P.O BOX 429, NUKU ALOFA, Tel: (676) Fax: (676)

Similar documents
Regulatory Annual Report 2014/15 In Compliance with the Reporting Requirements of Schedule 13 of the Electricity Concession Contract (I)

Commercial-in-Confidence Ashton Old Baths Financial Model - Detailed Cashflow

NJ Solar Market Update As of 6/30/15

MONTHLY PERFORMANCE DASHBOARD

Electricity Industry Code Minimum Service Standards & Guaranteed Service Levels Quarterly Report July September 2008

NJ Solar Market Update

MONTHLY PERFORMANCE DASHBOARD

MONTHLY PERFORMANCE DASHBOARD

MONTHLY PERFORMANCE DASHBOARD

System Status Briefing

MONTHLY PERFORMANCE DASHBOARD

GAZIFÈRE INC. Prime Rate Forecasting Process 2017 Rate Case

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*

MONTHLY PERFORMANCE DASHBOARD

NJ Solar Market Update As of 2/29/16

NJ Solar Market Update As of 10/31/15

FY2/18 2Q(March 2017~August 2018)

FOR IMMEDIATE RELEASE

1. Trends in the current fiscal year and previous fiscal year 3. Business overview 2. Secular trends in first quarter financial results

FOR IMMEDIATE RELEASE

PDR Energy Baseline Alternative. Proposal for Discussion October 27, 2015

FY2/18 (March 2017~February 2018)

Ameren Missouri. AMENDED Renewable Energy Standard Compliance Report Prepared in Compliance with 4 CSR

FOR IMMEDIATE RELEASE

Review of Reliability Must-Run and Capacity Procurement Mechanism BBB Issue Paper and Straw Proposal for Phase 1 Items

FOR IMMEDIATE RELEASE

FOR IMMEDIATE RELEASE

Solar and Smart Meter Update. 1 April 2014 to 30 June 2014 Released July 2014

Massachusetts Electric Company and Nantucket Electric Company, Docket No. D.T.E

Up and Down Months of the Stock Market

November 2018 Customer Switching Report for the Electricity and Gas Retail Markets

Economics of Integrating Renewables DAN HARMS MANAGER OF RATE, TECHNOLOGY & ENERGY POLICY SEPTEMBER 2017

November 2017 Customer Switching Report for the Electricity and Gas Retail Markets

FOR IMMEDIATE RELEASE

Transmission Access Charges (TAC) Katie Ramsey Staff Attorney Clean Coalition mobile

Electric Vehicle Program

Docket No. DE Dated: 05/04/2015 Attachment CJG-1 Page 1

GROWTH IN TENTH DISTRICT MANUFACTURING ACTIVITY EDGED HIGHER Federal Reserve Bank of Kansas City Releases September Manufacturing Survey

Summer Reliability Assessment Report Electric Distribution Companies Perspective

FY2/17 3Q(March 2016~November2016)

Glendale Water & Power Smart Grid Project

Renewable Energy & Storage Best Practice at TPL and Issues Faced. Murray Sheerin Power Generation Manager, Tonga Power Limited.

Monthly Operating Report. September 2016

WIM #37 was operational for the entire month of September Volume was computed using all monthly data.

Temporary Adjustments to Rates for Low-Income Programs.

Total Production by Month (Acre Feet)

National Grid's Electric Revenue Decoupling Mechanism ("RDM") Reconciliation Filing for the Year Ending March 31, 2013 Docket No.

Factory activity accelerated further in our region this month, posting its highest composite reading since 2011, said Wilkerson.

December 2018 RenewableGenerations Monthly Report

UNITIL ENERGY SYSTEMS. INC. CALCULATION OF THE EXTERNAL DELIVERY CHARGE

Customer Service, Operations and Security Committee. Information Item III-A. January 12, 2017

RE: Advice Schedule 45 Public DC Fast Charger Delivery Service Optional Transitional Rate REPLACEMENT PAGES

University of Michigan Eco-Driving Index (EDI) Latest data: October 2017

What is the Future of Competitive Markets? Some Fundamental Preliminaries and View from Events in the PJM Market

Consumer Price Index

October 23, September year. in 1Q confidence in our. exacerbated by the. 0.3 percent. outpu. (over) Index of Sales. Mar 12.

