MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017

Similar documents
TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012.

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

POWER SYSTEM INCIDENT REPORT NORTHERN POWER STATION STABILISER OUTAGE APRIL AND MAY 2010

POWER SYSTEM INCIDENT REPORT: OVERLOAD OF WAUBRA- HORSHAM 220 KV TRANSMISSION LINE AND INSECURE OPERATION OF THE SYSTEM ON 13 DECEMBER 2012

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Jemena Electricity Networks (Vic) Ltd

ELECTRICITY TRANSMISSION USE OF SYSTEM PRICES - 1 JULY 2014 TO 30 JUNE 2015

SOUTH AUSTRALIAN HISTORICAL MARKET INFORMATION REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

South Australia Victoria (Heywood) Interconnector Upgrade. RIT-T: Project Specification Consultation Report

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

TRANSMISSION PLANNING CRITERIA

SUBSTATION INTERLOCKING SCHEMES

The Energy Queensland Group Notice of no non-network options

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Energy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

SOUTH AUSTRALIAN HISTORICAL MARKET INFORMATION REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

Investigation into UK socket-outlets incorporating USB charging points

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

Thank you for the detailed information regarding the Refurbishment Project at Marchwood MTS. This project will facilitate equipment maintainability.

Main Transmission System Planning Guideline

B kv Gas-insulated Substations

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

18/10/2018. Mr Peter Adams General Manager, Wholesale Markets Australian Energy Regulator. By

Shunt Capacitor Bank Protection in UHV Pilot Project. Qing Tian

Electricity Industry Code Minimum Service Standards & Guaranteed Service Levels Quarterly Report July September 2008

Technical Standard - TS 129. Small Inverter Energy Systems (IES) - Capacity not exceeding 30kW. SA Power Networks. Published: November 2017

Emerald Reactive Support Alternative Solution Expressions of interest

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Electricity Networks. Empowering your energy future. Tom Langstaff- Network Planning. 21 March 2018

Distributed Energy Resources

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Motor Protection. Voltage Unbalance & Single-Phasing

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP)

Enquiry Form for Micro and Small Generators 5MW and Less

Exemptions currently in force

CHAPTER 8 - GAS AND ELECTRICITY TRANSMISSION COMPARATIVE CASE STUDY

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Guidelines for connection of generators:

Eyre Peninsula electricity supply options investigation

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

TECHNICAL SPECIFICATION FOR INDEPENDENT POWER PRODUCERS. NB Power Customer Service and Distribution. June 2008

National Grid UK Electricity Transmission plc. NATIONAL SAFETY INSTRUCTION and Guidance

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

City of Palo Alto (ID # 6416) City Council Staff Report

Seabrook Substation Reliability Improvement Project

II DISTRIBUTION & SUBSTATION TYPE C

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

Smart Grid Automation and Centralized FISR

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Eyre Peninsula Electricity Supply Options

Merger of the generator interconnection processes of Valley Electric and the ISO;

Grid Tied Limiter User Manual

GAS METERING CTM DATA REQUIREMENTS

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

Facilities Study for Alberta to US Available Transfer Capability

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

100 MW Wind Generation Project

The outlook for electricity industry restructuring in Australia

2015 WDC Disturbance and Protection Standards Overview

Specification for 1500V DC Traction Supply WOS 01.E

Distributed resource participation in the Australian National Electricity Market

White Paper. Ground Fault Application Guide. WL Low Voltage Power Circuit Breakers

CERTIFICATION MEMORANDUM

Basic Connection Services Application and Price Guide

Sub Regional RTEP Committee Western Region ATSI

Final Capacity Auction Results 2019/2020 T-1 Capacity Auction. Date 01/02/2019 Document: FCAR1920T-1 Version 1.0

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Utilization of Electric Power Laboratory 3 rd Year G2: Testing & Characteristic of MCCB Used in Commercial and Industrial Applications

Northeast Wisconsin/Upper Peninsula Separation 11/14/01. Incident Investigation Report

EROAD Inspect In-Vehicle User Guide

New 115 kv Disconnect Switches at Bloomsburg MTS

Inverter-based DER Ride Through and IEEE Standard 1547

15 Nelson-Marlborough Regional Plan

GUIDELINES FOR OPERATING, METERING AND PROTECTIVE RELAYING FOR. NET METERED SYSTEMS UP TO 50 kw AND BELOW 750 VOLTS

Alberta Electric System Operator Saleski Transmission Project Needs Identification Document

