INCREASING electrical network interconnection is

Similar documents
Increasing Distribution Network Capacity using Automation to Reduce Carbon Impact

15 Nelson-Marlborough Regional Plan

MVDC link in a 33 kv distribution network

15 Nelson-Marlborough Regional Plan

Targeted Application of STATCOM Technology in the Distribution Zone

TRANSMISSION PLANNING CRITERIA

Underpinning Research Power Electronics in Distribution Networks

Novel Use of Existing Data for Smart Grid Preliminary Analysis and for Asset Optimization

Integrated System Models Graph Trace Analysis Distributed Engineering Workstation

RECONFIGURATION OF RADIAL DISTRIBUTION SYSTEM ALONG WITH DG ALLOCATION

Lesotho Electricity Authority REPORT ON ANALYSIS OF LEC LOAD SHEDDING FOR PERIOD APRIL JULY 2008

Expected Energy Not Served (EENS) Study for Vancouver Island Transmission Reinforcement Project (Part I: Reliability Improvements due to VITR)

Deploying Power Flow Control to Improve the Flexibility of Utilities Subject to Rate Freezes and Other Regulatory Restrictions

THE APPLICATION OF CONSERVATION VOLTAGE REDUCTION (CVR) TO DISTRIBUTION NETWORKS WITH HIGH UPTAKE OF HEAT PUMPS AND ELECTRIC VEHICLES

Cost Benefit Analysis of Faster Transmission System Protection Systems

A Cost Benefit Analysis of Faster Transmission System Protection Schemes and Ground Grid Design

SPN High Value Project PO Route. RIIO-ED1 Investment Justification Reinforcement for PO Route Network: SPN

Agility in energy Ahead of the challenge, ahead of the change

PID 274 Feasibility Study Report 13.7 MW Distribution Inter-Connection Buras Substation

City Power Johannesburg: Response to Potential Load Shedding. Presented by : Stuart Webb General Manager : PCM October 2014

CONNECTION OF NEW GENERATORS IN THE ELECTRICAL POWER SYSTEM OF KOSOVO. Rexhep Shaqiri 1, Bogdanov Dimitar 2.

INTEGRATING PLUG-IN- ELECTRIC VEHICLES WITH THE DISTRIBUTION SYSTEM

The Swedish Government Inquiry on Smart Grids

100 MW Wind Generation Project

Building a 21 st Century Electric Grid. February 23, 2018

EH2741 Communication and Control in Electric Power Systems Lecture 3. Lars Nordström Course map

Reasonableness Test RT 015 /11 Salisbury Substation 11kV Feeders

Electric Vehicles Coordinated vs Uncoordinated Charging Impacts on Distribution Systems Performance

UK Research Activities on Advanced Distribution Automation. Dr. Graham Ault

EXPERIMENTAL STUDY OF DYNAMIC THERMAL BEHAVIOUR OF AN 11 KV DISTRIBUTION TRANSFORMER

Impacts of Fast Charging of Electric Buses on Electrical Distribution Systems

Smarter Network Storage: Introduction to grid-scale storage and applications, the DNO perspective

American Electric Power s Energy Storage Deployments

City of Palo Alto (ID # 6416) City Council Staff Report

Adaptive Power Flow Method for Distribution Systems With Dispersed Generation

TEN YEAR PLANNING GUIDE SHASTA LAKE ELECTRIC UTILITY

ATTACHMENT - DFO STATEMENT OF NEED

Interconnection System Impact Study Report Request # GI

Electric Power Research Institute, USA 2 ABB, USA

Recharge the Future Interim Findings

GIBRALTAR ERDF OPERATIONAL PROGRAMME POST ADOPTION STATEMENT

STOR Market Information Report TR27

Presented By: Bob Uluski Electric Power Research Institute. July, 2011

Managing the renewables challenge in secondary distribution networks. Tim Spearing, Product Marketing Manager Lucy Electric, United Kingdom

Hardware Testing of Photovoltaic Inverter Loss of Mains Protection Performance

Microgrid solutions Delivering resilient power anywhere at any time

Interconnection Feasibility Study Report GIP-226-FEAS-R3

Distribution Feeder Upgrade Deferral Through use of Energy Storage Systems

EMERGING REQUIREMENTS

Enhancement of Transient Stability Using Fault Current Limiter and Thyristor Controlled Braking Resistor

