POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013

Similar documents
POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012.

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

POWER SYSTEM OPERATING INCIDENT REPORT MULTIPLE CONTINGENCY EVENT IN NORTH WEST TASMANIA ON 6 APRIL 2012

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

Power System Operating Incident Report Trip of Murray Lower Tumut No kv Transmission Line at Murray End Only on 18 November 2013

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

Power System Operating Incident Report Trip of Red Cliffs Horsham and Red Cliffs-Wemen Kerang 220 kv transmission lines on 15 January 2014

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

POWER SYSTEM INCIDENT REPORT NORTHERN POWER STATION STABILISER OUTAGE APRIL AND MAY 2010

TRIP OF HORSHAM-REDCLIFFS 220 KV TRANSMISSION LINE AND MURRAYLINK INTERCONNECTOR ON 12 NOVEMBER 2015

MULTIPLE LINE OUTAGES IN THE MOUNT ENGLAND TARONG AREA IN QUEENSLAND, 13 FEBRUARY 2017

POWER SYSTEM INCIDENT REPORT: OVERLOAD OF WAUBRA- HORSHAM 220 KV TRANSMISSION LINE AND INSECURE OPERATION OF THE SYSTEM ON 13 DECEMBER 2012

Jemena Electricity Networks (Vic) Ltd

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

Guideline for Parallel Grid Exit Point Connection 28/10/2010

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Utilities (Technical Regulation) (Electricity Transmission Supply Code) Approval 2016 (No 1)*

Guidelines for connection of generators:

Summary of General Technical Requirements for the Interconnection of Distributed Generation (DG) to PG&E s Distribution System

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Final Capacity Auction Results 2019/2020 T-1 Capacity Auction. Date 01/02/2019 Document: FCAR1920T-1 Version 1.0

TRANSMISSION PLANNING CRITERIA

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

Final Capacity Auction Results 2018/2019 T-1 Capacity Auction. Date 26/01/2018 Version 1.0

Grid Tied Limiter User Manual

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Feasibility Study for the Q MW Solar Project

SUBSTATION INTERLOCKING SCHEMES

ELECTRICITY TRANSMISSION USE OF SYSTEM PRICES - 1 JULY 2014 TO 30 JUNE 2015

Emerald Reactive Support Alternative Solution Expressions of interest

SOUTH AUSTRALIAN HISTORICAL MARKET INFORMATION REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

User Agreement For Transfer To/From Other Financial Institution (A2A) Transfer Service

Enquiry Form (Non-Registered Generator With Capacity less than 5 MW)

Managing Electrical Safety on Boats

GUIDELINES FOR OPERATING, METERING AND PROTECTIVE RELAYING FOR. NET METERED SYSTEMS UP TO 50 kw AND BELOW 750 VOLTS

Telhio Credit Union Account to Account (A2A) Transfer Service User Agreement

Enquiry Form for Micro and Small Generators 5MW and Less

Energy Regulation : Australian Experience. Engr.Khondkar Abdus Saleque

Hurricane Sandy. Preparations, Response & Recovery. Wes Yeomans Vice President Operations Management Committee Meeting November 2, 2012

Date Issued: 10 August 2009 Status: ISSUED Review Date: 10 August 2011 Ref: NS5.3 DISTRIBUTED GENERATION TECHNICAL REQUIREMENTS TABLE OF CONTENTS

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

South Australia Victoria (Heywood) Interconnector Upgrade. RIT-T: Project Specification Consultation Report

15 Nelson-Marlborough Regional Plan

The Energy Queensland Group Notice of no non-network options

Washington, DC Area Low Voltage Disturbance

APPLICATION FOR INSTALLATION OF SMALL SCALE EMBEDDED ELECTRICITY GENERATION

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)

Western Power s list of exemptions from compliance from Technical Rules granted after 1 July 2007.

