Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)

Similar documents
Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

XXXXX. Kokish River Hydroelectric Project. Interconnection Facilities Study and Project Plan

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

Decision on Merced Irrigation District Transition Agreement

NPCC Natural Gas Disruption Risk Assessment Background. Summer 2017

100 MW Wind Generation Project

METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES (VILLAGE OF ANMORE)

A Guide to the medium General Service. BC Hydro Last Updated: February 24, 2012

2016 Load & Capacity Data Report

POWER SYSTEM INCIDENT REPORT NORTHERN POWER STATION STABILISER OUTAGE APRIL AND MAY 2010

APPENDIX F: Project Need and Description

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Interconnection Feasibility Study

Why Japan remains skeptical of restructuring Study of Electricity Market Bidding Characteristics for Modeling Generation Capacity Growth

INCREASING electrical network interconnection is

2018 Load & Capacity Data Report

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Header. Reasonableness Test RT 007/11 Balhannah & Uraidla 66 / 33 kv Substations. RT Balhannah and Uraidla - Final Draft Page 1 of 8

Siemens Hybrid Power Solutions. Technical and Financial Simulation Tools for High Penetration Hybrid Power Systems, Bangkok June 2015

The Energy Queensland Group Notice of no non-network options

POWER SYSTEM INCIDENT REPORT: TRIP OF NO 1 AND 2 NEW OSBORNE 66 KV BUSBARS ON 26 SEPTEMBER 2010

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

ABB POWER SYSTEMS CONSULTING

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

A REPORT TO THE SoMo OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. System Planning. Overhaul Diesel Engines.

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

XXXX. Skookum Creek Power Project. Interconnection System Impact Study

Assessing the Potential Role of Large-Scale PV Generation and Electric Vehicles in Future Low Carbon Electricity Industries

Oklahoma Gas & Electric P.O. Box 321 Oklahoma City, OK, Main Street, Suite 900 Cambridge, MA 02142

Impact of Distributed Energy Resources on Transmission System Reliability

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

Hybrid Wind Solar Generator

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF B 220 KV BUSBAR AT GEORGE TOWN ON 27 NOVEMBER 2012.

Merger of the generator interconnection processes of Valley Electric and the ISO;

Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Impact Analysis of Fast Charging to Voltage Profile in PEA Distribution System by Monte Carlo Simulation

SOLAR GRID STABILITY

POWER SYSTEM OPERATING INCIDENT REPORT LIGHTNING STRIKES IN TASMANIA AND PACIFIC ALUMINIUM POTLINE LOAD REDUCTIONS 21 MARCH 2013

SUMMARY OF REPORT TO ENERGIAVIRASTO SEPTEMBER Study on the amount of peak load capacity for

Climate change drivers for a single and smart EU grid

Next Generation of UHVDC System. R. Montaño, D Wu, L. Arevalo, B. Jacobson ABB - HVDC Sweden

Facilities Study for Alberta to US Available Transfer Capability

Operational Opportunities to Minimize Renewables Curtailments

ATCO ELECTRIC LTD. (Transmission System) SERVICE QUALITY AND RELIABILITY PERFORMANCE, MEASURES AND INDICES Revision 0

Cost Benefit Analysis of Faster Transmission System Protection Systems

Grid Impacts of Variable Generation at High Penetration Levels

The 6 th Basic Plan for Long-term Electricity Supply and Demand (2013~2027)

POWER SYSTEM OPERATING INCIDENT REPORT TRIP OF 220 KV C BUSBAR AT GORDON POWER STATION ON 26 NOVEMBER 2011

BC Hydro OATT - Balancing Area Transmission Service Workshop. January 20, 2014

The Grid Link Project. Summary of the Report for the Independent Expert Panel

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

TRANSMISSION PLANNING CRITERIA

Electrical Transmission System Analysis EE 456 project. Team Members Abdulaziz Almarzouqi Hamzah Abeer

Ambient PM 10 Monitoring Sechelt, B.C Update

Interconnection Feasibility Study Report GIP-226-FEAS-R3

15 Nelson-Marlborough Regional Plan

Electricity industry structure and capacity growth trends

Utility Distribution Planning 101

The impact of electric vehicle development on peak demand and the load curve under different scenarios of EV integration and recharging options

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Supplemental Report on the NCTPC Collaborative Transmission Plan

Reliability Analysis of Radial Distribution Networks with Cost Considerations

Sunmine Solar Project. Interconnection System Impact Study

Computer Aided Transient Stability Analysis

Analysis of Turbine Missile & Turbine-Generator Overspeed Protection System Failure Probability at NPPs: A case study from PSA perspective

Interconnection System Impact Study

THE TRES AMIGAS PROJECT

Interconnection Process for Generation Systems

Appendix L-2 Calculating Combined-Cycle and Cogeneration

The Rollover Request customer accepts a reservation term for the rollover at least as long as that offered by any competing customer.

