PV-ezRack SolarTerrace III-A Installation Guide V1.4

Similar documents
New! Price List and Sizing Chart. Single Row Series. Double Row Series. Series 5000 for 21 2 Schedule 40 pole (formerly U-22)

Array Frame Engineering Certificate

My Reserve 500 Install Guide

Please note the inverter supplied with your solar system is AS4777 accredited.

RSV16 Retro-Fit Cartridge Acorn Controls SV16 Valve Cartridge

Installation Instructions Studio Makeup Station

BMW X3 UNDERBODY PANEL TRIM DIAGRAM in

POSITIVE DISPLACEMENT FLOWMETERS

GROSS LOAD CAPACITY WHEN USED AS A WEIGHT CARRYING HITCH: 2,000 LBS. TRAILER WEIGHT & 200 LBS. TONGUE WEIGHT.

FOR TECHNICAL ASSISTANCE

Dyna Flood SO / HO. User guide

Model AS-FM64 Wall Mount. Full Motion Television Wall Mount

Installation Guide. Installation Requirements for Rainwater Tanks

ELB ELB

13316 INSTALLATION INSTRUCTIONS

Guardian Taper Grid Shaft Coupling

s_enn Exterior Stainless Steel Shading System by Draper

Nor East. Instructions Safety Messages. Inspection. Parts. DeZURIK Service. Type 05 Pneumatic Actuator Used With Globe Valves

A Member of the. Integrated Metering Technologies

A Member of the. Integrated Metering Technologies

EX Series User Manual

DODGE CUMMINS COOLANT BYPASS KIT

IMPORTANT OPERATING CONDITIONS. Failure to comply with any of these conditions invalidates the warranty. STANDARD CONFIGURATIONS

Installation Instructions Vanishing Lid Bracket

Linear One Exterior. User guide

Fitting Instruction for EZI-GRIP Bike Rack

Raychem CSJA Safety Instructions. Safety Instructions. Customer Service. Kit Contents. Installation Instructions

ATTENTION: PLEASE READ AND UNDERSTAND ALL INSTRUCTIONS AND WARNINGS BEFORE ASSEMBLING, INSTALLING OR USING THIS PRODUCT.

31033 INSTALLATION INSTRUCTIONS

Model FM2642 Wall Mount. Full Motion Television Wall Mount

HOG SLAT. Pit Scraper System. Installation Instructions. Take special note of any warnings or safety decals on the equipment and in this manual.

10 Year Limited Warranty

Model T2642 Wall Mount. Television Wall Mount with Tilt Option

31033 INSTALLATION INSTRUCTIONS

11417 INSTALLATION INSTRUCTIONS

AMERICAN AVK COMPANY TABLE OF CONTENTS

Transit Wheelchair. user guide. Profiled grip attendant handles. Padded seat and backrest. Lift up, padded armrests. Park brakes

FOR TECHNICAL ASSISTANCE

RUSH WALL TOP ASSEMBLIES EXT D 15MM PRODUCT CODE: FINISH: RU067 MB MATTE BLACK 3/4 TURN OPERATION PREMIUM FINISHES

Access Riser Fits PRO370 and PRO380 Series

INSTRUCTIONS AND SERVICE MANUAL WITH PARTS LIST

Power. On Your Terms.

EASY CONNECT CRANE KIT Festoon Conductor Systems

K1013 K1013. Fitting Instructions for Basic Carrier. x 4 x 4 x 1 x 8. x 4 x 1 x 4 x 1. x 4 x 1 x 1 x 2. Revision No: 1A 1

Installation / Operation Instructions Sunnex ORION Series Exam Lights

PVI 1800/PVI Residential/Commercial Grid-Tied Photovoltaic Inverter WARRANTY MANUAL. Subject to Change REV , Solectria Renewables

Precision Center Pivot

DODGE CUMMINS COOLANT BYPASS KIT

P SERIES PUMPS. 18mm Versions Nickle-Aluminum Bronze Models: P , P , P , P , P , P , P

580RK SERVICE GUIDELINES For coupling models: 580 & 580J

Breeder Control Installation Manual

MAGNAGLIDE AIR OPERATOR VERTICAL MOUNT

Using the power override wire. LED Interior Light System (Optional) Adjusting the shelves: TIPS:

Washer, Electrical Equipment Bond. WEEB Patent Pending INSTALLATION INSTRUCTIONS. For Professional Solar only

INSTALLATION INSTRUCTIONS

11333 INSTALLATION INSTRUCTIONS

Installation Instructions

Read this entire manual before operation begins.

