Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER

Similar documents
Transient Stability Analysis Tool (TSAT) Update April 11, Hongming Zhang EMS Network Applications Manager

To Shift or not to Shift?

Generator Interconnection Facilities Study For SCE&G Two Combustion Turbine Generators at Hagood

Guide. Services Document No: GD-1401 v1.0. Issue Date: Title: WIND ISLANDING. Previous Date: N/A. Author: Heather Andrew.

Essential Reliability Services Engineering the Changing Grid

Distributed Energy Resources

Grid Integration Costs: Impact of The IRP Capacity Mix on System Operations

RMEL Generation Conferance. Case Studies: Emerging Technologies, Innovative Practices and Successful Implementations to Meet Energy Priorities

REDUCING VULNERABILITY OF AN ELECTRICITY INTENSIVE PROCESS THROUGH AN ASYNCHRONOUS INTERCONNECTION

Demand Optimization. Jason W Black Nov 2, 2010 University of Notre Dame. December 3, 2010

Guideline for Using IEEE 1547 for Solar PV Interconnection Page 1

Impact of Distributed Energy Resources on Transmission System Reliability

Accidental Islanding of Distribution Systems with Multiple Distributed Generation Units of Various Technologies

The Role of Electricity Storage on the Grid each location requires different requirements

Generator Interconnection System Impact Study For

RESERVOIR SOLUTIONS. GE Power. Flexible, modular Energy Storage Solutions unlocking value across the electricity network

CIS-IEEE 2017 Conference Renewable Energy Session Renewable Energy s Impact of Power Systems

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Renewable Grid Integration Research in the U.S.

Department of Energy s Smart Grid Demonstration Projects on Maui

IFC Workshop on Distributed Generation, 13 February 2013, Moscow, Russia

Operational Opportunities to Minimize Renewables Curtailments

Implementing a Microgrid Using Standard Utility Control Equipment

GRID MODERNIZATION INITIATIVE PEER REVIEW

NEDO s Smart Grid Demonstration Projects in the U. S. JUMPSmartmaui Project in Hawaii

SEL Microgrid Lessons Learned

Energy Security Electrical Islanding Approach and Assessment Tools. Dr. Bill Kramer Senior Research Engineer Distributed Energy Systems Integration

Small Electrical Systems (Microgrids)

PES Cook Islands KEMA Grid Study Final Report

2009 Wind-Diesel Workshop. Microgrid Control System Technology GE Digital Energy, Markham Ontario

RULE 21 GENERATING FACILITY INTERCONNECTION APPLICATION SMUD s Distribution System - (SMUD FORM 2655)

The Evolution of System Protection Schemes for the Sarawak Power System By Victor Wong Sarawak Energy Berhad Presented at PQSynergy 2012, Sarawak

Grid Code Frequency Response Working Group Stewart Whyte System Development

Interconnection System Impact Study Report Request # GI

2019 BQDM Extension Auction Frequently-Asked Questions Updated January 29, 2018

TEPCO's operational technologies to prevent cascading outage

Large Scale Solar Integration

Overview of State Distributed Generation Interconnection Rules

Electric Storage Resources & Wholesale Electricity Markets

Measuring the Smartness of the Electricity Grid

Ancillary Services & Essential Reliability Services

Project #148. Generation Interconnection System Impact Study Report

ENERGY STORAGE AS AN EMERGING TOOL FOR UTILITIES TO RESOLVE GRID CONSTRAINTS. June 18, 2015 E2Tech Presentation

Grid Operations & Planning R&D Area Overview

Small Generator Interconnection Program Interconnection Technical Requirements

DER Portfolio Optimization and Dispatch, Tertiary Control/Monitoring Strategies

PLANNING, ELIGIBILITY FOR CONNECTION AND CONNECTION PROCEDURE IN EMBEDDED GENERATION

TD-2306B-001, Interconnecting Large 2-20MW Generation Systems. Employees involved with generation interconnection on electric distribution circuits.

