FSITE November 3, 2015
FY2016 Passenger Projection Tampa International Airport is projected to handle 18,871,526 passengers in FY2016, a 2.7% increase over FY2015. 21 Passengers (Millions) 20 19 19.3 18.7 13.8% 18.5 18.9 18 17 17.1 16.6 16.7 16.8 16.9 17.3 16 15 14 FY2007 FY2008 FY2009 FY2010 FY2011 FY2012 FY2013 FY2014 FY2015 FY2016 Budget
FY2016 Passenger Projection Tampa International Airport is projected to handle 18,871,526 passengers in FY2016, a 2.7% increase over FY2015. 450 400 350 300 250 200 150 100 50 0 196 204 243 75% 260 296 342 Passengers (Thousands) FY2010 FY2011 FY2012 FY2013 FY2014 FY2015 FY2016 Budget Growth Rate: 4.3% 19.4% 6.9% 13.6% 12.2% 19.6% 396
20-Year Passenger Forecast
Master Plan Findings Main Terminal: Nearing maximum capacity Rental Cars: At capacity today with no ability to expand Curbside: Nearing maximum capacity Roadways: Nearing maximum capacity Long Term Parking: At maximum capacity A measured approach to growth Phase 1: Decongestion 2013-2018 Phase 2: Enabling 2018-2023 Phase 3: Expansion 2023-2028 When all phases of the master plan are complete, the capacity of TPA will double to 34 MAP.
Master Plan - Phase 1 Estimated Cost: $953 million Jobs created/saved: More than 9,000 Timeline: 2014-2017 Minority contracting: $122 million Projects: 2.6 million-square-foot rental car center 1.4 mile Automated People Mover Transfer level expansion/concessions redevelopment Benefits: Removes 2.7 million cars and buses Allows rental car companies to grow Adds 2,414 spaces to long-term parking Connections to regional transportation
Main Terminal Expansion Budget Estimate:$131.3 million Design Builder: Skanska/HOK East & West Expansion of Transfer Level Relocate Main Terminal Shuttle Lobbies Replace Escalators Reconfigure all Concessions Spaces All New Interior Finishes & Signage Construction is underway Complete November 2017
Automated People Mover Budget Estimate: $414.9 million Design Builder: Austin Commercial/Gresham Smith/Lea Elliott/Mitsubishi 1.4 miles 12 cars Removes 2.7 million cars/buses each year Three Stations: Main Terminal, Economy Garage and Rental Car Center Complete October 2017 Main Terminal APM Station - Interior
Taxiway J Budget Estimate: $414.9 million Design Builder: Austin Commercial/Gresham Smith/Lea Elliott/Mitsubishi 1.4 miles 12 cars Removes 2.7 million cars/buses each year Three Stations: Main Terminal, Economy Garage and Rental Car Center Complete October 2017 View from the South
Taxiway J Taxiway J Bridge in February Earlier this month
Rental Car Center Budget Estimate: $320.9 million Design Builder: Austin Commercial/Gresham Smith/Demattei Wong 60-acre Site 2.6 million square feet, 3 levels Multi level fueling and detailing 180,000-square-foot customer service building 4 rental car service center buildings Complete October 2017
O Brien Street Airport Service Road Real Estate Plan Draft Layout Cellphone Lot Economy Parking Road Parking Garage Office Atrium Pedestrian Trail Upscale Hotel CRE Access Drive Dry Pond ConRAC Realigned Airport Service Road Select Service Hotel Retail Convenience Commercial
Master Plan Expansion Virtual Tour
FSITE November 3, 2015