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Information Bulletin. Fire Pump Battery Failures. Version 1.1 Approved for release August 2011

Port Hacking cable crossing project Community engagement and feedback summary August 2016

/12/$ IEEE. M. Bashir M.Sc student, Student Member, IEEE Ferdowsi University of Mashhad Mashhad, Iran

Net Metering Interconnection Requirements

ISO Rules Part 300 System Reliability and Operations Division 304 Routine Operations Section Electric Motor Start Requirements

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

Solar and Smart Meter Update. 1 April 2014 to 30 June 2014 Released July 2014

Net Metering Interconnection Requirements. Customer Generation Capacity Not Exceeding 100 kw. Date: Version: 1

Final Capacity Auction Results 2018/2019 T-1 Capacity Auction. Date 26/01/2018 Version 1.0

Feasibility Study for the Q MW Solar Project

Transcription:

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017 REVIEWABLE OPERATING INCIDENT REPORT UNDER THE NATIONAL ELECTRICITY RULES Published: 3 August 2017

INCIDENT CLASSIFICATIONS Classification Detail Time and date of incident 1709 hrs Monday 13 February 2017 Region of incident Affected regions Event type Generation Impact Customer Load Impact Queensland Queensland Environmental - lightning No generator was disconnected or limited as a result of the incident. No customer load was disconnected as a result of the incident. Associated reports Multiple 275 kv Transmission Line Trips at Mount England in Queensland, 13 February 2017 ABBREVIATIONS Abbreviation AEMO CB kv MW NER PS VT Term Australian Energy Market Operator Circuit Breaker Kilovolt Megawatt National Electricity Rules Power Station Voltage Transformer Australian Energy Market Operator Ltd ABN 94 072 010 327 www.aemo.com.au info@aemo.com.au NEW SOUTH WALES QUEENSLAND SOUTH AUSTRALIA VICTORIA AUSTRALIAN CAPITAL TERRITORY TASMANIA WESTERN AUSTRALIA

IMPORTANT NOTICE Purpose AEMO has prepared this report in accordance with clause 4.8.15(c) of the National Electricity Rules, using information available as at the date of publication, unless otherwise specified. Disclaimer AEMO has made every effort to ensure the quality of the information in this report but cannot guarantee its accuracy or completeness. Any views expressed in this report are those of AEMO unless otherwise stated, and may be based on information given to AEMO by other persons. Accordingly, to the maximum extent permitted by law, AEMO and its officers, employees and consultants involved in the preparation of this report: Copyright make no representation or warranty, express or implied, as to the currency, accuracy, reliability or completeness of the information in this report; and are not liable (whether by reason of negligence or otherwise) for any statements or representations in this report, or any omissions from it, or for any use or reliance on the information in it. 2017. Australian Energy Market Operator Limited. The material in this publication may be used in accordance with the copyright permissions on AEMO s website. Australian Energy Market Operator Ltd ABN 94 072 010 327 www.aemo.com.au info@aemo.com.au NEW SOUTH WALES QUEENSLAND SOUTH AUSTRALIA VICTORIA AUSTRALIAN CAPITAL TERRITORY TASMANIA WESTERN AUSTRALIA

CONTENTS 1. OVERVIEW 5 2. PRE-EVENT CONDITIONS 5 3. INCIDENT 6 4. PARTICIPANT INVESTIGATION 6 4.1 Powerlink investigation 6 4.2 CS Energy investigation 8 5. POWER SYSTEM SECURITY 8 5.1 Voltage Fluctuations 8 5.2 Reclassification 9 6. MARKET INFORMATION 9 7. CONCLUSIONS 10 APPENDIX A. POWER SYSTEM DIAGRAM 11 APPENDIX B INCIDENT LOG 12 AEMO 2017 4