INTERCONNECTION STANDARDS FOR PARALLEL OPERATION OF SMALL-SIZE GENERATING FACILITIES KILOWATTS IN THE STATE OF NEW JERSEY

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

2015 WDC Disturbance and Protection Standards Overview

The Ultimate Smart Grid Solution INSTRUCTION MANUAL

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

2013 Grid of the Future Symposium. Utilizing Single Phase Operation Scheme on Untransposed 765kV lines for a Stability-Limited Plant

Feasibility Study for the Q MW Solar Project

Smart Grid Automation and Centralized FISR

Installation Power Management Unit Battery Cables and Battery Harness

2017 Interim Area Transmission Review of the New York State Bulk Power Transmission System

An Introduction to Completing a NERC PRC Study

WARRANTY POLICY. Grid-Tied Photovoltaic Inverters. Revision D. 2014, Solectria Renewables, LLC DOCIN

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Louisville Gas and Electric Company

The Ultimate Smart Grid Solution INSTRUCTION MANUAL

MICROCARE 3 PHASE INVERTER MANUAL

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

Bald Hill on track to start lithium concentrate production this quarter

MMP Investigation of Arthur Kill 2 and 3

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Small Generator Interconnection Program Interconnection Technical Requirements

A member-consumer with a QF facility shall not participate in the Cooperative s electric heat rate program.

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

AN RPM to TACH Counts Conversion. 1 Preface. 2 Audience. 3 Overview. 4 References

Embedded Generation Guidelines

Case Study on On EHV Circuit Breaker Flashover NTPC-SINGRAULI

KIA Roadside Assist Terms and Conditions

Broadband PowerShield. CP27U Models. User Manual

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

GUIDE FOR MICROGENERATION INTERCONNECTION TO CITY OF MEDICINE HAT ELECTRIC DISTRIBUTION SYSTEM

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

II DISTRIBUTION & SUBSTATION TYPE C

When power interruptions happen.

STAY SAFE NEAR ELECTRICITY

Andatech SOBERPOINT 3. Wall Mounted Breathalyser USER S MANUAL

Eyre Peninsula electricity supply options investigation

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 RULE NO. 17 NET ENERGY METERING

Title Electrical Technical Maintenance Coding System. Reference Number PMP 01 (RIC Standard: EP SP)

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study

HYDRONIC LIFT SOLUTION FOR A3 AMENDMENT

DSA with wind security tool and automatic curtailment suggestion Siemens AG, EM SG PTI, 2015 All rights reserved

DISCOVER ADVANCED ENERGY SYSTEM - AES WARRANTY POLICY

16kA Solid Dielectric, Triple Option Reclosers Catalog VLT12

KAUAI ISLAND UTILITY COOPERATIVE KIUC Tariff No. 1 Lihue, Kauai, Hawaii Original Sheet 5 RULE NO. 2 CHARACTER OF SERVICE

Exemptions currently in force

ShipRight Notice 1A for

PPL GOLD Credit Union User Agreement for Account to Account (A2A) Transfer Service

Health and Safety Executive, Technology and Health Sciences Division, Magdalen House, Bootle.

Transcription:

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS MARCH 03 PREPARED Y: Systems Capability DATE: 7 June 03 FINAL

Disclaimer Purpose This report has been prepared by the Australian Energy Market Operator Limited (AEMO) for the sole purpose of meeting obligations in accordance with clause 4.8.5 (c) of the National Electricity Rules (NER). No reliance or warranty This report contains data provided by third parties and might contain conclusions or forecasts and the like that rely on that data. This data might not be free from errors or omissions. While AEMO has used due care and skill, AEMO does not warrant or represent that the data, conclusions, forecasts or other information in this report are accurate, reliable, complete or current or that they are suitable for particular purposes. You should verify and check the accuracy, completeness, reliability and suitability of this report for any use to which you intend to put it, and seek independent expert advice before using it, or any information contained in it. Limitation of liability To the extent permitted by law, AEMO and its advisers, consultants and other contributors to this report (or their respective associated companies, businesses, partners, directors, officers or employees) shall not be liable for any errors, omissions, defects or misrepresentations in the information contained in this report, or for any loss or damage suffered by persons who use or rely on such information (including by reason of negligence, negligent misstatement or otherwise). If any law prohibits the exclusion of such liability, AEMO's liability is limited, at AEMO's option, to the re-supply of the information, provided that this limitation is permitted by law and is fair and reasonable. 03 Australian Energy Market Operator Ltd. All rights reserved 7 June 03 Page of

Abbreviations and Symbols Abbreviation AEMO C DI EMMS EMS ENVI & LI kv MW NER OFGSS TL Term Australian Energy Market Operator Circuit reaker Dispatch Interval Electricity Market Management System Energy Management System Environment and Lightning Kilovolt Megawatt National Electricity Rules Tasmania Over-Frequency Generator Shedding Scheme Loss of transmission elements and load interruption 7 June 03 Page 3 of