POWER SYSTEM OPERATING INCIDENT REPORT SIMULTANEOUS TRIP OF 5A6 MT PIPER BANNABY 500 KV LINE AND MT PIPER NO. 2 UNIT ON 9 FEBRUARY 2012

System Status Briefing

Updated Transmission Expansion Plan for the Puget Sound Area to Support Winter South-to-North Transfers

Flexible Ramping Product Technical Workshop

a) The 2011 Net Metering and Buyback Tariff for Emission Free, Renewable Distributed Generation Serving Customer Load

Electrification of Domestic Transport

Caution and Disclaimer The contents of these materials are for information purposes and are provided as is without representation or warranty of any

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

Coordinated Charging of Plug-in Hybrid Electric Vehicles to Minimize Distribution System Losses

i-pcgrid Workshop 2017

XXXX. Crowsnest Pass Waste Heat Project. Interconnection System Impact Study

POWER SYSTEM OPERATING INCIDENT REPORT TRIPS OF YALLOURN W POWER STATION UNITS W1 AND W3 ON 14 NOVEMBER 2012

Enhancement of Reliability Analysis for a 6-Bus Composite Power System using the Combination of TCSC & UPFC

Copyright 2011 OSIsoft, LLC

City of Palo Alto (ID # 6416) City Council Staff Report

August 2011

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

Interconnection System Impact Study Report Request # GI

GridView An Analytic Tool for. ABB Inc. Electric Systems Consulting. Market Simulation & Asset Performance Evaluations. ABB Inc.

University of Alberta

A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES. Electrical. Mechanical. Civil. Protection & Control. System Planning

Impact of Increasing Electric Mobility on a Distribution Grid at the Medium Voltage Level. Julia Vopava

Electricity Transmission Infrastructure Development in New England

Transcription:

Report-BCTC-R009A Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) December 8, 2005 Prepared by Wenyuan Li System Planning and Performance Assessment British Columbia Transmission Corporation 1

DISCLAIMER This report was prepared by BCTC solely for the purposes described in this report, and is based on information available to BCTC as of the date of this report. Accordingly, this report is suitable only for such purposes, and is subject to any changes arising after the date of this report. Unless otherwise expressly agreed by BCTC, BCTC does not represent or warrant the accuracy, completeness or usefulness of this report, or any information contained in this report, for use or consideration by any third party, nor does BCTC accept any liability out of reliance by a third party on this report, or any information contained in this report, or for any errors or omissions in this report. Any use or reliance by third parties is at their own risk. COPYRIGHT NOTICE Copyright and all other intellectual property rights are expressly reserved to BCTC. Without prior written approval of BCTC, no part of this report shall be reproduced or distributed in any manner or form whatsoever. 2

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR) (Executive Summary) by Wenyuan Li System Planning and Performance Assessment British Columbia Transmission Corporation December 8, 2005 A report titled Reliability Evaluation of Three Scenarios for Vancouver Island Power Supply An Expected Energy Not Served (EENS) Study was released for the VIGP project in June 11, 2003 [1]. In that report, three scenarios of VIGP (Portfolio 2), 230 kv line and HVDC life extension were evaluated and compared. Based on various technical studies and the VIGP hearing, it was decided to go ahead with the 230 kv line project. The purpose of this study is to update the EENS evaluation for the 230 kv line scenario which is called the Vancouver Island Transmission Reinforcement project (VITR). The update is necessary due to the following: The new load forecast (December 2005) for Vancouver Island shows demand increases compared to the load forecast in 2002 which was used in the previous study in 2003. For example, the peak load forecast for 2008 has an increase of 153 MW compared to the peak load level used in the previous study. The annual load curve shape that is based on 2004 hourly records is available. The total generation capacity in Vancouver Island also has a small amount of increase. It will be 714 MW in 2008 while 688 MW was used in the previous study. By 2009, the generation capacity will be increased to 744 MW due to the generation smart project of BCH. In the 2003 study, HVDC was included in evaluation with an increasing unavailability caused by possible aging failures. Based on the information in the VIGP project hearing and BCTC/BCH s VI power resource plan, HVDC will be retired (zero dependable capacity) by 2007 for planning purposes. The time frame of this study is from 2008/09 to 20022/23 and the existing HVDC is not considered available and is excluded from the evaluation model. The impact studies of HVDC on VI reliability for only a short period (a couple of years before and after VITR in service) will be performed as a separate part of the VITR reliability study and summarized in Part IV of the report. The report summarizes the EENS study for the VITR project based on the updated data available in December 2005. The results indicate that the 230 kv AC line will provide an essential improvement to Vancouver Island power supply reliability over the study period from 2008 to 2022. The EENS reduction and risk cost reduction due to the 230 kv line addition in the 15 year s period will be 379,594 MWh and $1,897 million respectively. If the second 230 kv line was added in 2017, it would lead to the EENS reduction of 30,485 MWh or the risk cost reduction of $152 million in the 5 year s period from 2017 to 2022. This reduction would be increased if a longer 3

