Transparent Armor Cost Benefit Study

Similar documents
Transparent Armor Cost Benefit Study

UNCLASSIFIED: Dist A. Approved for public release. GVPM Track & Suspension Overview Mr. Jason Alef & Mr. Geoff Bossio 11 Aug 2011

TARDEC Technology Integration

Robot Drive Motor Characterization Test Plan

Energy Storage Requirements & Challenges For Ground Vehicles

TARDEC Robotics. Dr. Greg Hudas UNCLASSIFIED: Dist A. Approved for public release

Alternative Fuels: FT SPK and HRJ for Military Use

GM-TARDEC Autonomous Safety Collaboration Meeting

UNCLASSIFIED: Dist A. Approved for public release. GVPM Energy Storage Overview Mr. David Skalny & Dr. Laurence Toomey 10 August 2011

UNCLASSIFIED: DIST A. APPROVED FOR PUBLIC RELEASE. ARMY GREATEST INVENTIONS CY 2009 PROGRAM MRAP Overhead Wire Mitigation (OWM) Kit

Tank Automotive Research, Development and Engineering Command (TARDEC) Overview

Energy Storage Commonality Military vs. Commercial Trucks

U.S. Army s Ground Vehicle Energy Storage R&D Programs & Goals

UNCLASSIFIED: Dist A. Approved for public release. GVPM Non-primary Power Systems Overview Kevin Centeck and Darin Kowalski 10 Aug 2011

UNCLASSIFIED: Distribution A. Approved for Public Release TACOM Case # 21906, 26 May Vehicle Electronics and Architecture

Feeding the Fleet. GreenGov Washington D.C. October 31, 2011

2011 NDIA GROUND VEHICLE SYSTEMS ENGINEERING AND TECHNOLOGY SYMPOSIUM POWER AND MOBILITY (P&M) MINI-SYMPOSIUM AUGUST 9-11 DEARBORN, MICHIGAN

Servicing Hawker Vehicle Batteries with Standard Battery Charging and Test Equipment

TARDEC OVERVIEW. Tank Automotive Research, Development and Engineering Center. APTAC Spring Conference Detroit 27 March, 2007

TARDEC Hybrid Electric Program Last Decade

DSCC Annual Tire Conference CATL UPDATE. March 24, 2011 UNCLASSIFIED: Dist A. Approved for public release

TARDEC --- TECHNICAL REPORT ---

Vehicle Systems Engineering and Integration Activities - Phase 3

EXPLORATORY DISCUSSIONS - PRE DECISIONAL

AFRL-RX-TY-TM

EVALUATING VOLTAGE REGULATION COMPLIANCE OF MIL-PRF-GCS600A(ARMY) FOR VEHICLE ON-BOARD GENERATORS AND ASSESSING OVERALL VEHICLE BUS COMPLIANCE

FTTS Utility Vehicle UV2 Concept Review FTTS UV2 Support Variant

US ARMY POWER OVERVIEW

Automatic Air Collision Avoidance System. Auto-ACAS. Mark A. Skoog Dryden Flight Research Center - NASA. AutoACAS. Dryden Flight Research Center

Evaluation of Single Common Powertrain Lubricant (SCPL) Candidates for Fuel Consumption Benefits in Military Equipment

Joint Light Tactical Vehicle Power Requirements

INTELLIGENT ENERGY MANAGEMENT IN A TWO POWER-BUS VEHICLE SYSTEM. DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.

Vehicle Systems Engineering and Integration Activities - Phase 4

An Advanced Fuel Filter

REMOTE MINE AREA CLEARANCE EQUIPMENT (MACE) C-130 LOAD CELL TEST DATA

Up-Coming Diesel Fuel and Exhaust Emissions Regulations For Mobile Sources. Parminder Khabra RDECOM-TARDEC TACOM LCMC March 22, 2006 JSEM

Center for Ground Vehicle Development and Integration

FINAL REPORT FOR THE C-130 RAMP TEST #3 OF A HYDREMA MINE CLEARING VEHICLE

U.S. Army/CERDEC's Portable Fuel Cell Evaluation and Field Testing 2011 Fuel Cell Seminar & Expo Orlando, FL 31 Oct 2011

Helicopter Dynamic Components Project. Presented at: HCAT Meeting January 2006

Evaluation of SpectroVisc Q3000 for Viscosity Determination

High efficiency variable speed versatile power air conditioning system for military vehicles

Does V50 Depend on Armor Mass?

