Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006

Similar documents
Feasibility Study Report

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Evaluation of the Performance of Back-to-Back HVDC Converter and Variable Frequency Transformer for Power Flow Control in a Weak Interconnection

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

St. Leon Wind Farm Interconnection Evaluation Study

Supplemental Report on the NCTPC Collaborative Transmission Plan

Transmission Coordination and Planning Committee 2016 Q4 Stakeholder Meeting

LONG-TERM DEVELOPMENT PLAN for Manitoba Hydro's Electrical Transmission System

Interconnection System Impact Study Report Request # GI

Interconnection Feasibility Study Report GIP-157-FEAS-R2

Project #94. Generation Interconnection System Impact Study Report Revision

EL PASO ELECTRIC COMPANY (EPE) FACILITIES STUDY FOR PROPOSED HVDC TERMINAL INTERCONNECTION AT NEW ARTESIA 345 KV BUS

Project #148. Generation Interconnection System Impact Study Report

100 MW Wind Generation Project

Dunvegan Hydroelectric Project. For Glacier Power Limited. Preliminary Interconnection Study

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Interconnection Feasibility Study Report GIP-369-FEAS-R1

Feasibility Study Report

Feasibility Study Report

New Tie Line Loop Flow Impact

MILLIGAN SOLAR PROJECT

Illinois State Report

New Jersey State Report

ABB POWER SYSTEMS CONSULTING

Interconnection Feasibility Study Report GIP-084-FEAS-R2

SYSTEM IMPACT STUDY EC300W ERIS FINAL REPORT. El Paso Electric Company

PJM Generator Interconnection R81 Emilie (Fords Mill) MW Impact Study Re-Study

Design and Hardware Implementation of a Supervisory Controller for a Wind Power Turbine

XXXXXXXXXXXXXXXXXXXXXXXXX TRANSMISSION/GENERATION FEASIBILITY STUDY FATAL FLAW AND FEASIBILITY ANALYSIS

DETOUR GOLD CORPORATION SYSTEM IMPACT ASSESSMENT FOR DETOUR LAKE PROJECT

Interconnection Feasibility Study Report GIP-IR373-FEAS-R1

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Interconnection Feasibility Study Report GIP-023-FEAS-R1. Generator Interconnection Request # MW Wind Generating Facility Inverness (L6549), NS

Manitoba - United States Transmission Development Wind Injection Study

System Impact Study Report

Merger of the generator interconnection processes of Valley Electric and the ISO;

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

New 115 kv Disconnect Switches at Bloomsburg MTS

Interconnection Feasibility Study Report GIP-222-FEAS-R3

Memorandum. This memorandum requires Board action. EXECUTIVE SUMMARY

2012/13 Power Resource Development Plan The Sales Package

Q87 Generation Interconnection

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

Facilities Study for Alberta to US Available Transfer Capability

TOLTEC POWER PARTNERSHIP TOLTEC POWER PROJECT INTERCONNECTION STUDY SYSTEM IMPACT STUDY

CUSTOMER/ TWIN ARROWS PROJECT

Generator Interconnection System Impact Study For

XXXXXXXXXXXXXXXXXXXX GENERATION INTERCONNECTION FACILITIES STUDY SHORT CIRCUIT ANALYSIS FOR PROPOSED GENERATION AT NEWMAN 115 kv BUS

THE NECESSITY OF THE 500 KV SYSTEM IN NWE S TRANSMISSION SYSTEM TO MAINTAIN RELIABLE SERVICE TO MONTANA CUSTOMERS

welcome to the BC Hydro community open house

Feasibility Study for the Q MW Solar Project

Gateway South Transmission Project

XXXXXXXXXXXXXXXX Transmission Interconnection Feasibility Study

FIRSTENERGY S PROPOSED SOLUTION AND REQUEST FOR CONSTRUCTION DESIGNATION

PSE Attachment K Puget Sound Area Transmission Meeting

Request for Payment Instructions Wholesale Distribution Access Tariff (WDAT) Attachment I - GIP

2015 Grid of the Future Symposium

Final Draft Report. Assessment Summary. Hydro One Networks Inc. Longlac TS: Refurbish 115/44 kv, 25/33/ General Description

Maddox Creek to Southwest Lima 345kV New Transmission Line November 15, 2016

PUD ELECTRIC SYSTEM INTERCONNECTION

Journal of American Science 2015;11(11) Integration of wind Power Plant on Electrical grid based on PSS/E