Decision on Merced Irrigation District Transition Agreement

Coordinated Charging of Plug-in Hybrid Electric Vehicles to Minimize Distribution System Losses

Southern California Edison Rule 21 Storage Charging Interconnection Load Process Guide. Version 1.1

Supplemental Report on the NCTPC Collaborative Transmission Plan

Potential Impact of Uncoordinated Domestic Plug-in Electric Vehicle Charging Demand on Power Distribution Networks

Introducing Nexans Superconducting Fault Current Limiters (SCFCLs)

The Power Potential Project A guide to participating

Flexible Distributed Generation. FDG-F Burwell (EPN) May 2017

Computer Aided Transient Stability Analysis

IEEE-PES Chicago Chapter Presentation November 11, Smart Grid. Mike Born. Principal Engineer, Capacity Planning

BC Hydro Case Study: Battery Energy Storage in Field, British Columbia, Canada. IEEE PES Meeting July 2014

THE TRES AMIGAS PROJECT

Smart Grid 2.0: Moving Beyond Smart Meters

Renewable Generation Electrical Infrastructure and Grid Connection Services Provided by Power Systems Project and Consultancy Services (PCS) Ltd

The Grid Link Project. Summary of the Report for the Independent Expert Panel

Approved by This document is the property of Network Rail... Date: It shall not be reproduced in whole Phil Collins Head of Asset Management (E&P)

Journal of Emerging Trends in Computing and Information Sciences

CONNECTION ASSESSMENT & APPROVAL PROCESS. Cardinal Substation Modification of 115kV Substation

A TRIAL OF ALTERNATIVES TO DIRECTIONAL OVERCURRENT PROTECTION ON GRID TRANSFORMERS TO IMPROVE THE NETWORK CAPACITY TO ACCOMMODATE REVERSE POWER FLOW

Utility and project update 2-3 Project description 4

Co-location Informal Guidance Note. March 2018 Version 1.1

IEEE-PES Smart Grid Super Session

Galapagos San Cristobal Wind Project. VOLT/VAR Optimization Report. Prepared by the General Secretariat

Approved by This document is the property of Network Rail... Date: It shall not be reproduced in whole Phil Collins Head of Asset Management (E&P)

Energy from Waste Grid Connections

Karl Elfstadius, ABB Smart Grid Program Mmanager / SMART GRID TAIWAN, Smart Grid Overview. ABB SG_Presentation_V4.

Next-generation SCADA and Control Technologies for Large-scale Use of Photovoltaic Generation on Electric Power Grid

DIRECT CONTROL OF EV CHARGING ON FEEDERS WITH EV CLUSTERS

Assessing Feeder Hosting Capacity for Distributed Generation Integration

Optimal Power Flow Formulation in Market of Retail Wheeling

FAULT ANALYSIS OF AN ISLANDED MICRO-GRID WITH DOUBLY FED INDUCTION GENERATOR BASED WIND TURBINE

Energy Storage: A UK Perspective

Turbo boost. ACTUS is ABB s new simulation software for large turbocharged combustion engines

Asset Category Batteries LPN

Power Potential Guide to Participating : A technical 0 guide to the services for synchronous and non-synchronous DER participants 04/10/2017

Service Requested 150 MW, Firm. Table ES.1: Summary Details for TSR #

Energy Management for Regenerative Brakes on a DC Feeding System

An Integrated Grid Path for Solar. Thomas Key, EPRI Senior Technical Executive. ISES Webinar. April 22, 2016

High-voltage Direct Inverter Applied to Induced Draft Fan Motor at Takehara Thermal Power Station No. 3 of Electric Power Development Co., Ltd.