Presented by Mr. Greg Kilchenstein OSD, Maintenance. 29August 2012

Dual Use Ground Vehicle Condition-Based Maintenance Project B

Monolithically Integrated Micro Flapping Vehicles

BALANCE OF PERFORMANCE PARAMETERS FOR SURVIVABILITY AND MOBILITY IN THE DEMONSTRATOR FOR NOVEL DESIGN (DFND) VEHICLE CONCEPTS

LESSONS LEARNED WHILE MEASURING FUEL SYSTEM DIFFERENTIAL PRESSURE MARK HEATON AIR FORCE FLIGHT TEST CENTER EDWARDS AFB, CA 10 MAY 2011

Open & Evolutive UAV Architecture

Multilevel Vehicle Design: Fuel Economy, Mobility and Safety Considerations, Part B

Cadmium Repair Alternatives on High-Strength Steel January 25, 2006 Hilton San Diego Resort 1775 East Mission Bay Drive San Diego, CA 92109

US Army Non - Human Factor Helicopter Mishap Findings and Recommendations. Major Robert Kent, USAF, MC, SFS

Fuel Efficient ground vehicle Demonstrator (FED) Vision

Robust Fault Diagnosis in Electric Drives Using Machine Learning

INLINE MONITORING OF FREE WATER AND PARTICULATE CONTAMINATION OF JET A FUEL

REPORT DOCUMENTATION PAGE

Program Overview. Chris Mocnik Robotic Vehicle Control Architecture for FCS ATO Manager U.S. Army RDECOM TARDEC

Application of Airbag Technology for Vehicle Protection

ITC-Germany Visit. Chuck Coutteau, Associate Director Ground Vehicle Power and Mobility Overview 10 November 2011

U.S. Army s Ground Vehicle Energy Storage R&D Programs & Goals

F100 ENGINE NACELLE FIRE FIGHTING TEST MOCKUP DRAWINGS

HIGH REPETITION RATE CHARGING A MARX TYPE GENERATOR *

Development of Man Portable Auxiliary Power Unit using Advanced Large Format Lithium-Ion Cells

Navy Coalescence Test on Petroleum F-76 Fuel with Infineum R655 Lubricity Improver at 300 ppm

Hydro-Piezoelectricity: A Renewable Energy Source For Autonomous Underwater Vehicles

IMPACT OF FRICTION REDUCTION TECHNOLOGIES ON FUEL ECONOMY FOR GROUND VEHICLES G. R. Fenske, R. A. Erck, O. O. Ajayi, A. Masoner, and A. S.

Navy Coalescence Test on Camelina HRJ5 Fuel

Predator B: The Multi-Role UAV

Power Technology Branch Army Power Division US Army RDECOM CERDEC C2D Fort Belvoir, Virginia

Hybrid Components: Motors and Power Electronics

SIO Shipyard Representative Bi-Weekly Progress Report

Evaluation of Digital Refractometers for Field Determination of FSII Concentration in JP-5 Fuel

TRANSIENT MAGNETIC FLUX DENSITY MEASUREMENT RESULTS ON A FUSELAGE-LIKE TEST SETUP AND INVESTIGATION OF THE EFFECTS OF APERTURES

GVSET Power & Energy Preview Mr. Chuck Coutteau Associate Director (Acting) Ground Vehicle Power & Mobility 19 August 2009

DEVELOPMENT OF COMPACT VARIABLE- VOLTAGE, BI-DIRECTIONAL 100KW DC-DC CONVERTER

Research Development and Engineering Command TARDEC/NAC

Power Distribution System for a Small Unmanned Rotorcraft

Predator Program Office

Developing a Methodology for the Evaluation of Hybrid Vehicle Thermal Management Systems

Materials for Ground Platform Survivability

NDCEE National Defense Center for Energy and Environment

Additives to Increase Fuel Heat Sink Capacity

Portable Fluid Analyzer

DESULFURIZATION OF LOGISTIC FUELS FOR FUEL CELL APUs

Membrane Wing Aerodynamics for µav Applications

Tank-Automotive Research, Development, and Engineering Center

Additional Transit Bus Life Cycle Cost Scenarios Based on Current and Future Fuel Prices

Joint Oil Analysis Program Spectrometer Standards VHG Labs Inc. Qualification Report For D19-0, D3-100 and D12-XXX Series Standards

Methylene Chloride Alternative HAP-Free Chemical Paint Strippers at Anniston Army Depot