The Development of Competitive Renewable Energy Zones in Texas

Transmission and Distribution Substation Projects. Operating Company: Entergy Gulf States - Texas. Customer: PID # 202

Feasibility Study For MPC01400 Wind-Powered Generation Facility Interconnected at Euclid, ND

DUKE ENERGY PROGRESS TRANSMISSION SYSTEM PLANNING SUMMARY

EL PASO ELECTRIC COMPANY (EPE) GENERATOR INTERCONNECTION SYSTEM IMPACT STUDY FOR PROPOSED XXXXXXXXXXXXXXXXXX GENERATION ON THE AMRAD-ARTESIA 345 KV

APPENDIX I: Description and Functional Specifications for Transmission Facilities Eligible for Competitive Solicitation

System Impact Study Report

New Mexico Transmission Expansion Concepts For Wind Resources

Interconnection Feasibility Study Report Request # GI Draft Report 600 MW Wind Generating Facility Missile Site 230 kv Substation, Colorado

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Merchant Transmission Interconnection PJM Impact Study Report. PJM Merchant Transmission Request Queue Position X3-028.

Stability Study for the Mt. Olive Hartburg 500 kv Line

Emera Maine Representative: Jeffrey Fenn, P.E., SGC Engineering LLC

Connection Engineering Study Report for AUC Application: AESO Project # 1674

The Long-Range Transmission Plan

Interconnection System Impact Study Final Report February 19, 2018

Sub Regional RTEP Committee - Southern. August 19, 2011

SYSTEM IMPACT RESTUDY H252W ERIS REPORT. El Paso Electric Company

Generation Interconnection Facilities Study For

Experience on Technical Solutions for Grid Integration of Offshore Windfarms

QP 311 Kingdom Community Wind Project Interconnection Feasibility Study. July, 2010 FINAL REPORT. Prepared by:

The Role of Electricity Storage on the Grid each location requires different requirements

ENERGY RESOURCE INTERCONNECTION SERVICE STUDY DRAFT REPORT

Decision on Merced Irrigation District Transition Agreement

Generation Interconnection Feasibility Study For XXXXXXXXXXXXXXXXXXXXXX MW generator at new Western Refinary Substation

Energy Storage Interconnection Initiative

CITY OF VANCOUVER ADMINISTRATIVE REPORT

TransWest Express Project

Transmission Improvements Plan for 575 MW Network Service Request Wansley CC 7 Generation Facility (OASIS # ) Georgia Transmission Corporation

Consulting Agreement Study. Completed for Transmission Customer

ENERGY STRATEGY FOR YUKON. Independent Power Production Policy

COLORADO SPRINGS UTILITIES RESPONSE TO Xcel ENERGY INTERCONNECTION SYSTEM IMPACT STUDY REQUEST # GI , RESTUDY 1 (August 6, 2009)

Guideline for Parallel Grid Exit Point Connection 28/10/2010

Feasibility Study. Shaw Environmental, Inc. 12MW Landfill Gas Generation Interconnection. J.E.D. Solid Waste Management Facility. Holopaw Substation

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Harry Allen to Eldorado 2015

Final System Impact Study for. Sierra Pacific Industries 31 MW Generation Project. Mount Vernon, WA. November 16, 2006

Small Generator Interconnection Program Interconnection Technical Requirements

Interconnection Feasibility Study Report GIP-046-FEAS-R2

Transient Stability Analysis Tool (TSAT) Update April 11, Hongming Zhang EMS Network Applications Manager

Transcription:

Manitoba Hydro Generation Interconnection Exploratory Study Notice September 28, 2006 As per the Manitoba Hydro Open Access Interconnection Tariff, the Transmission Owner has contracted TransGrid Solutions Inc. to perform an Exploratory Study to provide prospective interconnecting Generators with a rough approximation of the costs associated with the interconnection of a Facility and delivery of energy from a Facility to Manitoba load. This Exploratory Study shall be conducted in such a manner to ensure the efficient implementation of Manitoba Hydro s transmission expansion plan in the light of the System s capabilities. Following completion of the Exploratory Study the results will be posted on this MHEB OASIS site. The scope of the Exploratory Study is contained in the following outline.

