Enelion Vertica kw Installation manual for the specialists ver..6 Enelion 05.07
Enelion VERTICA General notes At various points in this manual you will see notes and precautionary warnings regarding possible hazards. The symbols used have the following meanings: WARNING! Indicates a potentially hazardous situation which, if not avoided, could result in death or serious injury. CAUTION! Indicates a potentially hazardous situation which, if not avoided, may result in minor or moderate injury. ATTENTION! Indicates a situation which, if not avoided could result in property damage. ESD This symbol reminds you of the possible consequences of touching electrostatically sensitive components. Notice Notes on use of equipment and useful practical tips are identified by i. Notices do not contain any information that draws attention to potentially dangerous or harmful functions. Additional important information. Technical Specifications Two charging panels: socket / cable (depends on version), x00v AC ~ 50Hz, kw (A) for one charging panel, P+N+PE, Standby power - W for one charging panel. Installation manual ver..6, Enelion 05.07
Important information Important information. Safety instructions WARNING! Not observing the safety instructions can result in risk of death, injuries and damage to the device! ENELION LTD assumes no liability for claims resulting from this! Do not remove any notices on the device, such as safety symbols, warning notices, rating plates, nameplates or cable markings! Observe the instructions given for selecting the location and the constructional requirements! If the specifications for the location are not observed, this can result in death, serious physical injury or equipment damage if the corresponding precautionary measures are not met! Electrical hazard! The installation, commissioning and maintenance of the charging station may only be performed by correctly trained, qualified and authorized electricians who are fully responsible for the compliance with existing standards and installation regulations. Pull the charging cable only at the plug and not at the cable out of the connector. Ensure that the charging cable is not mechanically damaged (bent, pinched or run over) and the connection area does not come into contact with heat sources, dirt or water. Only supply the terminals from phases 00V with grounded sources! Before commissioning, check all screw and terminal connections for firm seating! The connector panel cover may never be left open unattended. Mount the connector panel cover if you leave the charging station. 5 safety rules: - Shut down all poles and all sides! - Secure against reactivation! - Check that the equipment is voltage-free! - Ground and short-circuit! - Cover adjacent live parts and restrict access to hazardous areas! Use of the charging station with open cable insertion openings is prohibited. Do not carry out any unauthorized conversion work or modifications to the charging station! Repair work to the charging station is not permitted and may only be performed by the manufacturer (replacement of the charging station)! Installation manual ver..6, Enelion 05.07
Enelion VERTICA Important information Risk of damage! ATTENTION! Make sure that the charging station is not damaged by improper handling (anchoring, housing cover, socket, inner parts etc.). Do not open the lid of terminal in the rain! Risk of damage the aluminium and plexi housing! - Use only detergents dedicated for anodised aluminium / plexi, - Do not tighten the mounting screws with force. Electrostatically sensitive components Information for technicians who are permitted to open the device: Risk of damage! Electronic components can be destroyed if touched! Before handling components, make sure you perform an electrical discharge by touching a metallic, grounded object!. Intended use NOTICE Enelion Vertica is a charging terminal for outdoor area at which electrically operated vehicles can be charged. Two vehicles can be charged at the same time, with phases, A and maximum kw power. The charging station is designed for installation on a pavement mounted column. The respective national regulations must be observed with regard to the installation and connection of the charging terminal. The intended use of the device always includes the compliance with the environmental conditions for which this device was developed. The device was developed, manufactured, inspected and documented in compliance with the relevant safety standards. Therefore, the products do not pose any danger to the health of persons or a risk of damage to other property or equipment under normal circumstances, provided that the instructions and safety precautions relating to the intended use are properly observed. The instructions contained in this manual must be followed precisely in all circumstances. Failure to do so could result in the creation of potential sources of danger or the disabling of safety devices. Apart from the safety instructions given in this manual, the safety precautions and accident prevention measures appropriate to the situation in question must also be observed. Only electrical vehicles or their chargers may be connected. A connection of other loads (e.g. electric tools) is not permitted! Installation manual ver..6, Enelion 05.07
6 7 5 0 8 8 7 5 5 0 9 7 PART NO. PART Housing Profile Alu Ground Plate Front Panel Socket Core 5 Socket Cover With Flap 6 B8..M - 6 x.0 x 6 Hex SHCS -- 6SHX 7 Top Cover Plate 8 Upper Structural Rib 9 Structural Rib - Connector 0 0 Wago Connector Male B8.M - Plain washer, 6 mm, regular B8..6M - M5 x 0.8 x 0 Hex Socket Cone Pt. SS --S Center Element 5 B8...M - Hex nut, Style, M6 x --D-S B8...M - Hex nut, Style, M x 0.5 --D-S 6 M5 Security Screw 7 Motherboard 8 LCD 9 RFID 0 Pilot Box Wago Connector Female 6 Distance Screw Hex Mx8 Distance Screw Hex M.5x8 Distance Screw Hex M.5x0 5 Computer with gsm (optional) 6 DIN Rail 7 Connector Mount 8 Lower Alu Plate 9 Lower Panel 0 DIN Rail - Short Pilot RP Mount v 9 8 fig. Top Gasket Wago Connection Terminal Installation manual ver..6, Enelion 05.07