period was considered. The second 230 kv line was included in the study only for information. There is no decision yet on the second 230 kv line. It should be noted that the risk cost estimates in the study are based on the unit interruption cost of $5/kWh, which was used in risk evaluation of system planning at BC Hydro in the past [4, 5], and are only for reference. More information regarding the range of the unit interruption cost can be found in Section 6 of Part IV of the report. This report is the first part of the whole reliability study for the VITR project, which focuses on the comparison between the do-nothing and 230 kv line cases from 2008 to 2022. The other reliability studies for the VITR project are presented in the other parts of the report. 4

December 8, 2005 Expected Energy Not Served (EENS) Study for Vancouver Island Reinforcement Project (Part I: Reliability Improvements due to VITR) 1. Introduction by Wenyuan Li System Planning and Performance Assessment British Columbia Transmission Corporation A report titled Reliability Evaluation of Three Scenarios for Vancouver Island Power Supply An Expected Energy Not Served (EENS) Study was released for the VIGP project in June 11, 2003 [1]. In that report, three scenarios of VIGP (Portfolio 2), 230 kv line and HVDC life extension were evaluated and compared. Based on various technical studies and the VIGP hearing, it was decided to go ahead with the 230 kv line project. The purpose of this study is to update the EENS evaluation for the 230 kv line scenario which is called the Vancouver Island Transmission Reinforcement project (VITR). The update is necessary due to the following: The new load forecast (December 2005) for Vancouver Island shows demand increases compared to the load forecast in 2002 which was used in the previous study in 2003. For example, the peak load forecast for 2008 has an increase of 153 MW compared to the peak load level used in the previous study. The annual load curve shape that is based on 2004 hourly records is available. The total generation capacity in Vancouver Island also has a small amount of increase. It will be 714 MW in 2008 while 688 MW was used in the previous study. By 2009, the generation capacity will be increased to 744 MW due to the generation smart project of BCH. In the 2003 study, HVDC was included in evaluation with an increasing unavailability caused by possible aging failures. Based on the information in the VIGP project hearing and BCTC/BCH s VI power resource plan, HVDC will be retired (zero dependable capacity) by 2007 for planning purposes. The time frame of this study is from 2008/09 to 20022/23 and the existing HVDC is not considered available and is excluded from the evaluation model. The impact studies of HVDC on VI reliability for only a short period (a couple of years before and after VITR in service) will be performed as a separate part of the VITR reliability study and summarized in Part IV of the report. This report provides the first part of the study for the VITR project reliability assessment, which focuses on the difference in the EENS index to Vancouver Island supply between the do-nothing case and the VITR project. The results show the reliability benefit due to the VITR project. The method and the computing tool used in this study are mature and have been recognized by the academic field and the power industry for years [2, 3]. The failure data for the 500 kv lines and local generating units were based on historical statistics from the BC Hydro outage database. The failure data are the same as those used in the 2003 report. 5