Electricity Industry Code Minimum Service Standards & Guaranteed Service Levels Quarterly Report July September 2008

Evaluation and modelling of demand and generation at distribution level for Smart grid implementation

Battery Energy Storage System addressing the Power Quality Issue in Grid Connected Wind Energy Conversion System 9/15/2017 1

CRITICAL ISSUES DOWNTOWN CONTINGENCY PORTFOLIO

Issues for connection of distributed generation in rural/remote power systems

/12/$ IEEE. M. Bashir M.Sc student, Student Member, IEEE Ferdowsi University of Mashhad Mashhad, Iran

A Method for Determining the Generators Share in a Consumer Load

BALL BEARING TESTS TO EVALUATE DUROID REPLACEMENTS

ERCOT Overview. Paul Wattles Senior Analyst, Market Design & Development. Solar Energy Industries Association July 11, 2012

Elbert County 500 MW Generation Addition Interconnection Feasibility Study Report OASIS POSTING # GI

METRO NORTH TRANSMISSION STUDY ELECTRIC AND MAGNETIC FIELD PROFILES (VILLAGE OF ANMORE)

Transcription:

Analysis and Quantification of the Benefits of Interconnected Distribution System Operation Steven M. Blair, Campbell D. Booth, Paul Turner, and Victoria Turnham Abstract In the UK, the Capacity to Customers (C 2 C) project is underway to determine the potential benefits of increased interconnection in distribution systems, combined with demand side response technology. Managed contracts with customers, i.e., the agreement that certain loads are interruptible following system faults, allows distribution circuits to be loaded beyond the limits presently required for security of supply. This potentially permits load growth but avoids the cost and environmental impact of conventional network reinforcement. This paper provides the results of electrical system modelling to quantify the benefits of the C 2 C operation, using actual circuit data and typical load distributions. Based upon simulations of these circuits, it is shown that increased interconnection generally leads to minor improvements in electrical losses and system voltage. By connecting managed (i.e., interruptible) loads, circuits typically can be loaded significantly further than the present practice in the UK an average increase of 66% for radial operation and 74% for interconnected systems. Index Terms Automation and control, demand side response, distribution, interconnection, load flow. I. INTRODUCTION INCREASING electrical network interconnection is presently of interest for both transmission and distribution systems [1]. For distribution systems, interconnection offers several potential benefits, including: increased capacity for connecting load and generation, and therefore deferral or avoidance of network reinforcement costs; greater flexibility in the use of the available capacity; improved voltage profiles and voltage support; and reduced losses and voltage harmonic distortion due to lower system impedance. This is particularly relevant in the UK where 6.6 kv and 11 kv ring circuits, operating as two radial feeders, are common [2]. This paper quantifies the benefits of increased network interconnection, within the context of the Capacity to Customers (C 2 C) project [3] presently being led by Electricity North West Limited in the UK. The project involves a consortium of ten industrial and academic partners. The aim of the C 2 C Project is to test new technology, network operational practices (i.e., increased network interconnection), and commercial demand response contracts. These changes will allow the network operator to increase the loadings on a selection of trial circuits representing approximately 10% of its 6.6/11 kv network without resorting to conventional network reinforcement. The project will thereby release inherent spare capacity in the S. M. Blair and C. D. Booth are with the Institute for Energy and Environment, Department of Electronic and Electrical Engineering, University of Strathclyde, Glasgow, G1 1XW, UK (e-mail: steven.m.blair@strath.ac.uk). P. Turner and V. Turnham are with Electricity North West Limited, Salford, Greater Manchester, M6 6QH, UK. 6.6/11 kv system in order to accommodate the future forecast increases in demand, whilst avoiding (or deferring) the cost and environmental impacts that are associated with traditional network reinforcement. This paper focuses on the analysis of the effects of C 2 C operation on electrical losses, the circuit voltage profile, and the available network capacity. This has been achieved using real system data for a representative proportion of the trial circuits. II. PROJECT BACKGROUND Fig. 1 provides a simplified overview of the aims of C 2 C. Spare capacity normally reserved for use during circuit outages when the system is operating in a reconfigured state, typically through a shift in the location of the normallyopen point (NOP) will be offered to new customers. This is possible due to a derogation from the normal requirements for security of supply in distribution networks in the UK, governed by Engineering Recommendation (ER) P2/6 [4]. By closing NOPs during normal system operation, additional loads with managed contracts for post-fault conditions can be connected: effectively sharing the capacity available from both radial feeders and avoiding or deferring the need for network reinforcement. The managed contracts permit the C 2 C loads to be interrupted following fault conditions for a defined period of time. As depicted in Fig. 1b, by closing the NOP, it is also possible to connect a single large load using the spare capacity from both radial feeders (where each feeder has a maximum thermal capacity for 6 MVA of load). Network automation is important for ensuring correct and timely restoration of customers after faults, and for managing the available capacity. A field trial of C 2 C operation is presently underway, involving 180 ring circuits throughout the Electricity North West network, as shown in Fig. 2. These circuits have been selected due to their relatively low historical rates of fault occurrence, and to ensure that excessive fault levels are not introduced by closing NOPs; these practical conditions would also be applicable if the C 2 C method is offered beyond the trial period. From the 180 trial circuits, 36 circuits have been selected for detailed monitoring and analysis. A. Circuit Data III. ELECTRICAL SYSTEM MODELLING Data have been combined from a variety of sources, including: detailed distribution network data (including the full electrical topology) in a legacy format; cable and overhead line capacity ratings and impedance values; and historical loading