Contents Disclaimer... Abbreviations and Symbols... 3 Incident summary... 5 Introduction... 6 Incident in Tasmania at 834 hrs March 03... 6. Pre-Contingent System Conditions... 6. Summary of events... 7.3 Immediate actions taken... 8 3 Incident in Tasmania at 90 hrs March 03... 9 3. Summary of events... 9 3. Immediate actions taken... 0 4 Incident in Tasmania at 057 hrs March 03...0 4. Summary of events... 0 4. Immediate actions taken... 5 Follow-up Actions... 6 Power System Security Assessment... 7 Conclusions... 8 Recommendations... 7 June 03 Page 4 of

Incident summary Date and time of incident 834 hrs March 03 90 hrs March 03 057 hrs March 03 Region of incident Affected regions Tasmania Tasmania Event type Loss of transmission elements and load interruption (TL) Primary cause Impact Associated reports Environment and Lightning (ENVI & LI) Significant Nil 7 June 03 Page 5 of

Introduction Three contingencies occurred on the Tasmanian power system on March 03 that resulted in a reduction of load at the Pacific Aluminium potlines: a. Simultaneous loss of Farrell - Sheffield No. and No. 0 kv transmission lines at 834 hrs March 03. Pacific Aluminium reduced in load by 8 MW. b. Loss of George Town Sheffield No. 0 kv transmission line at 90 hrs March 03. Pacific Aluminium reduced in load by 00 MW. c. Loss of George Town - Sheffield No. 0 kv transmission line at 057 hrs March 03. Pacific Aluminium reduced in load by MW. This report has been prepared under clause 4.8.5 (c) of the National Electricity Rules (NER) to assess the adequacy of the provision and response of facilities and services and the appropriateness of actions taken to restore or maintain power system security. This report is largely based upon information provided by Transend. AEMO's Energy Management System (EMS) and Electricity Market Management System (EMMS) have also been used in analysing the incident. All references to time in this report are to National Electricity Market time (Australian Eastern Standard Time). Incident in Tasmania at 834 hrs March 03. Pre-Contingent System Conditions There was significant lightning activity across Tasmania on March 03. The following contingencies had been re-classified as credible due to lightning: a. Simultaneous loss of Farrell Reece No. and No. 0 kv transmission lines. Constraint set F-T-FARE_N- was invoked in DI ending 555 hrs. Market Notice 496 was issued at 556 hrs. b. Simultaneous loss of Farrell Sheffield No. and No. 0 kv transmission lines. Constraint sets F-T-FASH_N-, T-FASH_N-_HM_C and T-NIL_HM_CLOSE were invoked in DI ending 60 hrs. Market Notice 496 was issued at 6 hrs. The normally open 0 kv transmission link between Farrell and urnie was closed at 609 hrs in accordance with contingency plans, and the Farrell 0 kv buses isolated from each other, refer to Figure. In this configuration, the 0 kv network will be supplied from urnie for the loss of Farrell Sheffield No. and No. 0 kv transmission lines, and generation at Farrell may be islanded. c. Simultaneous loss of George Town Sheffield No. and No. 0 kv transmission lines. Market Notice 4965 was issued at 744 hrs. Constraint set T-GTSH_N- was invoked at 745 hrs. The status of the power system prior to the incident is shown in Figure. For clarity only equipment relevant to this incident has been included in the diagram. Prepared by Transend and agreed to by AEMO. 7 June 03 Page 6 of

