THORNTON SUBSTATION. Why is the substation needed? How were the three potential sites identified?

Similar documents
JCP&L Verbatim Response to Middletown Township s Questions

Mystic to Woburn Line Project. Town of Winchester Board of Selectmen Lincoln School Auditorium February 11, 2016

The Capital Grid Project:

Powering Sydney s Future

Operations Center FAQs

WOLVERINE TO BHP JANSEN NEW TRANSMISSION LINE PROJECT FALL 2017

Tehachapi Renewable Transmission Project. Chino Hills Proposed Alternative. for Segment 8A of the. Chino Hills - September 11, 2007

STAFF REPORT. To: Planning Commission Meeting date: April 12, 2017 Item: UN Prepared by: Robert Eastman

STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS ENERGY FACILITY SITING BOARD

Attachment D Environmental Justice and Outreach

LEED v4 Building Design and Construction Quiz #3 LT

April 18, Mr. David Schmit, County Manager Arapahoe County 5334 S. Prince Street Littleton, CO Conoco Phillips Section 6 Swan Well

LEGAL DESCRIPTION REZONE PARCEL

NEW ECTOR COUNTY NORTH TO MOSS 138 kv TRANSMISSION LINE PROJECT PUBLIC OPEN HOUSE MEETING

welcome to the BC Hydro community open house

Right-of-Way Obstruction Permit Fee Structure Minneapolis Department of Public Works May 10, 2001

US 81 Bypass of Chickasha Environmental Assessment Public Meeting

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

METRO Orange Line BRT American Boulevard Station Options

City of Pacific Grove

Alberta Electric System Operator Needs Identification Document Application. Mowat 2033S Substation

PROJECT BACKGROUND 3

appendix 4: Parking Management Study, Phase II

3.14 Parks and Community Facilities

Bohn to Kettle River Transmission Project

ANDERSON PROPERTY SITE ANALYSIS

ARTICLE X OFF-STREET AUTOMOBILE PARKING AND LOADING AND UNLOADING SPACES

Requests Conditional Use Permit (Open Air Market) Staff Recommendation Approval. Staff Planner Kristine Gay

Kendall Drive Premium Transit PD&E Study Project Kick-Off Meeting SR 94/Kendall Drive/SW 88 Street Project Development and Environment (PD&E) Study

Kettle River Transmission Project

Included in this Stakeholder Information Package:

# BP Gas Station Special Use Permit Amendment for Signs Project Review for Planning and Zoning Commission

Energize Eastside. Underground transmission lines and EMF webinar. Leann Kostek. Senior Project Manager, Puget Sound Energy

Chirmorie Wind Farm Grid Connection

Planning Commission Staff Report Ordinance Amendment Hearing Date: November 14, 2018

10 May 14, 2014 Public Hearing

DISTRICT. Regional Commercial (RC) Light Industrial (LI) No maximum. maximum. 60 acres. Smaller areas may be added to an existing RC area.

CASE NUMBER: 15SN0627 APPLICANT: Stafford H. Cassell

Currant Lake Transmission Project

Big Easy RV & Boat Storage A Green Energy Project Jana Lane Wildomar, California

QUALITY OF LIFE EXECUTIVE SUMMARY REPORT I O N S TAT I O N

SANDAG 3D Visualization Howard Blackson 6:15. Sub Area A Coalition Massing/Phasing - Mike Labarre 6:30

11 October 12, 2011 Public Hearing APPLICANT:

Parking Management Element

FasTracks News. RTD s Eagle P3 Transit Project Nears Halfway Mark to Opening Day EP3 will add three commuter rail lines to metro area in 2016

King Soopers #116 Thornton, Colorado

Energy Technical Memorandum

5.12. DOWNTOWN AREA INFILL INCENTIVE DISTRICT (IID)

Community Advisory Committee. October 5, 2015

Welcome to Inside FasTracks - - your monthly update about FasTracks news, progress and people