3-5 Hours Professional installation recommended

Safe-T-Glide Installation Instructions

Jeep Wrangler (TJ)

Product/ Title Guardian Super Flex Shaft Coupling Product/ Title

Self-Deploying Rail Kit OEM INSTALLATION MANUAL

Guardian Steel Gear Shaft Coupling

Model P-40 & Model P-25 POWER PUSHER

Models PR-12F PR-12C PR-15C SURFACE MOUNTED TWO-POST LIFTS INSTALLATION AND OPERATION MANUAL

PFS Rotameter. Variable Area Flowmeter. Instruction Manual PFS-RM200, RM230, RM250

INSTALLATION INSTRUCTIONS FOR MOUNTING HARDWARE KIT F-105K2.5

Top-of-Pole Mount for 15 Modules (TPM15) For Module Types E, F, & G ASSEMBLY INSTRUCTIONS

LED144 - PRODUCT INFORMATION

Down and Out Motor Mount Assembly & Installation Directions

Nanometrics Solar Power System

11068 INSTALLATION INSTRUCTIONS

13541 INSTALLATION INSTRUCTIONS

INSTALLATION AND MAINTENANCE GUIDE TUBULAR SERIES WALL MOUNTED ELECTRONIC FAUCET FOR COLD OR PREMIXED WATER

SIGMADUR 520. PRODUCT DATA SHEET December 12, 2014 (Revision of May 01, 2013) DESCRIPTION

YGE-Z 60 Cell Series PV Modules

ALULIFT Portable Aluminium Gantry Crane Operation & Maintenance Instructions

13410 INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS

EZ SunBeam Ground Mount System. with Self-grounding Hardware UL2703 Compliant. Pub. D10034-V003 Copyright of 28

For AEE SnapNRack Only Please read carefully before installing.

Giant Hydraulic Disc Brake System

Read this entire manual before operation begins.

DODGE CUMMINS COOLANT BYPASS KIT

Thruster control assemblies ref iss.1

Colt Series C400, C500

INSTALLATION INSTRUCTIONS

Instruction Sheet SRSR SERIES. Rotating Sliding Rail System

DALI 650mA LED Driver

12114 INSTALLATION INSTRUCTIONS

panelclaw.com Polar Bear III for 10 Degree

1000mA - 650mA Phase Dimmable LED Driver

Mechanical Physician Scale Installation & Operation Instructions PN

Installation and Operation Guide October 2010

Allen-Bradley Parts. CENTERLINE 2500 Motor Control Centers Installing, Joining and Splicing Columns. Installation Instructions. Catalog Number 2500

Atlas PV-9WP Addendum

TM INSTALLATION GUIDE TM 1

PENBERTHY FROST PROOF EXTENSION INSTALLATION, OPERATION AND MAINTENANCE INSTRUCTIONS

TBM Series 3-Way Ball Valve

Transcription:

PV-ezRack SolarTerrace III-A Installation Guide V1.4 CONTENT 1. Introduction...2 2. Tools & Components...3 3. Installation Guide. 8 4. Service..15 Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 1 of 15

1 Introduction Clenergy PV-ezRack SolarTerrace III-A is a pre-assembled ground mount system suitable for large scale commercial and utility scale installations. PV-ezRack SolarTerrace III-A has been developed to fit any PV module. The innovative and patented SolarTerrace III-A T-Rails simplify and improve the accuracy of the installation. Using high quality engineered components SolarTerrace III-A saves developers and installers, time and money when delivering large scale projects. Please review this manual thoroughly before installing your SolarTerrace III-A system. This manual provides (1) supporting documentation for building permit applications relating to PV-ezRack SolarTerrace III-A Mounting system, and (2) planning and installation instructions for SolarTerrace III. SolarTerrace III-A parts, when installed in accordance with this guide, will be structurally adequate and will meet the AS/NZS 1170.2:2011 Amdt. 3-2012 standard. During installation and especially when working on the ground, you will need to comply with the appropriate occupational health and safety regulations. Please also check other regulations relevant to your local region. Make sure that you are using the latest version of the installation instruction guide, which you can do by contacting Clenergy by email on sales@clenergy.com.au, or contacting your local distributor. The installer is solely responsible for: Complying with all applicable local or national building codes, including any that may supersede this manual; Ensuring that ezrack and other products are appropriate for the particular installation and the installation environment; Using only ezrack parts and installer-supplied parts as specified by ezrack (substitution of parts may void the warranty and invalidate the letter of certification on page 2); Ensuring that the ground condition are suitable; How to recycle: according to the local relative statute. How to disassemble: reverse installation process. Ensure that there are no less than two professionals working on the panel installation. Ensure the installation of the electrical equipment is performed by a professional and accredited electrician. Ensuring safe installation of all electrical aspects of the PV array. Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 2 of 15

