TECHNICAL BRIEF OKLAHOMA GAS & ELECTRIC (OG&E) FIVE TRIBES PECAN CREEK 161 KV LINE

Similar documents
Preliminary Report on Oak Ridge National Laboratory Testing of Drake/ACSS/MA2/E3X

Table 1. Sample Identification and Comparison Connectors Used in Experiments Sample Conductor Size

Looking Towards the Future: Advantages of 765-kV Transmission Technology

Live-line transmission lines upgrade projects. First-in-Africa project

3M Brand Composite Conductor Connector Current Cycle Qualification Test for 795 kcmil Compression Connectors

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Falcon-Midway 115 kv Line Uprate Project Report

How Aerospace Technology is Improving the Efficiency, Capacity and Reliability of the Smart Grid

OTAHUHU-MANGERE-ROSKILL- HEPBURN ROAD 110 KV CIRCUITS

National Seminar on New Generation High Performance Conductors. 4 th Dec 14

APPENDIX F: Project Need and Description

CONDUCTOR CONDUCTOR. Overhead Electric Distribution Standards INTRODUCTION

High-Temperature Low Sag (HTLS) conductors. for easy Upgrading of Overhead Transmission Lines

Sub Regional RTEP Committee Western Region ATSI

Impact, Torsion, and Crush Tests for 477 kcmil and 795 kcmil 3M Brand Composite Conductor. 3M Company Purchase Order

STATE OF NEW HAMPSHIRE Inter-Department Communication

Wheeler Ridge Junction Substation Project Description and Functional Specifications for Competitive Solicitation

Transmission Corporation of Telangana, Jawaharlal Nehru Technological University Hyderabad

ABB POWER SYSTEMS CONSULTING

Substation Design Volume III

Gridlines. Composite Reinforced. Aluminum Conductor. In This Issue: AECC Uses 3M ACCR to Complete Challenging Upgrades...1

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Grid Operations and the Increasing Challenges of Balancing Renewable Energy ALBUQUERQUE QUALITY NETWORK

Protecting. Grid. Integrity. More amps, more confidence. 3M Aluminum Conductor Composite Reinforced (ACCR) High-capacity transmission conductor

Dynamic Control of Grid Assets

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Power System Analysis I TRANSMISSION LINE PARAMETERS

Aluminum Conductor Composite Reinforced Installation Guidelines and Maintenance

Appendix D Black Hills Project Summary

How Aerospace Technology is Improving the Efficiency, Capacity and Reliability of the Smart Grid. D.C. BRYANT 1 CTC Global Corporation United States

Overhead transmission lines Spacers

Illinois State Report

Initial Field Trials of Distributed Series Reactors and Implications for Future Applications

Northeast Wisconsin/Upper Peninsula Separation 11/14/01. Incident Investigation Report

The Narragansett Electric Company. d/b/a National Grid (Interstate Reliability Project) RIPUC Dkt. No Testimony of. David M. Campilii, P.E.

TABLE OF CONTENTS FIGURES: MAP EXHIBITS: TABLES:

100 MW Wind Generation Project

Supplement to ISO Transmission Plan. Harry Allen-Eldorado Project Description and Functional Specifications

Western Alberta Transmission Line (WATL) HVDC Project

Standard Compression Dead End for ACSR and ACSS Conductor CAUTION: ACSR Dead Ends Cannot Be Used on ACSS HT Conductor

Out of Sight Out of Mind Revisited. EEI Transmission, Distribution, & Metering Conference October 14, 2009 Ken Hall Hall Energy Consulting

Substation Equipment (Bushings)

MILLIGAN SOLAR PROJECT

INFRASTRUCTURE RENEWAL FOR THE NEXT GENERATION PATCO High Speed Line Power Infrastructure Renewal

Electric Power Transmission: Research Needs to Sustain a Critical National Infrastructure