CITY PLANNING COMMISSION AGENDA

ARTICLE 15 PARKING AND LOADING REQUIREMENTS

ZEV COHEN & ASSOCIATES. INC. Main Office: Ormond Beach St. Augustine Amelia Island Edgewater

Turnpike Mitigation Program Application

STAFF REPORT FOR THE PLANNING COMMISSION MEETING OF JULY 29, 2009 FILE NO: ZCA AGENDA ITEM: H-4

5 June 12, 2013 Public Hearing APPLICANT: BARTON HERITAGE, LLC T/A SANDBRIDGE BEACH BUGGIES PROPERTY OWNER: LOWER 40, LLC

Preliminary Alternatives Analysis Caltrain Modernization & High Speed Train Projects City of Millbrae

Pace Bus Depot Location Analysis

OPERATIONS NOISE STUDY FOR A PROPOSED AUTOMATIC CAR WASH IN THE SHERMAN OAKS DISTRICT OF LOS ANGELES

FINAL UTILITY REPORT Eastcreek Farm Thornton, CO

BOARD OF ZONING ADJUSTMENT STAFF REPORT Date: November 7, 2016

FREQUENTLY ASKED QUESTIONS

August 2, 2010 Public Meeting

San Rafael Civic Center Station Area Plan May 2012 DRAFT FOR PUBLIC REVIEW

Federal Way Link Extension

RAILYARDS SUPPORT A VARIETY OF OPERATIONS INCLUDING: LOCOMOTIVES, ON-ROAD AND OFF-ROAD TRUCKS, CARGO-HANDLING EQUIPMENT, TRANSPORTATION

DRIVEWAY STANDARDS EXHIBIT A. The following definition shall replace the definition of driveway in Section 62:

CORE AREA SPECIFIC PLAN

APPENDIX VMT Evaluation

MOTOR VEHICLE ORIENTED BUSINESSES.

TRAFFIC DEPARTMENT 404 EAST WASHINGTON BROWNSVILLE, TEXAS City of Brownsville Speed Hump Installation Policy

Mountainland Association of Governments SPRINGVILLE-SPANISH FORK AREA TRANSPORTATION STUDY APRIL 2012

Electric Service Conversion Overhead-to-Underground Xcel Energy Electric Connections. Minnesota North Dakota South Dakota

MAP OR PHOTO. Public Meeting & Open House July 23, Project Roadway Limits From: FM 1957 To: FM 471. Counties Bexar & Medina

STH 60 Northern Reliever Route Feasibility Study Report

SECTION 1 DESCRIPTION OF THE PROPOSED PROJECT

SH 249 IN GRIMES COUNTY. Open House April 3, 2014

SECTION 830 "T-P" - TRAILER PARK RESIDENTIAL DISTRICT

TRANSPORTATION REVIEW

Public Meeting. March 21, 2013 Mimosa Elementary School

Public Information Workshop

FREQUENTLY ASKED QUESTIONS

Ravenswood Avenue Railroad Crossing Project City Council Meeting Study Session April 4, Ravenswood Avenue Railroad Crossing Project

Turnpike Mitigation Program Application

Lower River Floodplain Restoration and Levee/Towne Road Re-Alignment Noise Analysis

4/15/2015 Item #10D Page 1

THE WAY WE MOVE LRT FOR EVERYONE

FIRE DEPARTMENT ACCESS Based on the 2012 edition of the International Fire Code

FREQUENTLY ASKED QUESTIONS

1.1 Purpose of This Environmental Impact Report EIR Process Use of This Report Report Organization...

Bus Stop Optimization Study

Parking and Loading. Page 1 of 7

SECTION 500. PARKING, LOADING AND STORAGE REGULATIONS

Rolling Road (Route 638) Widening Project

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Decision on Merced Irrigation District Transition Agreement

Green Line LRT: Beltline Segment Update April 19, 2017

3. Site Information: Address: TBD Location: Southeast corner of Meridian Rd and Old Meridian Rd Size: 2.48 acres Zoning: CR Commercial Regional