2. Method, Computing Tool and Model The method used to conduct EENS studies is the probabilistic reliability evaluation technique using Monte Carlo simulations. The EENS is a probabilistic index that is a combination of consequences and probabilities of all failure events sampled in the simulation. The method has been proved and recognized for many years [2]. The number of samples used in the study was 100,000 for each load level in the 15-step load model. The computing tool used in the study is the MCGSR program (Monte Carlo Generation System Reliability), which is an evaluation tool for generation source system reliability. The basic concept and the simulation approach used in the program have been published for years and can be found in [2]. The EENS evaluation model for Vancouver Island power supply is shown in Figure 1. The 500 kv lines, 230 kv line and on-island generating units were modeled. The second 230 kv line was included in the model only for the study purpose and there is no decision yet on the second 230 kv line. There are some very small local generating units with a capacity ranging from 0.8 to 3.8 MW. No failure data for these units is available. In the evaluation, these units were not individually modeled but rather, they were considered by distributing their capacities to other relatively large units. For the same reason, the UCO and Zeballos generating units were combined as one with the same failure data as the ASH unit. The second 230 kv line was assumed only for the study purpose. This is a generation-demand reliability model, since all power supply sources, including generating units and transmission components, play a role of generation source. At the load side, an annual load curve is used. Individual failures of each power supply source and combinations of their failures are sampled using the Monte Carlo simulation technique. Each state in which the load cannot be met contributes to the EENS index. All components were modeled using two-state (up and down states) random variables. The common cause failure of the two 500 kv lines due to lightning was simulated using an independent random variable. 3. Data 3.1 Failure data The failure data for the 500 kv lines and on-island generating units were based on historical failure records. The failure data for a new 230 kv AC line includes two portions for overhead line and submarine cable. The failure data for the overhead portion were based on the average of existing 230 kv lines in the BC Hydro system, which were obtained from BCTC s CROW (Control Room Operations Window) system. The failure data for the submarine cable were based on an engineering estimate. This is a relatively pessimistic estimate since the repair time is assumed to be 3 months (2190 hours) considering that repair activities under water will be extremely difficult. The failure data of the phase shift transformer (PST) that is in series with the 230 kv line is based on historical failure records of the PST on 2L112 in the HC Hydro system. These data are the same as those used in the 2003 report [1] and are given in Appendix A and B. 6

3.2 Load data The load model used in the study was the most recent Vancouver Island peak load forecast for 2008/09 to 2022/23. The 8760 hourly load records in 2004 were used to model the annual load curve shape. The peak load forecast and the total VI generation MW are given in Appendix C. 1200 MW 500 kv line 1200 MW 500 kv line Vancouver Island load 170 MW JOR 304 MW in total ASH JHT 1-6 PUN LDR1-2 SCA1-2 UCO/Zeballos 27 MW 21 or 26 MWx6 24 MW 24 MWx2 32 MWx2 15 MW 170MW Steam 70MW ICG 600 MW 230 kv AC line (2008) 600 MW 230 kv AC line (2017) Figure 1 EENS Evaluation Model for Vancouver Island supply 4. Study Conditions The time frame in the study is 15 years from 2008/09 to 2022/23. The 2008/09 is the first year by which the 230 kv line will be in service. Any planning study associated with a capital investment should be conducted over a long time frame. The local transmission network on Vancouver Island (including network constraints and failures of network components) was not included in the model. Also, the grid system at the Lower Mainland side has been assumed to be perfect and was not incorporated into the study. These assumptions do not cause any negative impact on the results since the focus is the EENS indices to Vancouver Island supply. 7

The peak loads from 2008 to 2022 were based on the most recent load forecast (December 2005) while the annual load curves for all the 15 years under the study follow the same shape that is based on the hourly load records in 2004. HVDC was not included in the model since HVDC is considered to be zero capacity from 2007 (retired) from a planning viewpoint. The reason of excluding HVDC has been given earlier in the section of Introduction. The phase shifting transformer (PST) was modeled by assuming that it is in series with the 230 kv line and no bypass operation for the PST. This is a pessimistic assumption because in real life, when the PST fails, it can be bypassed and the 230 kv line will continue to supply in most cases according to the design. The capacity of two 500 kv lines is assumed to be the continuing rating (1200 MW). A short time (2 hours) overloading capacity (1300 MW) is not considered since the repair time used in the simulation (138 hours) is much longer than 2 hours. In other words, considering a 100 MW higher capacity for only 2 hours will not have effective impacts on the results for one year s simulation. Also, the same 500 kv line capacity is used in all the cases for comparison. The EENS evaluation was based on the adequacy concept, i.e., the loss of load in any system state was assumed to be exactly equal to the difference between the load level and the total available source capacity. In real life, there is a tendency of over-shedding of load if a system state is associated with transient or voltage instability and load shedding protective relaying systems. 5. EENS Evaluation 5.1 Cases The following three cases are studied: (1) Do Nothing This is the existing system without any new power source and by assuming that HVDC will be retired in 2007. The system includes two 500 kv lines with each having 1200 MW capacity, 15 local generating units with a total capacity of 714 MW in 2008/2009 and 744 MW from 2009/2010 to 2022/2023. (2) New 230 kv AC line to Vancouver Island (2008 in service) The new 230 kv AC line with 600 MW capacity is added in 2008. It comprises 35.6 km of overhead line, 31.15 km of submarine cable and a phase shifting transformer. (3) The second 230 kv AC line to Vancouver Island (2017 in service) 8