Study Outline for Manitoba Hydro Exploratory Wind Studies Submitted to: David Jacobson Interconnection & Grid Supply System Planning Manitoba Hydro Winnipeg, MB CANADA Submitted By: TransGrid Solutions Inc. 200-137 Innovation Dr. Winnipeg, MB R3T 6B6, CANADA

Introduction: The Exploratory Wind Studies will be looking at reliability limitations with up to 500 MW of wind, including St. Leon 100 MW wind farm, connected to the Manitoba Hydro transmission system. There is currently 100 MW of pre-existing wind power in Manitoba. Recently, an RFP was announced for an additional 300 MW. The studies will be performed at 500 MW to provide a 100 MW margin for uncertaintly. The project has been divided into four phases as described in the upcoming sections. The principal objective of the project shall be to divide the province into zones and determine a MW limit and connection costs for wind generation in each of these zones. After review and comparison of the Manitoba Hydro Generation Connection Queue and the list of Expressions of Interest (EOI) for wind generation in Manitoba, the potential wind farm locations were plotted on a map of Manitoba as shown in Appendix 1. The wind farm locations and sizes were also placed into a spreadsheet as shown in Appendix 2. Each queue position and EOI location were located on a map of Manitoba that contained the 66-500 kv transmission network. The nearest station to each location was assumed to be the interconnection point, wherever possible the location was assumed to be a 110 kv or 230 kv connection as opposed to 66 kv or lower. Typically the maximum size of wind farm that can be connected to 66 kv is approximately 50 MW and these connections will not be addressed in this study. In some cases, the nearest station is more than approximately 50 km away from the proposed wind plant collector substation. In these cases, existing 115 kv or 230 kv transmission lines would be sectionalized with a new substation. The goal is to divide the province into zones. A preliminary estimation of the zones are listed in Table 1 below. Please see the Manitoba map in Appendix 1 and a more detailed spreadsheet in Appendix 2 for further information. 2 TransGrid Solutions Inc.

Table 1. List of Preliminary Zones. Preliminary Zones Individual Bus Location 6 Minnedosa Neepawa 230 kv Minnedosa 110 kv Raven Lake 230 kv Birtle 230 kv 5 West of Brandon Virden 230 kv Reston 230 kv Souris 230 kv 3 Brandon Brandon 230 kv Glenboro 230 kv Treherne 110 kv 4 Lena Lena (G82R) 230 kv 2 St. Leon St.Leon 230 kv Stanley 230 kv 1 Letellier Letellier 230 kv 9 Elie Portage 230 kv Elie 230 kv Dorsey D54C 230 kv 7 West Lk Manitoba Ashern/A6V 230 kv Dauphin/Vermillion 230 kv 8 East Lk Manitoba A3R/A4D (Lk Mb) 230 kv 10 East Lk Winnipeg Grand Beach 110 kv 11 Northern Manitoba Grand Rapids 230 kv Churchill 138 kv The 10 th and 11 th zones, East Lake Winnipeg (Grand Beach) and Northern Manitoba, will not be included in the analysis. The existing transmission system would require extensive new transmission in order to relieve the significant congestion that would be caused by these interconnections. More focus will be given to the interest expressed in the Manitoba Hydro generation connection queue as opposed to the EOI list. That being said, Table 2 below lists the interconnection points in the order that they exist in the queue, after the existing 100 MW St. Leon wind farm. Some of the buses listed above in Table 1 will not be studied as they are too far away from the connection queue locations. 3 TransGrid Solutions Inc.

Table 2. Nearest Connection Points for MH Wind Generation Queue. Connection Point Wind farm size (MW) Elie 100 Lena 100 St. Leon 100 St. Leon 100 Lena 100 St.Laurent (East Lk Mb) 25-200 Letellier 100 St.Leon 100 Virden 10-50 St. Leon 40-200 Letellier 100-200 Lk Mb Narrows (A6V) 30-200 Letellier 100 Lk Mb Narrows (A6V) 100 St.Leon 100-300 St.Laurent (East Lk Mb) 100-200 Neepawa 20-120 Glenboro/Lena 50-100 Treherne 50-100 Virden 60-80 D54C/Elie 50-100 Portage/Elie 100-200 Portage/Elie 100-200 Neepawa 66-266 Reston 200 St. Leon 200 Deloraine 66 40-50, 150 Virden 200 Souris 200 Glenboro 200 Letellier 100 Based on Table 2, the following buses have the most interest and will be studied in further detail throughout the Exploratory Studies: St. Leon 230 kv - 1000 MW Letellier 230 kv / Rosenfeld 110 kv - 500 MW A3R new tap - 400 MW Portage 230 kv or D54C new tap - 400 MW Neepawa 230 or Minnedosa 110-400 MW Virden 230 kv - 330 MW A6V new tap - 300 MW Reston 230 kv - 200 MW Souris 230 kv - 200 MW Glenboro 230 kv - 200 MW Elie 230 kv - 200 MW Lena 230 kv - 200 MW Treherne 110 kv - 100 MW Stanley 230 kv - 100 MW 4 TransGrid Solutions Inc.

