Transmission Expansion Advisory Committee

Similar documents
Transmission Expansion Advisory Committee

Market Efficiency RTEP Proposal Window

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

Market Efficiency RTEP Proposal Window

Sub Regional RTEP Committee - Southern. August 19, 2011

Sub Regional RTEP Committee Mid-Atlantic

Reliability Analysis Update

Sub-Regional RTEP Committee PJM South

Transmission Expansion Advisory Committee

Reliability Analysis Update

Sub Regional RTEP Committee Mid-Atlantic

Reliability Analysis Update

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

Sub Regional RTEP Committee Mid-Atlantic

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Sub Regional RTEP Committee - Southern

Sub Regional RTEP Committee Mid-Atlantic

Transmission Expansion Advisory Committee

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

PJM Regional Transmission Expansion Planning (RTEP) Process

Transmission Expansion Advisory Committee

Market Efficiency Update

Market Efficiency Update

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

Transmission Expansion Advisory Committee. Reliability Analysis Update

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Supplemental Report on the NCTPC Collaborative Transmission Plan

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Appendix D Black Hills Project Summary

Transmission Expansion Advisory Committee Meeting. April 23, 2008

Illinois State Report

Market Efficiency Update

Sub Regional RTEP Committee Mid-Atlantic

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

New Jersey State Report

Interconnection System Impact Study Report Request # GI

Generation Deactivation Notification Update

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

APPENDIX F: Project Need and Description

Black Hills Project Summary

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

TRANSMISSION PLANNING CRITERIA

MILLIGAN SOLAR PROJECT

100 MW Wind Generation Project

Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Market Efficiency Update

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Status of PNM s Completed Transmission Construction Projects 11/30/2017

CUSTOMER/ TWIN ARROWS PROJECT

Sub Regional RTEP Committee South

Sub Regional RTEP Committee Western Region ATSI

Project #148. Generation Interconnection System Impact Study Report

Sub Regional RTEP Committee Mid-Atlantic

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

West Station-West Cañon 115 kv Transmission Project

Reliability Analysis Update

Gateway South Transmission Project

System Impact Study Report

Reliability Analysis Update

South Dakota 890 Study

Manual 3: Transmission Operations Updates Version 52

High Lonesome Mesa 100 MW Wind Generation Project (OASIS #IA-PNM ) Interconnection Facility Study. Final Report November 2, 2007

PJM SRTEP Meeting Questions Pertaining to Proposed Projects & Scopes AEP: Ambler Ridge:

Designated Entity Pre-Qualification Materials. Exelon Corporation

Generator Interconnection System Impact Study For

MTEP13 SPM #2- Central Region. March 25, 2013

March 18, Subject: Imperial Irrigation District 2014 Annual Progress Report - Rev 1

Western Area Power Administration Rocky Mountain Region Annual Progress Report. Projects. Weld Substation Stage 04

Western NY Public Policy Transmission Planning Report

15 Nelson-Marlborough Regional Plan

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

North Oregon Coast Area Study. Adam Lint

Western Area Power Administration Sierra Nevada Region

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

New 115 kv Disconnect Switches at Bloomsburg MTS

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Feasibility Study Report

15 Nelson-Marlborough Regional Plan

The Long-Range Transmission Plan

Energy Policy Implications: PJM Planning

Pacific Gas and Electric Company s Revised 2016 Annual Progress

2015 Grid of the Future Symposium

Western Area Power Administration Sierra Nevada Region

Manual 3: Transmission Operations Updates Version 52

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Entergy Texas, Inc. Transmission Draft Construction Plan Update 1 Projects

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

ATTACHMENT Y STUDY REPORT

Pacific Gas and Electric Company s Revised 2015 Annual Progress

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

City of Palo Alto (ID # 6416) City Council Staff Report

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Twin Cities Minnesota Zone Meeting Xcel Energy. May 11, 2005 Bloomington, MN

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Transcription:

Transmission Expansion Advisory Committee March 6, 2014 1

2014 RTEP Update 2

2014 RTEP Update Initial 2019 Summer base case and corresponding machine list update complete PJM staff has been reviewing and checking the 2019 base case Validating the modeling of RTEP upgrades in the case with the TOs Each TO was sent an itemized list of upgrades to verify modeling Currently running benchmarking simulations Targeting the week of March 17, 2014 to begin initial RTEP simulations RTEP proposal window communication to follow 3

2019 Winter Study Update Winter study case out to TOs for review and topology update Similar to the PJM Light Load Reliability Criterion, PJM currently gathering data for: Generation Dispatch Generation capacity factors Area interchange Historical metered data Other considerations Analysis to begin late March 2014 4

