Sub Regional RTEP Committee - Southern. August 19, 2011

Similar documents
Sub Regional RTEP Committee - Southern

Sub-Regional RTEP Committee PJM South

Sub Regional RTEP Committee South

Sub Regional RTEP Committee South

Reliability Analysis Update

Transmission Expansion Advisory Committee. Reliability Analysis Update

Transmission Expansion Advisory Committee

Surry Skiffes Creek Whealton Modeling and Alternatives Analysis Review

On July 18, 2018, PJM submitted a historical clean-up filing to revise Schedule 12

Sub Regional RTEP Committee Western Region ATSI

System Impact Study Report

Sub Regional RTEP Committee Mid-Atlantic

Feasibility Study Report

Sub Regional RTEP Committee Mid-Atlantic

Illinois State Report

100 MW Wind Generation Project

AMERICAN ELECTRIC POWER 2017 FILING FERC FORM 715 ANNUAL TRANSMISSION PLANNING AND EVALUATION REPORT PART 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic

Sub Regional RTEP Committee Mid-Atlantic

Falcon-Midway 115 kv Line Uprate Project Report

New Jersey State Report

Reliability Analysis Update

Feasibility Study Report

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

Supplemental Report on the NCTPC Collaborative Transmission Plan

Transmission Expansion Advisory Committee

South Dakota 890 Study

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

PJM Sub Regional RTEP Committee Mid-Atlantic January 22, Esam Khadr, Sr. Director Electric Delivery Planning, PSE&G

Feasibility Study Report

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Interconnection Feasibility Study Report GIP-084-FEAS-R2

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Transmission Expansion Advisory Committee (TEAC) Recommendations to the PJM Board

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Interconnection System Impact Study Report Request # GI

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

South Carolina Electric and Gas Company Planned Transmission Projects $2M and above Total 5 Year Budget

Market Efficiency RTEP Proposal Window

Generation Deactivation Notification Update

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

MILLIGAN SOLAR PROJECT

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

MTEP13 SPM #2- Central Region. March 25, 2013

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

SERTP rd Quarter Meeting

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

PG&E s 2012 Request Window Proposals

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Status of PNM s Completed Transmission Construction Projects 11/30/2017

Transmission Coordination and Planning Committee 2014 Q4 Stakeholder Meeting. December 18, 2014

Cromby Units 1 and 2 and Eddystone Units 1 and 2. Deactivation Study

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Gateway South Transmission Project

North Oregon Coast Area Study. Adam Lint

Midway/Monument Area TTC Study

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

ATTACHMENT Y STUDY REPORT

Energy Policy Implications: PJM Planning

Targeted Application of STATCOM Technology in the Distribution Zone

Sub Regional RTEP Committee Mid-Atlantic

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

15 Nelson-Marlborough Regional Plan

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

Large Load Serving Study Report for La Plata Electric Association, Inc. Alternatives. Addendum. San Juan Major Project

3 Reliability Issues and Solutions

Generator Interconnection System Impact Study For

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Reliability Analysis Update

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Market Efficiency RTEP Proposal Window

Market Efficiency Update

Pacific Gas and Electric Company s Revised 2016 Annual Progress

Key to Status Fields in the Project List

Black Hills Project Summary

VACAR STABILITY STUDY OF PROJECTED 2014/2015 WINTER PEAK LOAD CONDITIONS

Rogers Road to Clubhouse 230kV New Transmission Line April 1, 2016

Electric Power Delivery To Big Cities

TRANSMISSION PLANNING CRITERIA

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

2013 ANNUAL PROGRESS REPORT

CUSTOMER/ TWIN ARROWS PROJECT

First Energy Generator Deactivation Request - January Deactivation Study Results and Required Upgrades April 25, 2012

Proposed New Construction for

LLC FACILITIES STUDY TRANSMISSION SERVICE REQUEST

Transmission Expansion Advisory Committee

Feasibility Study. Customer Kingman Area Photovoltaic Generation Project Interconnection