Crew integration & Automation Testbed and Robotic Follower Programs

Linear Algebraic Modeling of Power Flow in the HMPT500-3 Transmission

FCS Technology Insertion and Transition

NoFoam Unit Installation, Evaluation and Operations Manual

Quarterly Progress Report

Blast Pendulum Testing of Milliken Tegris Panels

REPORT DOCUMENTATION PAGE

A GENERAL PURPOSE VEHICLE POWERTRAIN MODELING AND SIMULATION SOFTWARE - VPSET

Endurance Testing of Redesigned Tab Spring for MI-RAMS System

Presented by: Dr. Richard Gerth U.S. Army National Automotive Center (NAC) Tank Automotive Research Development and Engineering Center

Report No. D November 24, Live Fire Testing of Light Tactical Wheeled Vehicles was Effective for the Portions Completed

Transcription:

Transparent Armor Cost Benefit Study Lisa Prokurat Franks RDECOM (TARDEC) and David Holm and Rick Barnak TACOM Cost & Systems Analysis Directorate Distribution A. Approved for Public Release; distribution unlimited. 10/30/2006 1/15 Committed to Excellence Supporting America s Warfighters

Report Documentation Page Form Approved OMB No. 0704-0188 Public reporting burden for the collection of information is estimated to average 1 hour per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Washington Headquarters Services, Directorate for Information Operations and Reports, 1215 Jefferson Davis Highway, Suite 1204, Arlington VA 22202-4302. Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to a penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. 1. REPORT DATE 22 JAN 2007 2. REPORT TYPE N/A 3. DATES COVERED - 4. TITLE AND SUBTITLE Transparent Armor Cost Benefit Study 5a. CONTRACT NUMBER 5b. GRANT NUMBER 5c. PROGRAM ELEMENT NUMBER 6. AUTHOR(S) Prokurat Franks, Lisa; Holm, David; Barnak, Rick 5d. PROJECT NUMBER 5e. TASK NUMBER 5f. WORK UNIT NUMBER 7. PERFORMING ORGANIZATION NAME(S) AND ADDRESS(ES) US ARMY TARDEC 6501 E 11 Mile Road Warren, MI 48397-5000 8. PERFORMING ORGANIZATION REPORT NUMBER 16571 RC 9. SPONSORING/MONITORING AGENCY NAME(S) AND ADDRESS(ES) 10. SPONSOR/MONITOR S ACRONYM(S) TARDEC TARDEC 12. DISTRIBUTION/AVAILABILITY STATEMENT Approved for public release, distribution unlimited 13. SUPPLEMENTARY NOTES The original document contains color images. 14. ABSTRACT 15. SUBJECT TERMS 11. SPONSOR/MONITOR S REPORT NUMBER(S) 16571 RC 16. SECURITY CLASSIFICATION OF: 17. LIMITATION OF ABSTRACT SAR a. REPORT unclassified b. ABSTRACT unclassified c. THIS PAGE unclassified 18. NUMBER OF PAGES 15 19a. NAME OF RESPONSIBLE PERSON Standard Form 298 (Rev. 8-98) Prescribed by ANSI Std Z39-18

Agenda Background Current Demand Data Government Cost/Benefit Analysis Timeline 10/30/2006 2/14

Equipping Our Soldiers in Iraq and Afghanistan Up-Armored HMMWVs (M1114s) 12000 10000 8000 6000 4000 2000 0 2003 2005 2006 10/30/2006 3/14

Early OIF Recent History 2004-2005 - GPK Curb Wt: 10,300lbs GVW: 12,100lbs 2006 Iraqi Pope Glass A jerry-rigged glass cocoon of (3) 2- inch thick bulletproof windshields welded around the top of the turret. Adds an additional 400 lbs to an already overweight vehicle. Soldiers have already added this cocoon to approximately 100 HMMWVs in Ramadi. 10/30/2006 4/14

Future Transparent Gun Shields Requirement: Upgrade GPKS with transparent armor for enhanced situational awareness while maintaining soldier cover within armor envelope. Baseline Initial AHI GS & GPK Upgraded Gunner Shield Transparent Armored Gun Shield (TAGS) Field Modified GS & APK Interim Objective Interim Solution Marine Corps TAGS Future Solution Modified Solution based upon 10/30/2006 5/14 (MCTAGS) theater recommendations

HMMWV M1114 Glass Demand Left Windshield Average Monthly Demand Quantity Quantity 1200 900 600 300 0 1200 900 600 300 0 FY04 FY05 FY06 Fiscal Year Right Windshield Average Monthly Demand FY04 FY05 FY06 Fiscal Year Door Window Average Monthly Demand Over $5.2 Million was spent per month in FY05 for the Up-Armored HMMWV windshields and door windows. Demand for both right and left windshields increased 133% and 101% respectively from FY05 to FY06. Demand for door windows increased 658% from FY05 to FY06. 1800 1500 Quantity 1200 900 600 300 0 Bottom Line: Army needs a better Transparent Armor solution! FY04 FY05 FY06 10/30/2006 Fiscal Year 6/14