The second 230 kv AC line with 600 MW was assumed to be in service in 2017. 5.2 Results EENS indices and risk costs The EENS indices for the do-nothing and 230 kv line cases from 2008 to 2022 are summarized in Table 1 and depicted in Figure 2. The EENS indices for the first 230 kv line and possible second 230 kv line cases from 2017 to 2022 are summarized in Table 2 and depicted in Figure 3. The EENS for the do-nothing case increases constantly and non-linearly over time. For the 230 kv AC line case, the EENS index is much lower compared to the do-nothing case and has a normal slow increase due to the load growth with the years. If the second 230kV line was added, it would provide the further decrease of the EENS index since 2017 compared to the first 230 kv line case. The reduction in the EENS index due to the 230 kv line from 2008 to 2022 sums to 379,594 MWh. The average EENS reduction in one year for the 15 year s period is 25,306 MWh/year. If a value of $5/kWh is applied, which is the unit interruption cost used in risk evaluation of system planning at BC Hydro in the past [4, 5], the risk cost reduction due to 230 kv line addition from 2008 to 2022 will be up to $1,897.97 million. The risk cost reductions for each year are also given in Table 2. If the second 230 kv line was added, the reduction in the EENS index due to its addition from 2017 to 2022 would sum to 30,485 MWh. The average EENS reduction in one year for the 5 year s period would be 6,097 MWh/year. If the $5/kWh was applied, the risk cost reduction due to adding the second 230 kv line from 2017 to 2022 would be $152.43 million. The risk cost reductions for each year are also given in Table 2. If a longer the period was considered, the second 230 kv line would result in a higher risk cost reduction since the load growth beyond 2022 would lead to much higher EENS indices. It should be noted that the risk cost estimates based on the unit interruption cost of $5/kWh are only for reference. More information regarding the range of the unit interruption cost can be found in Section 6 of the Part IV of the report. 9

Table 1 EENS index (MWh/year) and risk cost reduction (M$/year) for do-nothing and 230 kv line cases Year Do-nothing 230 kv line Difference in EENS (MWh) Difference in risk cost (M$) 2008 14998 2870 12128 60.64 2009 14542 2779 11763 58.82 2010 16268 2969 13299 66.50 2011 17298 3085 14213 71.07 2012 19101 3281 15820 79.10 2013 21130 3523 17607 88.04 2014 23163 3769 19394 96.97 2015 25080 3991 21089 105.45 2016 28709 4348 24361 121.81 2017 32626 4692 27934 139.67 2018 36720 5152 31568 157.84 2019 40915 5710 35205 176.03 2020 46194 6238 39956 199.78 2021 52084 6989 45095 225.48 2022 57969 7807 50162 250.81 total 379594 1897.97 Table 2 EENS index (MWh/year) and risk cost reduction (M$/year) for the first and possible second 230 kv line cases Year 230 kv line Second 230 kv line Difference in EENS (MWh) Difference in risk cost (M$) 2017 4692 726 3966 19.83 2018 5152 831 4321 21.61 2019 5710 929 4781 23.91 2020 6238 1053 5185 25.93 2021 6989 1203 5786 28.93 2022 7807 1361 6446 32.23 total 30485 152.43 10

60000 50000 Do-nothing 230 kv line 40000 EENS(MWh/year) 30000 20000 10000 0 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 year Figure 2 EENS index for do-nothing and 230 kv line cases (MWh/year) 8000 7000 6000 230 kv line Second 230 kv line EENS(MWh/year) 5000 4000 3000 2000 1000 0 2017 2018 2019 2020 2021 2022 Year Figure 3 EENS index for the first and second 230 kv line cases (MWh/year) 6. Conclusions 11