Appendix D Black Hills Project Summary

East. Dalton Utilities. GTC (Georgia Transmission Corporation) MEAG (Municipal Electric Authority of GA) Southern Company Transmission

Q217 Generator Interconnection Project

Reliability Analysis Update

Transcription:

Sub Regional RTEP Committee - Southern August 19, 2011

2011 RTEP Analysis Summary 2010 2015 Project Updates 2016 Analysis NERC Category A, B NERC Category C (N-1-1 in progress) Load Deliverability Generator Deliverability 2

Summer 2013

2013 Summer Region with thermal issues NERC Category B Violations Problem: For the loss of 115kV line #74 at Chesapeake, the Great Bridge switch 16T74 will be closed to restore service to line #74. The Hickory 230/115 kv autotransformer is overloaded for this condition. For the loss of the Hickory 230/115 kv autotransformer, the Great Bridge switch 16T74 will be closed to restore service to line #16. 115 kv line #74 is overloaded for this condition. Proposed Solution: Move Hickory loads off the 115 kv system by replacing the 115/34.5 kv transformer #1 at Hickory with a 230/34.5 kv transformer. Estimated Project Cost: $ 0.75 M Expected IS Date: 6/1/2013 4

Summer 2014

2014 Summer NERC Category B Problem A: For the N-1 loss of line #27 (Greenwich 115 kv to Davis Corner 115 kv) the loading on line #27 (Virginia Beach 115 kv to Bains Store 115 kv) exceeds its emergency rating. Problem B: For the tower line outage of both line #27 and line #67 at Greenwich 115 kv, line #27 cannot pick up all of the loads on line #67 (about 167 MVA in summer 2014) New 115 kv line Oakwood-Burton Potential Solutions: Option A: Add 4 breaker ring bus at Burton 115 kv substation. Construct a 115 kv line approximately 3.5 miles from Oakwood 115 kv substation to Burton 115 kv substation Option B: Rebuild Line #27 from Virginia Beach to Bains Store Option C: Open Line #27 into two radials 6

2014 Summer Solution Evaluation: Estimated Rightof ih Does solution resolve criteria i Project Way violations? Cost Solutions Considered: A B Option A: Burton 115 KV Ring Bus and 115 $ 4.3 13 M Existing Yes Yes kv Line Option B: Rebuild Line #27 between Va $ 13 27 M Existing Yes Yes Beach and Bains Store Option C: Open Line 327(create two Existing Yes No radials) Recommended Solution: Option A - Add 4 breaker ring bus at Burton 115 kv substation. Construct a 115 kv line approximately 3.5 miles from Oakwood 115 kv substation to Burton 115 kv substation Expected IS Date: 6/1/2014 7

Summer 2015

NERC Category B&C 2015 Summer Update to existing PJM baseline upgrade B1332 - Cannon Branch to Cloverhill to Nokesville 230 kv Routing issues are requiring a re-route route of the proposed line. Terminal point for new 230kV line changed from Nokesville to new Liberty Substation to maximize utilization of existing ROW. Construct a 230kV line approximately 5.75 miles along existing right-of-way from Cloverhill Substation to Liberty Substation. Line #2101 will be looped in and out of the new Liberty Substation along existing right-of-way and a new 230/115 kv Tx will be installed. The section of 115 kv line between Gainesville and Liberty will be removed. Revised Proposed Solution - Build Cannon Branch to Cloverhill to Liberty 230 kv Line Estimated Project Cost: $44 M ($4 M increase) Expected IS Date: 6/1/2015 NOKESVILLE CLOVERHILL Old Route 9

Summer 2016

2016 Studies Summary No PATH or MAPP Warren Generation Addition (Queues V2-03, V4-018 & W2-030 Total 1340 MW) DVP Analysis includes all announced generation retirements per Virginia and North Carolina Integrated Resource Plan 11