Figure - Pre-contingent system conditions prior to the incidents in Tasmania on March 03 334 MW PACIFIC ALUMINUM TAMAR VALLEY CCGT GEORGE TOWN 0 KV (part) URNIE 0 KV F 3 4 5 G5 F5 X5 Y9F X9F 9C 5 A9C A5 A9D A9C F79F 79F A79F A9A A9 49 C49A C49 G79F G9A G9 F79 F9 75 79 A45 A49 A75 XA9 V9 0 kv usbar, line 3 kv usbar, line Out of service usbar, line 45 0 / 3 kv Transformer 0 kv network between urnie and Farrell. T GEORGE TOWN 0 KV 0 / 3 kv Transformer Closed C Open C Generator Closed Isolator JOHN UTTERS - synchronous condenser mode REECE REECE - out of - 00 MW service Z5 Y5 J5 K5 L5 Open Isolator 5 9A A49 A49 A45 T 49A D9A E9A A75 49 45 Wind Farm J5 E5 D5 H5 DH9 EJ9 H9 J9 FARRELL 0 KV (part) E A WZ9 Z9A J9 K9 J9E K9E XY9 Y9A GL9 SHEFFIELD 0 KV (part) L9 A55 T 55. Summary of events At 834 hrs March 03, the Farrell Sheffield No. and No. 0 kv transmission lines tripped out of service due to a fault associated with a lightning strike. The fault was cleared by protection within approximately 80 milliseconds. As a result of the trips, generating units Reece Unit (00 MW of generation) and John utters (operating as a synchronous condenser) were islanded and therefore also tripped out of service. The Tasmanian Over-Frequency Generation Shedding Scheme (OFGSS) operated to open the circuit breakers at the Farrell end of the generator transmission lines 3. Approximately seconds after the fault was cleared Pacific Aluminium reduced in load by 8 MW, on potline No.4. A summary of events is shown in Table. Table : Sequence of events during incident: 834 hrs March 03. Time Event 834 hrs March 03 0 kv C H5 at Farrell opens, due to lightning strike. 834 hrs March 03 0 kv C J5 at Farrell opens, due to lightning strike. 834 hrs March 03 0 kv C Y5 at Sheffield opens, due to lightning strike.. Farrell-Sheffield No. 0 kv transmission line removed from service. 834 hrs March 03 0 kv C Z5 at Sheffield opens, due to lightning strike. Farrell-Sheffield No. 0 kv transmission line removed from service. 834 hrs March 03 0 kv C 5 at Farrell opens due to operation of the OFGSS. John utters unit disconnected from Farrell Red phase and blue phase fault to ground on No. line. Three phase fault to ground on No. line. 3 The present configuration of the OFGSS is to trip line circuit breakers of generating units operating in synchronous condenser mode, in addition to generating units supplying active power. 7 June 03 Page 7 of

Time Event 834 hrs March 03 0 kv C E5 at Farrell opens due to operation of the OFGSS. Reece Unit disconnected from Farrell 00 MW of generation lost. 834 hrs March 03 Pacific Aluminium reduces in load by 8 MW. 834 hrs March 03 0 kv C 5 at Reece Unit opens on operation of over-frequency protection. 835 hrs March 03 0 kv C 5 at John utters opens, on relay indication of insufficient line current to sustain synchronous condenser mode. The status of the power system immediately after the incident is shown in Figure. Figure :- Status of the power system immediately after the incident 834 hrs March 03. PACIFIC ALUMINUM Reduced by 8 MW to 6 MW TAMAR VALLEY CCGT GEORGE TOWN 0 KV (part) URNIE 0 KV F 3 4 5 G5 F5 X5 Y9F X9F 9C 5 A9C A5 A9D A9C F79F 79F A79F A9A A9 49 C49A C49 G79F G9A G9 F79 F9 75 79 A45 A49 A75 XA9 V9 0 kv usbar, line 3 kv usbar, line Out of service usbar, line 45 0 / 3 kv Transformer 0 kv network between urnie and Farrell T GEORGE TOWN 0 KV 0 / 3 kv Transformer Closed C Open C Generator Closed Isolator JOHN UTTERS - out of service REECE REECE - out of - out of service service Z5 Y5 J5 K5 L5 Open Isolator 5 9A A49 A49 A45 T 49A D9A E9A A75 49 45 Wind Farm J5 E5 D5 H5 DH9 EJ9 H9 J9 FARRELL 0 KV (part) E A WZ9 Z9A J9 K9 J9E K9E XY9 Y9A GL9 SHEFFIELD 0 KV (part) L9 A55 T 55.3 Immediate actions taken The Farrell Sheffield No. and No. 0 kv transmission lines were returned to service at 846 hrs. Load restoration at Pacific Aluminium commenced at 849 hrs. Generating units Reece Unit and the John utters were returned to service at 953 hrs and 957 hrs respectively. AEMO issued Market Notice 4975 at 036 hrs, advising the market of the incident. At 049 hrs AEMO issued Market Notice 4977, advising the market that the loss of Farrell Sheffield No. and No. transmission lines and Pacific Aluminium load had been re-classified as a credible contingency. 7 June 03 Page 8 of

