Capability

DEMONSTRATION OF ESSENTIAL RELIABILITY SERVICES BY A 300-MW SOLAR PV POWER PLANT

American Electric Power s Energy Storage Deployments

OPTIMIZING COMMERCIAL SOLAR

Contents. 1. Introduction. 2. Construction. 3. Operation Plan

PES Cook Islands KEMA Grid Study Final Report

Distribution Line Transformer / Secondary

Assessing the Potential Role of Large-Scale PV Generation and Electric Vehicles in Future Low Carbon Electricity Industries

Assessing Feeder Hosting Capacity for Distributed Generation Integration

B-4: Reducing Peak Demand through Distributed Grid Edge Control

BROCHURE. End-to-end microgrid solutions From consulting and advisory services to design and implementation

SCE's Experience Distribution Volt/VAR Control:

Distribution Capacity Impacts of Plug In Electric Vehicles. Chris Punt, P.E. MIPSYCON 2014

Electric vehicles and heat pumps providing flexibility to facilitate integration of large amounts of intermittent renewables

ANCILLARY SERVICES WITH VRE (VARIABLE RENEWABLE ENERGY): FOCUS PV

USAID Distributed PV Building Blocks

IEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning

a) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

DRAFT. Guidelines on Power quality & safety issues in usage of roof-top solar pv system CENTRAL ELECTRICITY AUTHORITY

Electrification of Domestic Transport

Southern Company Interconnection Process. Dexter Lewis Research Engineer Research and Technology Management

ALBERTA SOLAR MARKET OUTLOOK. CanSIA Solar West 10 May 2017

Underpinning Research Power Electronics in Distribution Networks

Energy Storage and Impact on Renewable Power Grid Integration Nate Blair

Sensitivity Analysis of Photovoltaic Hosting Capacity of Distribution Circuits

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011

Technology Roadmap for zzzzzzzzz Grid Automation

Solar Plus: A Holistic Approach to Distributed Solar PV Eric O'Shaughnessy, Kristen Ardani, Dylan Cutler, Robert Margolis

MEMORANDUM. Assessment of CPAU s Distribution System to Integrate Distributed Energy Resources

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

New Trends in Grid Integration of Solar Photovoltaic Energy Systems

PV and opportunistic electric vehicle charging in a Swedish distribution grid

Impact of High Photo-Voltaic Penetration on Distribution Systems. Design Document

National Grid New Energy Solutions (NES)

PNM/EPRI Smart Grid Demonstration. Photovoltaics through Grid Automation, Energy Storage and Demand Response

Study Results Review For BPU EV Working Group January 21, 2018

Clark W Gellings, P.E. Fellow CEPSI 2014 October 29, Electric Power Research Institute, Inc. All rights reserved.

Solar PV and Storage Overview

Distributed Energy Resources: How Do Utilities Accommodate Customer Owned Generation?

Analysis of the Volt/VAr Control Scheme for Smart Distribution Feeders

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Dynamic Control of Grid Assets

Conservation Voltage Reduction (CVR) Phillip Anderson P.E. Engineering Project Leader Research, Development & Deployment

Presentation to the PJM NEMSTF Interconnection Issues. Interconnecting Solar Projects on the PSE&G Distribution System

i-pcgrid Workshop 2017

UNC-Charlotte's Power Engineering Teaching lab

Workshop on Grid Integration of Variable Renewable Energy: Part 1

Solar Inverters. No. 6, R. A. De Mel Mawatha, Colombo

Electric Transportation and Energy Storage

2015 Grid of the Future Symposium

Using Opal-RT Real-Time Simulation and HIL System in Power and Energy Systems Research

Dynamic Control of Grid Assets

Enhancing the Voltage Profile in Distribution System with 40GW of Solar PV rooftop in Indian grid by 2022: A review

PV inverters in a High PV Penetration scenario Challenges and opportunities for smart technologies