Region with thermal issues NERC Category B Violations Problem: The 2016 summer base case indicates the following deficiencies: Block load addition is adding 90-110 MW An outage of Line #124(Gainesville Loudoun) overloads the Gainesville 230/115 kv Transformer #3 (This feeds NoVEC circuits #921 & #923) An outage of Line #2030(Gainesville Loudoun) overloads the Gainesville 230/115 kv Transformer #3. 921 2016 Summer 912 Proposed Solution: Install a 230/115 kv Transformer at a new Liberty Substation in the area Estimated Project Cost: $4.3 M Wheeler 922 923 LIBERTY Expected IS Date: 6/1/2016 NOVEC 115 kv CLOVERHILL 12

Region with thermal issues NERC Category B Violations 2016 Summer Problem: An outage of Line #553(Cunningham Elmont 500 kv) overloads the Edinburg 138/115 kv Transformer with no Warren generation online per Dominion s criteria Potential Solution Install 2 nd 138-115 kv Transformer at Edinburg Estimated cost $4.5 M Expected IS Date: 6/1/2016 13

Region with thermal issues 2016 Summer NERC Category B & C Violations (Generation Deliverability & Dominion Analysis) Studied with drought conditions: (Kerr Dam, Gaston and Roanoke Rapids generation off line) Problem: N-1 outage of Line #556 (Clover Carson 500 kv) overloads Line #33 (Halifax Chase City 115 kv) N-1-1 outage of Line 556 (Clover-Carson) and Line #127 (Halifax - Buggs Island 115 kv) overloads Line #33 (Halifax Chase City 115 kv) N-1-1 outage of Line #556 (Clover-Carson) and Line #36 (Chase City Buggs Island) overloads Line #33 (Halifax Chase City 115 kv) N-1-1 outage of Line #556 (Clover Carson 500 kv) and Line #296 (Halifax Person 115 kv) with Halifax 230/115kV Tx #5 overloads Line #33 (Halifax Chase City 115kV) and the Halifax 230/115kV Tx #4 PJM Operations is currently experiencing loading issues on Line 33 (Halifax Chase City 115kV) Potential Solution(s): Interim solution: Apply Dynamic rating technology to achieve higher conductor rating Long Term Solution: Rebuild Line #33 Expected IS Date: 6/1/2016 14

2016 Summer Region with thermal issues NERC Category B Violation Problem: An outage of Line #90 breaker at Kerr 115 kv overloads Line #22 (Eatons Ferry Carolina 115 kv) without Surry 230 kv generation available per Dominion planning criteria Potential Solution Wreck and rebuild remaining section of Line #22 Expected IS Date: 6/1/2016 15

2016 Summer Region with thermal issues NERC Category B Violations Problem: An outage of Line #81 breaker at Carolina overloads Line #123 (Rocky Mount Battleboro 115 kv) Existing operating procedure opens 115 kv (tie line) breaker at Rocky Mount Potential Solution Install a 230/115 kv Tx at Battleboro and re-configure 115 kv lines in area. Expected IS Date: 6/1/2016 16

2016 Summer Region with thermal issues NERC Category B Violations Problem: An outage of Line #2012 (Roanoke Valley Earleys 230 kv) line overloads Line #54 (Carolina to Earleys 115 kv) without Surry 230 kv generation available per Dominion planning criteria Potential Solution Uprate Line #54 (Carolina to Earleys 115 kv) to a higher h rating Expected IS Date: 6/1/2016 17

2016 Summer Region with voltage issues NERC Category B Violations Problem: The 2016 summer base case indicates the following deficiencies: An outage of Line #41 (Kitty Hawk Colington 115 kv) results in low voltage magnitude on the Outer Banks. An outage of SVC at Colington low voltage magnitude on the Outer Banks. 41 Potential Solution Install additional reactive support. May need to be dynamic. Expected IS Date: 6/1/2016 18

2016 Summer Region with thermal issues NERC Category B Violations Problem: An outage of the Wharton 115 kv Capacitor bank causes low voltage magnitude at Pantego Potential Solution Split Wharton 115 kv capacitor bank into two smaller units Adjust area LTC program Add additional reactive support in area Expected IS Date: 6/1/2016 19

