The Evolution of System Protection Schemes for the Sarawak Power System By Victor Wong Sarawak Energy Berhad Presented at PQSynergy 2012, Sarawak

Similar documents
Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Use of High-Power Thyristor Technology for Short-Circuit Current Limitation in High Voltage Systems

Texas A&M Microgrid and Electrical System Study. Cushing Memorial Library & Archives

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

TEPCO's experiences of automatic voltage controllers and SIPS as measures to prevent massive power outages

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

15 Nelson-Marlborough Regional Plan

SSF Section Location of Change SSF Issue Change(s) Comments Chapter Part B All Multiple Formatting, spelling and minor Changes applied -

Operational Planning Study Report. RTA to BCH transfer limit updates For Kitimat 4 Capacitor Banks

STABILIZATION OF ISLANDING PEA MICRO GRID BY PEVS CHARGING CONTROL

Transient Stability Analysis Tool (TSAT) Update April 11, Hongming Zhang EMS Network Applications Manager

Illinois State Report

El PASO ELECTRIC COMPANY 2014 BULK ELECTRIC SYSTEM TRANSMISSION ASSESSMENT FOR YEARS

Ancillary Services & Essential Reliability Services

TRANSMISSION PLANNING CRITERIA

APPENDIX F: Project Need and Description

APPENDIX E: Project Need and Description

Jemena Electricity Networks (Vic) Ltd

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Diane Lindsey CenterPoint Energy SWEDE 2010

South Dakota 890 Study

APPENDIX E: Project Need and Description

North Oregon Coast Area Study. Adam Lint

Distributed Energy Resources

S C ELECTRIC EUROPE LTD. Excellence Through Innovation. Harnessing the Wind. November 2011 Descriptive Bulletin E

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Southern California Edison s Circuit of the Future

Advanced Protective Relay Training

Impact of Distributed Energy Resources on Transmission System Reliability

COGENERATION PLANT SWITCHGEAR REPLACEMENT IMPROVES SAFETY AND RELIABILITY WHILE MAINTAINING SERVICE TO CRITICAL LOADS

NETSSWorks Software: An Extended AC Optimal Power Flow (AC XOPF) For Managing Available System Resources

Sub Regional RTEP Committee Mid-Atlantic

TD-2306B-001, Interconnecting Large 2-20MW Generation Systems. Employees involved with generation interconnection on electric distribution circuits.

ISO Rules Part 500 Facilities Division 502 Technical Requirements Section Interconnected Electric System Protection Requirements

Control System for a Diesel Generator and UPS

Laboratory Scale Microgrid Test-Bed Hardware Implementation

HVDC Back-to-Back Interconnections Enabling reliable integration of power system

BC HYDRO REAL TIME OPERATIONS SYSTEM OPERATING ORDER 7T-35. PEACE 138/230 kv NETWORK OPERATION Supersedes 7T-35 issued 15 June 2017

100 MW Wind Generation Project

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

15 Nelson-Marlborough Regional Plan

TransWest Express Project

Implementing a Microgrid Using Standard Utility Control Equipment

Dynamic Line Rating as a Means to Enhance Transmission Grid Resilience

REPORT. System Impact Assessment Report. Thierry Mine Development CONNECTION ASSESSMENT & APPROVAL PROCESS CAA ID

EPRI Intelligrid / Smart Grid Demonstration Joint Advisory Meeting March 3, 2010

Wang Bin & Michael Ho, TIIAE Power management system

Agility in energy Ahead of the challenge, ahead of the change

Utility Distribution Planning 101

TEPCO's operational technologies to prevent cascading outage

Outer Metro 115 kv Transmission Development Study. (Scott Co, Carver Co and Hennepin Co)

Entergy Gulf States, Inc. (Texas) Proposed Transmission Reliability Projects

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

Breakout Session 1 Report-out presentations

Project #148. Generation Interconnection System Impact Study Report

ATTACHMENT Y STUDY REPORT

SEL Microgrid Lessons Learned

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Dynamic Control of Grid Assets