Increase In Door Glass Demand Soldiers are adding another piece of glass to each door for added protection. Adds additional weight to an already overweight vehicle and reduces payload capacity! 10/30/2006 7/14

Causes Of Current Glass Failures Insurgent Attacks (IEDs, RPGs,, shrapnel, bullets) Sandstorm Damage Rock Strikes Improper removal and installation Clouding Delamination caused by environmental degradation Improper curing process Improper cleaning techniques 10/30/2006 8/14

Other Problems with Current Glass Weight Weight of current glass adds significant weight to vehicle. Visibility Thickness of glass can cause distortion and glare 10/30/2006 9/14

Transparent Armor Solutions Cost Cost for 3 x 3 piece ranges from $500 - $3000 depending on desired thickness and treatments ARL Ceramic Glass/Plastic Ballistic Current Laminate ARL Glass Current (2006) 2007 2008 2009 2010 Time ARL Army Research Lab 10/30/2006 10/14

Basic Research Effort GE Global Research and Nanocerox partnership Goal is to develop nano-structured ceramic bodies with a combination of high optical transmission and exceptional mechanical properties and capable of effective performance in an outstanding transparent armor system. Two Funding Opportunities of Effort: FY05: : Develop design rules from the system level armor requirements to the mechanical and optical properties of the ceramic body and then into the properties of the nanopowder. Objective is for a process to be in place for the fabrication of 2 x 2 2 x 0.375 samples. FY06: : Scale up the materials systems to a final dimension of 4 4 x 4 x 4 x 0.375.. Characterize and deliver samples for ballistic testing. 10/30/2006 11/14

Government Cost Benefit Study Purpose: Determine break-even cost for new transparent armor solution based on expected reliability improvement and required investment. Use current fleet of Up-Armored HMMWV as the study platform for initial look. Approximately 11,000+ vehicles in Army inventory. NSN 2510-01 01-435-9693 Right Windshield $2,759 (FY06$) NSN 2510-01 01-435-9690 Left Windshield $2,759 (FY06$) NSN 2510-01 01-435-9692 Door Window $1,025 (FY06$) Expand analysis to include rest of TWV fleet. 10/30/2006 12/14

Cost-Benefit Methodology Obtain current demand data and cost data to determine operations cost for status quo. Completed LH Windshield Unit Cost vs. Improved Reliability Obtain investment costs for new transparent armor. Parametric Analysis Determine operations cost for transparent armor solution. Determine savings between status quo and transparent armor alternative. Calculate Net Present Value and Savings to Investment Ratio. $3,000 Cost $2,000 Break $1,000 $0 Even Cost Contractor provides reliability improvement factor estimate and estimated cost for transparent armor Material at end of Phase I. 10/30/2006 13/14 Unit Cost $10,000 $9,000 $8,000 $7,000 $6,000 $5,000 $4,000 Break Even Curve 0 +10% +20% +30% +40% +50% +60% +70% % Improvement Over Current Failure Rate

Cost Benefit Parametric Analysis Up-Armored HMMWV Glass Unit Cost LH Windshield Unit Cost vs. Improved Reliability $10,000 $9,000 $8,000 $7,000 $6,000 Increased Costs $5,000 $4,000 $3,000 $2,000 Cost Savings $1,000 $0 0 +10% +20% +30% +40% +50% +60% +70% Break Even Curve % Improvement Over Current Failure Rate Unit Cost RH Windshield Unit Cost vs. Improved Reliability $10,000 $9,000 $8,000 $7,000 Increased Costs $6,000 $5,000 $4,000 $3,000 $2,000 Cost Savings $1,000 $0 0 +10% +20% +30% +40% +50% +60% +70% Break Even Curve % Improvement Over Current Failure Rate Door Window Unit Cost vs. Improved Failure Rate $4,000 $3,500 Unit Cost $3,000 $2,500 $2,000 $1,500 $1,000 $500 Increased Costs Break Even Curve Cost Savings Curves Based on the FY05 Demand Data $0 0 +10% +20% +30% +40% +50% +60% +70% % Improvement Over Current Failure Rate 10/30/2006 14/14

Timeframe FY05 FY06 FY07 FY08 DRAFT RFP Final Solicitation Released FY 05 Congressional FY 05 Contract Award IPR IPR FY 06 Congressional FY 06 Contract Award IPR IPR Data Collection & Parametric Analysis Evaluation Phase II Effort Cost Benefit Analysis 10/30/2006 15/14