The report summarizes the EENS study for the VITR project based on the updated data available in December 2005. Compared to the study for the VIGP project in 2003, the peak load forecast, on-island generation and load curve shape have been different. Also, the HVDC is excluded in this study since the HVDC will be retired (zero capacity) by 2007 for the planning purposes. The results indicate that the 230 kv AC line will provide an essential improvement to Vancouver Island power supply reliability over the study period from 2008 to 2022. The EENS reduction and risk cost reduction due to the 230 kv line addition in the 15 year s period will be 379,594 MWh and $1,897 million respectively. If the second 230 kv line was added in 2017, it would lead to the EENS reduction of 30,485 MWh or the risk cost reduction of $152 million in the 5 year s period from 2017 to 2022. This reduction would be increased if a longer period was considered. The second 230 kv line was included in the study only for information. There is no decision yet on the second 230 kv line. It should be noted that the risk cost estimates in the study are based on the unit interruption cost of $5/kWh, which was used in risk evaluation of system planning at BC Hydro in the past [4, 5], and are only for reference. More information regarding the range of the unit interruption cost can be found in Section 6 of the Part IV of the report. This report is the first part of the whole reliability study for the VITR project, which focuses on the comparison between the do-nothing and 230 kv line cases from 2008 to 2022. The other reliability studies for the VITR project will be presented in other parts of the report. 12

References [1] BCTC Report, Reliability Evaluation of Three Scenarios for Vancouver Island Power Supply an Expected Energy Not Served (EENS) Study, filed to BCUC in June 2003 [2] R. Billinton and Wenyuan Li, Reliability Assessment of Electric Power Systems Using Monte Carlo Methods, Plenum Press, New York, 1994 [3] Wenyuan Li, Risk Assessment of Power Systems: Models, Methods, and Applications, IEEE and Wiley, 2005 [4] F. Turner, et al, Reliability Worth: Development of a Relationship with Outage Magnitude, Duration and Frequency, CEA paper, March 1994 [5] Wenyuan Li, Y. Mansour, et al, Application of Transmission Reliability Assessment in Probabilistic Planning of BC hydro Vancouver South Metro System, IEEE Transaction on Power Systems, 1995 13

Appendix A: Local Generating Unit Reliability Data Generating unit Capacity (MW) FOR Repair time (hrs) ASH 27 0.004 15.35 JHT-1 21 * 0.0795 926.51 JHT-2 21 * 0.0008 2.31 JHT-3 21 * 0.003 36.32 JHT-4 21 * 0.0026 7.84 JHT-5 21 * 0.0096 28.70 JHT-6 21 * 0.0003 3.77 PUN 24 0.0010 13.74 LDR-1 24 0.0063 19.15 LDR-2 24 0.0026 6.60 SCA-1 32 0.0027 5.33 SCA-2 32 0.0218 28.26 UCO/Zeballos 15 0.004 15.35 JOR 170 0.0124 5.99 ICG 240 0.1065 ** 50.30 ** Total 714 Note: 1. The reliability data for the local hydro generating units are based on historical outage records. These data are the same as those used in the following previous reports: [1] BC Hydro technical report, Reliability Assessment of Vancouver Island Supply 2000/01, Section 3 of Vancouver Island Operation Plan 2000/01 produced by NOS (Network Operation Services), Grid Operation Division, BC Hydro, January 15, 2001 [2] BC Hydro technical, Reliability Assessment for Vancouver Island Supply Options, produced by NPP (Network Performance Planning), BC Hydro, December, 2001 [3] BC Hydro technical report, Probabilistic & Economic Assessment of HVDC Short-term Investment Strategies, produced by NOS (Network Operation Services), Grid Operation Division, BC Hydro, June 2002 2. * The 6 units at JHT are assumed to increase their capacity by 5 MW each by 2009/2010. 3. ** The failure data for the ICG are based on historical statistics from the NERC database for combined cycle turbine units from 1977 to 2001. The raw data can be found at http://www.nerc.com/~filez/gar.html. The breakdown of forced and planned failure data is as follows: Unit Capacity (MW) Unavailability Failure Frequency Repair time (hrs) (f/year) Forced Planned Forced Planned Forced Planned ICG 240 0.03238 0.07407 13.22 5.32 21.46 122.0 14