Rapid Load Growth

2016 Summer Planning Area of Concern Problem: Rapid load growth in area Potential for an additional 300-900 MW over existing models System Evaluation: Develop a 2020 case to evaluate long term transmission expansion in area. Evaluate HV and EHV possibilities. Estimated Completion Date: 12/2011 Area of Concern 21

2016 Summer Planning Area of Concern Problem: Load growth in this area is continuing to cause reliability concerns. System Evaluation: Line #47 (Fredericksburg Four Rivers 115 kv) is currently constructed t for future 230 kv. Evaluate growth patterns to provide LSE s with potential conversion plan Estimated Completion Date: 2/2012 Area of Concern 22

2016 Summer Planning Area of Concern Problem: Potential rapid load growth area System Evaluation: Evaluate load growth patterns to determine when additional reliability deficiencies on lines #2, #11, #70 and #198 may occur. Objective is to provide local LSE s with insight into potential transmission expansion and potential conversion plans. Estimated Completion Date: 2/2012 Area of Concern 23

New Supplemental Projects

2012 Summer New 115 kv Shiloh delivery point Estimated load is 8 MW(s). Potential Solutions: Install 115 kv breaker and build 1.7 Mile long 115 kv line Loop 115 kv line to 1.7 miles to site Estimated Project Cost: $ 2-3 M Expected IS Date: 9/2012 25

2012 Summer New 115 kv Transco delivery point Estimated load is 28 MW Tap Line #91 (Sherwood to Bremo) and install line switches and associated equipment Estimated Project Cost $ 0.75M Expected IS Date: 10/2012 26

2012 Summer Convert Powhatan delivery point from 35 kv to 230 kv Estimated load 48 MW Tap existing Powhatan 230 kv bus and install associated equipment. Estimated Project Cost: $ 0.75 M Expected IS Date: 8/2012 27

2013 Summer New 230 kv Birdneck delivery point in Virginia Beach, VA. Estimated load is 60 MWs Tap line #2118 (Landstown to Virginia Beach) and install line switches and associated equipment. Estimated Project Cost: $0.75 M Expected IS Date: 6/1/2013 28

2013 Summer New 230 kv delivery point at Brandywine in Charlottesville, VA. Estimated load is 60 MWs. Tap line #233 (Dooms to Charlottesville) and install line switches and associated equipment. Estimated Project Cost: $0.75 M Expected IS Date August 2013 29

2014 Summer New 230 kv delivery point at Benn s Church. Estimated load is 31 MWs. Tap line #263 (Chuckatuck to Newport News) and install line switches and associated equipment. Estimated Cost $0.85 M Expected IS Date: 6/1/2014 30

2014 Summer New transmission delivery point at NSF Dahlgren Will serve a projected load of 45 MWs in 2014, growing to 85 MWs in 2017 Note: revised analysis based on 2011 load projections delayed previous voltage violations from 2014 to 2017 which removed the 2014 need for var correction. Potential solutions: Option A split existing 230 kv line in the vicinity of Arnolds Corner and loop the 230 kv line in and out of the Dahlgren. Estimated Project Cost $ 28.5 M 8-10 miles of new 230 kv line NSF Dahlgren Option B -establish a new 230 kv breaker station ti in the vicinity of Arnolds and build a radial 230 kv line to Dahlgren site. Estimated Project Cost $ 30.8 M Option C Build a radial 230 kv line from Morgantown PS to Dahlgren. Estimated Project Cost $ 70 M Recommended Solution : Option A Expected IS Date: 6/1/2014 31

New 115 kv delivery point named Elm Farm in Woodbridge, VA. 2015 Summer Elm Farm 115 kv Delivery Point Supplemental Project Estimated initial load is 30 MWs. Tap line #183 (Bristers to Ox) and install line switches and associated equipment. Estimated Project Cost: $0.75 M Expected IS Date: 6/1/2015 32