Reliability Analysis Update 5

AEP Sag Study Update Over 100 sag studies in progress On schedule to have remediation completed by second quarter of 2015 for all Sag Studies with a need date of June 2015 or sooner. Majority of the remediation include upgrades of limited scope Transmission Structure modification Replacement of a few spans Relocation of distribution or third party underbuilds Conductor hardware remediation 6

ComEd Transmission Zone Project Cancellation B1852.1: Upgrade five 345 kv circuit breakers (L1223, L11124, L14321, BT2-3 and BT3-4) at Electric Junction B1852.2: Modify reclosing on 138 kv line (L11103) at TSS 111 Electric Junction B0661, which will be in service this year, will operate the Plano 345 kv red-blue bus tie normally closed. It will relieve the overload on the Electric Junction 345/138/34.5kV transformer #83, which is the original driver for B1852.1 and b1852.2 Due to B0661, B1852.1 and b1852.2 are no longer needed. Original required IS Date: 6/1/2016 7

Dominion Transmission Zone NERC Category B: (DVP critical system condition) In 2018, the outage of Gordonsville 230-115 kv Tx#1 overloads Gordonsville 230-115 kv Tx#3 in Front Royal Stress Case (Front Royal Generation off) NERC Category C: In 2018, multiple N-1-1 Contingencies result in Non- Convergent Cases and overloads of Line #2 Mt. Run to Oak Green 115 kv, Line #70 Mt. Run to Remingtion 115 kv, Line #198 Oak Green to Chancelor 115 kv & Gordonsville 230-115 kv Tx #1 & #3. Contingencies include outages of: Line #255 North Anna to South Anna 230 kv & Line #2054/2135 Charlottesville to Hollymeade to Gordonsville 230 kv Line #573 North Anna to Spotsylvania 500 kv & Line # 575 North Anna to Ladysmith 500 kv Line #553 Cunningham to Elmont 500 kv & Line #255 North Anna to South Anna 230 kv Line #575 North Anna to Ladysmith 500 kv & Line #594 Morrisville to Spotsylvania 500 kv Operational Performance Issues Pratts & Sperryville loads on radial transmission lines Real time outages resulting in transmission line overloads Areas of Concern Continued on the next slide 8

Dominion Transmission Zone Continued from the previous slide: Proposed Solution : Convert 17 mile Gordonsville to Pratts 115 kv line to 230 kv Construct approximately 23 mile long 115 or 138 kv line from Pratts to Sperryville Additional 115/138kV transformer needed at Sperryville if 115kV line constructed between Pratts & Sperryville Construct approximately 38 mile long 230 kv line from Remington to Pratts and install 230 kv ring bus at Remington Install 230 kv Switching Station and 230/115 or 138 kv* autotransformer at Pratts Install 230 kv breakers at Gordonsville Estimated project cost: $200 M Projected IS Date: June 2018 Proposed solution provides good long term support to the 115 kv system in the Gordonsville - Culpeper - Remington corridor while offering improved reliability in the Pratts and Sperryville area by networking radial lines. Convert 115 kv Line to 230 kv* New 115 or 138 kv Line* New 230 kv Line 9

JCPL Transmission Zone B2234 Scope Change: Existing Scope: Install 260 MVAR reactor at West Wharton 230 kv. New Proposed Scope: Install -260/+40 MVAR SVC at West Wharton 230 kv substation. The SVC will have the ability to control an existing 350 MVAR capacitors at West Wharton. It replaces the loss of dynamic reactive reserve due to generator retirements in the area. It will mitigate any potential voltage collapse due to an excessive number of capacitor switching steps required. Estimated Project Cost: Existing $ 8.6 M New $ 41.4 M Expected IS Date: 4/1/2015 10

PENELEC Transmission Area Light Load Reliability Analysis The South Troy East Towanda 115kV line is overloaded due to various single contingencies Proposed Solution: Rebuild and Reconductor 115 kv line from East Towanda to S. Troy & upgrade terminal equipment at East Towanda, Tennessee Gas & South Troy. (b2463) Estimated Project Cost: $40 M Required IS Date: 3/1/2016 11

Short Circuit Upgrades 12

METED Transmission Area The Hunterstown 115 kv breaker 96192 is overstressed Significant Driver : Install 2 nd Hunterstown 230/115kV transformer (b2452) Proposed Solution: Replace the Hunterstown 115 kv breaker 96192 with 40kA rated breaker (b2452.3) Estimated Project Cost: $285 K Required IS Date: 6/1/2017 13