DOE/VT/EPRI Hi-Pen PV Project, Phase III

Evaluating Batteries: Deployment, Integration and Market Drivers

INTEGRATING PLUG-IN- ELECTRIC VEHICLES WITH THE DISTRIBUTION SYSTEM

Next-generation SCADA and Control Technologies for Large-scale Use of Photovoltaic Generation on Electric Power Grid

C PER. Center for Advanced Power Engineering Research C PER

Testing Energy Storage Systems: From EVs to Utility Grid

A day in the Life... stories

TECHNICAL IMPACTS OF ELECTRIC VEHICLES CHARGING ON AN ITALIAN DISTRIBUTION NETWORK

Transcription:

Y9. GEH2.3: FREEDM Cost Benefit Analysis based on Detailed Utility Circuit Models Project Leader: Faculty: Students: M. Baran David Lubkeman Lisha Sun, Fanjing Guo I. Project Goals The goal of this task is to enhance the Cost-Benefit Analysis for the FREEDM System based on the feedback from Y8 SVT. The efforts in the following: i. Identify the technologies/approaches that are alternative to FREEDM system, especially from the capability of integrating high penetration DER on a distribution system. ii. Conduct a Cost-Benefit Analysis for the FREEDM system by comparing the alternative technology/ approach to FREEDM system. II. Role in Support of Strategic Plan This Task is part of the cost-benefit analysis project. It has been undertaken by the engineering analysis group which focuses on the system analysis to determine system benefits. The other group -economic analysis group- aims to monetize the benefits and thus make an economics assessment of the system. III. Fundamental Research, Technological Barriers and Methodologies The main challenge in this task involves estimation of capabilities and the benefits of the new alternative technologies considered. To address these challenges we solicited help from industry members and worked collaboratively with the other team which focused on the economic assessment of the cases considered. IV. Achievements This is the third year of this project, and this year the work has focused on the two main sub-tasks that have been identified based on the feedback from NSF SVT. The work builds on the accomplishments made during the last year. Main accomplishments made this year include the following: 4.1 Unreported Work: FREEDM System benefits using representative feeders from industry Three actual distribution feeders have been obtained from a member utility in order to demonstrate the capabilities of the FREEDM system and quantify the benefits. These circuits are 12.47kV circuits and Table 1 shows their main characteristics. By using the circuit models and the yearly load data (15 min resolution) provided by the utility, quasi-static time series power flow analysis has been performed in OpenDSS [1]. All the following results were obtained through these yearly simulations. First, PV hosting capacities for these circuits are estimated. These cases define our base cases. Then the full FREEDM deployment case and the partial FREEDM deployment case are analyzed to determine and quantify the benefits of the FREEDM system.