3 Incident in Tasmania at 90 hrs March 03 3. Summary of events At 90 hrs March 03, the George Town - Sheffield No. 0 kv transmission line tripped out of service due to a fault associated with a lightning strike 4. The fault was cleared by protection within approximately 80 milliseconds. Following fault clearance, both circuit breakers at the George Town end of the transmission line automatically reclosed. Approximately seconds after the fault was cleared Pacific Aluminium reduced in load by 00 MW, on potline No. 3. A summary of events is shown in Table. Table : Sequence of events during incident: 90 hrs March 03. Time 90 hrs March 03 0 kv C L5 at Sheffield opens. Event 90 hrs March 03 0 kv C 5 at George Town opens. 90 hrs March 03 0 kv C 75 at George Town opens. George Town - Sheffield No. 0 kv transmission line removed from service. 90 hrs March 03 0 kv C 5 at George Town automatically recloses. 90 hrs March 03 0 kv C 75 at George Town automatically recloses. 90 hrs March 03 Pacific Aluminium reduces in load by 00 MW. The status of the power system immediately after the incident is shown in Figure 3. Figure 3:- Status of the power system immediately after the incident 90 hrs March 03. PACIFIC ALUMINUM Reduced by 00 MW to 30 MW TAMAR VALLEY CCGT GEORGE TOWN 0 KV (part) URNIE 0 KV F 3 4 5 G5 F5 X5 Y9F X9F 9C 5 A9C A5 Line opened at Sheffield end A9D A9C F79F 79F A79F A9A A9 49 C49A C49 G79F G9A G9 F79 F9 75 79 A45 A49 A75 XA9 V9 0 kv usbar, line 3 kv usbar, line Out of service usbar, line 45 0 / 3 kv Transformer 0 kv network between urnie and Farrell T GEORGE TOWN 0 KV 0 / 3 kv Transformer Closed C Open C Generator Closed Isolator JOHN UTTERS - out of service REECE REECE - out of - out of service service Z5 Y5 J5 K5 L5 Open Isolator 5 9A A49 A49 A45 T 49A D9A E9A A75 49 45 Wind Farm J5 E5 D5 H5 DH9 EJ9 H9 J9 FARRELL 0 KV (part) E A WZ9 Z9A J9 K9 J9E K9E XY9 Y9A GL9 SHEFFIELD 0 KV (part) L9 A55 T 55 4 Red phase fault to ground. 7 June 03 Page 9 of

3. Immediate actions taken The 0 kv C L5 at Sheffield was manually closed at 90 hrs, returning the George Town - Sheffield No. 0 kv transmission line to service. Load restoration at Pacific Aluminium commenced at 908 hrs. At 053 hrs AEMO issued Market Notice 4978, advising the market of the Incident. AEMO did not issue a market notice reclassifying the George Town Sheffield No. 0 kv transmission line and Pacific Aluminium; the incident happened a second time (Section 4 of this report) before AEMO had completed assessing this incident. 4 Incident in Tasmania at 057 hrs March 03 4. Summary of events At 057 hrs March 03, the George Town - Sheffield No. 0 kv transmission line tripped out of service due to a fault associated with a lightning strike 5. The fault was cleared by protection within approximately 80 milliseconds. While the fault was being cleared, Pacific Aluminium reduced in load by 9 MW on potline No. 4. Approximately second after the fault was cleared Pacific Aluminium reduced in load by 0 MW, on potline No. 3. A summary of events is shown in Table 3. Table 3: Sequence of events during incident: 057 hrs March 03. Time 057 hrs March 03 0 kv C L5 at Sheffield opens. Event 057 hrs March 03 0 kv C 5 at George Town trips to lockout. 057 hrs March 03 0 kv C 75 at George Town trips to lockout. 057 hrs March 03 Pacific Aluminium reduces in load by 9 MW. 057 hrs March 03 Pacific Aluminium reduces in load by 0 MW. The status of the power system immediately after the incident is shown in Figure 4. 5 Red phase and blue phase fault to ground. 7 June 03 Page 0 of