ATTACHMENT B - Table 1: LIST OF MANAGEMENT-APPROVED PROJECTS UNDER $50M

XXXX. Kokish River Hydroelectric Project. Interconnection System Impact Study

Falcon-Midway 115 kv Line Uprate Project Report

Effects of Smart Grid Technology on the Bulk Power System

Smart Grid Automation and Centralized FISR

Interconnection Feasibility Study Report GIP-369-FEAS-R1

PRESENTATION BY ENERGY COMMISSION OF GHANA ON TACKLING POWER SYSTEM LOSSES

American Electric Power s Energy Storage Deployments

Pacific Gas and Electric Company s Revised 2015 Annual Progress

Project #94. Generation Interconnection System Impact Study Report Revision

Pacific Gas and Electric Company s Revised 2016 Annual Progress

XXXX. Knob Hill Wind Farm Project. Interconnection System Impact Study

SMUD 2014 Ten-Year Transmission Assessment Plan. Final. December 18, 2014

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Seabrook Substation Reliability Improvement Project

POWER SYSTEM OPERATING INCIDENT REPORT: TRIP OF 837 TARONG MT. ENGLAND 275 KV LINE AND MT. ENGLAND NO KV BUSBAR ON 30 OCTOBER 2011

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

Status of PNM s Completed Transmission Construction Projects 11/30/2017

2013 Grid of the Future Symposium. Utilizing Single Phase Operation Scheme on Untransposed 765kV lines for a Stability-Limited Plant

Arc-Flash Mitigation Technologies. Dennis Balickie

OCTOBER 17, Emera Maine Representative: Jeffrey Fenn, P.E., LR/SGC Engineering LLC

Transmission Grid Reinforcement with Embedded VSC-HVDC. Jonatan Danielsson, Sugam Patel, Jiuping Pan, Reynaldo Nuqui

Protection with distributed generation, experience with the Mont-Soleil wind farm project

The Energy Queensland Group Notice of no non-network options

3 Reliability Issues and Solutions

4,1 '~ ~ ~ 1I1f lc/)~ul I Central Electricity Authority

Blackouts. 29/10/2014 Dirk Van Hertem & Steven De Boeck

Facilities Study for Alberta to US Available Transfer Capability

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

Smart Grid Initiatives in EHV Transmission in Indian Power Sector

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Wide area monitoring and control activities in Norway and the Nordic power system

BC HYDRO T&D SYSTEM OPERATIONS SYSTEM OPERATING ORDER 7T 30. NORTH COAST INTERCONNECTION Supersedes 7T-30 issued 07 June 2018

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Complete Power Management System for an Industrial Refinery

NEWFOUNDLAND AND LABRADOR HYDRO GULL ISLAND TO SOLDIERS POND HVDC INTERCONNECTION DC SYSTEM STUDIES VOLUME 1

Fifteenth National Power Systems Conference (NPSC), IIT Bombay, December 2008

Interconnection Feasibility Study Report GIP-046-FEAS-R2

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Transcription:

The Evolution of System Protection Schemes for the Sarawak Power System By Victor Wong Sarawak Energy Berhad Presented at PQSynergy 2012, Sarawak

Evolution of System Protection Scheme UFLS- Under Frequency Load Shedding Scheme ADS- Automatic Decoupling Scheme EADS- Enhance Automatic Decoupling Scheme ARS- Automatic reactor Switching Scheme SPS (P1)- System Protection Scheme Phase 1 SPS (P2)- System Protection Scheme Phase 2 SPS (P3)- System Protection Scheme Phase 3 1998 2003 2009 2012 2013 Future

Under Frequency Load Shedding Scheme (UFLS) Implemented before 1998 Objective : To ensure system stability under two major scenarios of disturbances: Loss of Generating units with Grid still intact Double circuit tripping of the transmission lines, resulting in power deficiency in the region west of Bintulu and in particular, Kuching Operation philosophy : Detects frequency decline and shed loads accordingly, thus preventing the power system to operate in an unstable operating zone which will inevitably lead to system brownout or blackout