Grid Stability Analysis for High Penetration Solar Photovoltaics

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Feasibility Study Report

100 MW Wind Generation Project

DER101: Distributed Energy Resources basics. May 4, 2017

The Supple Grid. Challenges and Opportunities for Integrating Renewable Generation UC Center Sacramento May 9, Dr. Alexandra Sascha von Meier

Solutions for Smarter Power Markets

Patrick Lee and Chuck Wells

Use of Microgrids and DERs for black start and islanding operation

Laboratory Scale Microgrid Test-Bed Hardware Implementation

Distributed Energy Resources

IEEE Workshop Microgrids

Grid Impacts of Variable Generation at High Penetration Levels

Eric Johnson, Director, External Affairs, ISO New England

BROCHURE. End-to-end microgrid solutions From consulting and advisory services to design and implementation

ABB Microgrids and Energy Storage. Nathan Adams, Director, Technology and Business Development

Guideline for Energy Storage and Generation Version 1.0

Microgrid Storage Integration Battery modeling and advanced control

PV Penetration on Island Mini-Grid or Grid!- Niue. King Island Connect 2015

2018 OPERABILITY ASSESSMENT

Smart Integrated Adaptive Centralized Controller for Islanded Microgrids under Minimized Load Shedding

Inverter Advancements in UL1741 and UL 62109

µ-grids Integration to the Puerto Rico Electric System CCPR Puerto Rico Energy Sector Transformation Condado Plaza Hilton San Juan PR

Guidelines for connection of generators:

Mixed Generation Interconnection, Metering & Settlement

POWER GRIDS GRID INTEGRATION. EssPro - Battery energy storage The power to control energy

ISLANDING SCHEME FOR STATION DURING GRID BLACK-OUT

DER Impacts on Bulk Grid Dynamic Performance

Smart Grids and the Change of the Electric System Paradigm

C PER. Center for Advanced Power Engineering Research C PER

SPIDER Modeling Sub-Group DER Modeling, CAISO Experience

POWER SYSTEM OPERATION AND CONTROL YAHIA BAGHZOUZ UNIVERSITY OF NEVADA, LAS VEGAS

PSO project EaseWind Enhanced ancillary services from Wind Power Plants. Anca D. Hansen DTU Wind Energy

Life Needs Power, Hannover Messe 2017 Inertia in Future Electrical Power Systems Challenges and Solutions Dr. Ervin Spahic

SCE Smart Grid. Creating a Cleaner, Smarter Energy Future. Metering, Billing / MDM America Conference. San Diego. March 9, 2010

Tieline Controls in Microgrid Applications

Asia Pacific Research Initiative for Sustainable Energy Systems 2011 (APRISES11)

i-pcgrid Workshop 2018

Solar Development in New Jersey, and PV Impacts on the Distribution System Carnegie Mellon Conference on the Electricity Industry - March 9, 2011

Effects of Smart Grid Technology on the Bulk Power System

Margarett Jolly DG Manager, Consolidated Edison Company of New York, Inc

WESTERN INTERCONNECTION TRANSMISSION TECHNOLGOY FORUM

SERTP - 1 st Quarter Meeting

Presentation of the European Electricity Grid Initiative

Utility Distribution Planning 101

West Virginia Energy Plan and Becoming an Electric Generator

PJM Generator Interconnection Request Queue #R60 Robison Park-Convoy 345kV Impact Study September 2008

Modeling and Simulation of Battery Energy Storage Systems for Grid Frequency Regulation. X. XU, M. BISHOP, D. OIKARINEN S&C Electric Company USA

Advanced Inverter Design

Georgia Transmission Corporation Georgia Systems Operations Corporation

Update on State Solar Net Metering Activities Lori Bird, NREL RPS Collaborative Summit Washington, DC September 23, 2014

Feasibility Study for the Q MW Solar Project

Transcription:

1 Hawai'i Island Planning and Operations MEASURES TO IMPROVE RELIABILITY WITH HIGH DER Lisa Dangelmaier Hawaii Electric Light lisa.dangelmaier@hawaiielectriclight.com

Hawai'i Electric Light System Overview 2 No interconnections Renewable energy sources: wind, hydro, geothermal, and solar Large amount of distributed PV (approx. 90-MW) and increasing Rely on Underfrequency Loadshed (UFLS) for a portion of contingency reserves. UFLS is implemented at the distribution circuit level

Hawaii Island Distributed Solar o Distributed solar (DG-PV) (over 90-MW) twice as large as any single generating plant. o Other generation provides all the balancing o No direct monitoring, no control 3

Increased DER Variability Ramping Volatility MW/MIN Volatility Sub-hourly Variability Regulation Capacity Uncertainty Seasonal Reserve Capacity 1/7/2019 4

