Project Budget and Schedule Status

Similar documents
Transit Project Delivery Status Report. Significant Issues

Mobility Corridor Updates. Transit & Active Transportation Projects

Mobility Corridor Updates. Transit & Active Transportation Projects

Phase 2 Exposition Metro Line Project

Crenshaw/LAX Transit Corridor. Transit Coalition Meeting June 26, 2012

Chief Capital Management Officer s Report

Exposition Corridor Transit Project

congestion management program

Executive Summary. Draft Environmental Impact Statement/Environmental Impact Report ES-1

Peninsula Corridor Electrification Project (PCEP)

Pomona Rotary December 19, 2017

congestion management program

Sepulveda Pass Corridor Systems Planning Study Update

Project Scoping Report Appendix B Project Web Site. APPENDIX B Project Web Site

I-405 Sepulveda Pass Improvements Project

Metro Green Line to LAX Alternatives Analysis. March 2012

DART Priorities Overview

SEPULVEDA PASS CORRIDOR

East San Fernando Valley Transit Corridor. Information Session, October 10, 2017

Peninsula Corridor Electrification Project Cost / Schedule Update

City of Palo Alto (ID # 6416) City Council Staff Report

Countdown to the Closure Extended 53-Hour Closure of I-405 Freeway Between U.S. 101 and I-10 Planned in Mid-July for Mulholland Bridge Demolition

LAX Specific Plan Amendment Study. CONCEPT DEVELOPMENT Public Meeting Series #5 August 23 & 26, 2006

Pacific Electric Right-of-Way / West Santa Ana Branch Corridor Alternatives Analysis

Delta Kappa Gamma January 22, 2018

Expo Light Rail Line. Expo Line Project Westside/Central Metro Service Council November 2014

Sepulveda Pass Corridor Systems Planning Study

Welcome. Please Sign In

Mobility Management: Caltrain

LOS ANGELES COUNTY CONGESTION REDUCTION DEMONSTRATION PROGRAM: STATUS REPORT

I-405 Sepulveda Pass Improvements Project

VAN NESS AVENUE BUS RAPID TRANSIT

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles February 2015

Westside Subway Extension Final EIS/EIR. January 2011 Community Update Meetings

Board of Directors authorization is required for all goods and services contracts obligating TriMet to pay in excess of $500,000.

Business Advisory Committee. July 7, 2015

SAN RAFAEL CITY COUNCIL AGENDA REPORT

Community Meetings. January/February 2019

Agenda. Utility Undergrounding Strategies & Laguna Canyon Road Master Plan

CITY OF TORRANCE PUBLIC WORKS DEPARTMENT ENGINEERING DIVISION INFRASTRUCTURE UPDATE

Transportation Committee Revised Project Scope and Cost Estimate. November 23, 2015

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: Recommend to Board. Final Action

Expo Light Rail Line Project Status Update Meeting Holman United Methodist Church January 27, 2011

ALTERNATIVE PROJECT DELIVERY

I b *A 1 I F IRPORT COMMISSIONERS REPORT TO THE QARD. "" 119,rte.1111.r;

30-Day Look Ahead Summary August 2011

RFP No. P3010 New l.i ght Rail Vehicles

Landside Access Modernization Program (LAMP)

MOTION NO. M Purchase of Thirty-one Articulated Hybrid Diesel Expansion and Replacement Buses

2.4 Build Alternatives

Peninsula Corridor Electrification Project (PCEP)

Community Meetings June 2018

Welcome and Agenda. Thank you for joining us! 6:00 pm Open House. 6:30 pm Welcome & Presentation. 7:00 pm Q&A. 7:15 pm Open House Resumes

Exposition Light Rail Transit Project

Los Angeles County One Gateway Plaza q.200n Tpl Metropolitan Transportation Authority Los Angeles, CA metro.4 I

Purple Line Light Rail P3 Project

ORANGE COUNTY TRANSPORTATION AUTHORITY. Agreement to Purchase Compressed Natural Gas Articulated Buses. Staff Report

Metropolitan Domestic Water Improvement District Board of Directors Meeting. August 8, July 2011 Report

Study Area, Related Projects and Travel Markets

Update of the Midwest Regional Rail Initiative. Tim Hoeffner Michigan Department of Transportation Director, Office of Rail Lansing, MI

APPROVE CONTRACT MODIFICATION AWARD

Chapter 2 Alternatives Considered

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction Update Los Angeles April 2014

STAFF REPORT ACTION REQUIRED

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT FEBRUARY 2015

TORONTO TRANSIT COMMISSION REPORT NO.