Table 1 Characteristics of Three Utility Circuits Circuit A Circuit B Circuit C Circuit Length (Backbone) 3 miles 4.3 miles 3.8 miles Number of Voltage Regulators 0 0 2 Number of Capacitors 4 4 4 Number of transformers (Total) 309 298 456 Number of Customers (Total) 1240 1511 1448 Efficiency 99% 99% 98% Peak kw 6800 kw 7427 kw 7900 kw PV hosting capacity PV hosting capacity is evaluated for two cases: partial PV deployment where PVs are clustered at certain parts of the feeder, and the full PV deployment where each node has PV installation. The main impact that limited the PV deployment on these circuits were voltage limit violations, especially the overvoltage violation during light load conditions. PV penetration levels are increased to see when the circuits are having overvoltage issues. The results are shown in Table 2. It can be seen from the table that Circuit C starts having overvoltage issues in lower penetration levels than the others. Also, note that the partial deployment case has a lower PV hosting capacity than full deployment case. Table 2 PV Hosting Capacity Circuit # Full PV deployment Partial PV deployment PV penetration % Duration (yr.) PV penetration % Duration (yr.) Circuit A 70% 0.23% 32% 0.14% Circuit B 70% 0.24% 46% 0.32% Circuit C 45% 0.15% 33% 0.15% Benefits of FREEDM System Deployment As the results in Table indices, the circuits considered have good PV hosting capability, and hence a full FREEDM deployment on these circuits offers only marginal benefits. Indeed our simulations indicate that due to the relatively larger loss of solid state transformer (SST), the system loss actually increases by deploying SST at every node. Furthermore the early FREEDM deployment will be more likely on circuits with partial PV deployment. Hence, we focused on this case partial FREEDM system deployment. The study involved increasing the PV penetration to around 50% for each circuit and then SSTs are added to fix overvoltage issues. The energy and peak demand savings are used to calculate system benefits due to higher penetration of PV. Then, more SSTs are added to allow for more effective conservation voltage reduction (CVR) on the circuits. The additional energy and peak demand savings by CVR is counted as FREEDM benefits. Table 3 summarizes these benefits. It can be seen from the table that the increased PV penetration leads to reduction in energy and line losses. However, it does not reduce the peak demand as much, as in this case the peak demand usually happens during the early morning or night when there is not too much PV output. As the table shows, there is small increase in transformer losses due to mainly relatively larger SST loss compared to the traditional transformer. The results also show the effectiveness of CVR, as there is a considerable drop in system peak kw and energy losses. CVR also help lower the total yearly energy demand. These results clearly illustrate that: (i) FREEDM systems facilitates higher PV penetration on these circuits by mitigating the overvoltage issues, and (ii) FREEDM system improves system efficiency by lowering both the peak demand as well as the power loss on these circuits.

#SST Added Overvoltage reduction (% time/yr.) Table 3 Partial FREEDM Deployment Results CVR ΔV Circuit A 32 2.70% 3.8V Circuit B 16 0.40% 4V Circuit C 58 1.32% 4V Diff Δ Energy MWh-yr. Peak kw Losses MWh-yr. Line XFMR Total DER -1187-2 -1 16 15 CVR -534-146 1-32 -32 Total% -1,721-147 0-17 -17 DER -969 0-4 0-5 CVR -483-92 0-21 -20 Total % -1,452-92 -4-21 -25 DER -1344-16 -18 16-2 CVR -559-149 3-36 -33 Total % -1,903-165 -15-20 -35 4.2 Accomplishments in Year 9 1) Alternative Technologies to FREEDM System Our search on the technologies that can be alternative to FREEDM system indicated that there are two technologies that can be adopted for partial PV deployment cases: Edge-of-grid devices and smart inverters. These technologies are selected because they have the capability to provide voltage mitigation on partial PV deployment cases, similar to that of a FREEDM deployment considered last year and reported above. Basic comparison of these technologies is as follow: In FREEDM system, the SST is the main device that provides voltage mitigation on a distribution stem. The key functionalities of SST are voltage regulation on load side and reactive power compensation on the source side. SST also has a DC port which facilitates DER connection (like PV, battery), and serving DC loads directly. Edge-of-grid device is a power electronics based equipment which is designed to be connected to the low voltage side of the traditional transformer. These devices provides services like voltage regulation and reactive power compensation. Smart inverter is the inverter designed to connect PV to the utility on the low voltage side. The newly emerging smart inverters have Volt-Var control capability by adjusting the reactive power at the point of interconnection. There are only a few products that are currently available with these functionalities. In our study, we have selected the GRIDCOSYSTEM s In-line power regulator (IPR) as the sample edge-of-grid device, and SMA Sunny Tripower inverter (STI) as the smart inverter. IPR is a low voltage, single phase device that combines utility-scale power electronics and advanced control algorithms [4]. IPR can be used for residential, commercial utility scale renewable integration, and/or for Conservation Voltage Reduction (CVR) to improve energy efficiency and for fault detection, isolation, and restoration (FDIR) [4]. Table 5 summarizes the comparison of SST, IPR and STI. The information for IPR and SMA smart inverter are based on the published product datasheet [4, 5] that are available online. In order to do the comparison, Gridco IPR is assumed to have the same power rating ranges as SST.