1. OVERVIEW This report relates to a reviewable operating incident 1 that occurred on 13 February 2017 at Mount England substation in Queensland. At 1709 hrs faults on the transmission system resulted in outages of multiple 275 kv transmission lines in the Mount England area, and the Mt England 275 kv No.1 busbar. There was extensive lightning activity in the area at the time. This was the second incident at the Mount England substation on this date; the other has been reported 2 separately. No load or generation was lost as a result of this incident. As a reviewable operating incident, AEMO is required to assess power system security over the course of each incident, and assess the adequacy of the provision and response of facilities and services and the appropriateness of actions taken to restore or maintain power system security. 3 AEMO has concluded that: 1. A lightning storm in the area resulted in faults on the following lines: Mt England Tarong No.837 275 kv line. Blackwall Tarong No.875 275 kv line. 2. These in turn, when combined with the pre-event plant configuration in place at Mount England substation, resulted in outages of the following: Mt England Wivenhoe No.823 275 kv line disconnected due to protection operation as a result of an overvoltage condition. No.1 275 kv busbar at Mount England substation disconnected when line 837 was disconnected as a result of a persistent high voltage fault. Mt England Abermain No.8823 275 kv line disconnected when the de-energised line 837 experienced a high voltage fault, resulting in an external flashover across the tie breaker CB between line 837 and line 8823 in the substation. 3. Other than a brief period (approximately five seconds) in which an overvoltage condition was observed, the power system remained in a secure operating state over the course of the incident. 4. The provision and response of facilities and services were appropriate and all protection operated as designed and as expected. 5. There are no outstanding issues to resolve as a result of this incident. This report is prepared in accordance with clause 4.8.15(c) of the National Electricity Rules (NER). It is based on information provided by Powerlink, CS Energy, and AEMO. National Electricity Market time (Australian Eastern Standard Time) is used in this report. 2. PRE-EVENT CONDITIONS The Mt England South Pine No.825 275 kv line (line 825) was out of service due to a previous fault, which has been separately reported, and is available on AEMO s website. The Mt England Tarong No.8812 275 kv line (line 8812) was out of service due to short notice planned work as part of repair works associated with the fault on line 825. Refer to Appendix A for a diagram of the power system immediately prior to this incident. 1 See NER clause 4.8.15(a)(1)(i), as the event relates to a non-credible contingency event; and the AEMC Reliability Panel Guidelines for Identifying Reviewable Operating Incidents. 2 Multiple 275 kv transmission line trips at Mt England in QLD available: <http://aemo.com.au/- /media/files/electricity/nem/market_notices_and_events/power_system_incident_reports/2017/multiple-275kv-line-outages-at-mt- England_20170213_1_final.pdf> 3 See NER clause 4.8.15(b). AEMO 2017 5

3. INCIDENT At approximately 1709 hrs on Monday 13 February 2017, an electrical storm passed through the Mount England and Tarong substation area, resulting in multiple faults on the following transmission lines: Mt England Tarong No.837 275 kv line (line 837). Blackwall Tarong No.875 275 kv line (line 875). The faults and subsequent tripping of these lines, resulted in outages of the following: Mt England Wivenhoe No.823 275 kv line (line 823). No.1 275 kv busbar at Mount England substation (Mt England No.1 busbar). Wivenhoe Power Station Unit 1 was offline at the time, so no generation was lost with the loss of line 823. Wivenhoe Power Station Unit 2 was generating at 160 MW throughout the incident and was not impacted. At approximately 1715 hrs, line 8812 was returned to service after remedial works were completed on that line. Seven seconds later, the Mt England Abermain No 8823 275kV line (line 8823) tripped. Refer to Appendix A for diagrams illustrating the power system as this incident progressed. The equipment was returned to service as follows: Line 875 successfully auto-reclosed both times it tripped. Mt England No.1 busbar was returned to service at 1751 hrs on 13 February 2017. Line 8823 was returned to service at 1858 hrs on 13 February 2017. Line 837 was returned to service at 1745 hrs on 14 February 2017 after repairs to plant. Line 823 was returned to service at 1623 hrs on 20 February 2017. The power system was in a secure state for the duration of the incident, other than a brief period (approximately five seconds) when a high voltage condition was observed on the Mount England No.1 275 kv busbar and connecting lines. As this was a multiple contingency event, AEMO is required to review it in accordance with the National Electricity Rules (NER) 4. 4. PARTICIPANT INVESTIGATION 4.1 Powerlink investigation The following section is based on information provided by Powerlink. Between 1709 hrs and 1715 hrs on 13 February 2017, multiple 275 kv transmission lines in the Mount England substation tripped. The electrical storm resulted in five separate high voltage faults on the transmission network over six minutes. All faults were cleared within mandated clearance times. 5 Table 1 details the sequence of events and further commentary regarding the high voltage faults that occurred in this period. A more detailed sequence of events, including circuit breaker (CB) operation is included in Appendix B. 4 NER Clause 4.8.15 5 NER Schedule 5.1a System Standards Clause S5.1a.8 AEMO 2017 6