Graph #1. Micro-Generation Generating Units in Alberta 20

Commuter Rail Update. October 25, 2018

NEU Regulatory Update

FY2/17 (March 2016~February 2017)

Sound Transit Operations July 2016 Service Performance Report. Ridership

Facilitated Discussion on the Future of the Power Grid

Growth cycles in Industrial production (IIP) (percentage deviation from trend*, seasonally adjusted) Sep 88 Sep 94. Dec 96. Mar 96

WIM #29 was operational for the entire month of October Volume was computed using all monthly data.

Information Packet Kissimmee Utility Authority Customer-Owned Renewable Generation Interconnection And Net Metering Program

August 2018 MLS Statistical Report

Distribution Charging Update

Unalakleet Update: Lessons learned & continual improvement. Alaska WWG

DRAFT. Total Month Average Point (MAP) A Massage 4/30/2014 8/1/2015 A CENTER E

NEU Electric and Natural Gas Price Update

Electric Vehicle Charge Ready Program

ELECTRIC SERVICE RATE SCHEDULES. Effective November 1, 2017

FY2/16(March 2015~February 2016)

ELECTRICITY TARIFFS 2013/2014

Presented by Eric Englert Puget Sound Energy September 11, 2002

A detailed copy of the proposed tariff application can be downloaded from Kenya Power and the ERC websites /

Growth cycles in Industrial production (IIP) (percentage deviation from trend*, seasonally adjusted) Jan-00 Aug-06 Sep-94. Dec-01.

October 17, Please contact the undersigned directly with any questions or concerns regarding the foregoing.

MCE Napa County Cleaner energy and lower rates. Honig Winery, Rutherford

NEWS Release. U.S. Manufacturing Technology Orders. Year-to-date U.S. manufacturing technology orders up 4.1% over 2011

ELECTRICAL UTILITY COST REDUCTION THROUGH PREDICTIVE CONTROL December 2008 BACKGROUND

II pepco. February 6, 2018

Monthly Operating Report. December 2017

AN OUTLINE HISTORY OF DANISH WIND TURBINE PRODUCTION: Output and Longevity from 1977 to 2014.

MSU Mankato and Ameresco. GESP Project. August 29, Ameresco, Inc. 2017, All Rights Reserved

Passive Investors and Managed Money in Commodity Futures. Part 2: Liquidity. Prepared for: The CME Group. Prepared by:

BOARD OF COUNTY COMMISSIONERS AGENDA ITEM SUMMARY. Consent Workshop [ ]

T&TEC s Annual Performance Indicator Report

FOR IMMEDIATE RELEASE

Energy Performance Information Request Timeline

Used Vehicle Supply: Future Outlook and the Impact on Used Vehicle Prices

September 2016 Water Production & Consumption Data

FY H1 Financial Results

AOBA Utility and Energy Market Update DC, Maryland, and Virginia May 6, 2015

Predict Future Failures From Your Maintenance Records

A Guide to the medium General Service. BC Hydro Last Updated: February 24, 2012

Pitti Laminations Limited

ABB Innovation & Technology Day

Innovation in Transport. Mike Waters

Transcription:

P.O BOX 429, NUKU ALOFA, Tel: (676) 27-390 Fax: (676) 23-047 Email: jvanbrink@tongapower.to 22 October 2012 Lord Dalgety Electricity Commission Tu atakilangi Nuku alofa Dear Lord Dalgety Compliance Reporting for the Month of October In accordance with the reporting requirements of the Concession Contract and in response to your request for additional information as specified in the suggested MOU dated May 2012, TPL submits the following reports for the month of October 2012. 1. Service & Metering Reporting Standards 2. Quarterly Capex Update 3. Quarterly Regulated Asset Value (RAV) Update 4. System Loss Report 5. Reliability Measures 6. Monthly Faults Events 7. Tariff Review Proposal Additional reporting items: 8. Generator Security Profile The above report items are described in detail below. 1. Service & Metering Reporting Standards TPL comply with all service and metering standards and meet all the performance targets specified in the Schedule 1 of the Concession Contract except for one overall standard (B2. Electricity quality & reliability) to which it partially complies. In accordance with this standard, TPL is as yet unable to fully test the voltage at the end of the feeders in the outer islands, due to the cost of the required permanent loggers and to lack of resources. The Tongatapu voltage is being logged at the power station and samples were taken at the ends of the feeders to provide a correlation until permanent facilities can be fitted. The voltage is also logged at the power station in the outer islands but samples cannot currently be taken at the end of the feeders. 1