Generation Deactivation Update 14

Unit(s) Transmission Zone Requested Deactivation Date Walter C Beckjord 4 (150MW) Big Sandy Unit 2 (800MW) McKee Units 1 & 2 (17MWs each) Deactivation Status PJM Reliability Status DEOK 4/16/2014 Reliability analysis complete for April 2014 deactivation date and no impacts identified. Unit deactivated on Feb. 17, 2014. AEP 6/1/2015 Reliability analysis complete. Impacts identified and upgrade expected to be completed 2nd quarter 2016. Interim operating measures will be utilized in interim period. Unit expected to deactivate as scheduled. DPL 5/31/2017 Reliability analysis underway. 15

Generation Retirements 16

Big Sandy Unit 2 AEP Transmission Zone 800 MW Deactivation date: 06/01/2015 Deactivation Update: Deactivation Notifications 17

Deactivations Big Sandy Unit 2 AEP Transmission Zone Generation Deliverability Violation Hazard 161/138 kv transformer is overloaded for the tower contingency loss of Dorton Lock Haven Clinch River 138 kv line and Beaver Creek Freemont 138 kv line, Freemont 138/69 kv transformer ( 408_2 ) Baseline upgrade (b2462): The reinforcement is to add two 138 kv circuit breakers at Fremont station to fix the tower contingency 408_2. Cost estimate: $1.2 M Required IS Date: 6/1/2015 Projected IS Date: 6/1/2016 Interim Solution will be implemented for the one year 18

Artificial Island PJM TEAC 2/6/2014 19

AI Analytical Issues Continue to coordinate discussion of Carrier Relay with the PJM Planning Committee (PC) and Relay Subcommittee (RS) SVC modeling during the transient timeframe EPRI feedback PSS/e version benchmarking 20

Artificial Island Constructability Overview 21

Southern Delaware Crossing Lines Submarine or aerial line over the Delaware New or expansion of existing substation in Delaware Proposing Entities: LS Power Proposal 5A Transource Proposal 2A, 2B Dominion (VEPCO) Proposal 1B 22

Constructability Review Preliminary Findings Dominion (VEPCO) Proposal 1B (overhead) Transource Proposal 2A (submarine) Transource Proposal 2B (submarine) LS Power Proposal 5A (submarine) LS Power Proposal 5A (overhead) Rights of Way and Land Acquisition No additional land for expansion of the existing Salem substation in New Jersey Availability of land proposed to be utilized in New Jersey is in question Availability of land proposed to be utilized in New Jersey is in question No additional land for expansion of the existing Salem substation in New Jersey No additional land for expansion of the existing Salem substation in New Jersey Land required for a 500/230kV substation in Delaware Expansion of the existing Cedar Creek substation in Delaware Land required for new switching station in Delaware Has acquired an option on a site for the proposed new switching station in Delaware Has acquired an option on a site for the proposed new switching station in Delaware Common Factors 1.5 to 3 miles of right of way needs to be acquired in Delaware All projects that have a new substation in Delaware have a proximity issue with route 9 - Impact to route 9 depends on substation location www.pjm.com 23

Constructability Review Preliminary Findings Siting / Permitting www.pjm.com Dominion (VEPCO) Proposal 1B (overhead) 3 mile 500kV aerial crossing of the Delaware river has potential impacts to viewshed and shipping channel Proposed Line right of way crosses or parallels Delaware state route 9, which is classified as a Scenic and Historic highway Transource Proposal 2A (submarine) 6 mile submarine crossing of the Delaware river No route 9 crossing Transource Proposal 2B (submarine) 3 mile submarine crossing of the Delaware river Proposed Line right of way crosses or parallels Delaware state route 9, which is classified as a Scenic and Historic highway Common Factors LS Power Proposal 5A (submarine) 3 mile submarine crossing of the Delaware river Proposed Line right of way crosses or parallels Delaware state route 9, which is classified as a Scenic and Historic highway LS Power Proposal 5A (overhead) 3 mile 230kV aerial crossing of the Delaware river has potential impacts to viewshed and shipping channel Proposed Line right of way crosses or parallels Delaware state route 9, which is classified as a Scenic and Historic highway All projects have comparable approximate 2 mile transmission right of way to be acquired in Delaware 24 All projects need a permit to cross the Delaware state lands on the river coast