(a) Conventional radial operation, with no usable spare capacity (emergency capacity not presently offered to customers) Fig. 2. Map of C 2 C trial locations highlighted in yellow, from [5] (Map data 2013 GeoBasis-DE/BKG ( 2009), Google) (b) C 2 C operation, with additional capacity for interruptible loads (large, single load) Fig. 3. Example half-hourly feeder current, 1 st January 2012 (c) C 2 C operation, with additional capacity for interruptible loads (distributed load growth) Fig. 1. Capacity increase due to C 2 C network operation data for all of the year 2012. Fig. 3 and Fig. 4 illustrate typical load current values for two radial feeders which form a ring circuit. IPSA [6] has been used as a platform for integrating the data sources, as well as providing load flow functionality for analysing the performance of the selected ring circuits. Fig. 5 summarises the process of integrating the data sources and generating results. This process is fully automated for all 36 ring circuits. The circuit loading data (as shown in Fig. 4) are processed to interpolate missing data values, although less than 0.5% of load current values are missing due to issues with the SCADA system or otherwise. The mean and peak annual loadings for each feeder are calculated and extracted. The electrical network data is imported into IPSA. Although IPSA has legacy data import functionality, this process has been significantly extended to cater for the requirements of

Fig. 5. IPSA import process Primary 6.6 kv busbar Fig. 4. Example daily mean feeder current, for 2012 this investigation. A geographically-accurate IPSA model of each ring circuit is generated, as illustrated in Fig. 6. Each substation, represented by blue dots in Fig. 6, has a load connected. For simplicity, it is assumed that no distributed generation is connected to the system. A script is executed within the IPSA scripting environment to: 1) Validate the electrical connectivity of the models. 2) Remove necessary elements from each model. 3) Connect a generator to the primary busbar to represent the grid infeed. 4) Determine the load scaling factor which matches the historical loading data for each feeder (based on either the annual mean or annual peak loading data). 5) Perform load flows, in both radial and interconnected configurations, and generate the results. B. Typical Circuit Results Fig. 7a and Fig. 7b illustrate typical load flow results using IPSA, with the system operating in radial and interconnected configurations, respectively. A. Losses IV. RESULTS Fig. 8 summarises the effect of C 2 C operation on electrical (I 2 R) losses, by extrapolating the reduction in total annual losses resulting from interconnected ring circuit operation (relative to radial operation). The majority of ring circuits exhibit NOP Fig. 6. Example of IPSA model of a ring circuit (blue dots represent substations) Fig. 8. Histogram of reduction in annual losses