Table 4: Comparison of FREEDM SST, Gridco System IPR and SMA STI Product FREEDM SST Gridco Systems IPR-50 SMA Smart Inverter Power Rating 0-100 kva Input Voltage 3.6 kv Vac Output Voltage 120Vac 200Vdc Voltage Regulation ± 10% 50 kva 240 Vac 240 Vac ± 10% 12 kw - 30 kw 1000 Vdc (max) 480/277 Vac 244V-305V VAR Compensation 20% of Rating (lead. or lag.) 10% of Rating (lead. or lag.) 0-1 power factor (ind. or cap.) Efficiency DC Port 95% Yes 99% No 98.3% No 2) Estimating the benefits of alternative technologies In order to determine the capabilities and to quantify the benefits that IPR and SMA inverter, simulations similar to the ones performed for the FREEDM system have been repeated for the two technologies considered. The case used is the partial deployment scenario on Circuit A. Table 6 shows the three cases simulated. (a) Base Case (b) Higher PV (c) Higher PV plus CVR Table 5: Test Cases Circuit A + 32% PV Circuit A + 43% PV + Devices Circuit A + 43% PV + Devices +CVR The PV deployment for the base case is the same as in FREEDM base case. For IPR alternative, simulations indicated that 32 IPRs are needed to accommodate the same level of PV penetration and same level of conservation voltage reduction benefits on the test feeder. For the SMA smart inverter case, it is assumed all the PVs in the cluster are equipped with the smart inverters. In this case, 133 STIs are used to accommodate 43% PV penetration. In this case, STIs allows for only 1V voltage reduction for CVR. For simulations, IPR and STI were modeled in OpenDSS. Models are setup based on the datasheets [4, 5] published online by the vendors. Figure 3 shows the modelling structures for each type of device. IPR is modeled using the voltage regulator block in OpenDSS. The losses are adjusted based on data the datasheet. STI is simulated using volt-var mode for PV inverters in OpenDSS. This model adjusts the reactive power to maintain the voltage within range of 0.95 to 1.05 per unit. As the figure shows both IPR and STI are connected to the traditional transformer (XFMR). Note also that PVs need inverter to connect to IPR. Figure 1 OpenDSS Modeling Structure for Three Technologies (a) SST (b) Gridco IPR (c) Smart Inverter

Table 7 shows the simulation results for three technologies considered as compared to the base case. In the table, DER savings indicate the difference between case (b) and the base case (a), and CVR savings is the difference between case (c) and case (b). It can be seen from the table that SST (FREEDM system) provides the highest benefits in energy reduction and peak demand savings. The result for IPR is quite close to that of the SST. SMA offers smaller savings in energy and peak demand. This is mainly due to the way STI provides voltage support, and also because of its limited ability in reducing voltages for CVR - it can only allow for 1V reduction, whereas both SST and IPR can do about 4V reduction. Table 6 Simulation Results for SST and Alternatives # Diff Δ Energy MWh-yr. Peak kw Losses MWh-yr Line XFMR Total DER -1,187-2 -1 16 15 SST to CVR -534-146 1-32 -32 Base Total -1,721-147 0-17 -17 Total % -8.7% -2.2% 0.00% -0.08% -0.09% IPR to Base STI to Base DER -1,110-3 -1 1 0 CVR -534-146 1-32 -32 Total -1,644-149 0-31 -31 Total % -8.3% -2.2% 0.00% -0.16% -0.16% DER -1,082-11 5 25 30 CVR -153-36 -3-19 -22 Total -1,236-46 2 6 8 Total % -6.2% -0.7% 0.01% 0.03% 0.04% 3) FREEDM Benefits through DC port of SST SST is designed to have a DC port to facilitate the direct connection of customer PV system to the utility. DC port also facilitates future residential homes with DC load, storage and electrical vehicle. The benefits through this additional feature have been investigated in this task as well. One of the main benefits is due to the potential energy that could be saved by switching the traditional AC residential house to a DC/AC hybrid house or a purely DC house. Some earlier work has done by Lawrence Berkeley National Laboratory (LBNL) [6]. The report estimates that a net-metered PV residence could save 5% energy if the house has no storage, and 14% if the house has storage. Our initial work involved setting up a spread sheet tool in order to calculate the net energy savings for different residential house scenarios. Figure 4 shows different power delivery systems considered: conventional AC house, DC house, FREEDM hybrid house, and FREEDM DC house. The voltage level in the DC house is 380V for high power DC load like cooling or heating load and 24V DC for the low power DC load. The voltage levels of 380V and 24V are based on the emerging standards for data center or commercial DC systems developed by Emerge Alliance [7]. The load data used in the analysis are the residential hourly load profile for Raleigh/Durham area published by US department of Energy on OpenEI [8]. The irradiance data from solar prospector by National Renewable Energy Laboratory (NREL) [9] is used to calculate the rooftop PV power output for a year. The spreadsheet tool developed based on the used provided results similar to that of LBNL s report. By using these prototype house models, total savings have been estimated for the partial FREEDM deployment case on circuit A where 32 SST are deployed. The total energy savings for the total load connected through the 32 SST is around 160 MWh for a year (using 5% savings per house). The total avoided energy cost from these savings is around $5000. More detailed analysis will be conducted to further estimate the benefits for different cases considered.