NORTH HOUSTON HIGHWAY IMPROVEMENT PROJECT (NHHIP): SEGMENT 3. April 19, 2018 NHHIP April 19, 2018

SAN FRANCISCO MUNICIPAL TRANSPORTATION AGENCY


1 YORK REGION TRANSIT EXTENSION OF EXISTING DIAL-A-RIDE PILOT PROJECT AND STOCK TRANSPORTATION SCHOOL BUS CONTRACTS

ExpressLanes cmc 2011 lacmta

Muni Forward: Get On Board! Siemens S200 SF Light Rail Vehicle

Doran Street and Broadway/Brazil Grade Separation Project

ACTION TRANSMITTAL No

Project Scoping Open House Welcome

Modernising the Great Western railway

Wentzville Parkway South Phase 2 & 2A

Metro Highway Program

BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY. Consent Workshop [ ]

I-4 Beyond the Ultimate. Florida Transportation Builders Association January 18, 2019

3.17 Energy Resources

Business Advisory Committee. November 3, 2015

3. PRELIMINARY DEFINITION OF ALTERNATIVES

ExpressLanes cmc 2011 lacmta

Merger of the generator interconnection processes of Valley Electric and the ISO;

STH 60 Northern Reliever Route Feasibility Study Report

National Treasury Presentation to the Standing Committee on Finance: South African Airways SOC Ltd ( SAA )

Washington Metropolitan Area Transit Authority

RTD Commuter Rail System APTA Rail Conference June 23, 2015

DRAFT Subject to modifications

Project Status Update January 2017

TORONTO TRANSIT COMMISSION REPORT NO.

Public Works Department

Gold Line Status Report FasTracks Citizens Advisory Committee March 19, 2014

East San Fernando Valley Transit Corridor. TAC Briefing December 4, 2013

Link LRT: Maintenance Bases, Vehicles and Operations for ST2 Expansion

MOTION No. M Purchase of Five 40-foot Buses PROPOSED ACTION

Late Starter. Tuesday, November 6, 2018

Corridor Management Committee. March 7, 2012

engineering phase and during the procurement of design build contracts.

Transcription:

Item 44 Program Management Project Budget and Schedule Status

Project Schedules* Project 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Expo Phase I Orange Line Extension I-405 Sepulveda Pass Improvements Project Congestion Reduction Demonstration Program Engineering & Design Major Construction Gold Line Foothill Ext. Expo Phase II Crenshaw/LAX Regional Connector Westside Subway South Bay Green East SFV N-S Eastside Transit Ph 2 West Santa Ana Branch Green Line Ext to LAX SFV I-405 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 * Assumes AFF funding. 2

Orange Line Extension Total ($ mil.) 215.6 180.0 Rev. Operation Summer 2012 June 2012 Project Control Staff evaluated remaining risks to the project and recommend a forecast at project completion of $180.0 million. Will continue to evaluate overall cost exposure to ascertain if additional savings can be achieved as project nears completion. Mitigated majority of the third party delays. Coordination between contractor, MTA and third parties as design-build contractor nears substantial completion. Timely support from third parties. 3

Crenshaw/LAX Transit Corridor Total ($ mil.) Adopted 1,749.0 1,749.0 Rev. Operation 2018 2018 Life-of-Project Budget adopted in October, 2011 A follow-up Risk Assessment Workshop in mid January 2012 to assess potential risks on costs and schedule contingency Received FTA Record of Decision December 30, 2011 Issued D-B Step 1 RFQ - December 23, 2011 Complete Industry Review - January 2012 Issue D-B Step 2 RFP anticipate March 2012 Assess constructability challenges with FAA; including longer construction windows for partially covered trench along ends of LAX runways. Complete bid option design for Vernon Avenue (Leimert Park) Station prior to release of RFP in March 2012. Finalize and execute formal agreement with BNSF regarding track abandonment prior to award of Design-Build contract in fall 2012. Complete property certifications/appraisals to support construction need dates. 4

Westside Subway Extension Total ($ mil.) 5,662.0 5,662.0 Rev. Operation 2022 2022 Based on FTA New Starts Application which is currently being reviewed. Includes Finance s. Late January/ Early February 2012 Target Release date of Final EIS/EIR for 30-day Review Period March 2012 - Board certification of Environmental Document & Project Adoption March/April 2012 -FTA Record of Decision MTA Board approval of staff recommended alignment and station location options (Century City, Westwood/UCLA & Westwood/VA Hospital) FTA reviews and approvals to support the Record of Decision date of March 2012. FTA approval for Entry into Final Design by mid-2012 5

Regional Connector Total ($ mil.) 1,343.0 1,343.0 Based on FTA New Starts Application which is currently being reviewed. Rev. Operation 2019 2019 December 20, 2011 Metro received Design/Build RFP documents for review January 20, 2012 Target Release date of Final EIS/EIR for 30-day review period February 2012 - Board certification of Environmental Document & Project Adoption March 2012 -FTA Record of Decision FTA reviews and approvals to support the Record of Decision date of March 2012 FTA approval for Entry into Final Design by mid-2012 6