Phase 1 Determining Bottlenecks and Network Upgrades, Defining Zones and Best Connection Points 1. Objective: The objectives of Phase 1 will be: 1. To determine what, if any, bottlenecks will occur when installing up to 500 MW of wind generation in Manitoba. 2. To determine a MW value of wind generation that can be connected to an individual bus before any bottlenecks occur. 3. To identify known fixes that have been budgeted or new Network Upgrades for obvious bottlenecks. 4. To identify the best buses and combine them into zones, possibly one bus per zone to simplify the zonal studies. 5. To determine the total area losses associated with connecting 300 MW of wind to each zone. 2. Study Procedure: 1) Perform PSS/E TLTG analysis on the following as per the list at the end of the Introduction section. a) Individual Bus TLTG determine maximum MW value of wind generation that can be connected before bottlenecks occur at an individual bus; identify the bottlenecks, known fixes currently in the budget, and new Network upgrades if the fix is obvious. Power Flow Cases: Year 2014 summer peak maximum MH export (2175 MW) at low NDEX (350 MW) Year 2014 summer peak maximum MH import (700 MW) at high NDEX (1950 MW) The power flow cases will include existing firm generation plus higher queued generation at Pine Falls (5 MW), Great Falls (4 MW), Pointe du Bois (130 MW total) and Kelsey (15 MW), as well as Wuskwatim (200 MW) and associated transmission (Birchtree- Wuskwatim, Wuskwatim-Herblet Lake, Herblet Lake-Ralls Is.). 2) Perform loss evaluation for each zone. Add 300 MW of wind per zone and sink to Dorsey and Grand Rapids. The same power flow cases described above will be used. Total area losses will be compared between zones. 5 TransGrid Solutions Inc.

3. Outputs: 1) Maximum MW value of wind generation that can be connected to an individual location before bottlenecks occur. 2) Bottlenecks and necessary Network Upgrades (known fixes currently in budget as well as new fixes) that occur when up to a maximum value (for example 100-300 MW) of generation is connected to an individual bus. 3) Zones and associated bus(es) in each zone. 4) Losses associated with 300 MW of wind per zone. 6 TransGrid Solutions Inc.

Phase 2 Look at Whole Manitoba Picture: All Zones and Combinations of Zones 1. Objective: The objectives of Phase 2 will be to look at all zones and combinations of zones to determine: 1. Where the first bottleneck occurs and which zone(s) triggered the bottleneck. 2. Favored zones and combinations of zones to minimize bottlenecks and Network Upgrades, taking into account zone popularity as shown by the generator connection queue. 3. Several practical, least-cost arrangements of 500 MW total wind generation in Manitoba, along with associated Network upgrades. 2. Study Procedure: 1) Perform PSS/E TLTG analysis on the following: 3. Outputs: a) Combinations of Zonal TLTG re-run TLTG analysis on combinations of zones for several arrangements of a total of 500 MW, finding mitigations for bottlenecks. Zone combinations could be in groups such as: 5 zones x 100 MW 4 zones x 125 MW 3 zones x 167 MW 2 zones x 250 MW Power Flow Cases: a. Year 2014 summer peak maximum MH export (2175 MW) at low NDEX (350 MW) b. Year 2014 summer peak maximum MH import (700 MW) at high NDEX (1950 MW) The power flow cases will include existing firm generation plus higher queued generation at Pine Falls (5 MW), Great Falls (4 MW), Pointe du Bois (130 MW total) and Kelsey (15 MW), as well as Wuskwatim (200 MW) and associated transmission (Birchtree- Wuskwatim, Wuskwatim-Herblet Lake, Herblet Lake-Ralls Is.). 1) List of bottlenecks and Network Upgrades for each combination. 2) List of preferred combinations of zones based on minimum bottlenecks and favored connection queue sites. 7 TransGrid Solutions Inc.