Submission on the Wellington Town Belt Bill. Local Government and Environment Select Committee Parliament Buildings Wellington

Exposition Light Rail Transit Project

Transcription:

THORNTON SUBSTATION Xcel Energy has been working for seven years to identify a new site on which to build a new electrical power substation. If approved by City Council, this will be the first substation to be built in Thornton since 1992 more than two decades ago. Without a new substation, Thornton businesses and residents are at high risk for service interruptions similar to the five-hour power outage in the summer of 2012. Why is the substation needed? Thornton s population has doubled over the last 25 years, with new residents flocking to the area for its reasonable cost of living, local recreational offerings, and proximity to Denver and the Rocky Mountains. This growth has also led to the development of new retailers and commercial centers. And soon, RTD will add a new commuter rail line to the area. This rapid pace of expansion puts ever-increasing demand on the power grid supplying electricity to a growing community. If approved, the substation will: Provide critical, reliable power to Thornton residences, businesses and community facilities, such as schools and hospitals. The substation will reduce the area s risk for extended outages that could disrupt residents everyday lives. Be constructed with underground power lines, as approved by the Colorado Public Utilities Commission (CPUC). Who is the Colorado Public Utilities Commission, and what is their role in the Thornton Substation Project? The CPUC is a division of the Colorado Department of Regulatory Agencies, and Xcel Energy s regulator. Its purpose is to assure the availability of safe, reliable, adequate and efficient electric, gas, steam and water services to utility customers. By granting a Certificate of Public Convenience and Necessity (CPCN) to the Project, the CPUC concluded that a new substation is a needed addition to the Thornton community to support current and future growth, and that existing facilities are inadequate to deliver the expected future load increases in the area the substation will serve. Be designed with neighbors in mind. Xcel Comply with the Colorado CPUC Certificate of Public Convenience and Necessity. In April 2015, Energy will incorporate landscaping, an architectural wall, and other community suggestions to ensure a cohesive design. the CPUC granted a Certificate of Public Convenience and Necessity (CPCN) to Xcel Energy for the Thornton Substation, acknowledging the current and future need for the proposed project to provide reliable power to Thornton residents and businesses. The CPUC considered the Company s proposed siting area for the substation, as shown in the map below, roughly between 120th and 136th avenues in its review and ultimate approval of the CPCN. This area was also supported by the City and ultimately led to the Commission s agreement in allowing the Company to install underground transmission lines to serve the proposed substation. How were the three potential sites identified? Xcel Siting Area Xcel Energy has identified three potential substation sites for the public to consider and comment on. Last year, Xcel Energy rolled out to the community a design for a substation located at the southeast corner of East 136th Avenue and Holly Street. We had evaluated numerous sites and determined that this site would meet electrical and land use criteria established for the project. During our outreach, we heard the community wanted more site options to consider and Xcel Energy went back to evaluate other sites and determine if there were other suitable locations within the siting area. All three sites meet the electrical need of the project and are within the siting area required to provide reliable service to Thornton.