Congestion Reduction Demonstration Program Total ($ mil.) 291 291 Construction Complete Budget and reflect an increase of $17M due to removal of contaminated soil at El Monte Transit Center Totals do not include Union Division 13, due to removal from CRDP Program in October 2011 El Monte Transit Center I-110 ExpressLanes I-10 ExpressLanes Patsaouras Plaza Sept 2012 Sept 2012 Oct 2012 Oct 2012 Feb 2013 Feb 2013 June 2014 June 2014 Additional drainage modifications are required on the I-110 Freeway, just north of the I-105. This issue will also be coming to the January 2012 Board Meeting to obtain approval to issue a Change Order The widening of the Adams Blvd. Bridge requires modification to the Expo Line rail crossing at Adams & S. Flower. This will require a PUC Application and approval, which is being expedited LADOT Management reported that the award of the TPS-ATSAC Contract has been delayed and is now on the critical path for the completion of the I-110 ExpressLanes opening 7

I-405 Sepulveda Pass Improvement Project Total ($ mil.) 1.04B 1.04B Construction Complete Planned May 2013 Sept. 2013 The project is developing a Re-assessment to identify potential cost exposure in all areas Preliminary estimates for the remaining Provisional Sums Scope of Work indicate that significant additional funds will be required to complete the work The completion is now Sept. 2013 Metro is working with contractor to mitigate any present and potential future schedule delays Schedule is delayed 4 months. Working with Kiewit to bring completion back to May 31,2013. Contractor performance, VA, Getty, Giro lawsuit potential mitigation, landslide at Wall 2004, and Mulholland Bridge work are the critical issues Contractor needs to mitigate delays to prevent any present and potential future schedule slippages Project is working with DOT-CalTrans-Kiewit to address significant traffic impacts on Sepulveda and freeway. This will continue to be a problem through next year Utility relocation has been a secondary critical path element in completing the work on time. All segments are working with Utility owners, City, and Kiewit to optimize and minimize utility work impacts to the schedule 8

Gold Line Foothill Extension (Phase 2A) Total ($ mil.) 764.5 764.5 Rev. Operation 2016 2016 The issuance of a limited NTP maintains proposal price. Acquisition of 50% of maintenance facility property needed to issue full NTP. Outstanding litigation could impact budget Limited NTP issued to contractor. Substantial Completion date established to be September 23, 2015. Outstanding litigation could impact schedule CEQA challenge of SEIR and legal challenge of property acquisitions Government approved bridge permits Real Estate costs Third Party impacts Scope growth/change Orders 9

Gold Line Foothill Extension (Phase 2A) RECENT ACTIVITIES/ISSUES Need to acquire 50% of maintenance facility property prior to release of all funding and issuance of full NTP California Supreme Court ruling eliminates redevelopment agencies CEQA challenge of SEIR denied Judge reversed decision Reversal based on inaccurate information I-210 bridge construction Completed two of three columns Completed one of two abutments Design-builder reporting 35 day delay Alignment design-builder mobilized project office and submitted project management submittals and some 30 and 60% design packages Received water related permits from regulatory authorities 10

Exposition Phase I Total ($ mil.) 932.0 935.4 Budget may be impacted by $3.4 million forecast overrun plus any contractor claims or other unknowns. Pursuing additional cost savings which include Third Party Reimbursable and other cost savings ($4 million). ROD La Cienega ROD Culver City Dec. 2011 Early 2012 1 st Quarter 2012 2 nd Quarter 2012 Began Metro Operator familiarization week of October 10 th. Pre-revenue operation to begin this month. Once Pre-Rev commences Metro will determine ROD. Change Orders/Claims Third Party overruns Cab signaling issue on the 865 cars 11

Exposition Phase I RECENT ACTIVITIES/ISSUES Latest independent Authority evaluation of FFP schedule estimates Substantial Completion in January 2012 Metro to begin Pre-Revenue Operations this month. After Pre-Revenue Operations commence, Metro will determine Revenue Operations Date Remaining construction elements of the Project are scheduled to be completed in early 2012: Farmdale Station & Culver City Work Elements Project Budget Budget may be impacted by $3.4 million forecasted overrun plus any contractor claims or other unknowns Pursuing third party reimbursable costs ($3 million) Other potential savings ($1 million) 12

Exposition Phase II Total ($ mil.) 1,511.2 1,511.2 Revenue Operations 2015 2016 No issues to report Begin Utility Relocations Begin Major Construction Begin Maint. Facil. Constr. Fall 2011 Summer 2012 Winter 2013 Fall 2011 Summer 2012 Winter 2013 Maintenance Facility construction contract not yet bid DB Contractor completing project wide utility potholing Structural capacity of Kenter Canyon Storm Drain Legal appeal of Certified Environmental Document Third Party Delays 13

Exposition Phase II RECENT ACTIVITIES/ISSUES Completed Preliminary Engineering on Maintenance Facility Balfour Beatty submitted the 95% design for the Venice Blvd. bridge Submitted final PSR/PR to Caltrans for Venice Blvd. bridge Skanska/Rados made 60% design submittal for: City of Santa Monica civil work Motor, Olympic and Sepulveda bridges Sepulveda, National/Palms and Olympic/26 th stations Skanska/Rados has begun structural analysis on the Kenter Canyon storm drain Continue close coordination of SCE and LADWP overhead power line relocations 14