Activities to Improve System Reliability 5 DER interconnection requirements for bulk system reliability Monitoring, Control, Disturbance ride-through Older (legacy) systems installed earlier do not have these capabilities Adaptive under-frequency load-shed Fast responding contingency reserve to mitigate legacy DER (mostly PV ) trip

Under frequency Load-shed Planning Studies 2014: initial study to determine impacts of DER (mostly solar PV) on the under frequency scheme Risks: Aggregate loss of DER at legacy settings: 59.3 Hz, 60.5 Hz, and high/low voltage Biggest risk is 60.5 he Interim static scheme implemented to reduce potential over-shed, possibly reaching 60.5 Hz. Identified the need for adaptive or dynamic assignment of circuits to UFLS for higher DG-PV levels due to variation in circuit 2015: Adaptive Study for DUFLS design. 6

2015 Adaptive Under frequency Study Results 7 Problem 1: Target load shed and circuit contribution varies throughout day Calculate right amount of under frequency load shed for present net load and circuit load telemetry measurement to avoid both Over- and Under-Shedding. Energy Management System (EMS) custom application to automatically assign UFLS Stages (trip settings) to the distribution circuit relays, based on System load and circuit load telemetry every 15-minutes. Problem 2: Need faster detection that load shed is required. Recommended triggering load-shed on fast rate of change of frequency Periodic review recommended (annual or biannual)

DER Impacts: Require Adaptive Scheme 8 60.5 Hz DG PV trip (Simulation) Daytime Exporting Circuits

Adaptive UFLS Design 9 Stage 1 and stage 2 should sum to 15% of the system net load maximum allowed load shedding for N-1 unit trips. Stage 1 through stage 4 should sum to 40% of the system net load which is the maximum allowed load shedding for N-1-1 unit contingencies Adjust the stages of UFLS to reflect a percentage of net system load on each stage. Df/dt 15%, 0.5 Hz/sec, 9 cycle relay plus breaker time (not currently active) Stage 1 5%, 59.1 Hz, 8 cycle relay plus breaker time Stage 2 10%, 58.8 Hz, 8 cycle relay plus breaker time Stage 3 10%, 58.5 Hz, 8 cycle relay plus breaker time Stage 4 15%, 58.2 Hz, 8 cycle relay plus breaker time Stage 5 10%, 57.9 Hz, 8 cycle relay plus breaker time Stage 6 20%, 57.6 Hz, 8 cycle relay plus breaker time Retain most recent UFLS settings in the event of SCADA/EMS communication failure until communications are restored.

Adaptive Scheme Implementation Scope 10 41 substations, required relay upgrades, RTAC installation 109/138 = 78% circuits on UFLS 70% peak load EMS custom application to assign circuits to UFLS Blocks, issue settings Monitor events to determine effectiveness of new UFLS scheme. Implemented late 2017.

Considerations Added to Initial Scope 11 Circuit rotation Hot line tag status considered 2017 study update identified requirement to turn ROCOF (Rate of Change of Frequency) on/off ( due to reduced legacy DER)

EMS Application Function 12 Monitors System load, and circuit loads, limited holdoffs, and number of UFLS operations. Calculates target MW for each stage Assigns circuits to UFLS stages to achieve MW targets Displays circuits by UFLS stage groups. Some alarms include: assigned loading target load Feedback stage Assigned stage

Inputs to the application 13 Each circuit is assigned a Priority (PRI): 1 Normal circuit, no restrictions. 2 Restricted circuit, avoid tripping if possible 3 Highly restricted circuit, last resort 4 Not participating, do not trip. Limited Hold-offs applied using a Hot Line Tag will add a small restriction. Circuits that operate frequently (FreqOp) due to UFLS will add a small restriction.

Participation Factor 14 UFLS circuits are assigned to blocks based on a participation factor (PART) of 1 through 9. Kicker Stage assignments utilizes a similar algorithm, but the Eligible circuits are taken from the normal stages (typically Stage 3 or 4).