Table 1: Detailed sequence of events, as provided by Powerlink Time (hrs) Event Comment Pre-event Lines 825 and 8812 out of service. Lines out of service for rectification activities after the incident earlier in the day. 17:09:03.300 Line 837 single phase trip due to single phase fault (phase A to ground). 17:09:08.029 Mount England substation 275 kv No.1 capacitor (Mt England No.1 capacitor) closed. 17:09:08.219 Line 823 trip due to intertrip signal received from Wivenhoe Power Station. 17:09:08.510 Auto-reclose attempt on line 837 to reenergise the out of service phase. Immediately on energising, protection systems operated to trip the line from service on all 3 phases due to the reoccurrence of the high voltage fault. 17:09:12.885 Mt England No.1 capacitor tripped due to a No Volt condition on the Mt England No.1 busbar. 17:15:35.056 Line 8812 returned to service from previous event. 17:15:42.644 Line 8823 trip due to operation of Circuit Breaker fail protection associated with CB 5042. (5042 is the tie breaker CB between line 8823 and line 837 at Mt England substation). This circuit breaker was already open due to the trip of line 837 at 17:09:08.510. Mount England No.1 busbar and line 823 connected to the transmission network via the two in service phases of line 837 only after the single phase trip. Emergency Voltage Regulation systems operated to close the capacitor as a result of a low voltage condition on the Mount England No.1 busbar. The low voltage condition was a result of the phase imbalance, given the bus was connected via only two phases following the trip of line 837. See Section 4.2 for details. After the trip of line 837, the Mt England No.1 busbar and line 823 were disconnected from the network on all phases, and de-energised. The busbar had been de-energised with the trip of line 837 at 17:09:08.510. Mt England No.1 busbar remained deenergised. Protection operated due to occurrence of a high voltage fault on the circuit breaker as a result of a further lightning strike on the out of service 837 line causing an external flashover across the open CB 5042. During this event, line 875 (from Tarong to Blackwall) also tripped twice and auto-reclosed each time. This had no impact on the events at Mt England. The first trip at 17:09:03.411 was single phase (phase A to ground), and the second trip at 17:09:48.903 was multi-phase (phase A to ground and phase C to ground). The Mt England No.1 Busbar was re-energised via CB 88122 (line 8812) at 1751 hrs on 13 February 2017. Line 8823 was returned to service at 1858 hrs on 13 February 2017. CB 5042 remained out of service until Powerlink could complete further investigations. Line 837 was returned to service at 1745 hrs on 14 February 2017 after repairs to plant. Line 823 was returned to service at 1623 hrs on 20 February 2017. All protection operated as designed and as expected. AEMO 2017 7