Automatic Decoupling Scheme (ADS) Implemented in 1998 Serve as Backup for the UFLS scheme Objective: To safeguard the distribution system supplying the sensitive loads in Samajaya Free Industrial Zone Operation Philosophy : Dedicated Kuching Biawak power station to supply Samajaya FIZ and in the event of major disturbance, the entire Samajaya FIZ distribution network together with the power station will be decoupled from the Grid system

Operation Philosophy for ADS Scheme MTB Bus B MTB Bus A ADS Zone To Grid System MW ~ Samajaya FIZ 49.0Hz Hz EADS Detection Algorithm Algorithm Logic to trigger the operation of ADS 1. Power Flow out of the ADS Zone + UF on MTB Bus < 49.0 Hz

Enhance Automatic Decoupling Scheme (EADS) System Issue : Automatic Decoupling Scheme (ADS) solution incurred high generation fuel cost UFLS scheme is no more effective in mitigating the power deficient condition at the Kuching load center resulted from the double circuits tripping of Engkilili-Mambong 275kV line and Bintulu-Oya 275kV line Solution : Implement EADS scheme Objective: Work with the present UFLS scheme to safeguard Sarawak power system against double circuits tripping of Engkilili-Mambong 275kV line and Bintulu-Oya 275kV line To replace ADS scheme Reduce Generation fuel cost Operation Philosophy : Detects the opening of the circuit breakers at both circuits to generate a logic controlled signal to trip load at transmission level

Operation Philosophy for EADS Scheme ENGKILILI OYA U7L5 SELANGAU KEMENA BINTULU ~ KEM U5L5 KUCHING Load center v ARS Detection Algorithm CB CONTROL SIGNAL 3 X 15MVar 49.70Hz Hz LOAD SHED SIGNAL EADS Detection Algorithm Logic to trigger the operation of EADS at Oya 1. Oya (U7L5 & U5L5) CBs status open + UF < 49.70HZ

System Protection Scheme Phase 1(SPS) System Issue : EADS and UFLS scheme are no more effective to safeguard Sarawak power system against the loss of any double circuits section in between Mambong-Engkilili-Oya-Selangau-Kemena-Bintulu 275kV transmission lines High generation fuel cost due to dispatching of Biawak diesel generation to safeguard Sarawak power system against the loss of double circuit tripping contingency Solution : Implement SPS system Objective: To safeguard Sarawak power system against the loss of double circuit tripping contingency Allow GSO more flexibility in operating the power system and utilize the generation resources more efficiently To replace EADS scheme

System Protection Scheme Phase 1(SPS) Operation Philosophy : Capture generation and load information, calculate quantum of sheddable loads required for a pre-defined set of contingent events, and the detection of the inception of the contingent event with sensors located strategically in the power system Event-based scheme consisting of five N-2 contingency detection zones Mambong Zone To safeguard Sarawak Power System against the loss of double circuit Engkilili-Mambong lines. Engkilili Zone To safeguard Sarawak Power System against the loss of double circuit Engkilili-Kemantan-Oya lines Oya Zone To safeguard Sarawak Power System against the loss of double circuit Oya-Selangau lines Selangau Zone- To safeguard Sarawak Power System against the loss of double circuit Selangau-Kemena lines Kemena Zone - To safeguard Sarawak Power System against the loss of double circuit Kemena-Bintulu lines

KUCHING SYSTEM MAMBONG ~ Operation Philosophy for SPS system ENGKILILI OYA SELANGAU ~ KEMENA BINTULU ~ BINTULU SYSTEM Goose signal Goose signal WIDE AREA NETWORK System Information MW,MVAR,Freq SUBSTATIONS A-Z (Trip 33/11kV feeders) Transmission Circuit Status System Information MW,MVAR,Freq SPS Arming signal STATE DISPATCH CENTER SPS SERVER Collect and archive the data Perform Load shed calculation and update load shedding table Generate arming or disarming to all affected feeder