2 Tools & Components 2.1 Installation Tools Allen Key 6mm (M8 Hexagon Socket Screw) Electric Drill (ST4.8x16 self-tapping screw & M8 Hexagon Socket Screw) Measuring Tape Marker Pen Torque Wrench String Wrench 2.2 Components List PV ezrack STIII-A End Clamp Inter Clamp T-Rail 110 Rail Clamp for T Rail S-Anchor Plate L Anchor Plate Rail Splice Pre-assemble support 30 degree Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 3 of 15

2.3 System Overview 1) End Clamp 2) Inter Clamp 3) T Rail Splice 4) Rail Clamp 5) T Rail 110*4200 6) T Rail 110 7) Truss support 8) Angle Al Support (Optional) 2.4 System Layout Support side view drawings for 20 and 30 degree with Panels up to 1700 x 1000 mm Support side view drawings for 20 and 30 degree with Panels up to 2000 x 1000 mm Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 4 of 15

Location planning of Anchors PLEASE NOTE THE DISTANCE BETWEEN FRONT LEG AND REAR LEG COULD BE DIFFERENT FOR DIFFERENT TILT ANGLES OR FOR DIFFERENT GIRDER LENGTHS. PLEASE CONTACT CLENERGY FOR CONFIRMATION. Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 5 of 15

2.5 Installation Spacing STIII-A Clearance and Spacing (Panels 1700 x 1000 mm) Wind Zone Region A, 30º tilt Region B, 30º tilt Region C, 20º tilt Region D, 20º tilt Wind Speed (m/s) 43 52 64 80 Clearance (m) 0.335 0.335 0.513 0.513 Leg Spacing (m) 3.20 3.00 3.00 2.35 STIII-A Concrete Footing Options (Panels 1700 x 1000 mm) (All dimensions are in meters) Continuous Paving Slab, L x T Region A, 30º tilt Region B, 30º tilt Region C, 20º tilt Region D, 20º tilt 2.50 x 0.15 2.50 x 0.19 2.50 x 0.19 2.70 x 0.25 Continuous Strip Footing, W x D 0.50 x 0.50 0.60 x 0.60 0.60 x 0.60 0.70 x 0.70 Individual Pad Footing, B x C x X Transverse Strip Footing, L x A x D 0.90 x 0.90 x 1.00 1.05 x 1.05 x1.00 2.50 x 0.70 x 0.70 2.80 x 0.75 x 0.75 0.95 x 0.95 x 1.00 2.60 x 0.75 x 0.75 1.05 x 1.05 x 1.00 2.80 x 0.80 x 0.80 Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 6 of 15

STIII-A Clearance and Spacing (Panels 2000 x 1000 mm) Wind Zone Region A, 30º tilt Region B, 30º tilt Region C, 20º tilt Region D, 20º tilt Wind Speed (m/s) 43 52 64 80 Clearance (m) 0.473 0.473 0.671 0.671 Leg Spacing (m) 3.10 2.80 2.85 2.00 STIII-A Concrete Footing Options (Panels 2000 x 1000 mm) (All dimensions are in meters) Continuous Paving Slab, L x T Region A, 30º tilt Region B, 30º tilt Region C, 20º tilt Region D, 20º tilt 2.60 x 0.19 2.70 x 0.25 2.50 x 0.25 3.10 x 0.30 Continuous Strip Footing, W x D 0.55 x 0.55 0.70 x 0.70 0.60 x 0.60 0.75 x 0.75 Individual Pad Footing, B x C x X Transverse Strip Footing, L x A x D 0.95 x 0.95 x 0.95 1.05 x 1.05 x1.00 2.80 x 0.75 x 0.75 2.95 x 0.85 x 0.85 0.75 x 0.75 x 0.75 2.80 x 0.85 x 0.85 0.80 x 0.80 x 0.75 2.80 x 0.90 x 0.90 Notes: * The footing example shown, recommended for firm soils with allowable end bearing capacity of 100 kpa minimum (damp clays, sandy clays, damp sands). Contact Clenergy for site specific conditions (to find out whether more cost effective solution is possible); * Concrete grade: N25 minimum, cover: 50 mm (contact Clenergy to find out whether more cost effective solution is possible, based on site specific conditions); * For the fixing of STIII-A to the concrete footing we recommend using M16 (Grade 5.8 Carbon Steel anchor studs or similar). Adopt minimum anchor embedment depth according the anchors manufacturer s manual. Clenergy STIII-A has 6 anchors per frame, 2 at front and 4 at rear; * Other footing options are possible contact Clenergy. Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 7 of 15