Constructability Review Preliminary Findings Project Coordination Complexity Dominion (VEPCO) Proposal 1B (overhead) Salem line attachment not detailed in proposal Transource Proposal 2A (submarine) Requires relocation of Salem-New Freedom line into new bay Transource Proposal 2B (submarine) Requires relocation of Salem-New Freedom line into new bay LS Power Proposal 5A (submarine) Auto-transformer located in existing Salem substation LS Power Proposal 5A (overhead) Auto-transformer located in existing Salem substation River crossing not detailed in proposal Longest Delaware river crossing (submarine) Submarine cable installation Submarine cable installation River crossing not detailed in proposal Substantial expansion to the existing Cedar Creek substation Common Factors All work in Artificial Island substations will be required to conform to nuclear generation facility work rules PJM TEAC www.pjm.com 3/6/2014 25

Constructability Review Preliminary Findings Proposed Schedule Dominion (VEPCO) Proposal 1B (overhead) 93 months (items run concurrent) Transource Proposal 2A (submarine) 42 months (items run concurrent) Transource Proposal 2B (submarine) 42 months (items run concurrent) LS Power Proposal 5A (submarine) 42 months (items run concurrent) LS Power Proposal 5A (overhead) 42 months (items run concurrent) Permitting - 24 months Permitting - 24 months Permitting - 30 months Permitting - 30 months Permitting - 30 months RoW acquisition 12 months RoW acquisition 12 months RoW acquisition 9 months RoW acquisition 9 months RoW acquisition 9 months Proposed Cost Estimate (millions) $141 No stated contingency $164 - $207 15 40% stated contingency $213 - $269 15 40% stated contingency $148 20% stated contingency $116 20% stated contingency www.pjm.com Basis of cost was recent RTEP projects of similar scope 26

Artificial Island LS Power Proposal 5A Salem Expansion Proposed 500/230kV Salem Expansion 27

Salem Substation LS Power Proposal 5A Salem Expansion 28

Artificial Island Transource Proposal 2A, 2B Salem Expansion Proposed 500/230kV Salem Expansion 29

Artificial Island Dominion (VEPCO) Proposal 1B Salem Expansion Proposed Salem Attachment 30

Proposed Line Routes Artificial Island 230kV Corridor Route 9 Potential Line Paths 31

230kV Corridor www.pjm.com 32 Proposed Line Routes Cedar Creek Substation

Artificial Island to Red Lion Lines 17 mile 500kV line Parallels 5015 Proposing Entities: LS Power Proposal 5B PSE&G Proposal 7K Dominion (VEPCO) Proposal 1C PHI/Exelon Proposal 4A Transource Proposal 2C 33

Constructability Review Preliminary Findings Dominion (VEPCO) Proposal 1C PSE&G Proposal 7K PHI / Exelon Proposal 4A LS Power Proposal 5B Transource Proposal 2C Rights of Way and Land Acquisition Transmission line Right of Way would need to be acquired on either side of the existing line New Hope Creek Salem tie within existing Artificial Island facility Transmission line to be on Right of Way owned as part of Lower Delaware Valley (LDV) assets in which PSE&G has ownership rights New Hope Creek Salem tie within existing Artificial Island facility Transmission line to be on Right of Way owned as part of Lower Delaware Valley (LDV) assets in which PHI and Exelon have ownership rights Right of Way would need to be acquired for transmission line on south/west side of the existing line. Right of Way would need to be acquired for transmission line on north/west side of the existing line. Right of Way for the Salem-Orchard (5021) relocation not addressed Common Factors Route is approximately 18 miles and adjacent to existing 5015 line (Red Lion Hope Creek) Minimal line distance in Delaware www.pjm.com Red Lion, Hope Creek and/or Salem expansions proposed to be within existing property boundaries 34

Constructability Review Preliminary Findings Dominion (VEPCO) Proposal 1C PSE&G Proposal 7K PHI / Exelon Proposal 4A LS Power Proposal 5B Transource Proposal 2C Siting / Permitting Common Factors Delaware River Basin Commission approval required Delaware and New Jersey CPCNs required US Army Corp of Engineers Section 404 and 10 authorizations Multiple US Fish and Wildlife permits required National Marine Fisheries Service www.pjm.com 35