Enelion VERTICA Installation guidelines Installation guidelines. Before Installing This document describes how to install Enelion Vertica charging station. Before any installation work is performed, study all drawings furnished by the supplier for the particular installation.. Safety Requirements Ensure that at all times when working, no power is connected. Eye protection with appropriate glasses (especially when using the electrical drill). In the installation be sure to not connect directly to power distribution network cables without additional protection. fig. Use appropriate tools for each function.. Delivery content packages Charging station is delivered to a client in separate packages containing: Case steel construction with attached aluminium profiles, connection for x00v (P+N+PE) and top cover with two security screws - fig. Two panels with electric elements, electronics and a socket or a charging cable (depends on a charger s version) - fig. fig. Foundation preparation kit (if ordered) - fig. Set of screws for panels installation, a key for security screws, RFID cards, RFID key holders. Upon receipt of shipment, examine the package for damage. If the shipping container must be opened outdoors, take proper precautions to prevent the entrance of moisture. fig. Installation manual ver..6, Enelion 05.07 5
. Installation Overview Before installation check local requirements for -phase electric device contact (terminal) and policy of electric devices installation in public spaces. prepare a foundation for terminal, mount a terminal case to the base, connect terminal to the power grid, install charging panels, close terminal.. PART Basis Plate(bottom)/ Leveling Plate (top) Threaded Rod M Nut M Washer M QUANTITY 6 NO. NO. PART Basis Plate(bottom)/ Plate (top) Leveling Threaded Rod M Nut M Washer M QUANTITY 6 fig.5 Terminal base preparation with Foundation Preparation Kit Installation.5 Terminal installation steps: Ensure that at all times when working, no power is connected. Terminal Foundation Kit (id ordered) contains four threaded rods, 6 M screws, and gaskets and basis plates fig.5. Mount to bottom basket four rods and tight the nuts onto. Repeat steps with top basket. On the top should be left 50mm rods free space fig.6. Insert mounted construction and cable conduit (not included) into concrete. Cable conduit should be guided via one of top basket hole fig.7. fig.6 50 500 PART QUANTITY Basis Plate(bottom)/ Leveling Plate (top) Installation guidelines Threaded Rod M Nut M 6 Washer M 50 O. Level position of top basket with screws under the plate. Screws should touch te concrete. Use M wrench. after concrete solidify, remove top base. fig.7 6 Installation manual ver..6, Enelion 05.07
Enelion VERTICA 50. Installation guidelines Mounting terminal case to the base Before installation pull up plexi panels from both sides of the case bottom, to get access to the inside installation area and to the contact (terminal) Install the terminal case on the prepared foundation fig.8,9 After installing the case, tightly screw the nuts on ø rods fig.0. Do not put the bottom plexi panels yet. fig.8 fig.9 PART Basis Plate(bottom)/ Leveling Plate (top) Threaded Rod M Nut M Washer M QUANTITY 6 500 NO. Installation manual ver..6, Enelion 05.07 fig.0 7
Installation guidelines. Connection to the power grid In the lower (bottom) part of the terminal there is a contact to the powergrid, which divides electric energy to two charging panels at the same time. Pull out black plexi panel to get access to the contact. The installation, commissioning and maintenance of the charging station may only be performed by correctly trained, qualified and authorized electricians who are fully responsible for the compliance with existing standards and installation regulations. Ensure that at all times when working, no power is connected. phase phase phase neutral earth Connect wires from the contact to the socket - fig. fig. Terminal must be earthed. Ensure, that yellow-and-green wire is connected to the working earhting contact! Ensure, that wires to power grid have proper diameter. It must be minimum 6mm. Insert (slide in) black plexi panels on each side of the case.. Charging panels installation Charging panels have a safe connection system with the powegrid through a contact with a socket and a plug. fig. Before installing a charging panel, make sure that a fuse and RCD are turned on (working) Lift the panel and slide it in the rails of an aluminium profile fig.. If there are any difficulties in sliding the panel in, put a drop of a thick grease into each rail. At the end of the sliding in, a plug on the panel will get inside the socket in the case - fig.. On the top, screw two screws to the case - fig.0. Repeat all above with the second charging panel. fig. 8 Installation manual ver..6, Enelion 05.07
Enelion VERTICA Installation guidelines. Connection to internet To connect to the internet, use the GSM SIM card. SIM card must be without PIN number. Card slot is located in hole at back wall of charging panel fig.. Unlock slot fig.5, Open slot fig.6, Insert SIM card with goldenpins faced to pins on GSM module fig.7. Close slot - fig 8. Lock slot - fig 9. fig. fig.5 fig.6 fig.7 fig.8 fig.9 Installation manual ver..6, Enelion 05.07 9
Installation guidelines 5. Closing the terminal Put a lid on the top and screw two security screws to the case - fig.. fig.0 fig. fig. 0 Installation manual ver..6, Enelion 05.07
Enelion VERTICA Installation guidelines.6 First start Turn the power on in the power grid supply. On the screens you will see a welcoming message. After connection with internet, terminal is ready to use. Please note: charger has list of current APN adresses and passwords to connect with mobile Internet Provider. If there is new provider, installer nedds to update memory card inside charger (please contact with Enelion specialist)..7 Online configuration Online charger works with Enelion Administration Software or with third parts software via OCPP.6. In Enelion Admin Software you can: To add to map and remotely manage charger. To add users and assign RFID cards. To make tariff plans to sell energy to users. To configure static and dynamic load balancing. To enable Enelion Admin Software please contact us: info@enelion.com Installation manual ver..6, Enelion 05.07