Transmission Why construct the transmission line underground? We have proposed underground transmission construction because the facilities are located in areas characterized by dense residential and commercial development. There is insufficient space between existing and proposed land uses and the edge-of-road right-of-way for an overhead transmission line. The City of Thornton worked with Xcel Energy and the CPUC to help Xcel Energy get state approval to underground the transmission lines for this project. How would you construct underground transmission lines? At any of the proposed three sites, Xcel Energy is proposing to construct the transmission line under existing roadways between the substation site and the existing 115kV transmission line. In preparation for construction, the right-of-way boundaries, sensitive resources (such as waterways), and existing underground utilities are identified and marked. The process of constructing an underground transmission line under a roadway is shown below. Underground transmission lines are constructed by excavating a trench, typically 2 to 3 feet wide and a minimum of 5 to 6 feet deep. The underground transmission line will primarily be constructed in a concrete-encased duct bank system providing for safety, minimizing the potential for dig-ins, and providing for thermal dissipation. After construction, the trench is filled with native soil and the street is repaved. The duct bank will likely have two underground vaults, which are large concrete boxes buried at 2,500-foot intervals along the construction route that help splice the cables and allow permanent access for any needed maintenance and repair. The underground vaults are accessed via two manholes. Trenching Backfill/Asphalt Repair Splice Vault Manholes Splice Vault Installation Temporary Plates Installation Will construction of this line cause problems with traffic and noise? Temporary congestion and noise can be expected during construction. To minimize inconvenience and to maximize safety, Xcel Energy prepares traffic-control plans and obtains street occupancy/street cut permits as part of design and engineering. Construction activities may be restricted during certain hours or during weekends. Xcel Energy will work with the City of Thornton to identify a work schedule that advances the project safely and quickly to minimize traffic impacts, but also accounts for any work hour restrictions necessary during rush hour and near residential areas.

THORNTON SUBSTATION Site Options All three sites meet the electrical need of the project and are within the siting area required to provide reliable service to Thornton. Regardless of the final site selected, Xcel Energy will work with neighborhood residents, the City of Thornton, and other interested stakeholders to develop a site-appropriate design. The design of the architectural wall will use a variety of colors, materials, textures, and heights to integrate the design into the surrounding development. Landscaping, berming, and open space buffers may be used to varying degrees, depending on the size and layout of the final site. A larger site will allow more space for landscaping and other design features. Largest Site (Southeast corner of East 120th Avenue & Holly Street) Will Incorporate Architectural Wall and Underground Power Lines Vacant, Developable Land Meets Electrical Engineering Criteria (will meet customers power needs) Located Furthest from Residences Offers Greatest Distance To Nearest School or Similar Use (Library) Opportunity to Integrate with New Development Minimizes Length of Transmission Line SITE 3B 8.09 Acres 300 Feet 1,055 Feet from Glacier Peak Elementary School 1.2 Miles No 1.8 Miles 425 Feet from AnyThink Library (Northeast corner of East 120th Avenue & Bellaire Way) (Southeast corner of East 136th Avenue & Holly Street) 5.95 Acres A larger site allows for larger buffer areas between neighboring properties that could be used for landscaping, berming, or other design features. Rationale 4.66 Acres An architectural wall and underground power lines would be utilized at all three sites. All three sites are vacant, developable land that have willing sellers. was not vacant during initial siting process (occupied residences were located onsite). In April 2015, the Colorado Public Utilities Commission certified that Xcel Energy s siting area will meet the electrical needs of the project. 180 Feet 185 Feet from Lord of Life Lutheran Church and School 90 Feet from Elms Haven Center 168 Feet 1,007 Feet from Horizon High School No 1.5 Miles All three sites provide enough space such that noise and electromagnetic field (EMF) exposure at proximate residences would not exceed State requirements. Residents and the City of Thornton have expressed a preference to maximize distance from schools and community centers. At, substation site can be incorporated into retail development proposal via partnership with the new landowner. Sites 4 and 10 are surrounded by existing development. The transmission line would be located under East 120th Avenue or East 136th Avenue. A shorter transmission line means less traffic disturbance during construction. Vicinity Map Xcel Siting Area LEGEND Adams County Boundary City of Thornton Multi-Use Trail Substation Site Boundary City of Thornton Zoning Neighborhood Services Community Retail Parks and Open Space Site Name SITE 4 SITE 10