System Protection Scheme Phase 2(SPS) System Issue : Frequency Instability during system islanding Loss of Bintulu-Similajau double circuits Loss of Similajau-Bakun double circuits Over frequency during loss of any double circuit in between 275kV Engkilili-Oya-Selangau-Kemena-Bintulu-Similajau lines Loss of N-1 275kV transmission lines reliability Loss of Engkilili-Kem-Oya single circuit Loss of Oya-Selangau single circuit Loss of Selangau-Kemena single circuit Loss of Kemena-Bintulu single circuit Loss of Bintulu-Similajau single circuit Power import at Engkilili or Oya or Selangau or Kemena exceed SPS capability limits Required to dispatch Biawak diesel generation to reduce import level Solution : Expand and reconfigure the existing SPS system

System Protection Scheme Phase 2(SPS) Objective: To Safeguard Sarawak Power system from collapse against either Bintulu-Similajau or Similajau-Bakun 275kV double circuit tripping contingency Prevent generating units at Mukah, Bintulu, Pujut and Bakun trip on over frequency protection during loss of any double circuits section in between Oya-Selangau-kemena-Bintulu-Similajau 275kV transmission lines Protect the 275kV transmission line conductor exceeds its stated capability limit during loss of any single circuit in between Engkilili- Oya-Selangau-Kemena-Bintulu-Similajau275kV transmission lines Manage grid system overvoltage within statutory limits during the system islanding condition Allow the GSO more flexibility to operate the power system and utilize the generation resources more efficiently

System Protection Scheme Phase 2(SPS) The development of SPS Phase 2 : Adaptive Over frequency Generator Shedding Scheme (AOFG) Adaptive (N-1) 275kV Line Overload Load Shedding Scheme (ALOLS) Adaptive Reactor Switching Scheme (ARSS) New Bintulu and Similajau Zone in SPS system for N-2 Bintulu-Similajau 275kV line and Similajau-Bakun 275kV line contingency respectively New Bulk Load tripping scheme for the existing SPS Oya, Engkililli, Selangau and Kemena zone

System Protection Scheme Phase 3(SPS) System Issue : Similajau-Samalaju 275kV transmission line conductor exceeds its stated capability limit due to loss of Similajau-Samalaju 275kV double circuits Power import at Mambong, Engkilili, Oya, Selangau, kemena, Bintulu and Similajau exceed existing SPS capability and load shed limits. Kuching extended power system overvoltage during system islanding condition SPS system malfunctions due to hardware and software failure Solution : Expand and reconfigure the existing SPS system Still under development, expected to be completed in middle of year 2013

System Protection Scheme Phase 3(SPS) Objective: Protect the 275kV transmission line conductor exceeds its stated capability limit during loss of Similajau- Samalaju double circuits Manage grid system overvoltage within statutory limits during the system islanding condition Allow the GSO more flexibility to operate the power system and utilize the generation resources more efficiently To increase SPS system reliability and availability To eliminate any single point of failure within the communication network equipments that connects SDC to all participating substations in SESCo s SPS System

System Protection Scheme Phase 3(SPS) The development of SPS Phase 3 : Adaptive (N-2) 275kV Line Overload Load Shedding Scheme Adaptive Capacitor bank Inter-tripping Scheme (ACTS) SPS System redundancy upgrade

Future development for SPS System New scheme to mitigate the following system issues ; Frequency Instability N-2 Murum-Murum Junction 275kV line ( Loss of whole Murum hydro power station ) Loss of whole Bakun hydro power station Voltage instability N-2 Similajau-Bakun 275kV line N-2 Similajau-Murum Junction 275kV line Outage of one Similajau-Bakun 275kV line and one Similajau-Murum Junction line 275kV Transmission Line conductor exceeds its rated capability limits N-2 Similajau-Bakun 275kV line N-2 Similajau-Murum Junction 275kV line Outage of one Similajau-Bakun 275kV line and one Similajau-Murum Junction line

Thank You