4.2 CS Energy investigation CS Energy investigated this incident and found the protection on Unit 1 at Wivenhoe Power Station operated as expected. Immediately prior to the incident, Wivenhoe Power Station Unit 1 was offline. At 17:09:08 hrs the Unit 1 Main Transformer differential protection operated and correctly sent an intertrip signal to open the 8232 CB at Mt England and disconnect the transformer. The differential protection operated due to a sudden increase in the 3 rd and 5 th harmonic currents as a result of overfluxing of the transformer core. This over-fluxing was the result of abnormally high voltages in one phase of the transformer when the No1 bus 275kV capacitor at Mt England was closed into service. Refer to Section 5.1 for more detail. The maximum voltage reached during the event was approximately 238kV phase-to-ground with a steady state value of around 228kV phase-to-ground (394kV to 412kV line voltage). Line 823 was returned to service at 1623 hrs on 20 February 2017, once CS Energy had tested and confirmed the transformer had not been damaged by the over-fluxing it experienced. 5. POWER SYSTEM SECURITY AEMO is responsible for power system security in the National Electricity Market (NEM). This means AEMO is required to operate the power system in a secure operating state to the extent practicable and take all reasonable actions to return the power system to a secure state following a contingency event, in accordance with the NER. 6 This section assesses how AEMO managed power system security over the course of this incident. AEMO invoked constraint set Q-MEWV_823 7 at 1720 hrs, approximately 11 minutes after line 823 tripped. This constraint was revoked at 0150 hrs on 15 February 2017. AEMO had already invoked constraint set Q-TRME at 1210 hrs on 13 February 2017, to manage the short notice planned works outage of line 8812, and Q-SPME_825 to manage the trip of this line earlier in the day. 5.1 Voltage Fluctuations The power system was not in a satisfactory state (and thus not secure) for a brief period (approximately five seconds) when voltage levels at Mt England and Wivenhoe Power Station exceeded the overvoltage limit set in the NER 8. The high voltage occurred as a result of the single phase disconnection of line 837, which resulted in a low voltage condition on the Mt England No.1 busbar and subsequent automatic switching into service of the Mt England No.1 capacitor. The low voltage condition was observed on the Mt England No.1 busbar when phase A was disconnected following the trip of line 837 at 17:09:03.300. The No.1 busbar and line 823 were then only connected to the rest of the grid by the remaining B and C phases, and the resulting phase imbalance produced the low voltage condition. At 17:09:08.029 Emergency Voltage Regulation systems operated correctly to close the Mt England No.1 capacitor bank and increase the voltage. As phase A was disconnected from the grid, and thus had minimal impedance, this phase experienced a particularly large voltage increase when the capacitor bank was switched in. The maximum line voltage on line 823 was measured to be approximately 412 kv, with a steady state of 394 kv. This is 43-50% greater than the rated line voltage of 275 kv, and thus exceeded the maximum permissible short time over-voltage of 130%. Protection systems operated correctly on the Unit 1 transformer at Wivenhoe Power System to trip line 823 at 17:09:08.219. Line 837 was disconnected on all three phases at 17:09:08.510 after an unsuccessful auto-reclose attempt, and the Mt England No.1 busbar was de-energised. At this point, 6 Refer to AEMO s functions in section 49 of the National Electricity Law and the power system security principles in clause 4.2.6 of the NER 7 Out= Mt England to Wivenhoe (823) line 8 NER Schedule 5.1a System Standards Clause S5.1a.4 - Power frequency voltage. The maximum permissible short time over-voltage is 130%. AEMO 2017 8

the power system returned to secure operating state. The capacitor banks automatically switched back out at 17:09:12.885 as a result of the No volt condition. No further action was required to maintain power system security over the course of the incident. 5.2 Reclassification Prior to the incident, AEMO was aware of lightning in the area. AEMO did not reclassify the simultaneous trip of any of the lines in the area as a single credible contingency as there was no reason to as these lines are not listed as vulnerable in the Power System Security Guidelines 9. After the event, AEMO assessed whether or not to reclassify the event as a credible contingency 10. Based on information provided by Powerlink for this incident, AEMO was satisfied that the cause had been identified and that the incident was unlikely to reoccur. AEMO issued Market Notice 57518 at 0151 hrs on 14 February 2017 to notify the market that the incident would not be reclassified as a credible contingency. In the time between the event and confirming that the incident would not be reclassified, line 837 remained out of service. Other than the short period in which voltage fluctuations were observed, the power system remained in a secure operating state over the course of the incident. Power system frequency 11 remained within limits and all faults were cleared within required timeframes 12. AEMO correctly assessed the incident and did not reclassify it as a credible contingency, and appropriate notifications were issued. 6. MARKET INFORMATION AEMO is required by the NER and operating procedures to inform the market about incidents as they progress. This section assesses how AEMO informed the market 13 over the course of this incident. For this incident, AEMO was required to inform the market on the following matters: 1. A non-credible contingency event - notify within two hours of the event. 14 AEMO issued Market Notice 57509 at 1736 hrs 27 minutes after the initial outage, to notify the market of a non-credible contingency event. 2. Reclassification, details, and cancelation of a non-credible contingency notify as soon as practical. 15 AEMO issued Market Notice 57518 at 0151 hrs 6 hours, 42 minutes after the event,to notify the market that AEMO does not intend to reclassify the event as a credible contingency. This is based on information received from the TNSP that the cause of the events at 1709 hrs has been identified and is unlikely to re-occur. AEMO delayed publication of this market notice until sufficient information had been received from the TNSP regarding the event, given line 837 remained out of service Over the course of this incident, AEMO issued appropriate and sufficiently detailed market information. 9 As per the Power System Security Guidelines, vulnerable transmission lines are double circuit transmission lines which fall into the categories for Probable or Proven. A double circuit transmission line in this category is eligible to be reclassified as a credible contingency event during a lightning storm if a cloud to ground lightning strike is detected within a specified distance of the vulnerable lines. 10 AEMO is required to assess whether or not to reclassify a non credible contingency event as a credible contingency - NER Clause 4.2.3A (c) - and to report how re-classification criteria were applied - NER Clause 4.8.15 (ca). AEMO has to determine if the condition that caused the noncredible contingency event has been resolved. 11 Operating Frequency Tolerance Band specified in AEMC Reliability Panel Frequency Operating Standards 12 NER Schedule 5.1a System Standards Clause S5.1a.8 Fault clearance times 13 AEMO generally informs the market about operating incidents as the progress by issuing Market Notices see AEMO website 14 AEMO is required to notify the Market of a non-credible contingency event within two hours of the event - AEMO, Power System Security Guidelines, Section 10.3 15 AEMO is required to notify the market of a reclassification NER clause 4.2.3(g), details of the reclassification 4.2.3(c) and when AEMO cancels the reclassification 4.2.3(h) AEMO 2017 9