Figure 2. House Structures (a) Ac House (b) DC House (c) FREEDM Hybrid House (d) FREEDM ALL DC House Some of the benefits that will be considered are the following: Customer benefits from energy saving by switching from AC to DC appliance. Customer saving by avoiding the cost of DC/AC power conversion equipment for DC appliances. Utility may have a tariff for providing DC service since customer gets benefits. Utility may offer SST+PV/Battery service package. Benefits in using SST to serve electric vehicles (EV) in case the EV get more and more popular. New Zero Energy Green House with FREEDM all DC structure References [1] OpenDSS Program, Distribution Systems Simulator, [Online]. Available through SourceForge.net, http://sourceforge.net/projects/electricdss. [2] L. Sun, J. Thomas, S. Singh, D. Li, M. Baran, D. Lubkeman, J. DeCarolis, A. Queiroz, L. White, S. Watts, Cost-Benefit Assessment Challenges for a Smart Distribution System: A Case Study, accepted by PESGM, Chicago, 2017. [3] Electric Energy Efficiency Potential for Pennsylvania, Final Report, Prepared for Pennsylvania Public Utility Commission, 2012. [4] Gridco systems IPR-50, [Online]. Available https://gridcosystems.com/products/lv-ipr-50-pole/ [5] SMA Sunny Tripower TL-US datasheet, [Online]. Available http://www.sma- america.com/products/solarinverters/sunny-tripower-12000tl-us-15000tl-us-20000tl-us-24000tl-us- 30000tl-us.html#Overview-137604

[6] Garbesi, Karina. (2012). Optimizing Energy Savings from Direct-DC in U.S. Residential Buildings. Lawrence Berkeley National Laboratory: Lawrence Berkeley National Laboratory. LBNL Paper LBNL- 5193E. Retrieved from: http://escholarship.org/uc/item/66c8n9s8 [7] Emerge Alliance, http://www.emergealliance.org/standards/occupiedspace/standardfaqs.aspx [8] Commercial and Residential Hourly Load Profiles for all TMY3 Locations in the United States, U.S. Department of Energy, Open Data Catalog, Office of Energy Efficiency and Renewable Energy, http://en.openei.org/doe-opendata/dataset/commercial-and-residential-hourly-load-profiles-for-alltmy3-locations-in-the-united-states [9] Solar Datasets, Solar Prospector, National Renewable Energy Laboratory (NREL) https://energydemo.github.io/solardatasets/show.html?title_id=solar-prospector