(a) Load flow radial configuration, mean loading Fig. 7. Example load flow results (b) Load flow interconnected configuration, mean loading an annual reduction in losses of approximately 5 MWh with the C 2 C configuration, assuming mean loadings. This equates to a modest reduction in the mean distribution losses, for the 6.6/11 kv ring circuits under study; the mean total losses are reduced from 0.57% (radial) to 0.53% (interconnected). B. Voltage Fig. 9 illustrates the effect of interconnected operation on the minimum voltage experienced at any point in the ring circuit, at peak loading. These data include all spurs which branch off from the main circuit, which may experience lower voltages than the voltage at the NOP. In most cases, the minimum voltage shows an improvement due to interconnected operation, even at peak loading. C. Capacity The potential capacity available by adopting C 2 C operation has been determined from the maximum possible additional interruptible load which can be connected, assuming that the load growth is distributed evenly throughout each ring circuit. Initially, each circuit is loaded to the conventional (i.e., according to ER P2/6) maximum capacity for non-interruptible loads. In each case, the load is increased until either: 1) A cable or line thermal headroom (i.e., the remaining thermal capacity) constraint is reached, or 2) A steady-state bus voltage constraint is reached (voltage less than 95% nominal voltage). TABLE I COMPARISON OF CIRCUIT CONSTRAINT TYPES Radial operation Interconnected operation Voltage constraints 22% 17% Thermal constraints 78% 83% The results are provided in Fig. 10. Approximately 80% of circuits are limited by a thermal constraint rather than a voltage constraint, as given in Table I. For interconnected operation, a mean increase in loading of 74% is possible, compared with 66% for radial operation; this can be attributed to the reduced occurrence of voltage constraints as shown in Table I. For circuit 16 in Fig. 10, which is a rural network with a significant presence of relatively long overhead lines, the system presently operates close to the voltage limit and there is no prospect for directly adding any interruptible load (without also implementing other measures to support the network voltage). V. CONCLUSIONS The results arising from the analyses of several circuits show that there generally are benefits to distribution losses and voltage support from increased interconnection, but these gains are often marginal. By allowing the connection of interruptible loads, the available capacity for distributed load is significantly

Fig. 9. Summary of difference in minimum voltage for C 2 C operation Fig. 10. Possible increase in circuit capacity resulting from C 2 C operation increased, by approximately 74%. Interconnected operation yields a further improvement in the available capacity, as well as potentially permitting the use of spare capacity from both radial feeders. Further work will analyse the impact of interconnection when connecting distributed generation and the feasibility of connecting single, large loads without requiring conventional network reinforcement. The effects of C 2 C operation on power quality will be evaluated, using data captured from power quality monitoring equipment during the trial. REFERENCES [1] J.-C. Kim, S.-M. Cho, and H.-S. Shin, Advanced Power Distribution System Configuration for Smart Grid, IEEE Transactions on Smart Grid, vol. 4, no. 1, pp. 353 358, Mar. 2013. [2] I. Chilvers, N. Jenkins, and P. Crossley, Distance relaying of 11 kv circuits to increase the installed capacity of distributed generation, IEE Proceedings - Generation, Transmission and Distribution, vol. 152, no. 1, p. 40, Jan. 2005. [3] Electricity North West Ltd., Electricity North West Capacity to Customers (C2C) project, 2013. [Online]. Available: http://www.enwl.co.uk/c2c [4] ENA, Engineering Recommendation P2/6 - Security of Supply, Tech. Rep., 2006. [5] Electricity North West Ltd, C2C - Postcode search, 2013. [Online]. Available: http://www.enwl.co.uk/c2c/are-you-affected/postcode-search [6] TNEI Services Ltd, IPSA Power, 2013. [Online]. Available: http://www.ipsa-power.com/ Steven M. Blair received the M.Eng. degree (with distinction) in computer and electronic systems in 2008, and the Ph.D. degree in electrical engineering in 2013 from the University of Strathclyde, Glasgow, U.K. He is currently a Research Associate at the University of Strathclyde. His research interests include power system protection, fault current limitation, marine electrical systems, communications, and real-time simulation. Campbell D. Booth received the B.Eng. and Ph.D. degrees in electrical and electronic engineering from the University of Strathclyde, Glasgow, U.K, in 1991 and 1996, respectively. He is currently a Senior Lecturer with the Institute for Energy and Environment, Department of Electronic and Electrical Engineering, University of Strathclyde. His research interests include power system protection; plant condition monitoring and intelligent asset management; applications of intelligent system techniques to power system monitoring, protection, and control; knowledge management; and decision support systems. Paul Turner joined United Utilities (subsequently Electricity North West) as a graduate engineer in 1999. Since then he has carried out a variety of roles in the control environment, such as outage planning manager and automation development manager. Paul is an authorised control engineer and is currently the technical manager for the Tier 2 Low Carbon Network Fund project, CLASS.

Victoria Turnham graduated from the University of Manchester in 2008 with a masters degree in electrical and electronic engineering. Since joining United Utilities (subsequently Electricity North West), Victoria has gained experience in EHV strategic network planning and more recently has worked on the technical and research elements of a Tier 2 Low Carbon Network Fund project, Capacity to Customers (C 2 C).