Dominion (VEPCO) Proposal 1C Constructability Review Preliminary Findings PSE&G Proposal 7K PHI / Exelon Proposal 4A LS Power Proposal 5B Transource Proposal 2C Project Coordination Complexity Red Lion expansion will require 5015 outages for construction and attachment of new line New line will need to cross existing 5015 line Hope Creek expansion outages may be limited to tie in New Hope Creek Salem aerial tie not detailed Red Lion expansion is a rebuild requiring multiple outages New line will need to cross existing 5015 line Hope Creek expansion within existing substation fence New Hope Creek Salem gas insulated bus tie within existing Artificial Island facility. Relocation of existing Salem - Hope Creek tie (5037) at Hope Creek Minor Red Lion expansion. New line to use existing 5015 position. New line will need to cross existing 5015 line Salem expansion within existing substation fence Anticipated to raise 5023, 5021, 5024 near Artificial Island to allow the new line to be installed underneath Minor Red Lion expansion. New line to use existing 5015 position. Salem expansion within existing substation fence. Reuse of the existing 5037 position. Relocation of existing Salem - Hope Creek tie (5037) into new Salem bay Anticipated to raise 5015 and 5023 near Artificial Island to allow the new line be installed underneath Minor Red Lion expansion Salem expansion within existing substation fence Create a new bay for and move the existing Salem- New Freedom (5024) line. Move the Salem-Orchard (5021) line into the 5024 bay and route new line for 1 mile. New line to use existing 5021 bay and rebuild 1 mile Anticipated to cross the 5023 near Artificial Island www.pjm.com Common Factors 36 Route is approximately 18 miles and adjacent to existing 5015 line (Red Lion Hope Creek)

Constructability Review Preliminary Findings Dominion (VEPCO) Proposal 1C PSE&G Proposal 7K PHI / Exelon Proposal 4A LS Power Proposal 5B Transource Proposal 2C Proposed Schedule 111 months (items run concurrent) 51 months (items run concurrent) 60 months (items run concurrent) 60 months (items run concurrent) 48 months (items run concurrent) Design and construction - 38 months Permitting - 24 months Property Acquisition 78 months Design and construction - 48 months Permitting - 48 months Property Acquisition 0 months Design and construction - 50 months Permitting - 34 months Property Acquisition 0 months Design and construction - 60 months Permitting - 27 months Property Acquisition 18 months Design and construction - 30 months Permitting 27 months Property Acquisition 15 months Proposed Cost Estimate (millions) www.pjm.com $199 No stated contingency Basis of cost was recent RTEP projects of similar scope $297 25% stated contingency $157 No stated contingency 37 $171 20% stated contingency $123 to $156 15 40% stated contingency

Proposed Hope Creek Attachment Artificial Island Dominion Proposal 1C Artificial Island Expansion Proposed New Station Tie Line 38

Red Lion Substation Dominion Proposal 1C 39

Proposed Hope Creek Attachment Artificial Island PSE&G Proposal 7K Artificial Island Expansion Proposed New Station Tie Line 40

41 Red Lion Substation PSE&G Proposal 7K

Artificial Island Transource Proposal 2C Artificial Island Expansion 42

Red Lion Substation Transource Proposal 2C 43

Artificial Island LS Power Proposal 5B Artificial Island Expansion 44

Red Lion Substation LS Power Proposal 5B 45

Artificial Island PHI/Exelon Proposal 4A Salem Expansion 46

Red Lion Substation LS Power Proposal 5B 47

SVC Locations Proposed SVC Locations: New Freedom Orchard Near Artificial Island 48

Constructability Review Preliminary Findings Rights of Way and Land Acquisition Siting / Permitting Project Coordination Complexity Artificial Island Orchard New Freedom Availability of land proposed to be utilized in New Jersey is in question Nuclear Regulator Commission coordination required Land would need to be acquired Potential noise limit concerns Common Siting / Permitting Factors DCA approvals required Multiple challenges with the proposed 500kV underground attachment facilities Salem and Hope Creek line attachments Expand Orchard ring bus Expansion proposed to be within existing property boundaries Potential noise limit concerns Create a new bay at New Freedom Common Project Coordination Complexity Factors SVC size limitations www.pjm.com 49

Constructability Review Preliminary Findings Schedule Risks Artificial Island Orchard New Freedom Property acquisition Property acquisition Assumption of land NRC approval availability for expansion Outage availability at Artificial Island 500kV cable lead time Common Scheduling Risk Factors SVC lead time Cost Estimate Risks 500kV cable costs No transmission line assumed No transmission line assumed SVC costs Common Cost Estimate Risk Factors www.pjm.com 50

Artificial Island SVC Proposed SVC Substation 51

Orchard SVC Orchard Substation www.pjm.com 52

New Freedom SVC Lines to Orchard and Artificial Island www.pjm.com 53

RTEP Issues Tracking 54

RTEP Next Steps 55

RTEP Next Steps Continue AI Work Begin 2014 RTEP Analysis Coordinate RTEP Proposal Window Continue PJM Winter Study 56

Questions? Email: RTEP@pjm.com 57