Substation Design What will the substation look like? Our goal is to work with neighborhood residents, the City of Thornton, and other interested stakeholders to develop a site-appropriate design. A preliminary concept shown below uses a variety of colors, materials, textures, and heights to incorporate the design into the surrounding area. These conceptual ideas will be refined further depending on the specific site selected, and the architectural and landscape character of the area surrounding that site. Xcel Energy welcomes input from the community about ways to incorporate the substation into the surrounding area. Some equipment, including the masts used to protect the equipment from lightning strikes, will extend above the wall. Equipment heights are set by the National Electrical Safety Code for safety of personnel and protection of the electric system. Setbacks from streets and adjacent land uses allow space for landscaping and berming and creating the perception of a smaller-scale facility. Interior lighting will only be used for emergency maintenance to restore power. Exterior lighting will be minimized and directed downward to prevent excessive intrusion into neighboring properties. Landscaping may include earth berming and planting a mix of deciduous and evergreen trees and shrubs for added screening and softening of views. Architectural wall will screen most of the equipment from view and will be an appropriate height within the context of the neighborhood. Open space buffers may be used to create the perception of a smaller-scale facility and provide additional separation between adjacent land uses.

Common Questions Are substations and transmission lines safe?. Xcel Energy makes every effort to ensure safety in construction, operation, and maintenance of all its facilities. Our practices meet or exceed standards mandated by the National Electrical Safety Code as well as those adopted by local governments. How would you respond to an on-site emergency? Emergencies are rare, but we recognize that they can happen and we plan for them accordingly. Xcel Energy substations are monitored and controlled remotely from an operations center. In the event of an outage or emergency, the equipment is instantaneously shut off and Xcel Energy personnel will respond in coordination with first responders. I have questions about... Electric and magnetic fields The CPUC also ensures that electric and magnetic fields (EMFs) meet the state s requirements. The CPUC found that the expected EMF values from the substation project, including the connecting power lines, are considered reasonable and do not need to be mitigated. The potential for EMF health effects has been studied extensively for decades. There is substantial agreement among experts that there are no adverse health impacts when substations are placed within 100 feet from homes, schools, or other organizations. For more Information about electric and magnetic fields, please visit xcelenergy.com and type EMF into the search box. Property Values Xcel Energy has consulted with third-party appraisers who completed a study of home and land values near substations in Denver, Arapahoe and Boulder counties. The results indicate there is no measurable market impact on property values because of proximity to substations. Increased Traffic The substation will be accessed from major roads in the city, typically once a week for inspections and maintenance. Other types of facilities that could be permitted in the Neighborhood Services Zone District would likely cause additional traffic, require additional lighting, and involve more noise in comparison to the substation. Sound The CPUC found that the expected audible sound values from the Thornton Substation project are considered reasonable and do not need to be mitigated. The substation will be designed, operated, and maintained so any sounds remain at or below City of Thornton and Colorado State decibel sound limitations associated with residential zone districts (Thornton Code of Ordinances 38-441(c) and Colorado Revised Statutes [CRS] 25-12-101 et seq.). Sound from heavy machinery during construction may create a short-term nuisance during daytime hours. Construction in the City of Thornton is not permitted between the hours of 9 p.m. and 6 a.m. Next Steps Xcel Energy s goal is to have this substation in-service, and providing reliable electricity to Thornton by summer 2018. To accomplish this, we plan to submit land use permit applications to the City of Thornton for one site in Spring/Summer 2016. Between now and then, we will conduct public outreach to solicit residents input, refine a site plan, and prepare permit application materials. We look forward to working with the city and members of the community to get input on which site will work best for everyone. Project Website and Contact Information Website: xcelenergythorntonsubstation.com Email: info@xcelenergythorntonsubstation.com Hotline: 1-844-551-6281 The Neighborhood Services Zone District All three potential sites are zoned as Neighborhood Services (NS) by the City of Thornton. The City s code lists the uses permitted in this District. Electric substations are permitted with a Specific Use Permit, Major Development Permit, and other construction permits. Other uses that could be permitted in the NS Zone District include oil and gas well sites or production sites, banks, offices, convenience-type stores, and food services. xcelenergy.com 2016 Xcel Energy Inc. Xcel Energy is a registered trademark of Xcel Energy Inc.Public Service Company of Colorado, an Xcel Energy Company 3/16