Appendix B: 500 kv Line and 230 kv Line Reliability Data Line Capacity (MW) FOR Repair time (hrs) 500 kv line 1200 0.0293 137.81 500 kv line 1200 0.0293 137.81 230 kv line 600 0.0259 383.74 Second 230 kv line 600 0.0259 383.74 Phase shift transformer 600 0.000116 3.06 Common cause failure of two 500 kv lines 0.0004 2.98 Note: 1. The reliability data for the 500 kv lines (including the common cause failure data) are the same as those used in the following previous reports: [1] BC Hydro technical report, Reliability Assessment of Vancouver Island Supply 2000/01, Section 3 of Vancouver Island Operation Plan 2000/01 produced by NOS (Network Operation Services), Grid Operation Division, BC Hydro, January 15, 2001 [2] BC Hydro technical, Reliability Assessment for Vancouver Island Supply Options, produced by NPP (Network Performance Planning), BC Hydro, December, 2001 [3] BC Hydro technical report, Probabilistic & Economic Assessment of HVDC Short-term Investment Strategies, produced by NOS (Network Operation Services), Grid Operation Division, BC Hydro, June 2002 2. The common cause failure of two 500 kv lines refers to their simultaneous outage due to a common cause (lightning and terminal breaker failures). 3. The failure data of phase shift transformer is based on historical failure records of the PST on 2L112 in the HC Hydro system. There were only 5 forced failures with a total of outage duration of 15.28 hours in the past 15 years since it was in service in 1990. This translates into the unavailability (FOR) of 0.000116, a forced failure frequency of 0.3333 failures /year and the repair time of 3.06 hours/repair. 4. The reliability data for the overhead portion of the new 230 kv line is based on the average of historical records of 230 kv lines in the BC Hydro system. The reliability data for the submarine portion is estimated as failure frequency=1/10 years and average repair time = 3 months. The total equivalent reliability data are calculated as follows (planned outage not considered): Submarine portion: f(cable)=1/10 years=0.1 f/year r(cable)=3 months =2190 hrs FOR(cable)=f(cable) r(cable)/8760 =0.025 Overhead portion- Line-related failure 15

f1=0.6945 /year/ 100 km*40 km=0.2778/year r1=16.85 hours Overhead portion- terminal-related failure f2=0.2136 r2=16.40 hours Overhead portion total f(overhead)=0.2778+0.2136=0.4914 r(overhead) = Σfr/Σf = (0.2778*16.85+0.2136*16.40)/(0.4914)=16.65 FOR(overhead)=f(overhead)*r(overhead)/8760 = 0.00093 The total reliability data for the new 230 kv line is estimated as: FOR(total) = FOR(cable) +FOR(overhead) FOR(cable)*FOR(overhead) = 0.025+0.00093-0.025*0.00093 =0.02591 f(total) = 0.1+0.4914=0.5914 r(total) = FOR(total)*8760/f(total) = 0.02591*8760/0.5914 = 383.74 hours 16

Appendix C: Load forecast and resources balance for 2005/06 to 2025/26 Vancouver Island Demand and Resource Balance (Based on the BC Hydro Dec 2005 load forecast) VI Demand VI Dep_Gen* 500 kv HVDC 1st cct 2nd cct Balance MW MW MW MW MW MW MW 05/06 2318 698 1300 240-80 06/07 2349 714 1300 240-95 07/08 2370 714 1300-355 08/09 2397 714 1300 600 217 09/10 2425 744 1300 600 219 10/11 2454 744 1300 600 190 11/12 2470 744 1300 600 174 12/13 2498 744 1300 600 146 13/14 2531 744 1300 600 113 14/15 2561 744 1300 600 83 15/16 2589 744 1300 600 55 16/17 2628 744 1300 600 16 17/18 2668 744 1300 600 600 576 18/19 2710 744 1300 600 600 534 19/20 2753 744 1300 600 600 491 20/21 2800 744 1300 600 600 444 21/22 2847 744 1300 600 600 397 22/23 2892 744 1300 600 600 352 23/24 2937 744 1300 600 600 307 24/25 2983 744 1300 600 600 260 25/26 3030 744 1300 600 600 214 * The VI dependable generations are assumed to be same as the previous (NITS2004 dependable resource). 3500 3000 Capacity (MW) 2500 2000 1500 1000 500 0 2nd VITR Circuit 1st VITR Circuit HVDC 500 kv Circuits VI Generation VI Total Demand 05/06 07/08 09/10 11/12 13/14 15/16 Year 17/18 19/20 21/22 23/24 25/26 17