Summary Display 15

Frequency (Hz) Dynamic Underfrequency Loadshed (DUFLS) - Events 16 5 events occurred following the loss of a geothermal plant to the grid due to lava impacts 1 st event occurred on June 14, 2018 after months of anticipation. A steam plant tripped offline, and the 2 nd kicker stage operated. It had a 59.5 Hz trip setting with 20-second time delay. 60.2 60 59.8 59.6 59.4 59.2 59 58.8 58.6 Freq Time (mm:ss.s)

Dynamic Underfrequency Loadshed (DUFLS) - Events 17 2 nd event was due to the loss of a combustion turbine that resulted in the 1 st stage of UFLS to operate. 3 rd, 4 th and 5 th events were cascading generation losses, resulted in multiple stages of UFLS to operate The scheme has performed well for single and multiple loss of gen, in each case System stabilized.

Contingency Reserve Battery Energy Storage System (BESS) For the small island system of Hawaii Island, over-frequency 60.5 Hz can occur for various scenarios Aggregate loss of legacy DER at 60.5 Hz is largest contingency, large losses for voltage excursions also possible Driver for need tor large, fast responding contingency storage

Overview 19 Storage (BESS) or Diesel Rotary Uninterruptable Power Supply (DRUPS) for Fast Contingency Reserves Loss of legacy DER will result in widespread customer outages and high risk of system failure Legacy DER not able to convert to full ride-through The following are the specific triggers: Voltage excursions for transmission faults Frequency excursions during faults, load trips, and unit trips Series of studies examined risks and solutions

20 Frequency Excursions can reach 60.5

21 DER Adding to Contingencies Today One example: Nov 6, 2018 a unit tripped at 11.9 MW. Under-frequency load shedding (UFLS) Stage 1 operated despite 12 MW of spinning reserve at the time. Legacy DER loss due to voltage and frequency excursion exacerbates impact UFLS Block 1 59.1 Hz

BESS Sizing Study Scenarios 22 Study analysis considered various future scenarios Geothermal plant online/offline Line reconfiguration for lava impacts Planned new resource additions (less responsive than displaced resources) Updated Legacy DG-PV Capacities based on supplier data and reports, engineering records New Under-frequency adaptive scheme Updated modeling of DER dynamics

Storage Assumptions and Study 23 Recommendation 0.1 Hz deadband with 1% droop Sized for planning criteria: No more than 2 stages of load shedding (15% net load) for unit trip contingencies System survives secondary fault-clearing Without storage, numerous cases were unstable Size was driven by unit trips and secondary fault clearing scenarios

24 Study Example : Avoid failure from delayed clearing of a fault on 6100 Line near Kanoelehua

Example : Avoid large outage for Unit Trip 25

Contingency Storage (BESS) Project 18 MW/18 MWh BESS Fast Contingency Response Reduce excessive customer outages and possible system failure; caused by high penetration DER Size reflects current configuration, resource plans, and legacy DER amounts 18 MW capacity 30 minute duration to bring standby generation online Propose increased duration to allow more flexibility to respond to over-frequency ( 1 hour) Integrate with SCADA/EMS system Proposing two locations geographically separated 26

Alternatives Analysis for Energy Storage 27 Retrofit all PV with full-ride through settings Estimated cost to retrofit inverters to full ride-through exceeded cost of storage Increase number of online generators, limiting output on certain generators, and increasing online spinning reserves Was somewhat helpful for n-1 Would not reduce size of battery required for secondary fault clearing Conventional plants would displace variable RE Would hasten need to control DG-PV for excess energy Pumped Storage Hydro (PSH) PSH would take much longer to implement, limited potential sites, significant environmental impact

Alternatives in order of effectiveness 28 1. Most effective: all DG retrofitted to full ride-through 2. Fast responding storage second most effective. 3. T&D and Protection improvements do not eliminate storage for unit trips. However, reduction in clearing time is needed to address possible system failure (in addition to storage). 4. Increasing gen reserves would reduce the size of battery required for unit trips, but does not eliminate need for storage. Cost increases for gen. 1. Do nothing: allow system risk and reliability impacts, no cost increase.

Demand Response Potential 29 Does DR offer alternatives with Storage? Initial evaluation does identify a small amount of fast-responding DR Conclusion: impact would be very limited impact on sizing (if any)

Other work in progress/completed 30 Breaker Failure Replacing 5 cycle oil breakers Reducing secondary clearing time Dual communication for POTT schemes Dynamic UFLS in service 12/2017

MAHALO LISA.DANGELMAIER@HAWAIIELECTRICLIGHT.COM 31