Phase 3 Determining Zonal Connection Costs 1. Objective: The objectives of Phase 3 will be: 1) To determine generic connection costs per zone based on what reasonably makes sense from the results of Phases 1 and 2, based on: a) Maximum reasonable value of wind generation per zone b) Network upgrades for that zone c) Actual direct connection costs, such as new breakers, new stations, and transmission lines to the connection points 2. Study Procedure: 1) Calculate cost estimates for each zone based ranges of MW values, including costs such as: a) New high voltage breakers b) New high voltage stations c) New high voltage transmission lines to Interconnection point There could be several cost estimates per zone depending on the how the zonal generation is shared between individual buses in that zone. For example, if all generation in a zone is connected to a single bus this would result in a different cost estimate than if the generation were split between three buses because the direct connect costs would be higher for the three bus scenario. 2) Calculate Network Upgrade cost estimates for each zone. 3. Outputs: 1) Direct connection costs per zone. 2) Network upgrade costs per zone. 3) List of least-cost combinations of zones to supply 500 MW of total wind generation. 8 TransGrid Solutions Inc.

Phase 4 Transient Stability Analysis: DFIG versus Induction Generator 1. Objective: The objectives of Phase 4 will be: 1. To compare the dynamic performance of the induction generator versus the doubly-fed induction generator 2. To determine whether or not dynamic reactive power support, such as an SVC, would be required 2. Study Procedure: 1) For the least-cost options as determined from Phase 3, perform transient stability analysis on the year 2014 maximum export power flow case to test for: a. Transient undervoltage violations / voltage collapse (summer peak) apply local three-phase line faults and stuck breaker single-line-to-ground faults b. Transient overvoltage ride-through (summer off-peak) - apply nbz fault loss of D602F followed by dc reduction 2) If dynamic VAR support is required, re-run worst cases with an SVC to determine approximate rating necessary to meet interconnection criteria. Incorporate a cost estimate for any required dynamic VAR support to the applicable zone(s). 3. Outputs: 1) For each of the least-cost options, a summary of transient stability results and dynamic performance of the two wind generator types, including the need for and approximate rating and cost estimate of an SVC. 9 TransGrid Solutions Inc.

Deliverables: Each phase of the project shall deliver a report describing the objectives, study procedures, study results and conclusions. Estimated Schedule: 1) The Phase 1 deliverables will be provided within three (3) weeks of project kick-off. 2) The Phase 2 deliverables will be provided within two (2) weeks of Phase 1 being completed. 3) The Phase 3 deliverables will be provided within three (3) weeks of Phase 2 being completed. 4) The Phase 4 deliverables will be provided within three (3) weeks of Phase 3 being completed. 5) A draft report of the entire study will be provided one (1) week after completion of Phase 4, the goal being by the first week of January 2007. 6) A final report will be provided two (2) weeks after receiving comments on the draft report. 10 TransGrid Solutions Inc.

Appendix 1. Wind Generation: Map of Manitoba 11 TransGrid Solutions Inc.

Appendix 2. Comparison of Wind Generation Expressions of Interest and Manitoba Generation Queue. 12 TransGrid Solutions Inc.

Preliminary Zones (MW) Preliminary Zones Individual Location EOI Queue EOI Queue Zone Bus Totals Totals Buses Buses Rank Rank 2 St. Leon St.Leon 230 kv 634 1097 535 1097 1 1 Stanley 230 kv 99 5 West of Brandon Virden 230 kv 788 750 100 200 2 8 Reston 230 kv 300 200 8 Souris 230 kv 388 350 5 4 Lena Lena (G82R tap) 230 kv 1037 589 877 299 3 6 Waskada/Deloraine (66kV) 160 290 7 9 Elie Portage 230 kv 424 575 325 396 4 3 Elie 230 kv 99 99 9 Dorsey D54C 230 kv tap 80 10 1 Letellier Letellier 230 kv 527 498 417 498 5 2 Arnaud/St.Malo (66 kv) 110 8 East Lk Manitoba A3R tap (Lk Mb) 230 kv 600 398 600 398 6 6 Minnedosa Neepawa 110 kv, 230 kv 1943 386 100 7 Minnedosa 110 kv 900 386 4 Raven Lake 230 kv 260 Birtle 230 kv 674 3 Brandon Brandon 230 kv 1039 350 639 50 8 11 Glenboro 230 kv 200 200 8 Treherne 110 kv 200 100 9 7 West Lk Manitoba Ashern/A6V 230 kv tap 497 299 299 299 9 6 Dauphin/Vermillion 230 kv 198 10 East Lk Winnipeg Grand Beach 110 kv 299 0 299 11 Northern Manitoba Grand Rapids 230 kv 384 0 299 Churchill 138 kv 85 Totals 8163 4942 Note: In the EOI list, there were several site locations that very either very vague or not descriptive enough. These site locations are not included in the above lists. Legend: Because more attention will be given to the queue list, these buses will not be studied in the Exploratoy Studies.