A World Bank project is commencing, the aim is for this additional equipment to be installed at the ends of the feeders on all islands so as to help satisfy the testing for this service standard completely. The cost of this is estimated at around T$200,000. As a result of fully complying with service and metering reporting standards, TPL has not paid any penalties to the public for last six months period. The above standards are now managed through TPL s Quantate Software and an extract of this comprehensive compliance report from Quantate is attached with this report for reference. 2. Quarterly CAPEX Update The graph below shows the capital expenditure for the first quarter of the 2012/13 financial year. A new generator (2.88MW MAK Generator No. 8) was forecast to be procured by now, based on demand analysis (see Section 8: Generation Security Profile), for Tongatapu to achieve the N-1 security. As a result of flat demands the project did not proceed as planned in the first quarter and now it has been postponed until after October 2012. Other capital expenditure has been moved into future months, to reflect phasing changes. Note that the generation expenditure shown below assumed full commitment of expenditure for the new generator, in effect once the project commences, expenditure will be reflected in several staged payments. $6,000,000 Budget Vs Actual Capital Expenditure - 2012/13 Quarter 1 $5,000,000 $4,000,000 $3,000,000 $2,000,000 $1,000,000 $0 Distribution network assets Generation equipment Tools & equipment Other aux equipment Furniture & fittings Office Motor vehicles equipment & IT Land & buildings Q1 Budget Q1 Actual Distribution capex followed the first quarter budget. About T$0.5million were spent on replacing ageing/missing LV/HV poles 1, replacing new transformer structures and meter replacements capex items. In addition, about T$375,000 was spent on motor vehicles including two cranes and two new cars. With regard to IT, computer and networking equipment was purchased costing about T$50,000 in total. Refer to the excel files Capex Summary for the Regulatory Period 2008-2015 and Capex Reconciliation July-Sept 2012 for further information on first quarter capital expenditure. 1 Note that missing poles are those locations where in previous years poles had been removed to be used elsewhere, thus creating double length spans. 2

3. Quarterly Regulatory Asset Value (RAV) Update Decription 2008-09 2009-10 2010-11 2011-12 2012-13 Q1 Opening Net Book Value 30,123,378 29,512,275 32,667,062 36,964,833 38,203,683 Generation Capital Expenditure - 2,350,792 1,912,142 52,767 - Distribution Capital Expenditure 385,605 1,952,145 3,638,383 3,483,179 505,270 Office Computers & Equipment 33,279 87,064 463,620 106,854 51,912 Furniture & Fixtures 4,007 13,221 20,532 18,850 5,921 Tools & Equipment 55,206 114,239 133,812 61,455 646 Vehicles 213,121 638,415 503,709 159,492 375,045 Other Auxiliary Equipment 1,348 31,467 93,001 - - Building 128,863 80,944 463,462 28,359 - Disposals and Retirements - (329,007) (614,553) - 0 Depreciation on Opening RAV (1,369,244) (1,369,244) (1,369,244) (1,369,244) (342,311) Depreciation New Assets (63,289) (415,248) (947,092) (1,302,862) (344,491) Closing Estimated RAV 29,512,275 32,667,062 36,964,833 38,203,683 38,455,675 The new RAV is recorded as T$38,455,675 as at 30 September 2012. 4. System Loss Report As shown in the graph below, the total system losses have decreased further in the month of August 2012. The 12 months rolling average has decreased from 14.7% (in July) to 13.9% (in August), closing in for the target 13%. In fact month on month reduction is from 16% (in July) to 9.3% (in August). While monthly changes reflect losses they are impacted by meter reading cycles, and hence is not such an accurate measure of gains made, but it does show the trend. Each of our four island grids has shown a reduction over the last month. Percentage 20.00% 19.00% 18.00% 17.00% 16.00% 15.00% 14.00% 13.00% 12.00% 11.00% 10.00% 9.00% 8.00% 7.00% 6.00% 5.00% 4.00% 3.00% 2.00% 1.00% 0.00% Tonga Power Ltd Total System Losses for all islands Parasitic Losses Line Losses Total System Losses Target System Losses Fuel Efficiency Jul-07 Aug-07 Sep-07 Oct-07 Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08 Oct-08 Nov-08 Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09 Jul-09 Aug-09 Sep-09 Oct-09 Nov-09 Dec-09 Jan-10 Feb-10 Mar-10 Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10 Jan-11 Feb-11 Mar-11 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 5.00 4.50 4.00 3.50 3.00 2.50 2.00 1.50 1.00 0.50 - KwH/L The ongoing improvement is due to ongoing activities covering installation of new meters, identification and reduction of theft, efficiency in billing, and decreasing inaccuracy of meter reading etc. In addition our ongoing network improvements are contributing to the reduction of technical losses. 3