7. CONCLUSIONS AEMO has assessed this incident in accordance with clause 4.8.15(b) of the NER. In particular, AEMO has assessed the adequacy of the provision and response of facilities or services, and the appropriateness of actions taken to restore or maintain power system security. AEMO has concluded that: 1. A lightning storm in the area resulted in faults on the following lines: Mt England Tarong No.837 275 kv line. Blackwall Tarong No.875 275 kv line. 2. These in turn, when combined with the pre-event plant configuration in place at Mount England substation, resulted in outages of the following: Mt England Wivenhoe No.823 275 kv line disconnected due to protection operation as a result of an overvoltage condition. No.1 275 kv busbar at Mount England substation, disconnected when line 837 was disconnected as a result of a persistent high voltage fault. Mt England Abermain No.8823 275 kv line, disconnected when the de-energised line 837 experienced a high voltage fault, resulting in an external flashover across the tie breaker CB. 3. Other than a brief period (approximately five seconds) in which an overvoltage condition was observed, the power system remained in a secure operating state over the course of the incident. 4. The provision and response of facilities and services were appropriate and all protection operated as designed and as expected. 5. There are no outstanding issues to resolve as a result of this incident. AEMO 2017 10

APPENDIX A. POWER SYSTEM DIAGRAM The power system in the area immediately before the incident The power system after the initial set of events at 1709 hrs. The power system after the next set of events at 1715 hrs. AEMO 2017 11

APPENDIX B INCIDENT LOG Time and Date Monday 13 February 2017 17:09:03.300 Event Line 837 single phase trip, Mt England substation CB 8372 and 5042 opened on phase A*. 17:09:03.411 Line 875 trip. 17:09:08.029 Mt England No.1 capacitor closed (Mt England CB 5812 closed). 17:09:08.219 Line 823 trip due to Wivenhoe Power Station unit 1 transformer protection operation (Mt England CB 8232 opened) 17:09:08.510 Line 837 trip (Mt England CB 8372 and 5042 opened on all 3 phases). 17:09:08.547 Line 875 auto-reclosed. 17:09:12.885 Mt England No.1 capacitor trip (Mt England CB 5812 opened). 17:09:48.903 Line 875 trip. 17:09:59.023 Line 875 auto-reclosed. 17:15:35.056 Line 8812 returned to service (Mt England CB 5052 closed). Line 8812 was out of service due to rectification activities from a previous event. 17:15:42.644 Line 8823 trip (Mt England CB 88232 opened). 17:20 Q-MEWV_823 invoked. 17:36 Market Notice 57509 issued advising of non-credible contingency event. 17:51 Re-energisation of No.1 busbar (Mt England CB 88122 closed) 18:58 Line 8823 returned to service (Mt England CB 88232 closed) Tuesday 14 February 2017 01:51 Market notice 57518 issued advising that the non-credible contingency event will not be reclassified. 17:45 Line 837 returned to service. Wednesday 15 February 2017 01:50 Q-MEWV_823 revoked. 18:50 Q-TRME revoked. Monday 20 February 2017 16:23 Line 823 returned to service (Mt England CB 8232 closed). * Only Mt England CB operations have been listed, unless otherwise specified, all 3 phases are opened or closed. AEMO 2017 12