Figure 4:- Status of the power system immediately after the incident 057 hrs March 03. PACIFIC ALUMINUM Reduced by MW to 45 MW TAMAR VALLEY CCGT GEORGE TOWN 0 KV (part) URNIE 0 KV F 3 4 5 G5 F5 X5 Y9F X9F 9C 5 A9C A5 A9D A9C F79F 79F A79F A9A A9 49 C49A C49 G79F G9A G9 F79 F9 75 79 A45 A49 A75 XA9 V9 0 kv usbar, line 3 kv usbar, line Out of service usbar, line 45 0 / 3 kv Transformer 0 kv network between urnie and Farrell T GEORGE TOWN 0 KV 0 / 3 kv Transformer Closed C Open C Generator Closed Isolator JOHN UTTERS Synchronous condenser mode REECE REECE - out of - 97 MW service Z5 Y5 J5 K5 L5 Open Isolator 5 9A A49 A49 A45 T 49A D9A E9A A75 49 45 Wind Farm J5 E5 D5 H5 DH9 EJ9 H9 J9 FARRELL 0 KV (part) E A WZ9 Z9A J9 K9 J9E K9E XY9 Y9A GL9 SHEFFIELD 0 KV (part) L9 A55 T 55 4. Immediate actions taken An attempt was made to re-energise the George Town - Sheffield No. 0 kv transmission line via 0 kv C L5 at Sheffield. 0 kv C L5 at Sheffield tripped approximately six seconds later and the transmission line remained out of service until the line was patrolled. At 03 hrs AEMO issued Market Notice 498, advising the market of the incident. Constraint set T-GTSH was invoked in DI ending 05 hrs. Restoration of load at Pacific Aluminium commenced at 5 hrs. At 4 hrs AEMO issued Market Notice 4984, advising the market that the loss of George Town Sheffield No. 0 kv transmission line and Pacific Aluminium load had been re-classified as a credible contingency. 5 Follow-up Actions Transend patrolled the George Town - Sheffield No. 0 kv transmission line on the morning of March 03. The George Town - Sheffield No. 0 kv transmission line was returned to service 7 hrs March 03. Constraint set T-GTSH was revoked at 335 hrs March 03. Pacific Aluminium investigated the three load reductions of their potlines. The load reduction at 834 hrs March 03 was determined to be due to a relay operating on phase asymmetry protection. The phase asymmetry relay function was subsequently disabled by Pacific Aluminium. The load reductions at 90 hrs and 057 hrs were due to emergency shutdown relays at Pacific Aluminium operating as a result of the voltage drop during the fault. The emergency shutdown relays are supplied by battery banks. The battery banks are supplied by battery chargers; and the battery chargers tripped during the fault. Due to the age of the battery banks, when the battery chargers tripped the DC voltage supplying the emergency shutdown relays dropped to a level seen as loss of voltage to the relays. The fail-safe design of the emergency shutdown relays tripped the potlines. 7 June 03 Page of

The battery banks supplying the emergency shutdown relays have subsequently been replaced by Pacific Aluminium. On 9 April 03, AEMO issued Market Notices 48 and 49, advising the market that the reclassifications associated with Pacific Aluminium had been cancelled. 6 Power System Security Assessment The post-contingent system voltages and frequencies remained within the normal operating bands and the power system remained in a secure operating state throughout each incident. The control of the Tasmanian frequency was consistent with the Tasmania Frequency Operating Standard. The fault clearance times on each transmission line trip was consistent with the NER. The load reductions at Pacific Aluminium were consistent with the NER as load is not required to ride through system disturbances. The provision and response of facilities was adequate to maintain power system security. 7 Conclusions The trip of the transmission lines in Tasmania at 834 hrs, 90 hrs and 057 hrs March 03 were caused by lightning strikes. The consequent load reductions at Pacific Aluminium in response to these faults were caused by plant protection operation; and operation of emergency shutdown systems failing safe due to loss of supply during the fault. AEMO is satisfied that Pacific Aluminium has carried out the appropriate work to mitigate the risk of a similar incident occurring in the future. AEMO correctly applied the criteria published in section 3 of its Power System Security Guidelines in assessing that the circumstances of these incidents warranted reclassifying similar incidents as a credible contingency event. 8 Recommendations There are no recommendations arising from this incident. 7 June 03 Page of