There are a number of Network Improvement Projects under development that will continue to decrease the system losses. The projects include: Tonga Village Network Upgrade Project Tongatapu, NZ Aid Proposed Nuku alofa LV upgrades (replacing old insulators and conductors) Prepay metering Advanced Metering Infrastructure Development TPL (this will enable TPL to target reduction of line losses in a number of ways such as decreasing the night time peak load) Meter replacement programme that reduces faulty readings, tampering and theft, and that eventually enables maintaining accuracy of billing database. 5. Reliability Measures 3500 3000 2500 Planned and Unplanned SAIDI Monthly Saidi_10_11 Saidi_11_12 Saidi_12_13 System Minutes 2000 1500 1000 500 0 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Month SAIDI minutes for the month of September 2012 have decreased dramatically to 5.66 minutes as affected HV faults were not severe in nature. Further information on SAIDI, SAIFI, and CAIDI can be found in the attached excel file Faults Report Graphs 2012-09. 6. Monthly Faults Events Unplanned Outage Events Comparision Jul-Sep 2012 700 600 500 400 300 200 100 0 Jul-12 Aug-12 Sep-12 Meter Customer requests Service lines LV Lines HV Pole HV Transformer HV Lines Generator problem The total number of outages has increased from 507 in August to 627 in September. Service lines outages have increased from 238 in August to 340 in September 2012. Further details of the monthly faults events can be found in the attached file Monthly Events 2012-09. 4

7. Tariff Review Proposal TPL conducted a Fuel Tariff Review recently and the Castalia Model output shows that the fuel component of tariff is under pressure due to sharply increased oil prices, despite the ongoing benefits from the Maama Mai solar facility. TPL expects to make an application to the Electricity Commission in the near future. Meanwhile a World Bank sponsored tariff review has been carried out, at this stage TPL is uncertain as to the outcome, and a work shop is anticipated involving Government representatives, in the next month or so. This may lead to further development work by TPL into tariff structure re-design. Additional Reporting Items: 8. Generation Security Profile The above graph shows proposed changes to TPL s generation profile, as new large scale renewables come on line, and diesel generation sets are replaced. The current thinking is that demand growth will not drive new investment. Rather the cost of diesel fuel and the end of life of diesel generators will set the timetable for new investments. TPL plans to decommission some diesel generators as the renewable energy generation increases, however the mix of generation types will be dictated by need to provide back up security in the event of failure of a generator in addition to coping with intermittency of the renewables. The following table sets out likely installed capacity, firm capacity (without renewable) and renewable energy capacity will increase now and in Dec. 2015 for all four islands. Intsalled Capacity (KW) Tongatapu Vavau Eua Haapai Total Increase (%) 2012 Oct 12580 1860 360 558 15358 2015 Dec 17901 2534 866 744 22045 44% Firm Capacity (KW) Tongatapu Vavau Eua Haapai Total Increase (%) 2012 Oct 11280 1860 360 558 14058 2015 Dec 14570 2034 866 744 18214 30% Renewable Energy (KW) Tongatapu Vavau Eua Haapai Total Increase (%) 2012 Oct 1300 0 0 0 1300 2015 Dec 4321 500 320 0 5141 295% 5

The above four graphs show that Tongatapu and Eua will have some difficulty in providing N-1 security of supply (that is being able to meet the highest demand should one generator fail) in the near term. Should you have any queries with the information provided, please do not hesitate to contact me. Yours Faithfully, Ajith Fernando Risk & Compliance Manager Tonga Power Limited Attachments: - Service Standards Report Oct 2012 - Capex Summary for Regulatory Period 2008-2015 - Capex Reconciliation Jul-Sep 2012 - Faults Report Graphs Sep 2012 - Monthly Faults Events Sep 2012 - Generation Capacities and Security Oct 2012 6