B kv T&D GAS INSULATED SWITCHGEAR

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

Dear Matt: Rick Bofinger Jerico Mechanical Office x 112 Cell

Gateway South Transmission Project

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Line using HTLS Conductors to increase

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Tehachapi Renewable Transmission Project 3.1 OVERVIEW OF PROPOSED PROJECT

Deploying Smart Wires at the Georgia Power Company (GPC)

TECHNICAL SPECIFICATION FOR SHACKLE HARDWARE FITTINGS SUITABLE FOR TENSION STRING TO BE USED FOR 11KV LINE

welcome to the BC Hydro community open house

Surry Skiffes Creek Whealton Modeling and Alternatives Analysis Review

Pulling & Support Grips

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

ACCC. CTC Global s High Performance Conductors for a Low Carbon World

The Electricity Grid Scottish Power Energy Networks Overview

Short Circuit Analysis with New Generation Proposed by XXXXXXXXXXXXXXXXXXXXXX Pursuant to a Transmission and Facilities Study

May 11, Ms. Kavita Kale Executive Secretary Michigan Public Service Commission 7109 West Saginaw Highway Post Office Box Lansing, MI 48909

HIGH TEMPERATURE SUSTAINED LOAD TEST ON A COMPRESSION DEAD-END CONNECTOR INSTALLED ON 1020 KCMIL, ACCC/TW DRAKE CONDUCTOR

Supplemental Report on the NCTPC Collaborative Transmission Plan

EDGE HOW IS IOT LINKING TO THE CLOUD? TOP 10. CIOs/CTOs AI - GOING DEEPER IN 2018 FLEX S KEVIN KETTLER TALKS INTELLIGENCE, CLOUD, AUTOMATION AND 5G

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

Interconnection System Impact Study Report Request # GI

Michigan Thumb Loop Transmission Line Project

Currant Lake Transmission Project

ACCELERATED CABLE AGING TESTS for DISTRIBUTION and TRANSMISSION CABLES PART 1 HV AC PAPER CABLES

TEKNISK RIKTLINJE TR05-10E

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

New Jersey State Report

Sacramento Municipal Utility District s EV Innovators Pilot

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Report. the feasibility of

Kansas Legislature. Briefing for the. March 6, Paul Suskie & Mike Ross

HIGH PERFORMANCE OVERHEAD LINE CONDUCTORS TO UPGRADE YOUR SYSTEM

MINIMUM DISTRIBUTION SYSTEM CONCEPTS AND APPLICATIONS. Larry Vogt. Manager, Rates

Power Infrastructure. PowerToGrowPHX.com

THE PROTEAN AND POC-MAST DESIGN

Managing California s Electrical Supply System after the shut down of San Onofre Nuclear Generating Station

Portland General Electric

Bohn to Kettle River Transmission Project

The Grid Link Project. Summary of the Report for the Independent Expert Panel

System Impact Study Report Request # T MW Firm Point-to-Point Transmission Service Request from Wyoming to Colorado

The comprehensive portfolio of the testing laboratories at Schaltwerk Berlin siemens.com/energy/psw

Power and Distribution Transformers

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY SHORT CIRCUIT ANALYSIS

Evaluating Losses in Electrical Equipment Focus on Transmission Utilities. CNY Engineering Expo 2016 Syracuse, New York Arthur C. Depoian P.E.

Minnesota Biennial Transmission. Zone Meeting 8

Generator Interconnection System Impact Study For

Kinectrics North America Inc. Report No.: K RC-0002-R00. October 2, Zsolt Peter Transmission and Distribution Technologies Business

Transcription:

Company: Oklahoma Gas & Electric (OG&E) is a regulated electric utility serving more than 800,000 retail customers in Oklahoma and western Arkansas, and a number of wholesale customers throughout the region. With about 6,800 megawatts of capacity, OG&E generates electricity from natural gas, coal and wind. OG&E's electric transmission and distribution systems span 30,000 square miles. Its parent company, OGE Energy Corp. (NYSE: OGE), is headquartered in Oklahoma City. Network Name: Five Tribes - Pecan Creek 161 kv Ckt 1 Description: Reconductor 4.07-mile Five Tribes - Pecan Creek 161 kv line and increase electric current rating to 2000 A Specification: All elements and conductor must have an emergency rating of at least 542 MVA Justification: To address the overload of the Five Tribes - Pecan Creek 161 kv Ckt 1 line for the loss of Agency - Pecan Creek 161 kv Ckt 1 line Location and Climate: On average, Muskogee, Oklahoma has 227 sunny days per year with a July high temperature of approximately 94 F and a January low temperature of 27 F. The number of days per year with any measurable precipitation is 87. Oklahoma City had a mild summer in 2014 with an average temperature of 80 F with mild winds. Situation: Five Tribes - Pecan Creek 161 kv Ckt 1 line was scheduled for an upgrade to increase capacity to 2000 A to meet the energy demands and reliability requirements of the growing economy. The existing line was built in 1954 on wood H-frame structures with 636 kcmil Grosbeak conductor. The structures displayed significant wear, so the line needed to be torn down and replaced with an entire new line. Installation of Drake/ACSR/E3X at Pecan Creek Substation. - 1 -

Challenge: The 2000 A current rating required to support future capacity on the Five Tribes Pecan Creek line exceeded the ampacity of OG&E s standard 795 kcmil Drake/ACSR. OG&E s next size in their standard conductor portfolio was a 1590 kcmil Lapwing/ACSR, which would more than adequately meet the future capacity. While new steel structures were required to replace the failing wood structures, upsizing to 1590 kcmil Lapwing/ACSR conductor would have required even taller and stronger structures and a significant increase to the overall project cost. This challenge provided an opportunity for OG&E to consider a new approach. To identify a cost-effective alternative to upsizing the conductor, OG&E decided to move forward with the 795 kcmil Drake/ACSR design while simultaneously test piloting General Cable s new TransPowr with E3X Technology on the southern phase of the line. Solutions: TransPowr with E3X Technology is a groundbreaking, heat-dissipating surface coated conductor that will transform power grid sustainability, reliability, efficiency and resilience. By lowering operating temperature, TransPowr with E3X Technology reduces power losses and increases power carrying capacity, allowing greater efficiency and lower total system costs. OG&E agreed to evaluate this new technology with the expectation that if a recordable lower operating temperature (up to 30%) were achieved, they would seriously consider using 795 kcmil Drake/ACSR/E3X coated conductor on all phases to allow for increasing the electric current rating to 2000 A. The line was selected because it represented the best short-term opportunity to install several miles of both conductors for direct comparison and evaluation. Five Tribes Pecan Creek 161 kv Line Energized - 2 -