3. Installation Guide Tilt angle: 30 degree Clearance is 472mm Panel size 1650x990x50mm as an example of the installation There are two installation solutions according to the length of the support legs. 3.1 Install Pre-assembled Support 3.1.1 Solution 1 Step 1: Unfold pre-assembled support as shown in Figure 2; Fig. 1 Step 2: Fasten the M12*100 bolts from Al Tube and H Joint first, then rotate L anchor plate and S anchor plate in order to keep them in a same line, as shown as Figure 5. Recommended Torque: M8: 18~20N m M12: 40~45N m Fig. 2 Fig. 3 Fig. 4 Fig. 5 Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 8 of 15

Solution 2: Step 1: Unfold pre-assembled support as shown in Figure 2; Fig. 1 Step 2: Fasten the M12*100 bolts from Al Tube and H Joint first, then rotate L anchor plate and S anchor plate in order to keep them in a same line, as shown as Figure 5. Fig. 2 Recommended Torque: M8: 18~20N m M12: 40~45N m Fig. 3 Fig. 4 NOTE: The screw heads have to keep in a same direction Fig. 5 Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 9 of 15

3.1.2 Connect the Pre-assembled Support and Concrete Base by using Foundation Bolts (M16x240) Recommended Torque: M16: 135~150N m 3.1.3 Check the system and fasten the rest of bolts. Recommended Torque: M8: 18~20N m M12: 40~45N.m 3.1.4 According to the planning, repeat the above operation. Note that all the Tri-Groove Beam must be in the same line. Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 10 of 15

3.2 Install the T Rail 3.2.1 Mark the locations for Rail on Tri-groove beam according to Planning layout.(the dimensions shown on the right is based on an example of panel size) 3.2.2 Before installing the T rails to the Tri-groove beam, make sure the rail is long enough, otherwise connect the T rails using T rail splice. It is recommended to connect the rails before installing them on the Trigroove Beam 3.2.3 Before installing the T rails, mark the position of the rails on the beam Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 11 of 15

3.2.4 Mark the panel array perimeter and attach T rail to Tri-groove beam with one T rail clamp on each side Recommended Torque: M8: 18~20Nm 3.2.5 Install the other rails. Note: The end of the rails must line up. Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 12 of 15

3.3 Install Angle Al Support (Optional) 1Insert M8 * 25 T -head bolt in the slot on the angle Al and rotate the bolt slightly. 2 Place the T-head bolt in the planned position of the Slotted Al-Tube 3 Fasten the T-bolt 4 Repeat the above operations and install T head bolt in another side of Al tube. 5The installation is now completed. Recommended Torque: M8: 18~20Nm Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 13 of 15

3.4 Install Panel 3.4.1 Install PV panel by Inter Clamps and End Clamps. 3.4.2 Keep 20mm vertical gap and 20mm horizontal gap between the two rows. Please take Inter Clamp U18 as the gap location. 20 20 3.4.3 Now the installation is completed. Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 14 of 15

4 Service 10 year limited Product Warranty, 5 year limited Finish Warranty Clenergy co. Ltd warrants to the original purchaser ( Purchaser ) of product(s) that it manufactures ( Product ) at the original installation site that the Product shall be free from defects in material and workmanship for a period of ten (10) years, except for the anodized finish, which finish shall be free from visible peeling, or cracking or chalking under normal atmospheric conditions for a period of five (5) years, from the earlier of 1) the date the installation of the Product is completed, or 2) 30 days after the purchase of the Product by the original Purchaser ( Finish Warranty ). The Finish Warranty does not apply to any foreign residue deposited on the finish. All installations in corrosive atmospheric conditions are excluded. The Finish Warranty is VOID if the practices specified by AAMA 609 & 610-02 Cleaning and Maintenance for Architecturally Finished Aluminum (www.aamanet.org) are not followed by Purchaser. This Warranty does not cover damage to the Product that occurs during its shipment, storage, or installation. This Warranty shall be VOID if installation of the Product is not performed in accordance with Clenergy s written installation instructions, or if the Product has been modified, repaired, or reworked in a manner not previously authorized by Clenergy IN WRITING, or if the Product is installed in an environment for which it was not designed. Clenergy shall not be liable for consequential, contingent or incidental damages arising out of the use of the Product by Purchaser under any circumstances. If within the specified Warranty periods the Product shall be reasonably proven to be defective, then Clenergy shall repair or replace the defective Product, or any part thereof, in Clenergy s sole discretion. Such repair or replacement shall completely satisfy and discharge all of Clenergy s liability with respect to this limited Warranty. Under no circumstances shall Clenergy be liable for special, indirect or consequential damages arising out of or related to use by Purchaser of the Product. Manufacturers of related items, such as PV modules and flashings, may provide written warranties of their own. Clenergy s limited Warranty covers only its Product, and not any related items. Clenergy Australia 1/10 Duerdin St, Clayton VIC 3168 T: +61 3 9239 8088 sales@clenergy.com.au Page 15 of 15