The new Five Tribes Pecan Creek line is 4.07-miles of which 3 miles are straight terrain with no elevation changes. The line design consisted of steel H-frame towers with a single conductor bundle in flat horizontal phase arrangement. For validation purposes, Drake/ACSR with E3X Technology was to be installed on the southern phase while standard Drake/ACSR was to be installed on the northern phase. Preinstallation: Three reels containing 10,400 feet of Drake/ACSR with E3X Technology produced at General Cable s Malvern, Arkansas manufacturing facility were used for this installation. General Cable shipped the conductor within standard bare transmission lead times. The addition of the E3X Technology did not negatively impact the timeline nor the delivery schedule of the product. As is customary, the reels were inspected prior to installation, and no damage was found to either the surface coating or the conductor. It is important to note that the E3X coating has been engineered to withstand transportation and storage handling without any special protection. The crew was introduced to the E3X coated conductor, which has a non-reflective, matte gray appearance similar to a non-specular surface finish. There is absolutely no change to the interior of an overhead conductor with E3X coating. New technologies often require changes in installation procedures. However, Drake/ACSR/E3X can be installed without any modification to installation, termination or maintenance. Therefore no special equipment or techniques were used during installation. The tension method was used to install the conductor with the aid of a standard offset multi-groove bullwheel tensioner. Special Observation: During the installation process, some coating material was found on the bullwheel tensioner. This material was determined to be excess un-adhered coating material in the strand interstices of the conductor. There was no impact from the removal of this material on the conductor or the installation. Installation: For electrical connection purposes, the standard practice of using a steel wire brush on overhead conductors prior to electrical termination was used on the Drake/ACSR/E3X to remove the coating. Wire brushing successfully removed the coating, and the light gray appearance of the coating served as an ideal visible indicator to ensure that the coating was completely removed. In contrast to standard electrical connection procedures, the only difference was a more deliberate wire brushing of the Drake/ACSR/E3X conductor to ensure that the coating was removed. Both the standard Drake/ACSR and Drake/ACSR/E3X conductors were sagged using the same method and criteria. The Drake/ACSR/E3X conductor was sagged and clipped in following standard sagging procedures. Standard AFL Quick Compress compression splices and dead-ends and standard MacLean Power System suspension clamps were used. There was no need to remove the coating for the mechanical connections as the E3X coating is a thin layer that increases conductor weight by less than 0.4% within the manufacturing tolerances of the aluminum weight. During the mechanical connection process, the installed Drake/ACSR/E3X conductor was visually inspected at the tower from a bucket truck and no issues were observed. - 3 -

Testing: Following installation, samples of the standard Drake/ACSR and Drake/ACSR/E3X coated conductors that had passed through the tensioner and all stringing sheaves were collected at the very end of the line. These samples were sent to General Cable s Marshall Technology Center in Marshall, Texas to determine what impact, if any, the installation process had on the performance of the coated and uncoated conductors. To test the installed Drake/ACSR/E3X coated conductors against the installed standard Drake/ACSR, the three coated conductors were placed in series with three standard conductors. The test loop was then subjected to electric current such that a temperature rise of 100 C over ambient was achieved during a 90-minute cycle. The results showed a temperature reduction of 22.4 C for the Drake/ACSR/E3X coated conductor compared to the Drake/ACSR. This was consistent with pre-installation testing on the coated conductor, which showed a reduction of 23.3 C over that of Drake/ACSR. Results: With a successful installation, the line was energerized in November, 2013 The Drake/ACSR/E3X conductor will remain in the air for an extended period of time to thoroughly evaluate the durability and environmental stability of the technology. Oklahoma had a mild summer in 2014. If temperatures and climate had been at their norm, results could have shown differently. Ongoing Field Analysis: Because the E3X coating performs better as temperatures increase, situations with high load requirements or contingency loads will realize the best possible outcome from the coating. Once there is sufficient load, OG&E will monitor the temperature reductions of Drake/ACSR/E3X coated conductor over time to determine performance. To validate that the lower operating temperature of the Drake/ACSR/E3X coated conductor results in less thermal expansion and conductor sag, OG&E will be measuring the sag in comparison to Drake/ACSR over time. - 4 -

General Cable s Drake/ACSR/E3X coated conductor was installed without modification alongside standard conductor for performance evaluation in the 4.07-mile Five Tribes - Pecan Creek 161 kv line. This was to identify an alternative for increasing capacity to 2000 A to meet energy demands and reliability requirements without the significant cost associated with conductor upsizing. Conclusion: The E3X coated conductor withstood transportation and installation, and did not require any special installation methods. Testing and validation will continue to demonstrate reduced operating temperature. Following this, OG&E can replace the other two phases with the Drake/ACSR/E3X coated conductor to realize the best possible benefits from the coating and to allow the load of the line to increase. More importantly, OG&E can incorporate the E3X new technology into their transmission network for increased power carrying capacity and design future lines with reduced power losses, achieving overall greater efficiency and lower total system costs. Cody Davis Lead Product Engineer, Utility General Cable Brandon Hayes Sr. Designer, Standards and Guides OGE - 5 -